draft basic assessment report for the proposed … draft bar...eskom holdings (soc) limited, limpopo...

119
ESKOM HOLDINGS (SOC) LIMITED, LIMPOPO OPERATING UNIT (LOU) DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED POWER LINE DEVELOPMENT AT THE MAMPHULI-DZWERANI EXT A SUBSTATION AT MAMPHULI VILLAGE AND AN APPROXIMATELY 6KM LOOP IN LOOP OUT BERSFORT OF 2X132KV POWER LINE FROM AN EXISTING 132KV POWERLINE AT TSHITUNGULWANE VILLAGE, NEAR VUWANI TOWN UNDER VHEMBE DISTRICT IN THE LIMPOPO PROVINCE DRAFT BASIC ASSESSMENT REPORT EIA CONSULTANTS APPLICANT MBOFHO CONSULTING AND PROJECT MANAGERS P.O Box 54 Polokwane 0700 Tel: 015 280 0088 Fax: 086 539 6388 Cel: 079 1930 634 Email: [email protected] Contact Person: Matodzi Silidi Eskom Holdings (SOC) Limited, Limpopo Operating Unit (LOU) 91 Hans Van Rensburg Street P.O Box 3499 Polokwane 0700 Tel: 015 230 1683 Fax: 086 244 2959 Cel: 084 967 5116 Email: [email protected] Contact person: Monica Mokgawa

Upload: others

Post on 19-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

ESKOM HOLDINGS (SOC) LIMITED, LIMPOPO OPERATING UNIT (LOU)

DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED POWER LINE DEVELOPMENT AT THE MAMPHULI-DZWERANI EXT A SUBSTATION AT

MAMPHULI VILLAGE AND AN APPROXIMATELY 6KM LOOP IN LOOP OUT BERSFORT OF 2X132KV POWER LINE FROM AN EXISTING 132KV

POWERLINE AT TSHITUNGULWANE VILLAGE, NEAR VUWANI TOWN UNDER VHEMBE DISTRICT IN THE LIMPOPO PROVINCE

DRAFT BASIC ASSESSMENT REPORT

EIA CONSULTANTS APPLICANT

MBOFHO CONSULTING AND PROJECT MANAGERS P.O Box 54 Polokwane

0700

Tel: 015 280 0088 Fax: 086 539 6388 Cel: 079 1930 634

Email: [email protected] Contact Person: Matodzi Silidi

Eskom Holdings (SOC) Limited, Limpopo Operating Unit (LOU)

91 Hans Van Rensburg Street P.O Box 3499

Polokwane 0700

Tel: 015 230 1683 Fax: 086 244 2959 Cel: 084 967 5116

Email: [email protected] Contact person: Monica Mokgawa

Page 2: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

2

REPORT DETAILS Project name: APPLICATION PROCESSES FOR THE PROPOSED

DEVELOPMENT OF MAMPHULI-DZWERANI EXT A SUBSTATION AT MAMPHULI VILLAGE AND AN APPROXIMATELY 6KM LOOP IN LOOP OUT BERSFORT OF 2X132KV POWER LINE FROM AN EXISTING 132KV POWERLINE AT TSHITUNGULWANE VILLAGE, NEAR VUWANI TOWN UNDER VHEMBE DISTRICT IN THE LIMPOPO PROVINCE.

CLIENT: Eskom Holdings (SOC) Limited, Limpopo Operating Unit (LOU) EIA Consultant: Mbofho Consulting and Project Managers Project Team: Matodzi A. Silidi, Pr.Sci.Nat: MA Env Management (UOFS),

Post Graduate Diploma in Museum and Heritage Studies (UCT), B.Env. Sc. (UNIVEN), ASHEEP (NOSA), SAMTRAC (NOSA), Environmental and Mining Rehab (UNW), Advanced Project Management (UNW), Handling, Storage and Transportation of Dangerous Goods and Hazardous Substances (UNW)

T.R Silidi: BA Social Sciences (Wits), BA Hons (Univen),

Masters in Social Impact Assessment (UJ), Negotiations (SARWA)

MS Arinao: B Environmental Science (University of Venda)

Mr Mugove Njovo: MSc Env Management (Midlands state University)

Status of report: DRAFT BAR Date of issue: JULY 2019 DEA Ref. No.: NONE

Consultants: MBOFHO CONSULTING AND PROJECT MANAGERS

Approved for Consultants by: …………………………………………. M.A Silidi

Page 3: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

3

TABLE OF CONTENT

1. CHAPTER ONE: INTRODUCTION AND BACKGROUND ................................................. 11

1.1 INTRODUCTION ................................................................................................................ 11

1.1.1 The key objectives of this Final BA process include the following: ..................... 13

1.1.2 The objectives of the report are the following: ....................................................... 13

1.1.3 Project Location .......................................................................................................... 14

1.1.4 MOTIVATION FOR THE PROJECT ........................................................................ 16

1.2 LEGAL REQUIREMENT ........................................................................................................... 17

1.2.1 Servitude Requirements and Clearances ............................................................... 19

1.2.2 Line clearances ........................................................................................................... 20

1.2.3 Foundations ................................................................................................................. 22

1.2.4 Access .......................................................................................................................... 22

1.2.5 Timing ........................................................................................................................... 23

1.2.6 Continuous Maintenance ........................................................................................... 23

1.2.7 Construction Process for the proposed line ............................................................ 23

1.2.8 Detailed description of the listed activities associated with the project as applied

for 24

1.3 STUDY APPROACH FOLLOWED ................................................................................... 25

1.6 DETAILS AND EXPERTISE OF THE ENVIRONMENTAL ASSESSMENT

PRACTITIONER ............................................................................................................................. 26

2. CHAPTER TWO: PROJECT INFORMATION ...................................................................... 28

2.1 SITE ALTERNATIVES .............................................................................................................. 30

2.1.1 Coordinates for the preferred and Alternative site: ................................................ 30

2.2 LAY-OUT ALTERNATIVES ....................................................................................................... 31

2.3 TECHNOLOGY ALTERNATIVES .............................................................................................. 31

2.4 OTHER ALTERNATIVES (E.G. SCHEDULING, DEMAND, INPUT, SCALE AND DESIGN

ALTERNATIVES) ................................................................................................................................. 31

2.5 POWER LINE DESIGN ALTERNATIVES .................................................................................. 32

2.6 ALTERNATIVE 1 (PREFERRED POWER LINE DESIGN) – SINGLE CIRCUIT OVERHEAD

POWER LINE ...................................................................................................................................... 32

2.7 ALTERNATIVE 2 (ALTERNATIVE POWER LINE TECHNOLOGY) – UNDERGROUND CABLING 32

2.8 NO-GO ALTERNATIVE ............................................................................................................ 32

2.9 PHYSICAL SIZE OF THE ACTIVITY .......................................................................................... 33

2.10 SITE ACCESS ........................................................................................................................ 34

2.11 LOCALITY MAP ...................................................................................................................... 35

Page 4: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

4

2.12 LAYOUT/ROUTE PLAN .......................................................................................................... 37

2.13 SENSITIVITY AREAS .............................................................................................................. 42

2.13.1 Watercourses and Flood Line ................................................................................... 42

2.13.2 Areas with indigenous vegetation ............................................................................ 43

2.13.3 Cultural and historical features ................................................................................. 44

2.13.4 Visual impact assessment ......................................................................................... 44

2.13.5 Avifaunal Habitats ....................................................................................................... 44

2.13.6 Major Known Impacts of Power lines on Avifauna ................................................ 46

2.13.7 High Risk Landscape Features ................................................................................ 46

2.14 SITE PHOTOGRAPHS ............................................................................................................ 47

2.15 FACILITY ILLUSTRATION ........................................................................................................ 47

3. CHAPTER THREE: APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES

58

3.1 APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES ................................................. 58

3.1.1 The Constitution .......................................................................................................... 58

3.1.2 The National Environmental Management Act, 107 of 1998 (NEMA) ................ 58

3.1.3 The Principles of NEMA ............................................................................................. 58

3.1.4 Integrated Environmental Management (Chapter 5) ............................................. 59

3.1.5 GN R 327 – The Environmental Authorisation process ........................................ 60

3.1.6 GNR 327 – Activities requiring an EIA .................................................................... 60

4. CHAPTER FOUR: STATUS QUO OF RECEIVING ENVIRONMENT .............................. 62

4.1 GENERAL ENVIRONMENTAL DESCRIPTION (INCLUDING VISUAL, LANDUSE

&LANDCOVER) .............................................................................................................................. 62

4.1.1 Climate ......................................................................................................................... 62

4.1.2 Surface Water ............................................................................................................. 62

4.1.3 Land Use Character 0f Surrounding Area .............................................................. 62

4.2 WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT ................................................... 63

4.2.1 Solid waste management .......................................................................................... 63

4.2.2 Waste permit ............................................................................................................... 65

4.2.3 Generation of noise .................................................................................................... 66

4.2.4 Energy Efficiency ........................................................................................................ 67

4.2.5 Property description/physical address ..................................................................... 67

4.2.6 Gradient of the site ..................................................................................................... 68

4.3 SOCIO-ECONOMIC CHARACTER OF THE LOCAL MUNICIPALITY .......................................... 68

4.3.1 Level of unemployment .............................................................................................. 68

Page 5: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

5

4.3.2 Economic profile of local municipality ...................................................................... 68

4.3.3 Level of education ....................................................................................................... 69

4.3.4 Project spin off ............................................................................................................. 69

5. CHAPTER FIVE: SPECIALIST REPORTS .......................................................................... 70

5.1 BIODIVERSITY ........................................................................................................................ 70

5.1.1 Habitat condition on site ............................................................................................ 71

5.1.2 Types of ecosystems ................................................................................................. 72

5.2 VEGETATION TYPE AND/OR AQUATIC ECOSYSTEM ............................................................. 72

5.3 CULTURAL/HISTORICAL FEATURES ..................................................................................... 74

6. CHAPTER SIX: PUBLIC PARTICIPATION .......................................................................... 75

6.1 PUBLIC PARTICIPATION PROCESS FOLLOWED ..................................................... 75

6.1.1 Advertisement and Notice ......................................................................................... 76

6.1.2 Placement of advertisements and notices .............................................................. 76

6.1.3 Site notice placement ................................................................................................. 76

6.1.4 Key stakeholders ........................................................................................................ 77

6.1.5 Issues raised by interested and affected parties ................................................... 78

6.1.6 Authority Participation ................................................................................................ 79

6.1.7 Conclusion of public participation programme ....................................................... 81

7. CHAPTER SEVEN: IDENTIFIED IMPACTS AND PROPOSED MITIGATION

MEASURES ........................................................................................................................................ 82

7.1 INTRODUCTION ...................................................................................................................... 82

7.2 132KV POWERLINE CORRIDOR AND THE SUBSTATION ALTERNATIVES ........ 82

7.2.1 Alternative S1 (Preferred) .......................................................................................... 82

