e guyed towers erection - etleretler.com/docs/bsp/incoming/dvd1/700/760/760-925-330_i1.pdf · e...
TRANSCRIPT
BELL SYSTEM PRACTICESOutside Plant EngineeringAntenna Supporting Structures
E GUYED TOWERS
ERECTION
1. GENERAL . .
2. PRE-ERECTION
3. INSTALLATION. . . . .
CONTENTS PAGE
. . . . . . . . .
CONSIDERATIONS . . .
OF BASEPLATE ASSEMBLY. . . . . . . . .
4. TEMPORARY WARNING LIGHTS . . .
5. ERECTION CONSIDERATIONS . . . .
6. GUY TENSIONS . . . . . . . .
1
1
2
3
3
10
1. GENERAL
1.01 This section outlines the general considerationsinvolved in erecting E Guyed Towers, and
includes recommended procedures and precautions.
1.02 Erection drawings are normally furnishedwith the tower, and provide information
necessary for the field assembly of the tower,including the location and orientation of everypiece and subassembly. All steel (except nuts,bolts, and washers) is identified by stencils, stamps,or metal tags which correspond to the markingsshown on the erection drawings. The identifyingmark of leg members is located on the outer facenear the lower end. These drawings also showthe number and length of bolts, nuts, and washersrequired to join the members. A more thanadequate supply of bolts, nuts, and washers isfurnished with the tower, but care must be exercisedto ensure that the proper size of each is used foreach joint, or a shortage of some sizes may develop.
SECTION 760-925-330,
Issue 1, August 1967
AT&TCo Standard
2. PRE-ERECTION CONSIDERATIONS
2.o1 Tower erection should not be started untilall required permits have been obtained,
as outlined in Section AG25.320.
2.o2 The permit issued by the Federal CommunicationsCommission (FCC) to construct and operate
a radio system usually indicates whether or notlighting and painting to improve visibility arerequired. Where only receivers are to be installedand it has been determined that FCC permissionis not required, the Federal Aviation Agency (FAA)will determine the necessity for lighting or paintingto improve visibility. If lighting is required,arrangements must be made to assure the availabilityof electric power at the site, and the lightingfacilities must be ordered and on hand at thetower site. Note that the standard lighting kitprovides only the material which goes on the tower.Conduit and wire from the base of the tower tothe lighting control panel in the building shouldbe ordered locally. Methods of lighting and paintingtowers are described in Sections AG25.230 andAG25.300. Information on temporary warning lightsis contained in Part 4 of this section.
2.03 Section AG25.320 provides information onfoundations and anchors for E Guyed Towers.
Steel erection should not be started until the resultsof concrete compression tests are known to besatisfactory. (See Section AG25. 130 for a discussionof concrete. )
2.04 The grounding system at the anchors shouldbe completed and the grounding connections
at the foundation should be readily accessible.Installation of the grounding system is describedin Section AG25.320.
@ American Telephone and T;legraph Company, 1967
Printed in U.S.A. Page 1
SECTION 760-925-330
2.05 All equipment to be installed on the towershould be available when required, and its
mounting location on the tower should be specifiedto the contractor in’ order that hoisting equipmentmay be positioned to avoid conflict.
2.06 If aerial electric power facilities are in alocation that may present a hazard to or
interfere with temporary guys, hoisting equipment,tag lines, etc, arrangements should be made tohave the power company relocate, de-energize, orinsulate its facilities.
2.07 Foundations and anchors should be carefullychecked to ensure that they are located
correctly and are of the right size. This shouldinclude checking the azimuths of the anchors, whichin turn fix the transmission blind sectors referredto in Section AG25. 310. Details of layout arecovered in Section AG25.320.
2.08 It may be desirable to install a talking circuiton the tower to facilitate adjustment of
antennas and reflectors during system lineup.Information on this subject is contained in SectionAG25.230. A physical circuit can be avoided byuse of the walkie-talkie radio, if this equipment isavailable. This equipment may also prove of valuein the erection of the tower itself.
3. INSTALLATION OF BASEPLATE ASSEMBLY
3.01 Both the foundation surface and the baseplateshould be cleaned of mud, grime, and other
foreign matter. The baseplate is then installed(Fig. 1) by placing it on four tapered steel wedgeslocated about midway between the anchor bolts.The plate is leveled by adjusting thethe baseplate is symmetrical aboutmay be installed without regard toon the pier.
wedges. Sincethe center, itits orientation
,.“
//GROUT APPROXIMATELY
STEEL WEDGE
TOP OF CONCRETE FOUNDATION
Fig. 1—Installation of Baseplate Assembly
Page 2
1ss 1, SECTION 760-925-330
3.02 After the baseplate has been leveled, theanchor bolt nuts should be tightened. The
wedges should provide a clearance of 3/4 to 1-1/4inches between the baseplate and pier to allowfor grout. The baseplate may be installed at anytime after the results of the compression tests onthe concrete are known to be satisfactory.
