dynamic var planning

Upload: anonymous-ngxdt2bx

Post on 04-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Dynamic VAR Planning

    1/31

    DYNAMIC VAR PLANNING IN A LARGE POWERSYSTEM USING TRAJECTORY SENSITIVITIES

    1September 5, 2009

    by

    Bishnu Sapkota

    Advisor : Vijay Vittal

    Arizona State University

  • 7/30/2019 Dynamic VAR Planning

    2/31

    Outline

    Background

    Objective

    Load modeling for voltage stability studies

    Corrective measures for voltage stability

    Dynamic VAr Planning

    Study results

    Conclusions

    2

  • 7/30/2019 Dynamic VAR Planning

    3/31

    Background

    Power system stability- The ability

    of an electric power system,

    operating at a given initial condition,to regain a state of operating

    equilibrium after being subjected to

    a physical disturbance, with most of

    the system variables bounded, sothat practically the entire system

    remains intact.

    Voltage stability - ability of a power

    system to maintain steady voltagesat all the buses in the system afterdisturbance.

    3

    Fig.1 Classification of power system stability

  • 7/30/2019 Dynamic VAR Planning

    4/31

    Background Based on actual incidents, short term voltage stability has been an

    increasing concern in power industry

    The short term voltage stability problem may arise in two forms. Slow voltage recovery

    Fast collapse

    Several events that have occurred and recent industry work mainly

    deal with slow voltage recovery following short circuits with stalling

    and slow tripping of residential air conditioner compressor motors

    However, the fast voltage collapse has not been addressed in the

    literature

    VAr planning using static criteria are well established.

    The suitability of dynamic reactive power source is another subject

    which has drawn significant attention regarding the fast voltage

    collapse4

  • 7/30/2019 Dynamic VAR Planning

    5/31

    Objectives of the study

    Fast voltage collapse problem associated with the fault on the bulkpower network in presence of significant induction motor loads

    Dynamic VAr planning methodology based on trajectory sensitivity

    analysis

    Comparison of efficacy of SVC and STATCOM to prevent fastvoltage collapse

    5

  • 7/30/2019 Dynamic VAR Planning

    6/31

    Voltage stability causes and analysis

    Causes of voltage instability Increase in loading

    Generators, synchronous condensers, or SVCs reaching reactivepower limits

    Tap-changing transformer action

    Load recovery dynamics Tripping of heavily loaded lines, generators

    Methods of voltage stability analysis Static analysis methods

    Dynamic analysis methods

    6

  • 7/30/2019 Dynamic VAR Planning

    7/31

    Load characteristics

    The accuracy of analytical results depends on proper modeling of

    power system components, devices, and controls

    Loads are most difficult to model

    Complex in behavior varying with time and location

    Statistical in nature, and consists of a large number of continuous and discrete

    controls and protection systems

    Dynamics of loads, especially, induction motors at low terminal

    voltage should be properly modeled

    7

  • 7/30/2019 Dynamic VAR Planning

    8/31

    Induction motor characteristics

    Impact of fault on transmission

    grid

    Depressed voltages at distributionfeeders and motor terminals.

    Reduction of electrical torque by the

    square of the voltage resulting in

    slow down of motors.

    The slow down depends on the

    mechanical torque characteristics

    and motor inertias.

    With fault clearing

    8

    Partial voltage recovery Slowed down motors draw high reactive currents, depressing voltage magnitudes

    Motor will reaccelerate to normal speed if, electrical torque>mechanical torque

    Else, the motors will rundown, stall, and trip

    The problem is severe in summer time period with large proportion of air conditionermotors

    Speed per unit

    Electric

    torque

    1.0

    Current

    Mechanical

    torque

    1.0

    5.0

    Torqu

    eor

    currentperuni

    t

    Fig. 2 Induction motor characteristics

  • 7/30/2019 Dynamic VAR Planning

    9/31

    Air conditioner motor characteristics

    Characteristics

    Main portion (80-87%) consumed by air compressor motor

    Electromagnetic contactor drop out between (43-56%) of the nominal

    voltage and reclose above drop out voltage

    Stalling at (50-73%) of the nominal voltage

    Thermal overload protection act if motors stall for 5-20 seconds The operation time of TOL (Thermal Over-load) protection relay is

    inversely proportional to the applied voltage at the terminal

    Air conditioners should be modeled to analyze the short term

    voltage stability problem Quite important for utilities in the Western interconnection