7.2.2 Alternative S2 (Optimal) ............................................................................................. 83

7.2.3 General project impacts ............................................................................................. 83

7.3 HERITAGE ISSUES ................................................................................................................. 84

7.3.1 Mitigation measures ................................................................................................... 84

7.4 BIODIVERSITY ISSUES ........................................................................................................... 84

7.4.1 Ecological impacts ...................................................................................................... 85

7.4.2 Avifaunal habitat destruction ..................................................................................... 86

7.4.3 Avifaunal electrocution ............................................................................................... 87

7.4.4 Avifaunal collision with infrastructure ....................................................................... 88

7.4.5 Soil erosion .................................................................................................................. 89

7.4.6 Continued dust generation and emissions .............................................................. 89

7.4.7 Visual disturbance of natural landscape and sense of place ............................... 89

Page 6: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

6

7.4.8 Job creation, empowerment and skills development ............................................ 90

7.4.9 Influx of construction workers and job seekers and risk of theft and damage to

property 90

7.4.10 METHODOLOGY APPLIED FOR THE ASSESSMENT OF POTENTIAL

IMPACTS ..................................................................................................................................... 90

7.4.11 No-go alternative (compulsory) .................................................................................. 1

7.4.12 Environmental impact statement ................................................................................ 1

7.4.13 Heritage .......................................................................................................................... 2

7.4.14 Avi-faunal ....................................................................................................................... 3

7.4.15 Visual .............................................................................................................................. 7

7.4.16 Current and Existing Land Use ................................................................................... 7

7.4.17 No-go alternative (compulsory) .................................................................................. 7

7.5 RECOMMENDATION OF PRACTITIONER ..................................................................... 9

Figure 1: Map showing the project location ...........................................................................15

Figure 2: Locality Map ..........................................................................................................17

Figure 3: Sensitivity map for the project area ........................................................................29

Figure 4: Access road that exist on site ................................................................................34

Figure 5: location of the study area ......................................................................................36

Figure 6: Locality map showing the project area in the red colours .......................................37

Figure 7: Flood line zones ....................................................................................................42

Figure 8: The critical biodiversity area map ..........................................................................63

Page 7: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

7

Figure 9: Regional vegetation map .......................................................................................73

Figure 10: Vegetation type found in the area of the proposed project ...................................74

Figure 11: Proof of on-site notices ........................................................................................77

Table 1: Definitions ................................................................................................................ 9

Table 2: Acronyms ...............................................................................................................10

Table 3: Regulations and listed activities ..............................................................................18

Table 4: Minimum standards to be used for vegetation clearing for the construction of a new

line ................................................................................................................................21

Table 5: EIA team .................................................................................................................27

Table 6: Coordinates for preferred substation and alternative substation .............................30

Table 7: Coordinates for the preferred Power line ................................................................30

Table 8: Coordinates for the alternative power line ...............................................................30

Table 9: The physical size, length and the servitude of the activity .......................................33

Page 8: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

8

Table 10: Example of the monopole .....................................................................................48

Table 11: EIA process ........................................................................................................55

Table 12: Waste Profile ........................................................................................................65

Table 13: Property description ..............................................................................................67

Table 14: Land owners .........................................................................................................67

Table 15; Level of Education ................................................................................................69

Table 16: Biodiversity planning category ..............................................................................70

Table 17: Ecosystem types ..................................................................................................72

Table 18: Public participation key stake holders ...................................................................77

Table 19: Comments and responses from key stakeholders.................................................78

Table 20: Impact significant ranking .....................................................................................91

Table 21: Impact rating .......................................................................................................... 1

Table 22: Construction phase ................................................................................................ 2

Table 23: Summary of impact rating ...................................................................................... 9

Table 24: Operational phase ................................................................................................11

Table 25: Operational impact rating ......................................................................................14

Page 9: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

9

DEFINITIONS Table 1: Definitions

Environmental Management Plan

A detailed plan of action prepared to ensure that recommendations for enhancing or ensuring positive impacts and limiting or preventing negative environmental impacts are implemented during the life-cycle of a project.

Environment In terms of the National Environmental Management Act (NEMA) (No 107 of 1998), “environment” means the surroundings within which humans exist and that are made up of:

The land, water and atmosphere of the earth;

Micro-organisms, plant and animal life, and

Any part or combination of (i) of (ii) and the interrelationships among and between them; and the physical, chemical, aesthetic and cultural properties and conditions of the foregoing that influence human health and wellbeing.

ESKOM‟s Project Manager The person appointed by the Eskom from time to time to act in the capacity and notified, by name and in writing by the Eskom to the Contractor, to act as required in the contract.

Environmental Control Officer

An individual nominated through the Project Coordinator to be present on site to act on behalf of the Project Coordinator in matters concerning the implementation and day to day monitoring of the EMP.

Contractor A person or company appointed by the ESKOM to carry out stipulated activities

Rehabilitation Rehabilitation is defined as the return of a disturbed area to a state which approximates the state (where possible) which it was before disruption. Rehabilitation for the purposes of this specification is aimed at post-reinstatement re-vegetation of a disturbed area and the insurance of a stable land surface. Re-vegetation should aim to accelerate the natural succession processes so that the plant community develops in the desired way, i.e. promote rapid vegetation establishment.

Site Manager The person, representing the Contractor, responsible for all the Contractor‟s activities on the site including supervision of the construction staff and activities associated with the construction phase. The Site Manager will liaise with the Principal Agent in order to ensure that the project is conducted in accordance with the Environmental Management Plan.

Page 10: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

10

ACRONYMS

Table 2: Acronyms

BA Basic Assessment

C Contractor

DEA Department of environmental affairs

DWA Department of Water Affairs

EAP Environmental Assessment Practitioner

ECO Environmental Control Officer

EMP Environmental Management Plan

EIA Environmental Impact Assessment

EIR Environmental Impact Report

I&AP Interested and Affected Party

OHSA Occupational Health and Safety Act

PPE Personal Protective Equipment

PM Project Manager

RE Resident Engineer

Page 11: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

11

1. CHAPTER ONE: INTRODUCTION AND BACKGROUND

The purpose of this chapter is to introduce the reader to the project and communicate the

process followed as well as the purpose of this document.

1.1 INTRODUCTION

Eskom Holdings (SOC) Limited, Limpopo Operating Unit (LOU) is mandated by the South

African Government to ensure the provision of reliable and affordable power to South Africa.

Eskom currently generates approximately 95% of the electricity used in South Africa. Therefore,

electricity must be generated in accordance with supply demand requirements. Eskom‟s core

business is in the generation, transmission (transport), trading and retail of electricity.

The reliable provision of electricity by Eskom is critical for industrial development and related

employment and sustainable development in South Africa. As electricity cannot be stored,

power is generated and delivered over long distances at the very instant that it is required. In

South Africa, thousands of kilometres of high voltage transmission lines (i.e. 765 kV, 400 kV and

275 kV transmission lines) transmit this power to Eskom‟s major substations. At these major

substations, the voltage is down-rated and distributed to smaller substations all over the country

via distribution lines (e.g. 132 kV, 88 kV and 66 kV power lines). Here the voltage is down-rated

further for distribution to industry, businesses, farms and homes. In order to maintain a reliable

power supply within the entire network, the voltages at all substations are required to be within

certain desired limits.

If the network is operated at voltages which are below these limits, voltage collapse problems

and power outages may be experienced. Reliable delivery of electricity concerns consumers

and industries which require a high quality of power supply for sensitive electronic equipment,

and which incur high expenses as a result of even a short electricity supply interruption. To be

reliable, the transmission network must have the capacity to supply the electricity required by

the customers at all times. That is, the network must be designed with reserve transmission

capacity in order to ensure an uninterrupted supply to customers if and when faults occur. As a

transmission network reaches capacity, the operation of the Transmission lines becomes more

critical.

In the event of a network being increasingly operated above its design capacity during peak

periods, and two particular concerns arise:

energy losses increase significantly along the transmission lines; and

the voltage drop along the lines increases to a point where supply becomes unstable

and the line “goes down”, and supply on that transmission line is lost.

Page 12: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

12

When a transmission line “goes down” it is usually possible to re-route the electricity via other

lines in the network. However, when the network is already close to capacity, there is a

greater risk that the entire network will “go down”, cutting supply to the region for an indefinite

period of time. In addition, routine maintenance on the transmission network becomes

restricted, resulting in the heightened deterioration of the network over time. This

deterioration, ultimately, also affects the performance of the transmission network.

There is a growing demand of electricity in the Vuwani/Dzwerani area contributed by the

electrification load, new Nandoni dam loads as well as the new residential developments in

the area.

Given the above observation, Eskom Holdings (SOC) Limited Limpopo Operating Unit (LOU)

intend to submit an application for environmental authorisation to the National Department of

Environmental Affairs for the proposed construction of Mamphuli-Dzwerani EXT A substation at

Mamphuli village and 2x132 kV loop in loop out from the existing Nesengani-Venula 132kV

power line at Tshitungulwane village, near Vuwani town, within Vhembe District Limpopo

Province

This draft BA Report focuses in depth on issues which were identified during the field

assessment and Public Participation phases. It consists of Heritage, bird, flood line and

ecological specialist investigations, a detailed desktop research, public participation process as

well as an impact assessment based on identified environmental aspects.

Impacts will be evaluated and assessed in terms of

Nature (what is affected and how)

Extent (local, region or national)

Duration (short, medium, long term or permanent)

Intensity (is the impact destructive or benign)

Probability (describing the likelihood of the impact actually occurring)

The Environmental Management Programme Report (EMPr), included in Appendix F of this

report has also been compiled to complete the draft BA Report. The main objectives of the

EMP are to identify actions and mitigation measures to minimize expected negative impact and

enhance positive impact during all development phases (design/pre-construction, construction,

and post-construction/operation) in terms of community issues, construction site preparation,

construction workers, habitat protection and security.

DEA will review the draft BA Report and EMPr and one of the following decisions may apply:

Accept the activity and give us the go ahead to submit the final BAR

Refer the report for specialist review

Request further information or investigations

Page 13: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

13

MBOFHO consulting and project managers endeavors to submit a comprehensive report

inclusive of all relevant data and information in order to enable DEA to make informed

comments subsequent to the submission of this draft Basic Assessment Report (BAR)

1.1.1 The key objectives of this Final BA process include the following:

Carry out relevant specialist studies;

Conduct public participation;

Assess receiving environment;

Undertake quantitative assessment of significant environmental impacts and identify concomitant mitigation measures;

Evaluate alternatives through a comparative analysis; and

Compile EIA Report in accordance with the requirements stipulated in GNR 327 Listing

Notice 1 (7 April 2017) regulation 32(2). Refer to Chapter 1 for the document‟s

composition, in terms of the regulatory requirements.