3.o3 The grout should consist of one part portlandcement (Type I or III ) to two parts sand
(by volume). Portland cement is described inSection AG25. 130. Clean sand from a reliablesupplier should be used in the grout. The watershould be clean and fit for drinking.
3.o4 The consistency of the grout must be verystiff. The sand and cement should be
thoroughly mixed in a dry condition and then watershould be added sparingly so that the mixtureretains a granular appearance. Grout of the properconsistency will form a lump when squeezed inthe hand, and the lump will crumble freely whendisturbed.
3.o5 Grout should be forced under the baseplatefrom all sides, and should completely fill all
voids. The wedges should then be removed, andthe void left by removing the wedges should befilled immediately with additional grout. The groutshould be beveled as illustrated in Fig. 1.
4. TEMPORARY WARNING LIGHTS
4.o1 The rules of the FCC and FAA require thattemporary warning lights be placed on any
tower which is required to have permanent airobstruction warning lights. The number of sets( or levels) of temporary lights required will bethe same as the number of levels of permanentlighting. Where two or three levels of permanentlights are required, only one temporary set of lightsis required (at the top) until the level of the firstpermanent lights is exceeded. Temporary lightsshould then be installed at approximately the levelof permanent lights and, in addition, a set oftemporary lights is always required at the uppermostpoint of the structure. Even on towers requiringonly one level of permanent lighting, a set oftemporary lights is required at the top of the
structure, and this applies even though only onesection of the tower may have been erected bysunset.
4.02 Temporary lights are to burn steadily fromsunset to sunrise. Top lights are to consist
of two 100-, 107-, or 116-watt lamps (A21/TS)enclosed in aviation red obstruction light globes.Two similar lights are required at each level wherepermanent lights are to be installed. (Permanentlights may be used in lieu of temporary lights. )All side lights are to be positioned so at least oneof the two lights at each level will be visible fromany angle of approach. Many contractors havetemporary warning lights for use during erection,but it is advisable to notify them if temporarylighting will be required, and whether it will beone-, two-, or three-level.
5. ERECTION CONSIDERATIONS
5.o1 Erection of steel towers is usually perforr,edby contractors rather than by Telephone
Company personnel. It should be noted that thecontractor is responsible for the job and for theconstruction methods he chooses to use, and ispresumably the best judge of the condition of hisequipment and the loads which it can handle.However, the Telephone Company representativeshould assure normal safeguards and require thecontractor to correct any obviously dangerous itemssuch as frayed winch lines and ropes.
5.02 The general appearance of the base of thetower is shown in Fig. 2. Note the use of
12-inch channels in the base, and 8-inch channelsfor internal bracing. Four bolts connect the towerbaseplate to the flange of each 12-inch channel. Awasher is placed under the head of each bolt, inaddition to the one used under the nut (Fig. 3).
5.o3 Most structural members of the tower areformed of angles. Legs are 60-degree angles;
lacing and horizontal bracing are all 90-degreeangles. Note that the legs are double-laced with1-1/2 by 1-1/2 by l/8-inch angies, ie, cross-braced,except for the top section. This is a tension-compressionsystem and to get the maximum strength out ofthese small angles, they are bolted together at
Page 3
\
SECTION 760-925-~
E
LEG
12 IN. ANGLE
CHANNELS
COMPLETE BASE OF TOWER
8 IN. CHANNEL
PLATE
WER BASE
ATE
INTERNAL BRACING OF TOWER BASE
Fig. 2—Base of Tower
the point where they cross. On a given face,since one set of lacing angles is bolted to the insideof the legs and the other is bolted to the outside,angles which cross each other are separated bythe thickness of the leg members. As shown inFig. 4, a spacer washer must be installed to avoidthe bending of these angles which would result ifthey were bolted together without the spacer inplace. Double washers are required at one locationin the top section as discussed in 5.22.
s.04 It is general practice for contractors toassemble the tower sections on the ground,
with the associated splice plates attached looselyat the top of each leg. The lower diagonals areusually left loose to facilitate lining up holes whenthe section is put in place. The sections shouldbe inspected for such items as correct assembly,spacer washers, tightness of bolts, etc. All boltsshould be equipped with a plain washer, hex nut,and PALNUT.
