Including Sustainability in the Brief Kate Mills Senior Sustainability Consultant, BRE [email protected]. Drivers and business needs. Identify policy drivers Environmental policies How does this integrate with the business needs? Identify capital and whole life resources. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/1.jpg)
Including Sustainability in the BriefKate MillsSenior Sustainability Consultant, BRE
![Page 2: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/2.jpg)
Drivers and business needs
• Identify policy drivers• Environmental policies• How does this integrate with the business needs?• Identify capital and whole life resources
![Page 3: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/3.jpg)
Identify user needs
• Regional and local plans• Existing community provisions or future needs• How will the development enhance the community?• Public consultations
![Page 4: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/4.jpg)
Options to meet user needs
• Develop options for project (site)• Consider overall economic, environmental and social impacts•Project specific public consultation•Consider refurbishment v new build•Assess costs and benefits using WLC
![Page 5: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/5.jpg)
Project sustainability
• Sustainability objectives• Identify all relevant sustainability requirements• Planning requirements and EIA• Specification and scope for project• Major risks• Project programme and budget for sustainability• The right integrated team• Procurement method?
![Page 6: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/6.jpg)
Project brief
• Pollution (land, air, water)• Internal environment• Community impact, equity and access• WLC• Site issues and ecology• Energy• Materials• Sustainability regulations• Transport• Waste• Water
![Page 7: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/7.jpg)
Tools and indicators
• Considerate Constructors Scheme• BREEAM for Offices, Retail, Industrial Units• BREEAM for Schools• NEAT for NHS• SmartWaste• Design Quality Indicators• Key Performance Indicators from Constructing Excellence• Environmental Management Systems and Environmental
Policies• EPIs – Constructing Excellence
![Page 8: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/8.jpg)
The site - Inverness
![Page 9: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/9.jpg)
Procurement
• Good advice at the start• Sustainability expertise as part of core team• Budget• Choice and use of procurement method?• Site and transport• Orientation
![Page 10: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/10.jpg)
Writing the brief
• Quantifiable benchmarks• Reporting requirements• Environmental Management System• Monitoring strategy
![Page 11: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/11.jpg)
The targets
• 0-8 kg/Carbon/m2 per annum• 4% average daylight factor and uniformity factor of 0.4• 6.4m3/per person/ per annum water consumption• A rated materials for external walls, windows, roof• Sustainable certified timber• Insulation without ODP and GWP less than 5
![Page 12: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/12.jpg)
The targets
• Green procurement system• Excellent BREEAM rating• Monitor carbon dioxide emissions• Considerate Constructors Scheme• Demolition audit and construction waste• Sustainable transport plan with client• Environmental Management System
![Page 13: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/13.jpg)
The process
• Use the procurement method• Measurable benchmarks • Selection of developer• Evaluation process and interviews
![Page 14: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/14.jpg)
The result
![Page 15: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/15.jpg)
The result
![Page 16: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/16.jpg)
Demolition
![Page 17: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/17.jpg)
Demolition
![Page 18: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/18.jpg)
Demolition
![Page 19: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/19.jpg)
Demolition
![Page 20: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/20.jpg)
SUDS
![Page 21: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/21.jpg)
SNH Inverness
![Page 22: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/22.jpg)
Monitoring and reporting
• Environmental policy• Environmental Management System• Monthly reporting by constructor• Use of BREEAM• Considerate Constructors Scheme• Client monitoring
![Page 23: Drivers and business needs](https://reader035.vdocuments.site/reader035/viewer/2022062323/5681587d550346895dc5dccc/html5/thumbnails/23.jpg)
Post construction review
• Post-construction BREEAM assessment• Monitoring of carbon target• Monitoring of water use• Implementing travel plan• Analysis of data collection from construction phase