1.1.2 The objectives of the report are the following:

To describe the need for the project;

To explain the environmental legal framework governing the project;

To explain the Environmental Impact Assessment (EIA) – Basic Assessment Process;

To present the assumptions and limitations associated with the EIA;

To describe how the proposed project will be executed during the project life-cycle;

To provide a description of the receiving environment that could be affected by the proposed project;

To provide a summary of the specialist studies conducted as part of the EIA;

To assess the significant impacts associated with the project;

To conduct a comparative analysis of the proposed;

To describe the public participation process that was undertaken to date, as part of the EIA phase; and

To draw conclusions regarding the EIA – BA Process and to make recommendations for decision making.

Description of Activity

Page 14: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

14

This draft Basic Assessment is being undertaken for the following main activities:

The proposed development of Mamphuli-Dzwerani ext a substation at Mamphuli village and

an approximately 6km loop in loop out Bersfort of 2x132kv power line from an existing 132kv

power line at Tshitungulwane village, near Vuwani town under Vhembe district in the

Limpopo province.

1.1.3 Project Location

Eskom Holdings (SOC) Limited Limpopo Operating Unit (LOU) proposes to establish a new

Mamphuli-Dzwerani EXT A substation and a 2x132kV power line LILO to connect at the

Nesengani-Venulu 132kV powerline at Tshitungulwana village near Vuwani town.

The project entails the following:

Establishment of 150m x 150m Mamphuli-Dzwerani EXT A Substation at GPS

coordinates S23°04‟40.79”E30°25‟38.08”

Establishment of a 6km Loop in Loop out (LILO) 2x132kV power lines from the new

Mamphuli-Dzwerani EXT A substation to connect to the existing Nesengani-Venulu

132kV power line at Tshitungulwane at GPS coordinates

S23°07‟25.12”E30°26‟04.46”

The proposed LILO route (Alternative route 1 preferred) is approximately 6 km of 132kV.

Page 15: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

15

Figure 1: Map showing the project location

The proposed new 132 kV power line and associated substation will be constructed on the

following farms:

The proposed substation falls in the Dzwerani 22LT, with the following SGID

T0LT000000000022LT00000

The following farms are affected by the power line;

Maltlicatt of Murziafera 25LT,

Alverton 26LT

Langverwacht 27LT

The following SGID are for the above named farms respectively:

T0TL000000000025LT00000

T0TL000000000026LT00000

T0TL000000000027LT00000

Page 16: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

16

1.1.4 MOTIVATION FOR THE PROJECT

The project will ensure that the current power supply is strengthened in the area (Vhembe

District: Makhado local municipality and Thulamela Local Municipality).

Currently electricity power supply in the area is very poor thus unable to meet the basic

needs for socio-economic development and upliftment in the area. In the broader sense the

proposed project will inevitable support various electricity requiring a stronger grid

connection.

From an overall environmental sensitivity and planning perspective, the proposed grid

connection supports the broader strategic context of the 2 of 3 of Municipalities as it is

directly linked to the strategic objectives of these Municipalities, which is a stronger and more

reliable electrification network. Moreover, a strong network is considered a driver for

economic growth in the region as per the Vhembe District Municipality‟s IDP. The non-

exceedance of social, ecological, hydrological, visual or avifaunal limit will results from the

construction of the proposed substation and the two power lines project and no significant

disturbance of biological diversity is anticipated, as detailed in this draft Basic Assessment

report and its Impact Assessment report.

Page 17: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

17

Figure 2: Locality Map

1.2 Legal requirement

The GNR 327 Listing Notice 1 (7 April 2017) and Sections 24 (2) (a) and (d) of the National

Environmental Management Act (NEMA) (Act No. 107 of 1998) as amended identifies

activities which may not commence without an authorisation from the competent authority,

the Department of Environmental Affairs, (DEA National). In order to apply for authorisation

for the investigation, assessment and communication of potential impacts of the activities

must follow the procedure as described in regulations 16 to 25 of the Environmental Impact

Assessment Regulations, (2014), promulgated in terms of section 24(5) of the Act.

The proposed project is subject to a Basic Assessment process in terms of the following

listed activities:

Page 18: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

18

Table 3: Regulations and listed activities

Activity No (s) Listed activity Description of project activity

Government Notice R.327 Listing Notice 1 GNR 327 Listing Notice 1 (7 April 2017) Item 11

The development of facilities or infrastructure for the transmission and distribution of electricity- (i) outside urban areas or industrial complexes with a capacity of more than 33 but less than 275 kilovolts

Proposed construction of Mamphuli-Dzwerani EXT A substation at Mamphuli village and 2x132 kV loop in loop out from the existing Nesengani-Venulu 132kV power line at Tshitungulwane, near Vuwani town,

Government Notice R.327 GNR 327 Listing Notice 1 (7 April 2017) Listing Notice Item 27

The clearance of an area of 1 hectares or more, but less than 20 hectares of indigenous vegetation, except where such clearance of indigenous vegetation is required for- (i) the undertaking of a linear activity; or (ii) maintenance purposes undertaken in accordance with a maintenance management plan.

The proposed Mamphuli-Dzwerani EXT A substation will cover an area of approximately 150m x 150m.

Government Notice R.324 GNR 324 Listing Notice 3 (7 April 2017 Item 4

The development of a road wider than 4 metres with a reserve less than 13,5metres. (a) In Free State, Limpopo, Mpumalanga and Northern Cape provinces: ii. Outside urban areas, in: (ee) Critical biodiversity areas as identified in systematic biodiversity plans adopted by thecompetent authority or in bioregional plans;

The proposed Mamphuli-Dzwerani EXT A Substation will need an access road which will be constructed with a width of more than 4m. Existing rural access roads and farm tracks will mainly be used. The alternative A2 (substation) and S2 (powerline) corridor traverses an area classified as CBA 2. The preferred A1 (Substation) will not affect any CBA’s.

Government Notice R.324 GNR 324 Listing Notice 3 (7 April 2017 Item 12

The clearance of an area of 300 square metres or more of indigenous vegetation except where such clearance of indigenous vegetation is required for maintenance purposes undertaken in accordance with a maintenance management plan. (a) In Eastern Cape, Free State, Gauteng, Limpopo,

The proposed Mamphuli-Dzwerani EXT A substation will cover an area of approximately 150m x 150m. the alternative A2 (substation) is identified at the area classified as CBA 2 The preferred A1 (Substation) will not affect any CBA’s

Page 19: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

19

North West and Western Cape provinces: ii. Within critical biodiversity areas identified in bioregional plans

Table 1: Listing Activities triggered

Technical Details regarding the proposed 132kV power line

Towers

The 132kV steel monopole structure has been chosen so as to cater for any future upgrades of the existing network i.e. should there be a necessity to increase the voltage in future. This configuration is designed to be highly flexible during broken conductor conditions, resulting in a very light structure.

Length

The proposed distribution power lines would commence from the proposed new Mamphuli-Dzwerani EXT A substation and connect to the existing Nesengani-Venulu 132kV powerline. The proposed total length is therefore approximately 6km.

1.2.1 Servitude Requirements and Clearances

Generally, 132 kV power lines require a servitude width of between 30m and 52m. The

proposed 132 kV power line will require a servitude width of 36m (18m either side of the

centre line of the power line).

On receipt of an approval of the final corridor by the environmental authorities and after

negotiations with landowners, the final definition of the centre line for the power line and

coordinates of each bend in the power line will be determined. Optimal tower sizes and

positions will be identified and verified using a ground survey (in terms of the Environmental

Management Plan (EMP) requirements).

Any extra area required outside the servitude shall be negotiated with the relevant land

occupiers and approved by Eskom. All areas marked as no-go areas, identified by means of

the EIA process, located inside the servitude shall be treated with the utmost care and

responsibility.

Page 20: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

20

1.2.2 Line clearances

High voltage power lines require a large clearance area for safety precautions. The

Occupational Health and Safety Act, 1993 (Act No. 85 of 1993) provides for statutory

clearances.

8 m on either side of the centre line will be cleared for 132kV power line. Grass and scrubs

will be managed in accordance with Annex B (refer to 240-52456757) which is biome and

land use dependant (Jan 2014)

If any tree or shrub in other areas would interfere with the operation and/or reliability of the

distribution line it will be trimmed or completely cleared. The clearing of vegetation will take

place, with the aid of a surveyor, along approved profiles and in accordance with the

approved EMP, and in accordance with the minimum standards to be used for vegetation

clearing for the construction of the proposed new distribution lines.

Page 21: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

21

Table 4: Minimum standards to be used for vegetation clearing for the construction of a new

line

Item Standard Follow up

Centre line of the

proposed Sub-

distribution line

Vegetation to be cut within 50mm of

the ground. Treat stumps with

herbicides.

Re-growth shall be cut within

50mm of the ground and

treated with herbicides, as

necessary.

Inaccessible

valleys (trace

line)

Clear a 1m strip for access by foot

only, for the pulling of a pilot wire by

hand.

Vegetation not to be

disturbed after initial clearing

– vegetation to be allowed to

re-grow.

Access/service

roads

Clear a maximum (depending on tower

type) 4m wide strip for vehicle access

within the maximum 8 m width,

including de-stumping/cutting stumps

to ground level, treating with a

herbicide and re-compaction of soil.

Re-growth to be cut at

ground level and treated with

herbicide as necessary.

Proposed tower

position and

proposed

support/stay wire

position

Clear all vegetation within proposed

tower position and within a maximum

(depending on tower type) radius of 4m

around the position, including de-

stumping/cutting stumps to ground

level, treating with a herbicide and re-

compaction of soil. Allow controlled

agricultural practices, where feasible.

Re-growth to be cut at

ground level and treated with

herbicide as necessary.

Indigenous

vegetation within

servitude area

(outside of

maximum 8m

strip)

Area outside of the maximum 8 m strip

and within the servitude area, selective

trimming or cutting down of those

identified plants posing a threat to the

integrity of the proposed distribution

line.

Selective trimming

Alien species

within servitude

area (outside of

maximum 8m

strip)

Area outside of the maximum 8 m strip

and within the servitude area, remove

all alien vegetation within servitude

area and treat with appropriate

herbicide.

Cut and treat with

appropriate herbicide.

Page 22: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

22

Once the tower positions have been marked, the vegetation clearing team will return to every

tower position and clear vegetation (in accordance with the EMP) for assembling and

erection purposes.

1.2.3 Foundations

Foundations will be done as follows:

The type of terrain encountered, as well as the underlying geotechnical conditions determine

the choice of foundation. The actual size and type of foundation to be installed would depend

on the soil bearing capacity (actual sub-soil conditions). Strain structures require more

extensive foundations for support than in-line suspension structures, which contribute to the

cost of the construction of the line.

Foundations would be mechanically excavated where access to the pole position is readily

available. The same applies to the pouring of concrete required for the setting of the

foundations. Prior to erecting the poles and filling of the foundations, the excavated

foundations will be covered in order to safeguard unsuspecting animals and people from

injury. All foundations are back-filled, stabilised through compaction, and capped with

concrete at ground level.

1.2.4 Access

The proposed power line is situated along the farms with existing routes that already consist

of access roads. There are farms along the proposed power line with enough access that will

be used to access the power line corridor.