FliEx tiEAO BOLT
BEVELED SURFACE
FLAT SURFACE
‘ExHEAoNu”@9‘ALN”T-Q9
Fig. 3—Use of Washer
5.05 Contractors will vary in the exact mannerin which they assemble the tower. Usually
the bottom section, and sometimes the two bottomsections, are bolted together on the ground andlifted onto the baseplate. Because of the ball-and-socket type of connection to the base pier, it isnecessary to use temporary guys to prevent thetower from overturning. Selection of the size andtype of temporary guys is the responsibility ofthe erection contractor. Temporary guys are tobe moved up with the tower so there is nevermore than one section (20 feet) extending abovethe levelintendedused for
of the temporary guys. Gu@-strandfor permanent gugs should not be
temporary gugs.
Page 4
1ss 1,SECTION 740-925-330
Q--.=-,,.,
LACINGANGLES
‘EXHEAD NUT+
“’’”’-69Fig. 4—Use of Space Washers
s.06 As soon as the first section (or sections) isin place and stabilized with temporary guys,
the grounding connections should be established.Each of the three 12-inch channels in the base ofthe tower has two 9/16-inch holes for a l/2-inchmachine bolt. Only one hole in two of the threefaces is used. The ground wire is secured undera grooved washer which is held in place by thel/2-inch machine bolt. Since the wire is tinnedcopper and the baseplate is galvanized, the presenceof water in the joint will cause galvanic actionbetween the dissimilar metals. The bolt shouldbe drawn up tightly and painted with hot pitch orother waterproofing material in order to preventthis galvanic action.
s.07 Permanent guys should be installed at theirappropriate level and correct tension as soon
as the tower reaches the height at which they arerequired. The structure should be made plumbbefore adding any more sections. Guy strand is
furnished in quantities sufficient to make up allguys with each anchor on a minus 6-degree(ground) slope, ie, a drop of about 10-1/2 feet perhundred feet.
5.08 The E Guyed Tower uses four differentsizes of guy strand as follows:
DIAMETER WEIGHT/FOOT ULTIMATE STRENGTH(INCHES) (LBS) (LBS)
1/2 .504 26,7009/16 .637 33,7005/8 .796 40,2003/4 1.155 58,300
The 80-, and 100-foot towers employ only one sizeof guy strand (9/16 inch); all other heights usetwo sizes of strand. Fig. 5 and 6 show the sizeand location of guys for all sizes of towers.Information on guy tensions is contained in Part 6of this section.
5.o9 A typical setup for erecting guyed towersis shown in Fig. 7. The gin pole is mounted
on one face of the tower and is fastened at twopoints The use of a wooden gin pole for erectingtowers is not recommended. The bottom of thegin pole is usually hung by two short lengths ofcable, shackled to each leg (Fig. 7A). The lowercables support the dead load of the gin pole plusthe loads imposed by hoisting. The upper set ofshackles (Fig. 7B) serves to support the gin polein a vertical position. Normally, the lengths ofboth sets of shackling cables are calculated so thatthe pole will not deviate from a vertical plane bymore than 10 degrees. This restricts the bendingmoment imposed on the tower and the gin pole.
5.10 Usually a gin pole will extend about 2 or 3feet above the top of the hoisted section.
This is necessary in order to provide headroomwhen a section is being set in place. The top ofthe gin pole is equipped with a pivoted head.When a section is being hoisted, the top of thegin pole will lean out to the limit of its top shackles.When the section reaches the upper block, hoistingis halted and the section is pivoted (Fig. 7, Sec. A-A)around the pole. With this transfer of weight,the top of the pole will kick-in, and the bottomwill kick-out. This action will put the center ofthe hoisted section near the center of the tower,and it can be lowered into place and bolted. It isrecommended that all bolts be installed and tightenedbefore progressing.
Page 5
SECTION 760-935-330
NOTE:
ALL TOP SECTIONS ARE IO EN TICALLEGs ARE 4X4X 5/161N.
5/8 INGUYS
9/16 IN.GUYS
65
Y “ ““
SIZE
OF LEG 3ANGLE y
\:
x
~
L .
9/16 INGUYS
2*>xN.
Tmxw.—
80 I00
N.
‘Tm
I20
Y’
40
\1/2 IN.
