ducting optimization – a case study

6
International Journal of Applied Research In Mechanical Engineering (IJARME), ISSN: 2231 –5950, Volume-1, Issue-2, 2011 31 Ducting Optimization – A Case Study C. Hemalatha 1 , T. Radhakrishnan 2 & K. Sankaranarayanasamy 3 1&2 Bharat Heavy Electricals Limited, Tiruchirappalli, India 3 National Institute of Technology, Tiruchirappalli, India E-mail: [email protected], [email protected] Abstract - Ducting system in a power plant is a conduit connecting one system to another through which either cold air or hot air or flue gas with ash is conveyed for continuous operation of the plant. To perform this function properly, careful design of ducting is required to take care of the stresses and forces exerted by various loadings and thermal expansion of the ducting and equipment it connects under given pressure and temperature. Ducting can be of any configuration viz. square, rectangular, circular, straight or bend, elbow or any other irregular shape. The design of large air and gas ducts is an extremely complex task which should meet both mechanical and structural design criteria. The purpose of ducts is to efficiently convey the air or flue gas from one location to another while maintaining the pressure drop and temperature drop as low as possible. This paper discusses about the optimization in the design engineering of the duct system. Keywords - CFBC, Primary Air, Secondary Air, Duct, Stiffeners, aspect ratio, optimum, weight, cost I. INTRODUCTION Engineering Design optimization both shortens design cycle time and finds new designs that are not only feasible, but also optimal based on the design criteria. Traditional engineering design processes involve strategies such as trial and error, use of previous experience etc., until the requirements are either met or changed to fit the performance. Often, the process is time consuming and does not produce the best design but just a feasible one. Since the process of design and engineering of ducting is time consuming, the process is automated by developing software. The software generates complete set of manufacturing and erection drawings for Circulating Fluidised Bed Combustion Boiler [1]. For the development of software the duct design is required to be parameterised and optimised. Engineering Design Optimization can both reduce the cycle time for the design iterations and find the best (optimal) design for the specifications. This process differs from the traditional process in that the iteration loop is computerized. An optimization problem is posed for which the design variable, the design objective and all constraints are specified. The analysis code performs the test phase of the iteration loop. The optimizer may function by perturbing each design variable to determine how each affect the performance and then seek a solution that optimizes the objective. While considering the design engineering of ducting system, the analysis can be done in various areas like fixing duct configuration or sizing, selection of material thickness, stiffener sizing, selection of expansion joint, maximum size for shipping etc., Among these, this paper deals with duct configuration, material thickness and stiffener spacing and sizing. Since, the total weight of the ducting and hence the cost for the customer mainly depends on the above parameters, they are taken up for optimization. II. DUCT DETAILS Any duct assembly is a combination of straight duct, transition duct, bend duct, metallic expansion joints or non metallic expansion joints, supports, damper, gates and man hole doors [2]. Straight duct can be of square, rectangle or circular cross section with adequate stiffeners on outside. For air duct and gas duct, carbon steel is used as duct material. Normally, square corner expansion joints are provided in the ducting assembly and while carbon steel is used as expansion joint material for air ducts, corten steel (carbon steel with minimum percentage of copper) is used for gas ducts. Wherever removal of duct is required for maintenance purpose flanges are provided with packing rope and in all other places ducts are welded permanently with each other and the gas tight joint is ensured. Manhole doors are provided in the ducting assembly preferably in a straight duct portion with appropriate access from the nearby floors. Care must be

Upload: nguyendat

Post on 10-Feb-2017

249 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Ducting Optimization – A Case Study

 International Journal of Applied Research In Mechanical Engineering (IJARME), ISSN: 2231 –5950, Volume-1, Issue-2, 2011

31  

Ducting Optimization – A Case Study

  

C. Hemalatha1, T. Radhakrishnan2 & K. Sankaranarayanasamy3 1&2 Bharat Heavy Electricals Limited, Tiruchirappalli, India

3National Institute of Technology, Tiruchirappalli, India E-mail: [email protected], [email protected]

 

Abstract - Ducting system in a power plant is a conduit connecting one system to another through which either cold air or hot air or flue gas with ash is conveyed for continuous operation of the plant. To perform this function properly, careful design of ducting is required to take care of the stresses and forces exerted by various loadings and thermal expansion of the ducting and equipment it connects under given pressure and temperature. Ducting can be of any configuration viz. square, rectangular, circular, straight or bend, elbow or any other irregular shape. The design of large air and gas ducts is an extremely complex task which should meet both mechanical and structural design criteria. The purpose of ducts is to efficiently convey the air or flue gas from one location to another while maintaining the pressure drop and temperature drop as low as possible. This paper discusses about the optimization in the design engineering of the duct system.

