DT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter replacement: a) Object type on device to be replaced i.e. On meter Object type should be either “DTM”, “FDRM” or ”RINM” depending on type of meter being replaced and “CT”, “PT” or “CTPT” depending on the type of transformer being replaced. b) Authorization group should maintained on the Meter c) Perform a Goods Receipt through MIGO transaction for new Meter and CT/PT device for the storage location of the respective Authorization group maintained on the device. d) Class should be attached on meter in Class overview on both Old and New Meters.

Upload: others

Post on 19-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

DT/ Feeder Meter MCO

Scenario 6: Only Meter replacement

Necessary tasks before performing Meter replacement:

a) Object type on device to be replaced i.e. On meter Object type should be either “DTM”,

“FDRM” or ”RINM” depending on type of meter being replaced and “CT”, “PT” or “CTPT”

depending on the type of transformer being replaced.

b) Authorization group should maintained on the Meter

c) Perform a Goods Receipt through MIGO transaction for new Meter and CT/PT device

for the storage location of the respective Authorization group maintained on the

device.

d) Class should be attached on meter in Class overview on both Old and New Meters.

Page 2: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Now Proceed with Meter replacement with new T-code ZDTMETER.

Step 1: Open T-code ZDTMETER.

Step 2: Now select check box “Replace DT/ Feeder meter”. Below options is displayed after

selecting the check box.

Page 3: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 3: Now select check box “Replace Meter” and click “SUBMIT” button.

Step 4: Now enter all parameters in the next screen displayed.

Page 4: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 5: After entering all fields click “SUBMIT” button.

Note: Enter “Date” in date format as highlighted below.

Step 6: In the pop-up “Create Device replacement order” displayed on screen click “OK”.

Page 5: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 7: Now issue Meter against the order created in previous step. Click on find button as

highlighted below.

Step 8: Click on execute button as highlighted below.

Page 6: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Now select new serial number of meter to be replaced. And click button as highlighted below.

Now click on check box “Item OK” as highlighted below.

Page 7: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 9: Now Click on “Check” button as highlighted below.

Step 10: Message in green is displayed below “Document is O.K.”. Now click “Post” button.

Material document is posted.

Page 8: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Next click green “Back” button as highlighted below.

Step 11: Pop-up is displayed “Proceed with full removal of meter”. Click OK.

Page 9: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 12: In next screen enter “meter readings” of DT/ feeder meter being removed and being

installed and “Activity reason”.

Page 10: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Click on save button as highlighted below.

Page 13: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 13: Pop-up “Do you want to remove modem from old meter and install on new meter ”.

Click OK.

Step 14: Pop-up “Proceed to Technical Completion of Device Replacement Order”. Click OK

Page 14: DT/ Feeder Meter MCO - Punjab State Power …docs.pspcl.in/docs/itmanuals051642114.pdfDT/ Feeder Meter MCO Scenario 6: Only Meter replacement Necessary tasks before performing Meter

Step 15: Pop-up “Meter Replacement is Complete”. Click OK