GUYS
5/8 IN.GUYS r
I 40 160
T’
$(1/2 INGUYS
4
80
180
‘!l/2”lN.GUYS
Fig. 5—1 80-Foot and Smaller Towers
Page 4
5/8 IN.GUYS
h
r
z—*>xN\7mxN\
Tm
I
1
/
SIZE
OF LEGANGLE +
\-
—*.
xexv
L,
200
NOTE:
ALL TOP SECTIONS ARE IDENTICAL
LEGS ARE 4 X 4 X 5/161N.
r
3/4 IN
GUYS
\Y
185
T
T
\
9/16 INGUYS /
220
205
T
120
\
\9/16 IN
GUYS
;0
\
\
1/16 IN,GUYS
: 73/4 IN,GUYS
3/4 IN.GUYS
r
225 g
*
7
>
xN\7m
2
:
xN>
ILx
I 40
:
h ‘f9/161N,GUYS
t-
/— \60
2
: r9/16 IN,
x GUYS*x*
L—_
240
xN>
!.! t
—
/ –
/ —
260
3/4 INGUYS
245
\
160
\
\9/16 IN
GUYS
Y
9/161N.GUYS
I
1ss 1,
3/4 INGUYS
\
265
160
‘\9/16 IN
GUYS
80
‘ \
9/161NGUYS
280
SECTION 760-925-330
285
T : ‘
~
*>
xN\
710xN>
1
y
L -
/ —180
‘19/16 INGUYS
I
I
z’—a<‘ax*x*
I
/—80
~‘ \
9/161N
GUYS
IL_
300
Fig. 6—200- to 300-Foot Towers
Page 7
SECTION 760-925-3~
SECTION A-A
Fig. 7—Typical Gin Pole Setup for Hoisting Tower Sections
s.1 I The gin pole is then raised to the nexthighest position, and the next section installed.
Normally, antennas or reflectors are hoisted onlyafter the tower is completely erected, all permanentguys have been installed at their proper tension,and the tower plumbed.
5.12 The gin pole method, when properly used,is capable of hoisting any single assembled
tower section, System Standard antenna or reflector(or comparable weights) without exceeding thedesign criteria of the tower. There are othersatisfactory construction methods used, such as
boom cranes, which are used quitecontractors erect supplementaryon the site for use in hoisting tower sections andequipment items.
frequently. Someportable towers
5.13 The ends of the guys are made up withpre-formed guy grips (Fig. 8), which are in
turn connected to the tower and to their respectiveturnbuckles. Care should be taken to install thesegrips properly so that the full strength of theconnection is developed. If it is necessary toremove the grip from the strand, it should bediscarded and not re-used.
Page 8
1ss 1, SECTION 760-925-330
PRE-FORMEO GUY GRIP
HEX JAM NUT
TURN8UCKLE
3/8 IN.\
TOWER BOLTS <
NuMBER OF UNUSECHOLES IN SPLICEPLATE VARIES WITHSIZE OF LEG—
Fig. 8—Lower End of GuySTANDARDSPLICE PLATE-
5.14 The tower is erected by joining abuttingleg angles using bolts and splice plates. For
economy in fabrication, only two sizes of spliceplates are used. One is 1-1/2 inches wider thanthe other, and has an extra hole for a step bolt.Both plates are the same length and each providestwo groups of seven bolt holes. Fig. 9 shows thestandard plate used at all leg splice locations wherestep bolts do not occur.
5.15 Bolt requirements at leg splices are asfollows:
LEG SIZE(INCHES)
4x4x5/16
4x4 xl/4
3-1/2 X 3-1/2X 1/4
3x3 xl/4
NO. OF BOLTS AT EACH END(EACH SPLICE PLATE)
7
6
5
4
2-1/2 IN,
2-1/2 IN.
/4 IN
/
f
7/8 IN
\
o
/’-’-”
“T2-3/4 IN,
4
2- 1/2 IN
‘t
2-1/2 IN
4
2-1/2 IN.
)
20-1/4 IN.
Pig. 9—Standard Splice Plate
Page 9
SECTION 760-925-330
Note that only the largest size leg members useall fourteen bolt holes, while the smallest size legsare spliced with only eight bolts, thus leaving sixunused holes in the splice plate. A11 holes inleg members must contain bolts at splices. Alltop sections are made with 4- by 4- by 5/16-inchangles, regardless of tower height. Details on sizeof leg members in other parts of these towers areshown in Fig. 5 and 6.