Keywords - CFBC, Primary Air, Secondary Air, Duct, Stiffeners, aspect ratio, optimum, weight, cost

 I. INTRODUCTION

Engineering Design optimization both shortens design cycle time and finds new designs that are not only feasible, but also optimal based on the design criteria. Traditional engineering design processes involve strategies such as trial and error, use of previous experience etc., until the requirements are either met or changed to fit the performance. Often, the process is time consuming and does not produce the best design but just a feasible one.

Since the process of design and engineering of ducting is time consuming, the process is automated by developing software. The software generates complete set of manufacturing and erection drawings for Circulating Fluidised Bed Combustion Boiler [1]. For the development of software the duct design is required to be parameterised and optimised.

Engineering Design Optimization can both reduce the cycle time for the design iterations and find the best (optimal) design for the specifications. This process differs from the traditional process in that the iteration loop is computerized. An optimization problem is posed for which the design variable, the design objective and all constraints are specified. The analysis code performs the test phase of the iteration loop. The optimizer may function by perturbing each design variable to determine how each affect the performance and then seek a solution that optimizes the objective. While considering the design engineering of ducting system, the analysis

can be done in various areas like fixing duct configuration or sizing, selection of material thickness, stiffener sizing, selection of expansion joint, maximum size for shipping etc.,

Among these, this paper deals with duct configuration, material thickness and stiffener spacing and sizing. Since, the total weight of the ducting and hence the cost for the customer mainly depends on the above parameters, they are taken up for optimization.

II. DUCT DETAILS

Any duct assembly is a combination of straight duct, transition duct, bend duct, metallic expansion joints or non metallic expansion joints, supports, damper, gates and man hole doors [2]. Straight duct can be of square, rectangle or circular cross section with adequate stiffeners on outside. For air duct and gas duct, carbon steel is used as duct material. Normally, square corner expansion joints are provided in the ducting assembly and while carbon steel is used as expansion joint material for air ducts, corten steel (carbon steel with minimum percentage of copper) is used for gas ducts. Wherever removal of duct is required for maintenance purpose flanges are provided with packing rope and in all other places ducts are welded permanently with each other and the gas tight joint is ensured. Manhole doors are provided in the ducting assembly preferably in a straight duct portion with appropriate access from the nearby floors. Care must be

Page 2: Ducting Optimization – A Case Study

International

taken that thelocation of duc

Ducts are or in combinaare type of boin fixed suppobottom supposupport memband allowed accommodate thermal expanwith the bottosupporting strueither with hconstant load supports to reduct [3].

III. CFBC DU

Ducts connot necessarilymay be circulthey may be upiece of majoheater or eletemperature cstructures whsuspended by

In a fluidisystem consisfan and Force(SA)) fan thatthe boiler. Thiboiler, the outpre heater wprecipitator oparticles are reflue gas to atm(ID) fans aredownstream ochimney. Theythrough the pthrough the ch

Fig.1: Sch

l Journal of Appl

ese doors arect stiffeners.

supported eithation. Fixed sttom supports.orts, the supprting member

ber is placed oto slide over

the movemensions. The slidm support platuctural membe

hanger rod ashangers. Res

estrict the mov

UCTING

nnect pieces oy considered plar or rectanguunusual in shaor power planctrostatic precchanges, ductshich “float” oa hanger system

ized bed boilerts of a combin

ed Draft (FD) t supply the aiis duct extendstlet flue gas uswhere it is r bag filter wemoved from thmosphere throue located withof the boiler by suck the fluprecipitator an

himney or stack

hematic of Duc

lied Research In

e provided co

her from bottomsupport and sli The basic diffort is directlyand in slidin

over the slide bthe slide bea

ents of the dde bearing platte and then we

er. The top supsembly or wi

straints are provement of the

of major equippart of the equiular in shape ape as they trant equipment cipitator. To s are usually

on slide bearim.

r system, (Fig.nation of Prim(also called S

ir needed for cs up to the air sually passes tcooled; an

where most ohe flue gas; theugh chimney. Ihin the duct setween the pr

ue gas out of tnd out to thek.