A vehicle access road is usually required to be established to allow access along the entire

length of the servitude. Access is required during both the construction and

operation/maintenance phases of the line life cycle. Areas without access points and roads

will be negotiated with landowners, and are to be established during the construction phase.

Access roads will be considered for the various alternative routes being evaluated for the

proposed project.

Page 23: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

23

1.2.5 Timing

Construction for the project is likely to commence during 2018/19 financial year and the

commissioning of the power line is likely to take place in 2018 (depending on the EIA

process, land acquisition and appointment of construction contractors).

1.2.6 Continuous Maintenance

During the life span of the proposed distribution line, on-going maintenance is required to be

performed from time to time. This maintenance work is undertaken by certified contractors

employed by Eskom, and in compliance with the approved Environmental Management

Programme (EMPr).

1.2.7 Construction Process for the proposed line

The proposed power line will be constructed in the following simplified sequence:

Step 1: Determination of technically feasible alternatives.

Step 2: EIA input into route selection and obtaining of relevant environmental permits.

Step 3: Negotiation of final route with affected landowners.

Step 4: Survey of the route.

Step 5: Selection of best-suited structures and foundations.

Step 6: Final design of line and placement of towers.

Step 7: Issuing of tenders and award of contract to construction companies.

Step 8: Vegetation clearance and construction of access roads (where necessary).

Step 9: Pegging of structures.

Step 10: Construction of foundations.

Step 11: Assembly and erection of structures.

Step 12: Stringing of conductors.

Step 13: Rehabilitation of disturbed area and protection of erosion sensitive areas.

Step 14: Testing and commissioning.

Step 15: Continued maintenance.

Page 24: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

24

1.2.8 Detailed description of the listed activities associated with the project as

applied for

Activity No (s) Listed activity Description of project activity

Government

Notice R.327

Listing Notice 1 of

2017

Item 11

The development of facilities or infrastructure for

the transmission and distribution of electricity-

(i) outside urban areas or industrial complexes

with a capacity of more than 33 but less than 275

kilovolts

Proposed construction of Mamphuli-

Dzwerani EXT A substation at

Mamphuli village and 2x132 kV loop in

loop out from the existing Nesengani-

Venulu 132kV power line at

Tshitungulwane, near Vuwani town,

within Vhembe District Limpopo

Province.

Government

Notice R.327

Listing Notice 1 of

2017

Item 27

The clearance of an area of 1 hectares or more,

but less than 20 hectares of indigenous

vegetation, except where such clearance of

indigenous vegetation is required for-

(i) the undertaking of a linear activity; or

(ii) maintenance purposes undertaken in

accordance with a maintenance management

plan.

The proposed Mamphuli-Dzwerani

EXT A substation will cover an area of

approximately 150m x 150m.

Government

Notice R.324

Listing Notice 3 of

2017

Item 4

The development of a road wider than 4 metres

with a reserve less than 13,5metres.

(a) In Free State, Limpopo, Mpumalanga and

Northern Cape provinces:

ii. Outside urban areas, in:

(ee) Critical biodiversity areas as identified in

systematic biodiversity plans adopted by the

competent authority or in bioregional plans;

The proposed Mamphuli-Dzwerani

EXT A Substation will need an access

road which will be constructed with a

width of more than 4m. Existing rural

access roads and farm tracks will

mainly be used. The alternative A2

(substation) and S2 (powerline)

corridor traverses an area classified

as Critical biodiversity area CBA 2.

The preferred A1 (Substation) will not

affect any CBA’s.

Government

Notice R.324

Listing Notice 3 of

2017

The clearance of an area of 300 square metres or

more of indigenous vegetation except where such

clearance of indigenous vegetation is required for

maintenance purposes undertaken in accordance

The proposed Mamphuli-Dzwerani

EXT A substation will cover an area of

approximately 150m x 150m. the

alternative A2 (substation) is identified

Page 25: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

25

Item 12 with a maintenance management plan.

(a) In Eastern Cape, Free State, Gauteng,

Limpopo, North West and Western Cape

provinces:

ii. Within critical biodiversity areas identified in

bioregional plans

at the area classified as Critical

biodiversity area Critical biodiversity

area CBA 2

The preferred A1 (Substation) will not

affect any Critical biodiversity area

(CBA’s).

The proposed power line route alternatives traverse the Livuvhu River (and secondary

tributary) and activities 12 and 19 of GN R983 as (amended), as well as 14 of GN R, 985(as

amended) are not triggered by the proposed development.

1.3 STUDY APPROACH FOLLOWED

The approach followed by the consultants was based on the specifications for the

undertaking of a Basic Assessment as provided in the document “Regulations in terms of

Chapter 5 of the National Environmental Management Act, 1998” as approved by the

Minister of the Department of Environmental Affairs (DEA), 2010. The study approach

followed by the Consultants entailed in short the following steps:

A preliminary site investigation to determine the scope of works of the project and to

familiarize with the site was done by the EAP‟s and the Eskom team.

An application form for a BA to be submitted to DEA

The Public Participation Programme (PPP) took place during June 2017 and

December 2017. It included the identification of key stakeholders, the distribution of

information letters with a request for comment to these stakeholders, as well as

advertising of the project in the local press and on site.

The proposed development is covered by the National Heritage Resources Act that

incorporates heritage impact assessments in the Final Basic assessment process. A

Phase 1 Heritage Impact Assessment was therefore undertaken by a specialist to

identify the potential impact on heritage resources.

Flood line, ecological and Avifaunal reports were done

Page 26: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

26

A Public Participation workshop was conducted on the 27 of January 2019 regarding

the proposed project. All I&AP‟s were invited to this meeting through site notices,

community structures and also assisted by the Ward Councilor of the Local

Municipality.

In the morning of the 27 of January 2019 we had a meeting with the community

representative stakeholders and at 10h00 we had a full public meeting at the local

hall.

The Final BA Report (this document) was distributed to the following stakeholders for

their comment:

DWS (Water Services as well as Water Resources Management Division)

Limpopo Heritage Resources Authority (LIHRA) / SAHRA

Department of Agriculture, Fisheries and Forestry (FORESTRY)

Department Agriculture, Fisheries and Forestry (AGRICULTURE)

Makhado Local Municipality

Department of Rural Development and Land Reform

Limpopo department of Economic development, Environment and tourism (LEDET)

1.6 DETAILS AND EXPERTISE OF THE ENVIRONMENTAL ASSESSMENT

PRACTITIONER

Mbofho consulting and project managers have been appointed by Eskom as the independent

Environmental Assessment Practitioner (EAP) to undertake the environmental assessment

for the proposed project.

In accordance with Regulation22 (2)a of GN No. R. 327 of 2017, this section provides an

overview of Mbofho consulting and project managers and the company‟s experience with

EIAs, as well as the details and experience of the EAPs that form part of the EIA team.

Mbofho consulting and project managers are an independent, specialist environmental,

social development and Occupational Health and Safety (OHS) consultancy, which were

founded in November 2011. The company is directed by a team of experienced and capable

environmental specialist.

The company has offices in Polokwane, Nelspruit, Gauteng and North West Province.

Team members of Mbofho consulting and project managers that are involved with the Basic

Assessment Process for the proposed Eskom project are captured in Table 5 below.

Page 27: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

27

Table 5: EIA team

Name Qualifications Experience Duties

Mr Matodzi A.

Silidi

B.Env Sc.

PG in Heritage st.

M.A Environmental Management

12 years Senior EAP

Mrs T.R Silidi BA (Hons)

MA Social Impact Assessment.

Negotiation

9 years Public Participation

Coordinator

Dr E. Matenga PhD Heritage and Archaeology

Co-Reviewer

20+ years Archaeologist

Mr. Mugove

Njovo

PhD Student in Environmental

science

Master science safety Health and

Environmental Management

BSc honors Geography and

Environmental science

BSc Geography and environmental

studies

Diploma in Education

11 years EAP

Page 28: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

28

2. CHAPTER TWO: PROJECT INFORMATION

The purpose is to supply relevant information regarding the proposed project to illustrate the

extent of the project components.

2. Feasible and Reasonable Alternatives

Two (2) route servitude/corridor and substation site alternatives were considered for the

proposed new Mamphuli-Dzwerani EXT A substation and 2x132 kV power line as

preferred and alternative.

These are as follows:

The preferred location of the proposed substation is situated on the Remainder of the Farm

Dzwerani 22-LT, just south of the village of Dzwerani. The preferred line leaves the

substation and heads in a south-south-easterly direction for approximately 500m

before crossing the Luvuvhu River. The line continues on the Remainder of the Farm

Matlicatt or Murzia Fera 25LT for approximately 640m, then turns and heads in a

south-south-westerly direction for approximately 1.5km. The line continues on the

Remainder of the farm Alverton 26-LT for another 920m before turning in a south-

south-easterly direction on Portion 1 of the Farm Langverwacht 27-LT for

approximately 1.9km. The line turns in a southerly direction for approximately 230m

before joining the existing high voltage line. The positive part of the preferred lines is

that they impact less to the environment since it is traversing already disturbed area.

The alternative site for the substation is situated 1.2km due east of the preferred site.

The Alternative line heads in a southerly direction for approximately 1km before

crossing the Luvuvhu River. The alternative line continues on the same path for

another 4.3km in a straight line before joining the existing high voltage line at the

same point as the preferred route.

The majority of the preferred route occurs within areas considered to be of medium

ecological sensitivity. Impact on the surrounding vegetation will therefore not be

severe and most impacts can be mitigated.

The alternative route, has sections within highly sensitive areas, where the impacts

on the vegetation will be high.

The preferred power line route is therefore recommended over the alternative route,

from a floral perspective

Page 29: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

29

The proposed alternative A2 Mamphuli-Dzwerani EXT A substation is found at the

Critical Biodiversity Area 2 (CBA2).

The alternative power line S2 crosses a small kopje and the alternative

substation is close to the kopje which makes it too expensive for Eskom to drill

and blast before construction. The drilling of a kopje to provide the foundation

for the pylons might have negative impacts on the kopje environment. The area

around the kopje is not ideal for the establishment of the substation

The alternative power line to the alternative substation S2 traverse through the

established private farms (orchard). The power line will have adverse impacts on

socio-economic of the area. Local community members who make the living from the

Orchard might lose their income if part of the orchard is impacted by the power lines.

The sensitive map below indicates the various sensitive maps within the project area.