5.16 Members which have been bent or buckledshould be replaced. Occasionally it will be
found that holes do not line up closely enough topermit bolting without drifting of holes. There isno objection to removing excess zinc (galvanizing)which may have unduly reduced hole size. iMemberswhich cannot be joined without further fieldfabrication should not be installed without checkingdimensions to determine the nature of the mistakein fabrication. Members which are merely too longmay be cut to proper length, provided distancesbetween bolt holes are correct and edge distanceswill be correct after cutting. Grinding may bepermitted in lieu of cutting; cutting by torch shouldnot be allowed.
5.17 Freshly cut surfaces, or any surface wheregalvanizing has been damaged should be
painted immediately. The best protection is probablyprovided by the zinc-rich type of paint. Thesepaints are 90 percent (or more) powdered zinc andwill provide some galvanic protection in the samefashion as galvanizing. They also have the propertyof preventing rust from creeping under the paintfilm. They should not be applied to steel whichis damp or wet, or coated with mud, oil, grease,mill scale, bird droppings, etc. To be effective,paint of this kind should not have a spreading ratewhich exceeds 350 square feetigallon. If this typeof paint is not available, zinc oxide—zinc dustpaint—is an acceptable substitute. It should beapplied over clean, dry metal and should conformto Federal Specification TT-P-641O Type I or Type H.
5.18 The tower has a series of 9116-inch holesspaced 16 inches apart on alternate sides of
one leg to accommodate step bolts which provideaccess to the structure. All step bolts are to beinstalled with a plain washer, a hex nut, and aPALNUT. Step bolts usually extend from thebottom of the tower to a point 5 feet above thegrating platform at the lower end of the top section.However, they may be omitted in the bottom 8
feet of the tower to discourage unauthorized climbing.This precaution is unnecessary if the tower baseis surrounded by a fence with a locked gate.
5.19 Each leg member has also been punchedwith three 9/16-inch holes in the same flange.
Facing the tower, these holes are on the right legof the tower face, are located 3, 13, and 18 feet,respectively, above horizontal bracing members ofeach panel, and have been provided to accommodatewave guide restrainers. These holes will normallybe left unfilled unless wave guide is to be installedon the tower.
5.2o An extra hole is provided in each leg ofthe tower to accommodate a 6M safety
strand. (See Section 081-725-200. ) These holes arelocated 4 feet above the horizontal bracing membersin all but the top panel. The strand is ordinarilyused only at the level having side obstructionlights, and is intended to provide protection forworkmen who have occasion to service those lights.
5.21 A platform consisting of three pieces of steelgrating (16 by 32 inches) is provided at the
lower end of the top section in all towers. Eachpiece of grating is fastened in place by four gratingclips equipped with 3/8- by 1-3/4 inch bolts withnuts, washers, and PALNUTS. The generalappearance of the platform is shown in Fig. 10.
5.22 The general appearance of the top sectionis shown in Fig. 11, which also shows the
location of mounting holes used with various kindsof radio equipment. Note that the second horizontalmember above the star mount is skewed, ie, nothorizontal. This is deliberately done to accommodatethe backstay of 8- and 10-foot parabolic antennas.Note also the requirement for double spacer washersat the crossing of the lacing angles marked A-A.
6. GUY TENSIONS
6.01 Measurement of guy tensions should beundertaken only under relatively calm or
windless conditions. Since ambient temperatureshave an appreciable effect on tension, Tables A,B, C, and D show the correct tension (T), and thecorresponding time (S) for 20 oscillations at differenttemperatures for the four sizes of guys. Tensionsshould be set within +5 percent of the specifiedvalues.
IPage ~0
1ss 1, SECTION 760-925-330
APPROX 4 FT
— 2 “ 8 ‘N”~I
[I FT 4 IN, P/’a
GRATING CLIP
STEP BOLTS
Fig. 10—Tower Platform
6.02 It may be desirable to use a greater numberof oscillations to improve the accuracy of
measurements. This may be done by adjustingthe indicated time in proportion to the oscillations,eg, time for 30 oscillations would be 1-1/2 timesthe value for 20 oscillations.