ct arrangement

Ducting Optim

n Mechanical En

onsidering the

m or from top iding supports fference is that y welded with ng support the bearing plates aring plate to ducts due to tes are welded elded with the

pport can be of ith variable / ovided in the e support and

pment, but are ipment. Ducts or sometimes

ansition into a like fan, air

accommodate y independent ing plates or

.1) air ducting mary Air (PA) Secondary Air combustion to pre heater. In

through an air electro static f the fly ash e ID fans vent Induced Draft system in the recipitator and the boiler and e atmosphere

 of CFBC

mization – A Case S

 

 ngineering (IJAR32

f

In CtemperatCFBC d

Fig

IV. CO

Opteffectivemost oroptimizatoggle componerequiremknowledknowledfeedbackstiffeneranalyseddesign pconsidervarious weight oand manthe calcuoptimumstiffener

V. DU

Whtypes of locationconsiderencounteduct andsituationsquare limitatioupon thethe sizindiscusse

Study

RME), ISSN: 223

CFBC boiler ture and pressu

ducting system

g. 2: Temperat

NCEPT OF O

timization is toe as possible wr use the beation, differendetails, varioents, stiffen

ments are codge and site wodge and acck, the use of r sizing and spd. As per the opparameters likred for any spduct configuraof the duct winufacturing cosulated values,

m value for drs, stiffener size

CT DESIGN

ile doing ducf ducts used dep. Circular ductring performanered during thd difficulty in pns the circuladuct is prefe

on of space rece size of the dung and spacinges about param

31 –5950, Volum

different zonure. The tempeis plotted as sh

ture profile of d

OPTIMIZATI

o make the sywith available est of the synt duct typesous support tning elementompared withorking experiencording to tvarious duct spacing with duperating conditke temperaturepecific systemation, stiffener th stiffeners anst are studied. G

the analysis iduct sheet thie, weight and c

OPTIMIZAT

ct engineeringpending on flowt is considered nce. But becaushe manufacturproviding supp

ar duct is avoerred. In placctangular duct uct and thickneg of the stiffenemeterizing and

me-1, Issue-2, 20

nes are at diferature profile hown in Fig.2.

ducting system

ION

ystem as perfefeatures to ge

ystem.[4]. In s, expansion types and suts and splh practical dnce. Based on the manufactsheet thicknesuct sizing casetion of the plane and pressur

m. Details regaspacing and s

nd duct designGraphically plis made to finickness, numbcost.

TION

, there are vaw area, velocitto be the best se of the difficring of the cirports, at most ooided, whereinces where the

is used. Depeess of the duct ers vary. This optimizing th

011

fferent of the

m

ect or et the

duct joint,

upport litting design

these turing s, the es are nt, the re are arding sizing, n cost otting

nd the ber of

arious ty and while

culties rcular of the n the ere is ending

plate, paper

he use

Page 3: Ducting Optimization – A Case Study

Ducting Optimization – A Case Study

 

 International Journal of Applied Research In Mechanical Engineering (IJARME), ISSN: 2231 –5950, Volume-1, Issue-2, 2011

33  

of stiffener spacing and sizing with the use of duct size and configuration so as to reduce the total weight of ducting system.

Objective of function:

Duct size and aspect ratio are required to be analysed to have the optimum duct configuration. The effect of thickness of the duct plate on stiffener sizing and spacing are analysed considering the manufacturing feasibility, because increase in duct weight almost due to duct sheet thickness and stiffeners.

Duct sheet thickness lies within the limited range and number of stiffeners required depends on the thickness of the plate. Based on the maximum stiffener spacing calculated, number of stiffeners is found and the stiffener size suitable to stiffen the duct size is selected. Number of stiffeners decides the number of welding which decides the maximum portion of the duct cost. So it is required to reduce the total cost by optimally selecting the duct plate thickness, stiffener size and spacing.

Case study:

To explain the optimization procedure followed in the present analysis, a portion of the ducting in CFBC Boiler, Induced Draft fan outlet duct is taken as a case study.

Parameters considered for optimization:

• Duct sheet thickness

• Duct configuration - aspect ratio

• Number of Stiffeners

• Stiffener size

• Duct material cost

• Duct fabrication cost  

While designing the duct panel the loads considered are,

• Positive and negative pressure load from mechanical design data. (PPL & NPL)

• Dead load according to the system (DL)

• Wind load (WL)

• Ash load(AL)

• Live load (LL)

The limiting conditions considered for the present case are

Design temperature: 200 deg C

Positive Pressure Load (PPL):+20 mbar

Negative Pressure Load(NPL): -10 mbar

Dead load (DL) : 100 kg per m2.