    9

  • 7/30/2019 Dynamic VAR Planning

    10/31

    Load modeling

    Old models

    Loads are represented as lumped

    load at the distribution feeder The diversity in composition and

    dynamic behavior of various

    electrical loads is not modeled

    WECC interim model 20% of the load as generic

    induction motor load

    80% constant current P and

    constant impedance Q

    Composite load model

    Representation of distribution

    system equivalent

    Parameters of various load

    components

    Substation

    Capacitor

    Transmission Bus

    Bus 1

    Bus 2

    Distribution Bus

    OLTC

    LM SM DL EL IL

    Distribution FeederBus 3

    Distribution

    Capacitor

    10Fig.3 Composite load model structure

  • 7/30/2019 Dynamic VAR Planning

    11/31

    Corrective measure- Static VAr

    compensator (SVC) Variable reactive power source

    Can generate as well as

    absorb reactive power Maximum and minimum limits

    on reactive power output

    depends on limiting values of

    capacitive and inductivesusceptances.

    Fixed capacitor with thyristor

    controlled reactor model is

    used.

    Droop characteristics of 2%

    over the control range is used.

    11

    CFixedCapacitor

    Transformer

    TCR

    XC

    XL

    Vref

    VXSL

    I

    Fig. 5 V-I Characteristics of SVC

    Fig. 4 Schematic diagram of an SVC

    V

    I

  • 7/30/2019 Dynamic VAR Planning

    12/31

    Corrective measure- Static compensator

    (STATCOM)

    Voltage source converter device

    Alternating voltage sourcebehind a coupling reactance

    Can be operated at its full output

    current even at very low voltages

    Depending upon manufacturer's

    design, STATCOMs may have

    increased transient rating both in

    inductive as well as capacitive

    mode of operation.

    PI controller to regulate the

    voltage and a droop

    characteristics of 2% over thecontrol range is used. 12

    VT

    ILmax ILTICmaxIICT

    InductiveCapacitive

    Transformer

    DC-AC switching

    converter

    I

    X

    System bus

    Cs

    Vdc

    E

    Fig. 6 Schematic diagram of STATCOM

    Fig. 7 V-I Characteristics of STATCOM

    VT

  • 7/30/2019 Dynamic VAR Planning

    13/31

    Trajectory sensitivity Why?

    The influence of parameters on the non-linear, non-smooth

    behavior exhibited by a disturbed power system is difficult toexplore

    Normal linearization techniques involving linearization of system

    model about an operating point are not very useful

    What?

    Based on linearizing the system around a trajectory rather than

    around an equilibrium point

    Change in trajectory due to small change in parameters isobserved

    13

  • 7/30/2019 Dynamic VAR Planning

    14/31

    Dynamic VAr planning

    The analytical description of power system is given by

    The flows of x and y can be defined as,

    Sensitivities of the system flow to the parameters are,

    14

    ),,( Oyxfx

    ),,(0 Oyxg

    ),,()( OI txtxox

    ),,()( OI txtyoy

    OOO

    O''

    w

    w' )()()( txtxtx

    OO

    O

    O''

    w

    w' )(

    )()( ty

    tyty

    (5)

    (6)

    (7)

    (8)

    (9)

    (10)

  • 7/30/2019 Dynamic VAR Planning

    15/31

    Dynamic VAr planning

    A simple numerical procedure is used to evaluate these

    sensitivities

    These sensitivities are calculated along the trajectory, and arecalled trajectory sensitivities

    Sensitivities of the change in bus voltage magnitudes to thereactive power injection at a given bus are calculated, where Vis one of the output variable represented by y, and reactivepower Q is one of the parameters represented by O

    15

    O

    OIOOI

    OO

    '

    '|

    w

    w

    ),,(),,( txtxxx oxox

    OOIOOI

    OO

    ' '|ww),,(),,( txtxyy oyoy

    (11)

    (12)

  • 7/30/2019 Dynamic VAR Planning

    16/31

    Dynamic VAr planning

    The trajectory sensitivity index (TSI) proposed in this work isdefined as,

    Wk is the weighting factor to designate the importance of the

    time instant k and Wbi is the weighting factor to represent theimportance of bus ion the sensitivity calculation