6.03 The formula for determining the elapsedtime for any number of oscillations for any
length of guy of any material at any tension is:
S = 0.352 NL m
where
S = time in seconds
N = number of oscillations
L = length of guy in feet
W = weight of guy in pounds per foot
T = tension of guy in pounds
Page 11
SECTION 760-92$=
MOUNTING PLATE FOR AIR OBSTRUCTION LIGHT
/
/
4
HOLE5 FT
I
~ PLATES FOR REFLECTORMoUNTING BRACKETS
HoLES FOR REFLECTOR’
PIPE BRACKET
HOLES FOR PIPEBRACKETS OF 8 FTANO 10 FT ANTENNAS
\ sTAR MOUNT
Fig. n-location of Mounting Holes for Equipment
Page 12
1ss 1, SECTION 760-925-330
Since the design tension is given, the formula forthe time for a predetermined number of oscillationswill reduce to:
S = KL
where
S = time in seconds
K = a constant, (0.352 NF
‘T)
L = length of guy in feet
Tables A, B, C and D also show the values of Kfor the specified tension at each temperature range.‘l’able E shows the length of the oscillating sectionof the guy for each height of tower on leoelground.
6.04 If there is a difference in ground elevationbetween the location of the pier and the
anchors, the length of the oscillating section willhe different from the values shown in Table Eand the time periods shown in Tables A, B, C,and D will not apply. In the case of top andmiddle guys, each foot of elevation difference will
;ause a difference of 1.41 feet in the length ofthe guy. In the case of bottom guys, each footof difference in elevation will cause 2.0 feet of
difference in the length of guy. The lengths shownin Table E should be increased if the groundelevation at the anchor location is lower than theground elevation at the base pier, and decreasedif the ground elevation at the anchor is locatedabove the ground elevation at the base pier. Thelength of oscillating section, as adjusted for differencein elevation, should then be multiplied by the Kfactor (corresponding to the height of tower, guysize, and temperature involved) to obtain the time,S, for 20 oscillations.
6.05 The tower should be checked to see that itis plumb after the correct guy tensions have
been reached. It is preferable to make observationsfor plumbness with the aid of a transit. Thetower should not deviate from vertical by morethan its total height divided by 720. The maximumallowable deviation between guy points is obtainedby dividing the distance between the two guypoints by 720. Section AG25.300 discusses proceduresfor observing tower plumb and bow.
6.o6 After the tower has been plumbed and thecorrect guy tensions have been set, the jam
nuts of the turnbuckles should be tightened. .%a further means of discouraging tampering, turnbucklesat any anchor may be locked together by a loopof strand. This precaution is unnecessary if theanchors are enclosed by fences with locked gates.
Page 13
TABL
EA
—TI
ME
FOR
20O
SCIL
LATI
ON
SIN
SEC
ON
DS
1/2
-lNC
HG
UY
S TOW
ERH
EIG
HT
180
FEET
(L:S
) ‘-”1
‘--s
(SEC
)
120
FEET
220
FEET
I16
0FE
ET14
0FE
ETTE
MPE
RATU
RE
T(L
BS)
s(S
EC)
11.4 8.8
11.6 9.0
11:8 9.2
1~.) 9.5
12.2 9.8
12.5
”-
10.1
K(1
:S)
——
.071
649
20
——
.073
946
10—
.—
—
.076
343
10
——
,079
040
00
——
.082
136
90
(S:c
)
— 11.3 . 11.6
. 12.0
— 12.5
— 13.0 .
—— 13.6 — 14.4
KT
(LBS
)
— 4880
(1:S
)
—K
Ks
[SEC
)K
s(S
EC)
— M L M L M L M L M L M L M L —
1
.067
1
.065
3
.068
3
.067
0
.069
4
.068
7
.070
7
.070
7
.072
0
.072
8
.073
4
.075
1
——
4870
13.2
Bel
ow–1
0°
—10
°to
+10°
10°
to30
°
30°
to50
”-’
5540
5860
5360
5570
5180
5290
5000
5000
4820
4710
4640
4430
4460
4140
—— 0713
— 10.0
— 10.3
— 10.7
— 11.0
—
,071
5
— 4940 — 4630 — 4310 — 4000
—
3690 — 3370 — 3060
.071
18.
1
— 8.3
—
—,-
-_:
——
,073
9
—
,076
3
—
,079
0
—
,082
1
—
,085
5-—
—
,089
5
— 0736
—
0761 —
,079
0
— 4580 — 4290 — 4000
.073
545
8013
.6—
—
.076
18.
642
9014
.1
— 14.6
—
.079
09.
0
— 9.3
4000 — 3710
——
50”
to70
°— 08
23
— 0858
——.
——
,091
1
— 3710
— 11.5
— 12.0
— 12.5
.082
315
.1
—70
°to
90°
— 9.8
—
“-+”
-— —
.085
533
90
——
.089
330
10
— 3420
.086
134
2015
.8
12.7
10.4
.074
8.0
777
Abo
ve90
°—
— 1120
— 16.5
.090
310
.331
30
dK
=.3
52N
:f
=4.