Wind load (WL) : 200 kg per m2

Ash load (AL): 300 kg per m2

Live load (LL): 100 kg per m2

By calculating the occurrence of different possible combinations of the loads the numerical maximum is taken as the design load of the respective panel.

A duct shell is considered to consist of at-least four duct panels (two sides, top and bottom). Each of the four panels may be designed independently to achieve the most economical design for a given application. If different stiffener spacing is considered for all the panels then the minimum of the values is considered as the maximum stiffener spacing. Stiffener sizing will vary depending upon the load acting over the top, side and bottom walls of the shell. Always the bottom wall is highly loaded because of the ash load and water wash load. For economic stiffener size, different sizing and spacing shall be maintained for the different side of the duct shell walls.

The stiffener span is calculated using Stress criterion (Eqn.1), Static Plate deflection (Eqn.2), Dynamic plate deflection (Eqn.3) and Vibration criterion (Eqn.4) methods [5].

Stress Criterion:

S=2tP

Ys2

+2” (1)

Static Plate deflection:

S = 44304.29

PEt

+2” (2)

Dynamic plate deflection criterion:

S = 4'2

3

)1()12(384

PEt

γ−Δ

+ 2’’ (3)

Plate vibration criterion:

S = f

Et893 + 2” (4)

where

S - stiffener spacing

Page 4: Ducting Optimization – A Case Study

mspwcS

S

S

S

International

t - plate thi

Ys- yield s

P - design p

E - Young

γ = Poisson

∆= plate de

p´=expecte

f = natural

Among tminimum valuepacing. Then f

width) to be scriterion (EqnStiffener vibrati

Stiffener stress

L ≤8PSMB

Stiffener deflec

L ≤ 3465

384x

Stiffener vibrati

L ≤ 183

Where

M= combin

B = allowa

L = Maxim

I = combin

K = lengthk=2 for mu

A = combi

A table hastiffener for thI sections) for

l Journal of Appl

ickness

strength

pressure

’s modulus

n’s ratio

eflection

ed pressure pul

frequency

he values froe is identifiedfor each stiffestiffened can

n.5), Stiffenerion methods (E

criterion:

3

2SS

MB+

ction criterion:

644

xPSEIK

ion criterion:

fA

EI

4

ned section mo

able bending st

mum allowable

ned moment of

h factor; k=1 fultiple lengths

ined cross secti

as been preparhe give span of

various duct p

lied Research In

lsation

om these fourd as the maximner size, the sbe calculated

r deflection Eqn.7).

odulus of (plate

tress

stiffener lengt

f inertia of (plat

for uniform sti

ional area (plat

red which givef the panel (botplate thickness.

Ducting Optim

n Mechanical En

r criteria, the mum stiffener span (depth or d using stress

(Eqn.6) and

(5)

(6)

(7)

e + stiffener)

th

te +stiffener)

iffener length,

te +stiffener)

es size of the th channel and

mization – A Case S

 

 ngineering (IJAR34

Table 1:

Thickness

in mm

3

4

5

6

8

For differentselected

TakstiffenermaximuApplyinPlate defcriterionobtainedmm. Thstiffenerconsider

a) If un

Stif

Stif

Nu

b ) If n

Max

Num

Fig.3:

Study

RME), ISSN: 223

Selection of c

ISMC75

ISMC100

ISM12

2289 2657 29

2265 2635 29

2220 2600 29

2170 2560 29

2061 2446 28

each individut channel / bfrom the stiffe

king a duct mr spacing and sum transport

g Eqn.1,2,3 aflection, Dynam

n for the sd are 1962mmhe minimum var spacing whred for analysis

niform stiffene

ffeners = lengt

ffener spacing (

mber of stiffen

on-uniform sti

x. Stiffener spa

mber of stiffen

Duct panel w

31 –5950, Volum

channel size fo

Channel siz

MC25

ISMC150

ISMC200

990 3281 3766

975 3275 3770

950 3255 3760

910 3220 3740

812 3134 3670

ual panel of beam size, thener table.

made of 4 mmstiffener sizes length of du

and 4 for Stremic plate deflespecified con

m, 1093.6 mm,alue is found thich is 698 s.