    If the voltage collapse is local in nature, then there will only be asmaller number of buses with non-zero W

    bi. The selection of

    the weights Wk

    depends upon the type of voltage instabilitybased on time frame of interest

    The bus with the highest trajectory sensitivity index is selectedas a candidate bus for dynamic VAr support

    16

    w

    w

    k

    k

    tt

    n

    i

    j

    i

    bi

    N

    kkj

    Q

    VWWTSI

    11(13)

  • 7/30/2019 Dynamic VAR Planning

    17/31

    17

    System description and tools

    Component Number

    Buses 14585Plants 1938

    Generators 1842

    Shunts 1179

    Lines 11655

    Transformers 4384

    Phase Shifters 59

    Converters 8

    Component Number

    Buses 581Plants 37

    Generators 32

    Shunts 39

    Lines 614

    Transformers 74

    Phase Shifters 0

    Converters 0

    System components Study subsystem components

    Number of 12.5 kV feeders in the subsystem = 375

    Following tools have been used in this study

    Dynamic security analysis tools PSAT,VSAT, and TSAT PSLF, Matlab

  • 7/30/2019 Dynamic VAR Planning

    18/31

    Load modeling

    Composite load model consisting of

    static and motor loads is used.

    The percentage of motor load (bothmegawatts and MVAr) at each

    distribution substation is about 72%

    of the total load at that substation.

    The induction motors are classifiedas,

    Small motors - Low inertia motors

    Large motors - High inertia motors

    Trip motors - Low inertia motors with theoption of tripping under low voltage

    condition

    18

    Fig. 8 Detailed load modeling sample at

    representative bus

    Static

    LoadLM STSM

    69 kV Bus

    DistributionTransformer

    12.5 kV Bus

    The percentages of small, large, and trip motors at each bus are

    63, 10, and 27 respectively.

  • 7/30/2019 Dynamic VAR Planning

    19/31

    Study case

    Fault on a 500 kV transmission line and the subsequent double line

    outage as follows, which causes voltage collapse in many zones.

    line connecting 500 kV Bus 9 and Bus 23line connecting 500 kV Bus 1 and Bus 4

    19

    Fig. 9 Double line outage considered most critical

    The lines are the major transmission corridors for importing power to the

    subsystem

  • 7/30/2019 Dynamic VAR Planning

    20/31

    Bus voltages without motor dynamics

    The contingency for the

    analysis is defined as follows,

    A fault is applied at an artificialbus 90000 which is created at

    40% of the 500 kV line 1-4

    The fault is cleared after 5

    cycles by removing the twolines

    No serious voltage problems

    are observed when motor

    dynamics are not included The bus voltages restore

    almost to the pre-fault values

    20

    Time (sec)

    Busvoltagemagnitudes(pu)

    Fig. 10 Bus voltages without motor dynamics

  • 7/30/2019 Dynamic VAR Planning

    21/31

    Bus voltages with motor dynamics

    The trip motor (27% of the

    motor load at each bus)parameter Vt is chosen as 0.55

    pu and Tv is chosen as 10

    milliseconds

    Low voltage magnitudes areobserved at most of the buses

    with few bus voltages dropping

    to as low as 40%

    Although the voltage drop hasbeen observed at 230 kV and

    500 kV level also, the drop is

    more pronounced at the 69 kV

    and 12.5 kV buses21

    Fig. 11 Bus voltages without motor dynamics and

    without corrective action

    Busvoltagem

    agnitude(pu)

    Time (sec)

    0.00 2.00 4.00 6.00 8.00 10.000.00

    0.22

    0.44

    0.66

    0.88

    1.10

    BUS108 230 kVBUS18 500 kV

    BUS333 69 kV BUS735 12.5 kV

  • 7/30/2019 Dynamic VAR Planning

    22/31

    Motor voltage and reactive power demand

    It is observed that the reactive

    power demand of the induction

    motor increases during the

    post contingency period

    This large increase in reactive

    power demand further reduces

    the voltage magnitudes in thesystem, thereby resulting in

    voltage collapse

    At such voltage levels, even

    the SM motor would stall,overload, and trip

    The typical tripping time for

    motors stalled at 50% voltage

    is 15-20 seconds

    Fig. 12 Reactive power demand of induction motorsat a representative bus

    Fig. 13 Terminal voltage magnitude of induction moto

    at representative bus

    Inductionmotortermin

    alvoltage(pu)