998/
T
,---
--
M=
Mid
dle
Gu
ysL
=L
ower
Gu
ys
TA
BLE
B—
TIM
EF
OR
20O
SC
ILLA
TIO
NS
INS
EC
ON
DS
9/16
-lNC
HG
UY
S
TO
WE
RH
EIG
HT
—.
.
TE
MP
ER
AT
UR
E28
0F
EE
T26
0F
EE
T24
0F
EE
T20
0F
EE
T10
0F
EE
T80
FE
ET
——
—
KK
‘K(1
:S)
(S:c
)(1
:S)
K(S
:c)
K(1
:S)
(sic
)(1
:S)
K(S
:c)
(1:S
)(S
:c)
(1:s
)(S
:c)
u—
——
——
——
——
——
—46
809.
9.0
821
4680
7.6
.082
1B
elow
–10°
M76
8014
.5.0
641
6680
15.5
.068
766
8013
.6.0
687
——
——
——
——
—
L80
9011
.2.0
625
7090
11.9
.066
771
5010
.1.0
665
7090
13.5
.066
7—
——
——
—
u-
-—
—-
—‘—
-—
——
“‘-—
-“4
450
10.1
”.0
842
4450
7.F
.084
2–1
0°to
+10°
M74
5014
.7.0
651
6450
15.8
.070
064
5013
.9.0
700
——
——
——
——
—
L77
3014
.4.0
640
6730
12.3
.068
567
7010
.4.0
683
6730
13.9
.068
5—
——
——
——
u—
——
——
--’”
——
--—
“—
“‘-
--—
4230
10.4
.086
442
307.
9.0
864
10°
to30
°M
7230
14.9
.066
162
3016
.1.0
712
6230
14.1
.071
2—
——
——
——
——
L73
6011
.7.0
655
6360
12.6
.070
563
8010
.7.0
703
5360
15.6
.076
7—
——
——
—--
u—
-—
-—
——
--
-“‘-
—‘—
—46
0610
.7.0
888
4000
8.2
.088
830
”to
50°
M70
0015
.2.0
672
6000
16.4
.072
560
0014
.4.0
725
——
——
——
——
—
L70
0012
.0.0
672
6000
13.0
.072
560
0011
.0.0
725
5000
16.1
.079
5—
——
——
—
u—
—-
——
—--
——
-—
——
‘“”37
7011
.0.0
915
”-’3
770
8;4
:091
550
°to
70°
M67
7015
.4.0
683
5770
16.7
.074
057
7014
.6.0
740
——
——
——
——
—
L66
4012
.3.0
690
5640
13.4
.074
856
2011
.4.0
750
5640
15.2
.074
8—
——
——
——
._—
-U
—-
——
—‘“—
—‘-
“-—
——
—35
5011
.3.0
943
3550
8.7
.094
370
°to
90°
M65
5015
.7.0
694
5550
17.0
.075
455
5014
.9.0
754
——
——
——
——
—
L62
7012
.7.0
710
5270
13.9
.077
452
3011
.8.0
777
5270
15.7
.077
4—
——
——
—
u-
—‘~
——
——
--—
——
—-
—33
201“
1.7
.097
533
209.
0.0
975
Abo
ve90
°M
6320
16.0
.070
753
2017
.4.0
770
5320
15.3
.077
0—
——
——
——
——
L59
1013
.1.0
731
4910
14.4
.080
248
5012
.3.0
807
4910
16.3
.080
2—
——
——
—I
U=
Upp
erG
uys
M=
Mid
dle
Gu
ysL
=L
ower
GU
yS
4-””
K=
.352
N~
d---
z.5
619/
T
u!
.
wI
m n .. =T
AB
LEC
—T
IME
FO
R20
OS
CIL
LAT
ION
SIN
SE
CO
ND
So z
5/8-
lNC
HG
UY
Sw m ? ~
TO
WE
RH
EIG
HT
180
FE
ET
..
..
...
.
160
FE
ET
—.
T“”12
0F
EE
T_.
— K
.-7
— —. K
0903 — — 0930 . — 0960 — — 0993 — — 1030 — — 107
1— — 111
7— —
300
FE
ET
200
FE
ET
T
1“s
(10S
)(S
EC
)
140
FE
ET
(1:s
)(S
:c)
4840
16.0
—.
