dsac i classificationdsac i classification karst ... creek updat… · wolf creek dam dsac i...
TRANSCRIPT
![Page 1: DSAC I ClassificationDSAC I Classification Karst ... Creek Updat… · Wolf Creek Dam DSAC I ClassificationDSAC I Classification -Karst foundation seepageKarst foundation seepage](https://reader033.vdocuments.site/reader033/viewer/2022060610/60612ddda41e5b769d68a2ca/html5/thumbnails/1.jpg)
Wolf Creek DamWolf Creek DamDSAC I Classification Karst foundation seepageDSAC I Classification - Karst foundation seepage $594M Cost, $572M Obligated, 93% CompleteBarrier Wall Completed March 2013Total Project Completion Estimated Summer 2014
Gallery GroutingComplete
j p
Grouting ‐ $70MCompleted Oct 2008Contractor: ACT
Barrier Wall ‐ $420MAward Jul 2008 – 95% CompleteContractor: Treviicos & Soletanche
S it h d W ll
Barrier WallComplete
Gallery Grouting ‐ $11.0MCompleted July 2012Contractor: Judy Company
Switchyard Wall15% Complete
p
)
Halcomb’s LandingComplete
Halcomb’s Landing ‐ $9.5M Completed Oct 2007Contractor: VCI‐Doyon JV
Rock Foundation Beneath CA 1
as of 4 Nov 13 1
![Page 2: DSAC I ClassificationDSAC I Classification Karst ... Creek Updat… · Wolf Creek Dam DSAC I ClassificationDSAC I Classification -Karst foundation seepageKarst foundation seepage](https://reader033.vdocuments.site/reader033/viewer/2022060610/60612ddda41e5b769d68a2ca/html5/thumbnails/2.jpg)
Wolf Creek Dam Safety Project UpdateB i W ll C l t d• Barrier Wall Completed March 2013
• Interim Lake Raise April th h A t 2013through August 2013 was successful
• Downstream switchyard ll d itwall and site
stabilization construction ongoing now complete bynow, complete by September 2014
• Goal is to return Lake Cumberland toCumberland to historical operations by Spring 2014
2