    Time (sec)0.00 2.00 4.00 6.00 8.00 10.000.00

    0.22

    0.44

    0.66

    0.88

    1.10

    Time (sec)0.00 2.00 4.00 6.00 8.00 10.00

    0.00

    3.00

    6.00

    9.00

    12.00

    15.00

    ST MOTOR

    SM MOTOR

    Inductionmotorreac

    tivepowerdemand(MVAR)

  • 7/30/2019 Dynamic VAR Planning

    23/31

    Generator response

    The outputs of the generators

    especially in zone 126 are

    exceeding their maximum VAr

    capacity, thereby stressing the

    generating units

    This shows that there is a

    deficiency of dynamic reactive

    power in the zone. If appropriate

    actions are not taken, the zone

    could be subjected to severe

    voltage instability

    23

    Fig. 14 Generator reactive power output

    Generatorreact

    ivepower(MVAR)

    Time (sec)

    0.00 2.00 4.00 6.00 8.00 10.00-70

    12

    94

    176

    258

    340

    GEN580

    GE581

    GEN579

  • 7/30/2019 Dynamic VAR Planning

    24/31

    Modal analysis

    Modal Analysis is performed in

    two ways

    Case A: By increasing the power

    transfer with the power factor same as inthe base case

    The zones associated with the critical

    modes do not represent the zones with

    very low post fault voltage magnitudes in

    time domain analysis

    Case B: By increasing the powertransfer at low power factor (0.3)

    Critical zones - 126,127,128, 129

    Modal analysis at point ofcollapse may not accurately

    pinpoint the buses or zones that

    require reactive power support

    when fast voltage collapse occurs24

    S. No. Modes Participating

    zones

    1 0.014904+j0 119/124/125

    2 0.048814+j0 1657

    3 0.057995+j0 1843

    4 0.063687+j0 1657

    5 0.069565+j0 1843/1844

    Case A: Critical modes at nose point

    S. No. Bus No. Zone No. Bus Participation

    Factor

    1 397 128 0.53294

    2 391 128 0.52416

    3 378 126 0.507754 591 129 0.50457

    5 396 128 0.50157

    6 595 126 0.4993

    7 379 126 0.49719

    8 389 128 0.49445

    9 333 126 0.49431

    10 380 128 0.49396

    Case B: Bus participation factors

  • 7/30/2019 Dynamic VAR Planning

    25/31

    Trajectory sensitivity and location of

    dynamic VAr W

    bihas been chosen to be 1 for

    all the buses, since the voltage

    collapse has affected all the busvoltage magnitudes

    Wk

    =1 for time instants t=0.1, 0.2,

    0.3, 0.4, 0.5, 0.6, 0.7, 0.8, 0.9, 1.0

    seconds after the fault, and zerofor all other instants

    It is observed that the 230 kV

    buses 108, 102, 107, and 96 have

    higher sensitivities

    These buses are selected primarily

    as the locations for reactive power

    sources

    25

    Fig. 15 TSI values

    T j t iti it d l ti f

  • 7/30/2019 Dynamic VAR Planning

    26/31

    Trajectory sensitivity and location of

    dynamic VAr

    STATCOMs with a rating of 350 MVAr

    each are placed at buses 108, 102,

    107, and 96 The 230 kV voltages recover to nearly

    1 pu in about 4 seconds

    However, the voltages at the 69 kV

    buses and the distribution feeders(12.5 kV) take much longer time (about

    7 seconds) to recover to pre-fault

    values

    Since the voltage collapse occurs at

    the low voltage level (69 kV, and 12.5

    kV), it appears that the shunt

    compensation must be provided at 69

    kV buses for effective voltage recovery

    Fig. 16 230 kV bus voltages in the system with 900 MVArSTATCOMS at three buses

    Fig. 17 Bus voltages (12.5-69 kV) in the system with

    900 MVAr STATCOMS at three 230 kV buses

    Busvolta

    gemagnitude(pu)

    Time (sec)

    0.00 2.00 4.00 6.00 8.00 10.000.00

    0.24

    0.48

    0.72

    0.96

    1.20

    Busvoltagemagn

    itude(pu)