——
4560
16.5
——
——
428~
17.0
——
——
4000
17.6
——
——
3720
18.2
——
——
3440
19.0
-—
——
—
316
019
.8—
——
—
TE
MP
ER
AT
UR
E
s(L
:S)
(SE
C)
.4!3
4021
.0—
——
—
-456
021
.7—
——
—
‘Izgo
~~
.4—
——
—
4000
23.1
——
——
37~o
24.o
——
.—
344
025
.0—
——
—
316
026
.0—
——
—
K(1
:s)
K
.090
3— —
.093
0— —
.096
0— —
,099
3— —
.103
0— —
.107
1— —
.111
7— —
(S:c
)K
SI(S
EC
)
18.5
— .— 19.1 — — 19.7 — — 20.4 — — ~1.1
— — ~~
,()
— — 22.9 — —
(S:c
)
+
K
og~
~
— — 08.4
2— — 0864 — — 0888 — — 0914 — — 0943 — — 0974 — —
T(1
0s)1
(LB
S)
i
u M L u M L u M L u M L u M L ~ M L u M L~
0903
4840
13.5
— —
0903
4840
5840
21.5
——
——
5560
22.1
——
——
5280
22.6
——
——
500-
623
.3—
——
—
4720
24.0
——
——
4440
24.7
——
——
416(
)25
.5—
——
—
— 8840
‘341
O
— 8560
8940 — s~so
8470 — 8000
!300
0
— 7720
7530 — 7440
7060 — 7160
6590
— 17.0
12.8
— 17.3
13.1
— 17.6
13.4 — 17.9
13.8
— 18.2
14.3
— 18.6
14.7 — 18.9
15.2
—
.066
8,0
647
.——
.067
9.0
664
—
.069
0.0
682
—
0702
0702 —
,071
5,0
724
—
.072
8.0
748
—
.074
2.0
774
Bel
ow–1
0°—
——
——
——
‘456
009
3013
.9 — — 14.3
— —
0930
4560
–10°
to+1
0”—
——
——
4280
0960
—09
6042
80
10°
to30
°—
——
——
—
0993
0993
4000
14.8 — —
—40
00
30°
to50
°—
——
—— 10
30
—— 1030
15.3 — — 16.0 — — 16.6 — —
3720
50°
to70
°—
——
——
—
3440
3440
1071
1071
70°
to90
°—
——
——
——
—
1117
1117
3160
Abo
ve90
0—
——
——
——
—
d“-
TL
nL
ower
Guy
sU
=U
pper
Gu
ys
\
TA
BLE
D—
TIM
EF
OR
20O
SC
ILLA
TIO
NS
IN
3/4-
lNC
HG
UYS
SE
CO
ND
S
TO
WE
RH
EIG
HT
260
FE
ET
TE
MP
ER
AT
UR
E1-
--3“
“ET
28G
FE
ET
240
FE
ET
T(1:S
)(S
:c)
7200
28.4
*
(S:c
)K
—K
I(1:S
)(1
:s)
(S:c
)(1
:S)
IIK
(sic
)
Bel
ow—
10°
+1-
U92
00
–10°
to+1
0°u
–88
00
31.8
.078
982
0031
.3.0
836
.085
7
.088
0
.090
4
.093
1
.096
1
.099
3
7200
6800
1=30.9
31.7
32.7
33.4
.089
2
32.5
33.3
6800
@E
.080
778
0032
.1.0
918
640@
–—
—64
00
6000
8400
.082
674
0033
.0.0
946
8000
34.1
35.0
.084
670
0033
.9.0
977
50°
to70
°m
i-70
°to
90°
“u
7600
.086
866
0034
.9
$+5600
35.0
.101
1
5200
36.3
.104
9
4800
37.8
‘:10
92
——
—.—
520-
7200
35.9
37.0
.089
262
0036
.0
Abo
ve“-
7---
90°
uT
!!!!IE ,——
—68
00.0
918
5800
37.3
.109
2I
3800
I35
.61.
1227
UE
Upp
erG
uys
. .
SECTION 760-92S
TABLE E — APPROXIMATE LENGTH OF GUYIN OSCILLATION — LEVEL GROUND
TOWERHEIGHT
(n)
80
100
120
140
160
183
200
220
240
260
280
300
To?GUYS
(Fl)
92
120
149
177
205
233
262
290
318
346
375
403
BOTTOMGUYS
(Ft)
—
—
114
140
158
185
203
134
152
179
179
197
MIDDLEGUYS
(FT)
—
—
—
—
—
—
—
170
198
227
227
255
page 1818 Pages