Figure 3: Sensitivity map for the project area

Page 30: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

30

2.1 Site alternatives

2.1.1 Coordinates for the preferred and Alternative site:

Table 6: Coordinates for preferred substation and alternative substation

preferred alternative S23 04 40.79 E30 25 38.08

Alternative: S23 04 23.94 E30 26 20.10

2.1.1.1 Coordinates for the preferred site

Table 7: Coordinates for the preferred Power line

Starting point of the activity S23 04 40.79 E30 25 38.08

Middle S23 06 28.70 E30 25 20.01

Other coordinates along the line

1 S23 07 25.15 E30 26 03.94

2 S23 07 17.44 E30 26 03.45

3 S23 06 28.79 E30 25 19.40

4 S23 05 14.74 E30 25 56.13

5 S23 04 40.79 E30 25 38.09

6 S23 07 17.25 E30 26 03.97

7 S23 06 28.70 E30 25 20.01

8 S23 05 14.73 E30 25 56.72

10 S23 04 23.12 E30 26 04.46

11 S23 07 25.92 E30 26 20.26

End point S23 07 25.12 E30 26 04.46

2.1.1.2 Coordinates for the Alternative power line

Table 8: Coordinates for the alternative power line

Starting point of the activity S23 04 23.94 E30 26 20.10

Middle S23 06 28.70 E30 25 20.01

End point S23 07 25.12 E30 26 04.46

The alternative is just but a straight line from the start to the end, so the given coordinates

will be connected with a straight line (start, middle and end)

Page 31: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

31

2.2 Lay-out alternatives

The design and layout of Eskom substation alternatives should conform to the Eskom‟s

technical standards and requirements, as such no lay out alternatives have been considered.

The design of the power lines is required to conform to the Eskom‟s technical standards and

requirements as it form part of the uniform National Electrical Supply network and should fit

in with the existing network systems, technology and infrastructure. The broader corridor

being assessed with this Environmental Impact Assessment Study allows for the avoidance

of the identified environmental sensitivities to some extent through the appropriate placement

of the 32m wide servitude within the 300m wide corridor

The width of the servitude radius that was assessed was 300m either side of the power line

and the actual Eskom servitude is 37, 5m.

The size of the substation within the 150mx150m footprint is not yet known. The designs are

still underway. What is known is that the substation will fit within the applied area.

There is an existing access road. It is only a matter of making it drivable. It will be

approximately 6km.

2.3 Technology alternatives

No technological alternatives exist for the distribution of electricity and as such the

Technology alternatives were not assessed

2.4 Other alternatives (e.g. scheduling, demand, input, scale and design

alternatives)

The design of substation and power lines will be based on widely proven and accepted

industry standards and does not significantly affect the environmental impacts of the

proposed development in any way, as its footprint will not exceed the specifications, or

extend beyond the assessed corridors of 300m or substation size of 150m x 150m. In

likelihood, use will be made of steel monopole structures for the proposed power lines, which

is preferred over the lattice tower structures due to the smaller overall footprint. This will

however be dictated by the site-specific conditions and landowner requirements. The power

lines and substation to be constructed according to the authorised standards for a power line

approved by the Eskom Holdings SOC Ltd

Page 32: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

32

2.5 Power line Design Alternatives

Two alternatives were assessed for the power lines. Underground cabling was not assessed

for the siting of this project as it is technically feasible over long distances

2.6 Alternative 1 (preferred power line design) – single Circuit Overhead Power

line

The use of single circuit overhead power lines to distribute electricity is considered the most

appropriate technology. The technology has been developed in consideration of

environmental conditions and terrain as specified by Eskom Specifications and best

international practice. Based on all current landscape and ecological parameters, a single

circuit overhead power line is considered the most environmentally practicable technology for

the distribution of power. This option is considered appropriate for the following reasons:

Lower installation and maintenance costs compared to other types of pylon structures

that could potentially be erected

Limited environmental damage during installation

2.7 Alternative 2 (alternative power line technology) – Underground Cabling

Underground cables are typically only used over short distances, are predominately used in

medium and low voltage networks, as well as for power distribution in densely built up areas

with high electricity demand. Furthermore, underground cables have economic and

ecological disadvantages and have thus not been taken into consideration for this project

2.8 No-go alternative

The no-go alternative is also referred as the do-nothing alternative and looks at the situation

where the proposed infrastructure will not be constructed. In this scenario the potential

positive and negative environmental and social impacts as described will not occur. The

status quo will be maintained.

Electricity is generated, supplied and distributed by Eskom via a network called a “Grid”. The

amount of electricity being fed into the grid must always match what the customers are taking

out. The amount of electricity required by the customers varies not just from day to day, but

from minute to minute. As electricity demand increases, and loads are connected, more

power stations and associated substations and lines need to be built to meet the electricity

demands.

Page 33: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

33

Eskom Grid Planning is responsible for establishing future electricity demands as a result of

growth and development. Once an area has been identified where future growth will result in

electricity constraints, methods for strengthening the grid to sustain future growth patterns is

considered. The current supply is not sufficient to carry the requisite load and as such the

new Mamphuli-Dzwerani EXT A substation and the 132kV power line to ensure a stable and

efficient electricity supply for the future. After Eskom Grid Planning has identified the selected

method to strengthen the grid, the power line between Elim and Malamulele which will be

required for this project was identified. This project is required to strengthen the grid in order

to ensure stable electricity supply. Without the proposed power line, the power outages will

continue, the Strengthening Scheme project cannot take place and the grid can therefore not

be strengthened.

If this project is not implemented, it will negatively impact the future electricity supply of the

area. Eskom will not be able to meet the current capacity demand of the region. That will

subsequently affect the economic growth of the country at large.

Ultimately, the project will improve the performance of the supply to the region, in turn

contributing to a greater availability of electricity to residents and industry in the area. By not

increasing the supply to the greater area, development will be constrained.

2.9 Physical size of the activity

The following are the physical size of the preferred activity/technology as well as alternative

activities/technologies (footprints):

Table 9: The physical size, length and the servitude of the activity

Item Options Size of the activity

1 Preferred activity 22500m2

2 Alternative 22500m2

Length of the activity

1 Preferred activity 6km

2 Alternative 7m

Size of the site/servitude

1 Preferred activity Servitude:36m Corridor:

300m

Page 34: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

34

2 Alternative Same as above

2.10 Site Access

The project will provide a new access road to the substation. There is an existing access

route to the project area. The main accesses connect from both Mamphuli-Dzwerani EXT A

and Mamphuli villages to the substation and also the power lines. There is an existing gravel

road currently used by the sand miners to the river in both sides. From Tshitungulwana

village, there is a new tar road to the village, and also a gravel road that runs parallel to the

new proposed power lines which service the Orchards and some fields. There is another

access from Tshino side that goes to Lwenzhe Technical School. Access roads have been

established linking to the proposed power line, which are those accessing farms and are

enough, where access roads are not in good condition, there will be maintained using the

same material as existing roads as they are shown on the map below;

Figure 4: Access road that exist on site

Page 35: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

35

2.11 Locality Map

Mamphuli Village is located on a low plain 15km distance from the foothills of the

Soutpansberg Mountains and the same distance southwest of Thohoyandou as the crow

flies. This area is close to the western limits of the Lowveld, a vast plain east of the

Soutpasberg Mountains, which stick out prominently from the plain. Drainage is controlled by

the Luvubu descending from the south-eastern slopes of the Soutpansberg. Mamphuli village

is spread on a minor watershed between the Luvubu to the south and a minor tributary to the

north, both rivers trending northeast to a confluence just before the tail end of Nandoni Dam.

Vegetation configuration is the Lowveld type although to an extent degraded with a few

mature scattered trees; this is due to human settlement and cultivation. But the edges of the

Luvubu River nestle good riverine woodland with some evergreen species. Grass cover is

dense on the river sides.

Page 36: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

36

Figure 5: location of the study area

Page 37: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

37

Figure 6: Locality map showing the project area in the red colours

2.12 Layout/Route Plan

A Map shows the layout/ route plan of the proposed power line. It is also included as part of

this report as Appendix C

Page 38: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

38

Page 39: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

39

Page 40: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

40

Page 41: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

41

Page 42: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

42

2.13 Sensitivity areas

2.13.1 Watercourses and Flood Line

The 1:50-year and 1:100-year flood lines were calculated using the HEC-GeoRAS and HEC-

RAS programmes; and The flood lines were plotted in ArcGIS with the proposed power line

in order to identify any potential encroachment. The power line traverses once through the

Luvuvhu River and its second tributary. No flood encroachment is indicated on the proposed

power line route except at the two points where the power line crosses the Luvuvhu River

and the second tributary. The development of surface infrastructure associated with the

power line at the river crossings should be outside the 1:100-year flood line in order for the

power line development to fully comply with the requirements of the National Water Act, Act

36 of 1998. The means that the installation of pylons at the river crossings should be guided

by the flood line extents as indicated in Figure 7.

Figure 7: Flood line zones

Based on the discussion of the hydrology and hydraulics of the proposed project power line

study, the following conclusions were drawn:

Page 43: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

43

The project is characterized by a MAP, MAE and MAR of 676 mm, 1647 mm and 136 mm,

respectively. These values indicate evaporative losses of more than 2 times higher than

incident precipitation which implies seasonal surface flow and associated flood risks on the

proposed power line development. Significant runoff is portrayed with an order of magnitude

of 20% of incident rainfall and this indicates the influence of paved areas associated with the

proximal built-up area to the project site.

The peak flow values used in hydraulic modelling ranged from 37.3 m3/s to 712.5 m3/s for

the analysed watercourses on the project area. These peak flows were calculated using the

RM3 method and were deemed more realistic for the site over those for the SDF and the

MIPI methods. Modelled flood lines show proportionate extents to the aforementioned initial

flow data and these provide an overview of low flood hazards in the assessed project site.

No flood encroachment is indicated on the proposed power line route except at the two

points where the power line crosses the Luvuvhu River and the second tributary. The

installation of surface infrastructure associated with the overhead power line at the river

crossings should be outside the 1:100-year flood line. This is achieved by superimposing the

proposed pylon locations at the river crossings on the 1:100-year flood line and where

encroachment is identified pylon locations should be shifted accordingly to avoid the

demarcated 1:100yr flood waterway. The power line elevation at the Luvuvhu River and the

Tributary 2 crossings should not be below 562.67 and 597.96 mamsl in order to be above the

highest water surface elevations at these crossings. The location of cross sections at the

river crossing points are presented in the attached flood line report.

If the recommended vertical and horizontal pylon installation specification measures are

implemented, no significant flood risks will be experienced in the power line development

project. As such, the power line will comply with the requirements of the National Water Act,

Act 36 of 1998 which stipulates that any development infrastructure should be placed outside

the 1:100-year flood line.

2.13.2 Areas with indigenous vegetation

Combretum apiculatum is the dominant tree species on the slopes and plains while

Senegalia (Acacia) nigrescens,Dichrostachys cinerea and Grewia bicolor dominate the

thickets in the bottomlands. Terminalia sericea is the common woody species in the deep

sandy uplands. Five stunted Marula trees Sclerocarya birrea subsp. caffra were recorded in

the northern section of the route to the north and south of the Levuvhu River. This is the only

formally protected tree species recorded in the survey area. The Marula is listed as a

provincially protected plant species under Schedule 12 of the Limpopo Environmental

Management Act – Act 7 of 2003

Page 44: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

44

2.13.3 Cultural and historical features

The Phase I HIA study for the proposed Power line Project did not reveal the presence of

any of the types and ranges of heritage resources as outlined in Section 3 of the National

Heritage Resources Act (No 25 of 1999) in the Project Area. There is consequently no

reason from a heritage point of view why Eskom‟s proposed power line and substation

Project should not continue.