er spacing is co

th/Max_sp=>ro

(S1) = 2500/4

ners (n) = 3

ffener spacing

acing (N1) = 6

N2 = 6

ers (n) = 3

with uniform sti

me-1, Issue-2, 20

or span of duct

ze

C ISMC250

ISMC300

6 4142 4561

0 4155 4575

0 4160 4580

0 4160 4575

0 4129 4542

the duct shelhe stiffener si

m plate for anaare calculated

uct as 2500 ess criterion, ection and Vibrditions the v,1195 mm andto be the maxmm for the

onsidered,

ound(3.5)=4

= 625 mm

is considered,

630 mm

620 mm

iffener spacing

011

size

ISMC400

5217

5235

5250

5255

5243

ll, for ize is

alysis, d for a

mm. Static ration values d 698 imum

case

Page 5: Ducting Optimization – A Case Study

International

Fig.4: Duct pa

Sl. N

o

Thic

knes

s m

m

1 3

2 3.5 3 4 4 5

5 6

6 8

From Taband 6 mm, edifferent, whstiffener spacimm plate thicksheet weight iof 3 mm plaincreased andMoreover weldifficult. For aconditions, bysuitable stiffenstiffener spacitabulated.

aspect ratio a

1.15 2.441

l Journal of Appl

anel with non-u

Max

. Stif

fene

r Spa

cing

(c

alcu

late

d)

mm

553

592.8 630 698

760

870

ble2, it is obseeven the maxhile considerining, number okness, no of stis more compaate thickness,

d this increaselding in 3mmall the above cy changing thners are selecting , total duc

b stiffenea

2.807 ISMC1

lied Research In

uniform stiffen

Uniform stiffenerspacing

spac

ing

(S1)

,

mm

num

ber o

f tif

f(

)

500 4

500 4 625 3 625 3

625 3

833 2

erved that for ximum stiffeneng uniform/ f stiffeners aretiffeners is redared with other

number of es number of

m plate is founcases, under abe aspect ratioed and keepinct weight is c

er_ Stiffener_b

00 ISMC125

Ducting Optim

n Mechanical En

ner spacing

r

stiff

ener

s (n)

spac

ing

mm

N1 553

553 630 698

760

870

ducts of 4, 5 er spacing is

non-uniform e same. For 8 duced but duct rs. In the case stiffeners has welding also.

nd to be very bove specified o of the duct, ng the uniform calculated and

Wt. Panel _a

191.61

mization – A Case S

 

 ngineering (IJAR35

Simsizes wtradition

Tabrequiredas 2500 uniform Table 2:duct plat

Non

Sample1

spac

ing

m

m

N2 420 4

420 4620 3552 3

490 3

380 3

Confor aspefrom taincludescost is cwelding total wemm for s

Table3-1.15

Wt. Panel_b

Tpan

220.349 82

Study

RME), ISSN: 223

milar way the rwere computednally used for f

ble 2 is prepd to stiffen the

mm. The datastiffener spaci

Stiffener requte thickness

Uniform stiffener sp

num

ber o

f st

iffen

ers

spac

ing

m

m

n N1550

550 630 698

760

870

nsidering a samect ratio of 1.1able1. Total ds duct panel wcalculated bascost. Table 3

eight and cost specified aspec

Table showing

Total nel_wt

no ostiffen

s

23.936 3

31 –5950, Volum

requirement ofd for differenfabrication of d

pared for numduct span keepa are found foing.

uirement and sp

pacing

Sample2

mm

spac

ing

m

m

N2 425

425 315 203

110

542 & 273

mple case of 415, the stiffeneduct weight is

weight and stiffed on materialists the samplfor the duct p

ct ratio.

g weight and co

of ner Total

_stiff_wt

360.64

me-1, Issue-2, 20

f stiffeners for nt cases of pducts.

mber of stiffping the duct l

or uniform and

pacing for vari

num

ber o

f st

iffen

ers

n 4 2

4 24 24 2

4 2

3 4 2

4 mm thickneser size is idens calculated wfeners weight. al cost and stifle calculated dplate thickness

ost for aspect r

Total weight tot

1185 16

011

other plates

feners length d non-

ious

Leng

th

m .5

.5

.5

.5

.5

.5

ss and ntified which Total

ffener data of s of 4

ratio

tal cost

65123

Page 6: Ducting Optimization – A Case Study

International

Similarly various duct between 3 mmminimum platmm, for furthVarious comband graphs are

VI. RESULT

Fig.5 relaconfiguration tons, for variosimilar for theaspect ratio ofmm thickness(aspect ratio comparing 3.53.5 mm plate mm, because comparing theaspect ratios, tduct is 1, thedemands diffegraph that 4 mthe duct for all

Fig.