    Time (sec)0.00 2.00 4.00 6.00 8.00 10.00

    0.00

    0.24

    0.48

    0.72

    0.96

    1.20

    BUS591 69 kV

    BUS817 12.5 kV

  • 7/30/2019 Dynamic VAR Planning

    27/31

    Trajectory sensitivity and location of

    dynamic VAr

    The 69 kV buses that areconnected to the 230 kV buses

    with high sensitivities are

    chosen as locations for

    STATCOMs The STATCOMs are removed

    from the 230 kV buses and then

    connected to 69 kV buses

    The maximum limit of the valueof shunt compensation at a 69

    kV bus is chosen to be 72 MVAr

    based on the physical

    constraints at the substation27

    Buses selected as STATCOM location

    S. NO. BUS NO. SIZE (MVAR)

    1 17 72

    2 102 72

    3 170 72

    4 322 72

    5 328 44

    6 342 72

    7 343 728 344 72

    9 357 72

    10 373 72

    11 375 72

    12 381 72

    13 477 72

    14 535 72

    15 550 72

    16 551 72

    17 554 72

    18 584 72

    19 591 72

    TOTAL 1340 (MVAR)

    Trajectory sensitivity and location of

  • 7/30/2019 Dynamic VAR Planning

    28/31

    Trajectory sensitivity and location of

    dynamic VAr

    The STATCOMs act quickly to

    increase their injected current and

    thus provide the required reactive

    power

    Voltages at all levels are restored to

    respective pre-fault values

    The STATCOMs are required toprovide the reactive power to their

    full capacity only for a short period

    of time right after fault

    Power electronic based shuntcompensation with high short term

    ratings may be an effective option to

    prevent voltage collapse caused by

    presence of significant inductionmotor loads

    Fig. 18 Bus voltages after placement of

    STATCOMs at 69 kV buses

    Fig. 19 STATCOM output for the fault under study

    Busvoltagemagnitude(pu)

    Time (sec)

    10.000.00 2.00 4.00 6.00 8.000.00

    0.24

    0.48

    0.72

    0.96

    1.20

    BUS18 500 kV

    BUS108 230 kV

    BUS333 69 kV

    BUS735 12.5 kV

    OutputcurrentofSTA

    TCOM(pu)

    Time (sec)

    0.00 2.00 4.00 6.00 8.00 10.00-1.00

    -0.78

    -0.56

    -0.34

    -0.12

    0.10

  • 7/30/2019 Dynamic VAR Planning

    29/31

    Comparison of SVC and STATCOM

    The bus voltage recovers to 1 pu in

    about 2 seconds when STATCOMs

    are used It takes about 4 seconds for the

    voltage to recover to 1 pu when SVCs

    are used

    The maximum VAr output of the SVCdecreases with the square of the AC

    system voltage, while that of

    STATCOM decreases linearly with

    the AC system voltage The STATCOM is therefore found

    more effective during large system

    disturbances

    29

    Fig. 20 Terminal voltage of Induction motor

    at a bus 735

    Inductionmotorterminalvoltage(pu)

    Time (sec)

    10.000.00 2.00 6.00 8.00

    0.24

    0.48

    8.000.00 2.00 4.00 6.00 8.000.00

    0.72

    0.96

    1.20

    4.00 6.000.00

    0.72

    0.96

    1.20

    Without VAr

    support

    With SVC

    With STATCOM

  • 7/30/2019 Dynamic VAR Planning

    30/31

    Conclusions

    Voltage collapse for the case under study is caused by short-term

    voltage instability initiated by a high reactive power demand of the

    induction motors during the disturbance period

    A fault on a high voltage transmission line might cause severevoltage dips at the distribution feeders, even though the voltage dips

    at high voltage level is not that severe

    Trajectory sensitivity analysis can be very useful in determining the

    location of dynamic VAr sources

    Power electronic based shunt compensation with high short term

    ratings may be an effective and attractive option

    STATCOMs provide a better option to improve short term voltageinstability problems than SVCs

    Smaller modules of STATCOMs at 69 kV buses are found to be

    more effective than larger modules at 230 kV buses in order to

    obtain faster voltage recovery30

  • 7/30/2019 Dynamic VAR Planning

    31/31

    31