2.13.4 Visual impact assessment

In terms of the visual impacts the proposed development (with mitigation) will have a

moderate to major negative impact over the short term; and moderate negative impact over

the long term

2.13.5 Avifaunal Habitats

The study area comprised mostly rural grazing lands in savanna bushveld, surrounded by

rural townships/peri-urban settlement, with a few agricultural fields and small farm dams in

the area. They are few power lines present in the landscape with the proposed route

crossing one 22kV line and joining a high voltage line in the south.

The proposed powerline route traversed mostly dryland habitat consisting of savanna

bushveld dominated by grass species in areas where the trees have been cleared for

grazing, and denser tree cover in areas where bush encroachment by microphyllous species

such as Dichrostachys cinerea (Sicklebush) was occurring. Large trees species such as

Ficus sur (Broom) and Sclerocarya birrea (Marula) dotted the landscape. Although disturbed

by subsistence grazing, many savanna bird species were observed in this habitat during the

field surveys. This habitat represented the most important habitat to birds in the study area.

Page 45: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

45

The northern section of the proposed powerline route crossed the Luvuvhu River and its

associated riparian habitat. A non-perennial tributary of the Luvuvhu River also occurred in

the study area, which the line crossed towards the southern end. High avifaunal activity was

detected in and around the riparian habitat associated with the river and its drainage lines. A

Hamerkop (Scopus umbretta) nest was observed in a large Ficus sur tree at the crossing

point on the north bank of the Luvuvhu River. Watercourses and wetlands are usually areas

of high avifaunal diversity as the riparian environment and dense vegetation provides

abundant cover, feeding and breeding habitat for many species of invertebrates, birds,

mammals, reptiles and amphibians. When it is available, surface water provides drinking

water, while the soft substrate provides burrowing environments for fossorial animals. The

increase in prey and vegetation attracts a high diversity of birds as well as terrestrial

mammals and reptiles

The region of the study area is biodiverse with around 463 bird species occurring in QDGC

2330AB according Roberts Multimedia (SA Birding, 2011).

To date SABAP2 has reported approximately 255 bird species recorded within the QDGC. Of

these, 38 species are of conservation concern. These include species with a national and/or

global conservation status higher than Least Concern. In additional, 61 bird species

occurring in the QDGC are of special concern as they are protected under the Convention on

the Conservation of Migratory Species of Wild Animals (CMS, 2017).

A total of 54 bird species were recorded in the study area during the field surveys (Table 4),

mostly in the savanna bushveld habitat and at the Luvuvhu River. A higher number of

species can be expected in the study area as sampling did not reach saturation due to the

short time in the field. None of these are currently listed as being of conservation/special

concern, and only a few that are considered vulnerable to the impacts of power lines.

Ten species of conservation concern were however given a high likelihood of occurring in the

study area. These consisted of species such as raptors, korhaans, and bustards. Such

species are also considered vulnerable to the impacts of power lines. In fact more raptors,

game birds and herons were expected to occur in the area due to the presence of suitable

habitat. The fact that more game birds were not recorded could be explained by the proximity

of the study area to residential areas and hunting pressure by the local people. This in turn

would explain the absence of raptors.

Page 46: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

46

2.13.6 Major Known Impacts of Power lines on Avifauna

Electrical infrastructure comprises a significant interface between wildlife and man due to the

nature and distribution of electrical structures within the landscape. The development of new

electrical infrastructure poses three primary threats to avifauna: (1) electrocution of birds

perching on or near conductors; (2) collisions of birds with overhead wires or moving parts of

power generators such as wind turbines; and (3) habitat loss through the destruction or

degradation of vegetation during construction. Electrocution and collision associated with

electrical infrastructure are common causes of unnatural mortality to many bird species and

may significantly impact on population structure (Sergio et al., 2004). Conversely, power

supply may be interrupted which has negative economic impacts resulting from damaged

equipment, loss of service to the power grid, human safety issues and veld fires.

2.13.7 High Risk Landscape Features

Cranes, bustards, flamingos, waterfowl, gamebirds, large birds of prey (including vultures)

and falcons are among the avian groups most frequently affected by electrocution and

collision associated with electrical infrastructure (Jenkins et al., 2010). These species

generally occur in a few key types of habitat with specific topographical landscape features,

i.e. open, flat areas such as grassland and wetlands, and mountainous or hilly areas with

ridges, cliffs or rocky outcrops. Topographic relief pattern affect avian flight paths by aligning

them along ridges, over passes and through valleys as they follow energetically economical

ways to travel across country (APLIC, 1994; Jenkins et al., 2010). Areas with high

topography also tend to have extreme weather conditions where the occurrence of mist, fog,

low cloud and high winds is frequent, putting the avifauna inhabiting the area at risk

(Bevanger, 1994).

A basic factor for survival requires birds to make regular and direct flights between resource

points. Waterbirds flying between wetlands are at risk of collision with powerlines as they are

generally large bodied, flocking species with low manoeuvrability, low ocular acuity and tend

to fly at powerline height. Similarly, gamebirds, bustards and cranes inhabiting grasslands

are at risk where short, open vegetation encourages low altitude flying (APLIC, 1994).

Species that engage in behaviours such as high-speed aerial chases and elaborate aerial

displays are at risk and are usually associated with open areas with short vegetation such as

grassland.

Page 47: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

47

Bird species with specific habitat requirements and restricted ranges are the most at risk with

respect to habitat destruction. As a result many priority bird species or species of

conservation concern are associated with vegetation types that are unique and are restricted

and/or isolated within the landscape. Examples of these habitat types within the study area

include grassland and wetland

2.14 Site Photographs

2.15 Facility Illustration

The project‟s facility illustration is shown below;

Page 48: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

48

Table 10: Example of the monopole

2.16 Activity Motivation

Both the substation and the power line corridor passes through land which is zoned as

agricultural land. An Environmental Authorisation is required to construct the proposed

22/132kVMamphuli-Dzwerani EXT A substation and 2 x ±6km overhead power line. The

activity is a linear infrastructure that will cross various properties. Eskom will be required to

negotiate right of way servitude for the power lines within the nominated preferred power

lines corridor.

2.16.1 Provincial Spatial Development Framework (PSDF)

Page 49: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

49

The provincial Spatial Development Framework aims at building a prosperous, sustainable

growing provincial economy to reduce poverty and improve social development. This section

notes that in order to promote economic growth in the Limpopo Province, the availability of

power lines and substations is needed. The proposed project will create job opportunities

and enhance the current electrical supply in the Dzwerani-Vuwani area. Further the proposed

upgrade will augment electrical supply and there reduce outages which will attract more

economic activities such as mining.

2.16.2 Urban edge / Edge of Built environment for the area

The project will not be at the urban edge. The activity is mostly traversing farms/ rural

communal areas to connect between the substation and the 132kV powerline which are

outside the urban edge. Though the proposed power line does not affect the urban edge, but

the proposed line would create a visual intrusion, however, the study area has various

existing distribution lines traversing it. Furthermore, the proposed line will help ensure that

there is continuous power supply in the surrounding areas. The reliable electricity source

would open the door to new economic opportunities, within the general area, in turn

contributing to an increase in the local GDP. The powerline would ensure continuous and

stable power supply in the area which would in turn stimulate growth, development and

improve quality of life. However, it was envisaged that the proposed line would impact people

(particularly farmers), slight environment and the local economy. To understand the potential

impacts, specialists were appointed to conduct in-depth evaluations.

The specialists appointed were:

Heritage Impact Specialist

Ecological Specialist

Flood line specialist

Avifaunal specialist

2.16.3 Approved Structure Plan of the Municipality

Eskom is a State Own Company (SOC) and all electrical planning is done at the behest of

Eskom. The development is necessitated by the need to increase more power to the area in

order to support future developments housing etc. But however, Vhembe District Municipality

and its two Local Municipalities (Thulamela and Makhado/ Lim3, 4, 5) are aware of the

project.

2.16.4 Environmental Management Framework (EMF)

The approval of this application will not compromise the Vhembe District Municipality

Environmental Management Framework.

Page 50: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

50

2.16.5 Integrated Development Plan (IDP) and Spatial Development Framework (SDF)

of the Local Municipality

The IDP of the Vhembe district municipality aims at ensuring the quality of life of the Vhembe

District Municipality community through purposeful; and quality service, and the effective and

optimal utilisation of resources. This project will assist in strengthening the local electricity

supply and will facilitate development in the area, thereby assisting in job creation which will

further help achieve IDP objectives. The proposed project will not compromise the objectives

of the Integrated Development Plan and the Spatial Development Framework but it will assist

in making sure that the electrical infrastructure or facilities as outlined in the National

Development Plan 2030 of the Republic of South Africa, is immensely enhanced. The

proposed development directly address the service delivery featuring prominently on the

Local Municipality IDP and SDF

2.16.6 Environmental Management Framework (EMF)

The approval of this application will not compromise the Vhembe District Municipality

Environmental Management Framework.

2.16.7 Any other Plans

During our Public Participation process, both Thulamela and Makahdo/Lim 3,4,5 Local

Municipality and Vhembe District Municipality were consulted and the indicated that

proposed power line does not impact on their plans.

2.16.8 Community response to the activity

During the stakeholder engagement, there was no objection to the proposed project raised

except the Substation name raised by the Chief of Mamphuli village. In line with the national

electricity generation and job creation priorities, the construction of the proposed Substation

and associated 132 kV powerline will provide significant benefit to the local community.

Benefits will firstly come in the form of employment as the project has potential to create

short term employment opportunities for the local community and skills development

opportunities primarily during the construction. Secondly, the more stable and constant

supply of adequate electricity to the local areas will assist in the improvement of livelihoods

and quality of living of the local communities. Local people could be employed during the

construction phase of the project as manual labour.

2.16.9 Services required and owner of the infrastructure

Page 51: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

51

No services are required for the construction or operation of the power line and a substation.

The construction of the power line infrastructure and a substation will therefore not place

additional pressure on the local area or Municipality either during construction or operation.

The power line and the substation will be owned and operated by Eskom. It therefore falls

outside of the infrastructure planning of the Municipality. The construction of the power line

infrastructure and a substation will therefore not place additional pressure on the local area

or Municipality either during construction or operation.

2.16.10 Strategic or non -strategic project

One objective regarding electricity distribution within the National Development Plan (NDP) is

that the proportion of people with access to the electricity grid should rise to at least 90 % by

2030, with non-grid options available for the rest. Resolving maintenance and the

refurbishment of backlogs is one of the actions set out in the NDP to solve this issue. This

proposed project will therefore assist in positively contributing to the improvement of the

national electricity supply situation.