The cost plotted for dexplicitly showfor all the aspe

Fi

Fig.7 showduct with samfor various du

l Journal of Appl

the total weighplate thickn

m and 3.5 mm pte thickness spher analysis 3binations of dae plotted.

TS AND DISC

ates the aspect with correspon

ous plate thickne plate thicknef 1.15 results ies. For 3.5 an

1) is found5 and 4 mm pla

is more whenof increased n

e weight of ththough the opte space availaerent aspect ramm duct gives l aspect ratios.

5 : Duct aspect

of the duct fordifferent aspecws that 4 mm ect ratios of the

ig.6 : Duct thic

ws the relationme flow area buuct thickness. F

lied Research In

ht and cost are ness. Since thplate are very pecified in lit.5 mm plate iata from table

USSION

ratio (depth/wnding weight nesses. The cusses of 4,5,6 an least weight

nd 4 mm platesd to be optiates, weight ofn comparing wnumber of stifhe other platestimum aspect rability at diffeatios. It is fouthe least over

t ratio with we

r various duct ct ratio.(Fig.6)

thickness plate duct.

ckness with co

nship between tut with variousFrom the grap

Ducting Optim

n Mechanical En

calculated for he difference minimum and

terature is 3.5 is considered.

e are analysed

width) of duct of the duct in urve pattern is and 8 mm. An

for 5,6 and 8 s, square duct imum. While f duct made of with that of 4 ffeners. When s with various ratio for 4 mm erent location und from the rall weight for

ight

thickness are ). This graph te is optimum

ost

the cost of the s aspect ratios ph, it is found

mization – A Case S

 

 ngineering (IJAR36

f

that 3.5manufacand stifffor all thoptimum

VII. CO

It optimizafan outle• Wh

decrfounthicsolu

• Thoanalstiffcon

• Thethicthe any

REFER [1]. He

SanEn

[2]. PatAS

[3]. RoGaApCoAm(A

[4]. KeDueng

[5]. RaFoPuEn

Study

RME), ISSN: 223

5 mm plate cturing cost wfeners weldinghe aspect ratio

m compared wi

Fig.7: Duc

ONCLUSION

is evident ation approachet duct system ile it appears threase the numnd from the kness and uni

ution for the givough various stlysis, it is prudfener spacingsidering the ov

e analysis shokness of 4 mmcost of ductinmanufacturing

RENCES emalatha nkaranarayana

ngineering. trick J.Brook

SHRAE Journaonald L.Schneias Ducts for Ppplications, Aommittee of merican SocSCE),1995

erry Penningtouctwork Desigineering, Oct

aymond.J.Roarkrmulas for st

ublishers, 2002ngineers, (ASC

31 –5950, Volum

is the worswhich includes g cost of 4 andos, the 4 mm pith other plate t

ct aspect ratio w

N

from the mh adopted on a of a CFBC boihat increase in

mber and size oanalysis pres

form stiffener ven design contiffener spacingdent to conclu

g is the moverall weight oows that the m, under designg which is theg industry.

C, Sunasamy K, Au

ks, Duct desal, Jan 2010, Vider, The StrucPower Stations

Air and Gas the energy

ciety of

on, Worley Paign and En2008, Vol.12 (k, Warren.Ctress and stra2, American E), 1995.

me-1, Issue-2, 20

st consideringboth material

d 5 mm platesplate is found thickness.

with cost 

mechanical dInduced Draft

iler that, n duct thicknessof stiffeners, sented that 4spacing is the

ndition. g are in use froude that the unost preferred f the ducting.ducting with

gn condition ree prime objecti

ndararajan utomation of

sign fundameVol.152. ctural Design os Industrial B

Structural DDivision of Civil Engin

arsons, Econongineering, P(10)

C.Young, Roain, Current

Society of

011

g the l cost s. But to be

design ft (ID)

s may , it is

4 mm e best

om the niform

one

plate educes ive of

S, Duct

entals,

of Air Boilers Design

The neers,

omical Power

oark’s Law Civil