The National Government recently adopted an Infrastructure Plan that is intended to

transform the economic landscape of South Africa, create a significant number of new jobs,

strengthen the delivery of basic services to the people of South Africa and support the

integration of African economies.

The Infrastructure Plan of South Africa sets out the challenges and enablers, which South

Africa needs to respond to, in the building and developing of relevant infrastructure.

Based on the work of the Presidential Infrastructure Coordination Commission (PICC),

seventeen Strategic Integrated Projects (SIPs) have been developed and approved to

support economic development and address service delivery in the poorest provinces. Each

SIP is comprised of a large number of specific infrastructure components and programmes.

The proposed development of the powerline will contribute to SIP 6 and 10.

SIP 6 regarding integrated municipal infrastructure projects, include projects that:

Develop national capacity to assist the 23 least resourced districts (19 million people)

to address all the maintenance backlogs and upgrades required in water, electricity

and sanitation bulk infrastructure; and

SIP 10, regarding electricity transmission and distribution for all, includes projects that:

Page 52: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

52

Expand the transmission and distribution network to address historical imbalances,

provide access to electricity for all and support economic development; and

Align the 10-year transmission plan, the services backlog, the national broadband

roll-out and the freight rail line development to leverage off regulatory approvals,

supply chain and project development capacity.1

The aim of the project is to expand the transmission and distribution network to address the

current electricity imbalance and provide access to electricity for the existing Dzwerani /

Vuwani residential area.

2.16.11 Land factor contextualisation

The study area falls within a landscape which is typical of most rural parts of the north

eastern Limpopo Province i.e. largely deforested open terrain (used mainly for communal

livestock free range grazing), areas of bush thickening by pioneer shrubs, fallow substance

agricultural fields interspersed with informal settlements. The proposed location for the

Substation is in the communal land under the Traditional Leadership. The Traditional

Authority is happy with the project. For this reason, the location is perfectly suited for the

proposed Substation and the powerline facility. The location and route chosen for the

powerline is therefore favourable in achieving the desired objective of electricity distribution

into the local grid while minimising the environmental impact as far as possible. The local

agricultural land-use of mostly grazing will not be adversely affected once the pylons have

been constructed as the actual footprint of natural areas transformed by the project will not

be of significant size

2.16.12 Development and the best practicable environmental option for this land/site

The project involves the establishment of a new power line in order to address the current

and future electricity supply challenges. The current environmental land-use capability is

already low. Once the pylons have been constructed the area will again be available for

agricultural utilisation mainly in the form of livestock grazing as is current practice. The

project will not adversely affect the current land-use capability and environmental potential.

The development of the powerline is essential in the success of the proposed substation

facility. Though there are some protected tree species such as Sclerocarya birrea, the

developer will need Permits for cutting, trimming and removal. The EMPr will thus provide

mitigation for any potential negative environmental impacts.

2.16.13 Project spin-offs

Page 53: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

53

Electricity has become a fundamental need and precursor of development and improvement

of people‟s quality of life. The establishment of power line will ensure that the continuous

distribution of electricity to the area is fundamental. The benefits of the proposed project will

significantly outweigh the potential negative impacts thereof. The proposed project will

contribute to improving the socio-economic conditions of the area. Local job creation, skills

development, improved livelihood and quality of life as well as adequate local electricity

supply are significant local benefits

The proposed development will provide an additional supply of electricity to the local area in

which it is proposed. The construction and subsequent operation of the proposed

development will also provide a significant financial boost to the area in terms of job creation

and skills development. The current imbalance in the electricity supply within the surrounding

areas will be restored and it will add to a higher quality of life to residents. The capacity for

the potential development of new residential areas will also be created once the proposed

electrical services development is completed. This will enhance the economic development

process within the area.

With the new project, Electricity shortages would decrease and the area would have a more

stable and sustainable supply of electricity. The continuous power supply would encourage

investors to contribute to local economic development and thus increase job creation. People

would be able to use the stable electricity supply to development their own local enterprises

and improve their exposure to the outside world through educational programs on television

and radios.

At local level, the construction phase will generate temporary employment and skills

development as part of the project proponent‟s supplier development policies that guarantee

local content in the execution of its infrastructure development programme. Local people

could be employed during the construction of the power line for manual labour (e.g. for bush

clearing and the digging of foundations).

Page 54: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

54

The negative impacts on the existing environment will be minimal due to the fact that the

proposed powerline will be constructed along the already disturbed area, with sand mining

taking place and other existing power line. Therefore, the environment has already been

exposed to similar activities and the aesthetic feel of the environment will not be greatly

affected from a visual perspective. The Ecological Impact Assessment as well as the

Heritage Impact Assessment conducted by specialists yielded a very low negative impacts

on the ecology and the very low significance on Heritage resources and impacts identified

can also be suitably mitigated to acceptable levels .This is considered to be the most feasible

solution proposed by Eskom Holding (SOC) Limited Limpopo Operating Unit (LOU), to

supply electricity to the area. No adverse impacts are anticipated from the proposed

establishment of 132kV power line. The local farmers raised their concerns regarding

irrigation areas and game breeding areas. Eskom Land and Rights will start the negotiations

with the farmers subsequent to the issuing of an Environmental Authorisation

2.16.14 Development and Precedent

There are other power lines and substation facilities in the area which distribute electricity to

various areas. The proposed powerline development will form part of a distribution network

required for electricity transmission in the area. Distribution networks are usually upgraded

and changed over time in order to optimise efficiency and adjust to the changes in

requirements and demands. It is therefore possible that the network may be altered in the

future. The new powerline will also run along the already existing line indicating that the area

has been approved for similar activities.

2.16.15 Any other need and desirability

No other need and desirability for the proposed project apart from supporting the

infrastructure development programme in line with the Government‟s New Growth Path

(NGP) and the National Development Plan to contribute to economic growth of the country.

The proposed development Electricity has become a fundamental need and precursor of

development and improvement of people‟s quality of life. The proposed establishment of new

power lines would greatly contribute to the future mining in the area. The establishment of

Power supply integrate well with the other Government initiative programs such as mining

development, service delivery and water supply as without reliable electricity supply, these

other services may not be realised. So this project appreciates the intentions of the Strategic

Integrated Projects. When the project is finished, it would further help ensure that there is

continuous power supply to the mining areas, agricultural fields, surrounding rural

communities and the entire Municipal area. The reliable electricity source would open the

door to new economic opportunities, within the general area, in turn contributing to the

increase of the local GDP

Page 55: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

55

2.16.16 EIA process

Below are various elements of the EIA process discussed in relation to the relevant sub-

sections complied with in Section 23 of NEMA:

Table 11: EIA process

Compliance Relevant sub-section in Section 23 of

NEMA

The EIA process is the selected

environmental management tool.

1

Refer to 19 below 2(c)

The assessment performed identifies,

predicts and evaluates actual and potential

impacts, and provides for mitigation of

such negative impacts.

2(b)

An EIA is performed before environmental

authorisation is granted.

2(c)

A comprehensive public participation

process has been followed in accordance

with EIA Regulation GN R327 of 2014

2(d)

Impacts with significant effects have been

brought to the attention of the competent

authority in this report.

2(e)

The general objectives of Integrated Environmental Management have been taken into

account in the development of the project by means of identifying, predicting and evaluating

the actual and potential impacts on the environment (the basic assessment process). The

risks, consequences, alternatives as well as options for mitigation of activities have also been

considered with a view to minimise negative impacts, maximise benefits and promote

compliance with the principles of environmental management.

Page 56: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

56

The required Basic Assessment (BA) in terms of the National Environmental Management

Act, 1998 (Act No. 107 of 1998) (NEMA) was undertaken for the proposed powerline, in

order to investigate and assess any potential environmental impacts associated with the

development prior to implementation. Alternatives were identified and the potential mitigation

measures of impacts to acceptable levels were also assessed during the Basic Assessment.

As part of the BA process, specialist studies were conducted to evaluate the actual and

potential impacts that the proposed development could have on the biophysical environment,

within the study area. In line with the general objectives of Integrated Environmental

Management, the risks and consequences of the various corridor alternatives were assessed

and mitigation measures were recommended by each specialist in order to minimise the

negative impacts to acceptable levels and maximise the benefits of the proposed project.

In addition, a comprehensive Public Participation Process (PPP) has been undertaken as

part of the Basic Assessment, which assists in informing of and consultation with various

interested and affected parties, key stakeholders.

2.16.17 Principles of environmental management

Through the undertaking of a Basic Assessment process by a competent Environmental

Assessment Practitioner, informed by guidelines, the consideration of impacts and

alternatives (advantages and disadvantages coupled thereto) has been made.

Moreover, the conducting of a public participation process and specialist investigations form

part of this basic assessment process, whilst mitigation measures and the needs and

desirability of the proposed project were interrogated. This ensured that all provisions of the

Act were considered and as such integrated environmental management were accounted for

as follows:

(2) Environmental Management must place people and their needs at the forefront of its

concern, and serve their physical, psychological, developmental, cultural heritage and social

interests equitably.

The goal of this Basic Assessment is to identify and adequately mitigate potential socio-

economic impacts in order to meet the terms of Section 24 of the Constitution. The project

will have considerable socio-economic benefits such as job creation, skills development and

transfer as well as adequate local electricity provision.

(3) Development must be socially, environmentally and economically sustainable.

Page 57: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

57

The overall goal of this draft Basic Assessment is to predict, identify and manage potential

positive and negative impacts in the socio-economic, cultural-heritage and biophysical

environments. This must be done in order to meet the needs of present generations without

compromising the needs of future generations (sustainable development). The distribution

and local provision of electricity will be a continuous and sustainable process while

environmental impacts will be acceptably mitigated.

(4)(a) Sustainable development requires the consideration of all relevant factors including the

following:

i. That the disturbance of ecosystems and loss of biological diversity are avoided, or,

where they cannot be altogether avoided, are minimized and remedied;

ii. that pollution and degradation of the environment are avoided, or, where they

cannot be altogether avoided, are minimized and remedied;

iii. that the disturbance of landscapes and sites that constitute the nation´s cultural

heritage is avoided, or where it cannot be altogether avoided, is minimized and

remedied;

that waste is avoided, or where it cannot be altogether avoided, minimized and reused or

recycled where possible and otherwise disposed of in a responsible manner;

Page 58: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

58

3. CHAPTER THREE: APPLICABLE LEGISLATION, POLICIES AND/OR

GUIDELINES

3.1 Applicable legislation, policies and/or guidelines

The environmental legislative framework and components for South Africa can best be

unpacked and summarised as follows.

3.1.1 The Constitution

Section 24 of the Constitution of the Republic of South Africa Act, 108 of 1996 provides the

basic right to an environment which is not harmful to a person‟s health or well-being, as well

as to have the environment protected through legislation and any measures which:-

Prevent pollution and / ecological degradation;

Promote conservation;

Secures ecological sustainable development; and

The sustainable use of resources.

At the same time, Section 25 of the Constitution guarantees everyone the right of access to

information which is essential for them to exercise their Constitutional right including any

information pertinent to the environmental assessment (EA) or EIA process. For this reason,

Public Participation is considered an essential mechanism for informing stakeholders of their

rights and obligations in terms of the project.

3.1.2 The National Environmental Management Act, 107 of 1998 (NEMA)

The National Environmental Management Act (NEMA) creates the fundamental legal

framework that gives effect to the environmental right guaranteed in Section 24 of the

Constitution and sets out the fundamental principles that apply to environmental decision

making.

3.1.3 The Principles of NEMA

The Principles of NEMA (Chapter 1) not only serve as a framework upon which

Environmental Management is based (Section 2(1)(b)), but ensures that people and their

needs are always considered (Section 2(2)). This is achieved through avoiding and

minimising:

Disturbance on ecosystems or loss of biological diversity (Section 2(4)(a)(i));

Pollution and degradation of the environment (Section 2(4)(a)(ii)); and

Negative impacts on the environment and people‟s environmental rights (Section

2(4)(a)(viii));

Page 59: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

59

The principles of NEMA further require that a cautious, methodological approach be applied

which takes into account knowledge or information gaps (Section 2(4)(a)(vii)) so that, as far

as possible, all positive or negative impacts on the environment are considered and

assessed in order to facilitate the decision-making process in mitigating these adverse

impacts (Section 2(4)(a)(i)).

3.1.4 Integrated Environmental Management (Chapter 5)

Section 24(1) of NEMA requires that the potential impacts of projects or activities must be

considered, investigated, assessed and reported to the Competent Authority, while Section

24(2) empowers the Minister (or MEC) to identify such projects or activities which require

authorisation. These activities are listed in Government Notice Regulation (GNR) 327

(Environmental Impact Assessment Regulations), R 324 Listing Notice 1 (activities requiring

Basic Assessment); GNR 326 Listing Notice 2 (activities requiring Scoping and

Environmental Impact Assessment) and GNR 325 (activities requiring Basic Assessment

dependent on provincial requirements) published in terms of Section 24D of NEMA. Section

24 (5) of NEMA empowers the Minister (or MEC) to Final regulations which provide a

framework for the authorisation process, and which is provided in GNR 327 Listing Notice (7

April 2017).

In terms of Section 24F, failure to obtain environmental authorisation for listed activities

constitutes an offence and, either jointly or severally, convicted persons can be fined up to

R5 000 000 as well as face imprisonment for up to ten years.

2.1.3 Additional Acts and Frameworks

In addition to NEMA, the following Acts have some bearing on the proposed activities:

Hazardous Substances Act, 15 of 1973;

The Conservation of Agricultural Resources Act, 43 of 1983;

Occupational Health and Safety Act, 85 of 1993;

Development Facilitation Act, 67 of 1995;

National Road Transport Act, 93 of 1996;

Extension of Security Tenure Act, 62 of 1997;

Basic Conditions of Employment Act, 75 of 1997;

Prevention of Illegal Eviction from and Unlawful Occupation of Land Act, 19 of 1998;

The National Water Act, 36 of 1998;

South Africa National Road Agency and National Roads Act, 7 of 1998;

The National Heritage Resources Act, 25 of 1999;

Promotion for Administrative Justice Act, 3 of 2000;

Mineral Petroleum Resources Development Act, 28 of 2002;

Page 60: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

60

The National Environmental Management: Protected Areas Act, 57 of 2003;

The National Environmental Management: Biodiversity Act, 10 of 2004;

The National Environmental Management: Waste Act, 59 of 2008;

Traditional Leadership and Governance Framework Amendment Act, 23 of 2009;

Application to the DEA for Environmental Authorisation in terms of NEMA does however not

absolve the applicant from complying with other statutory requirements, and in addition the

following national and provincial legislation will apply inter alia to the project.

3.1.5 GN R 327 – The Environmental Authorisation process

Based on NEMA and GNR 327 Eskom requires Environmental Authorisation from the

competent authority, the Department of Environmental Affairs. The provincial environmental

authority, the Limpopo Department of Economic Development, Environment and Tourism

(DEDET) will act as a commenting authority.

Application to the DEA for Environmental Authorisation in terms of NEMA does however not

absolve the applicant from complying with the above mentioned statutory requirements. In

this regard the following national and provincial legislation will apply inter alia to the project.

3.1.6 GNR 327 – Activities requiring an EIA

The proposed project and activities are listed in GNR 327, specifically:

Activity No (s) Listed activity

Government Notice

R.327 Listing Notice 1

of 2017

Item 11

The development of facilities or infrastructure for the transmission

and distribution of electricity-

(i) outside urban areas or industrial complexes with a capacity of

more than 33 but less than 275 kilovolts

Government Notice

R.327 Listing Notice 1

of 2014

Item 27

The clearance of an area of 1 hectares or more, but less than 20

hectares of indigenous

vegetation, except where such clearance of indigenous

vegetation is required for-

(i) the undertaking of a linear activity; or

(ii) maintenance purposes undertaken in accordance with a

maintenance management plan.

Government Notice

R.324

Listing Notice 3 of

The development of a road wider than 4 metres with a reserve

less than 13,5metres.

Page 61: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

61

2014

Item 4

(a) In Free State, Limpopo, Mpumalanga and Northern Cape

provinces:

ii. Outside urban areas, in:

(ee) Critical biodiversity areas as identified in systematic

biodiversity plans adopted by the competent authority or in

bioregional plans;

Page 62: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

62

4. CHAPTER FOUR: STATUS QUO OF RECEIVING ENVIRONMENT

4.1 GENERAL ENVIRONMENTAL DESCRIPTION (INCLUDING VISUAL, LANDUSE

&LANDCOVER)

4.1.1 Climate

The climate within the Granite Lowveld vegetation unit is typical of north-eastern Southern

Africa with summer rainfall and dry winters. The annual precipitation in this area ranges from

500mm per year in the eastern flats to about 900mm per year in the north-west and along the

escarpment. Mean monthly maximum and minimum temperatures are 38°C and 3.7°C for

January and July. The conservation status of this vegetation unit is considered to be

vulnerable with more than 20% already transformed by cultivation and settlement

development (Mucina & Rutherford 2006).

4.1.2 Surface Water

The route crosses a significant water course in the form of the Luvuvhu River just south of

the proposed substation. This perennial river is one of the most important ecological features

in the far-north eastern Limpopo Province. There is also a non-perennial watercourse that

the proposed power line will cross

4.1.3 Land Use Character 0f Surrounding Area

Agriculture is the land use and/or prominent feature that currently occurs within a 500m

radius of the site. There are plantations with various types of crops. The proposed sites

(including the alternative site) fall within Critical Biodiversity Area (as per provincial

conservation plan) and it‟s not in any of the following areas;

Core area of a protected area

Buffer area of a protected area

Planned expansion area of an existing protected area

Existing offset area associated with a previous Environmental Authorization

Buffer area

The Critical Biodiversity Area map is attached on Appendix A

Page 63: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

63

Figure 8: The critical biodiversity area map

4.2 Waste, effluent, emission and noise management

4.2.1 Solid waste management

All solid waste collected shall be disposed of at the registered/licensed municipal landfill site.

Skip waste containers and waste collection bins will be maintained on site and the contractor

will arrange for them to be collected regularly when needed and transported to the licensed

landfill site. Waste separation will be implemented. Under no circumstances will waste be

burned or buried on site. No solid waste shall be produced during operation phase.

Once the bins/skips are full they should (under normal circumstances) be taken to a

registered landfill site for disposal. The closest registered landfill site will be just outside

Thohoyandou under Thulamela Local municipal landfill site which is about approximately

20km from the furthest point of the proposed project area.

Page 64: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

64

The challenge will be the disposal of hazardous solid waste as currently there is no

registered landfill site exists for hazardous waste in Limpopo Province.

As such, the following protocol will need to be followed with regard to the disposal of

hazardous solid waste generated during the construction phase:

Contractors are advised to use the existing Thohoyandou municipal landfill site for

general waste, upon agreement with the relevant structures and the correct

procedures must be followed. Disposal waybills must be kept on file for inspection.

Any recyclable waste should be dropped off at the Recycling Centre; Landfill

(registered facility),

As no facility exists in the Province for the disposal of hazardous waste, it is

recommended by the EAP that proper storage be erected on site in which waste can

be accumulated before transported to the nearest registered hazardous landfill

facility;

The waste storage area for both the storage of general and hazardous waste must be

clearly indicated and demarcated to prevent unauthorised access. These containers

should have a cover or a closing mechanism to avoid wind-blown waste and rain

water filling the skips/containers; and

Upon disposal of waste by the Contractor or his agent, a disposal certificate must be issued

and kept on site for the duration of construction and until a close-out audit has been

undertaken. The hazardous waste which can be expected from the construction phase,

include disposables such as oil cans or containers, lubricants and cement bags.

The disposal of waste is also addressed in the Environmental Management Programme

(EMPr) for the proposed power line and substation development.

Solid waste is produced infrequently as the quantity of waste produced is primarily linked to

equipment failures where parts need to be replaced. Due to the fact that the frequency of

equipment failures cannot be predicted it is difficult for Eskom to determine monthly

quantities of solid waste to be produced

Solid wastes generated on site will be separated/classified as domestic waste, Paper,

hazardous waste, scrap metals, building rubble. Domestic wastes and building rubble will be

disposed of at the municipal landfill site. Other waste types will be stored, recycled and re-

used/disposed of as per Eskom waste management plan.

Page 65: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

65

Thulamela Local Municipal waste sites may be used for the disposal of small quantities of

solid waste. Blown transformers and equipment will be transported to the Eskom Depot in

Polokwane and disposed of by a waste contractor, which will be appointed upon

commissioning of the substation. The solid waste that does not feed into the municipal waste

stream will be recycled and/or reused. The customer network centres (CNC) also have

storage facilities to temporarily store equipment‟s collected from site. The nearest CNC is

Muledane CNC located at approximately 7km to the project area. Some of the components

such as the substation transformer contains transformer oil or is treated with oil. These

components will have to be discarded at hazardous waste disposal facilities. The oil will be

drained from the blown transformer(s) and sealed in drums. The drums and blown equipment

will be transported to the Eskom depot in Thohoyandou or Polokwane for disposal by an

appointed waste contractor. The oil will only be disposed of should it be contaminated.

Should the oil be free of contamination, the oil will be re-used. The Contractor will be

educated on the Waste Disposal Options, i.e Any recyclable waste should be dropped off at

the Recycling Centre; Landfill (registered facility),

Table 12: Waste Profile

Condition Approval

Can any part of the solid waste be classified as hazardous in terms of the

NEM: WA?

No

Is the activity that is being applied for a solid waste handling or treatment

facility?

No

Will the activity produce effluent, other than normal sewage, that will be

disposed of in a municipal sewage system

No

Will the activity produce any effluent that will be treated and/or disposed of

on-site?

No

Will the activity produce effluent that will be treated and/or disposed of at

another facility?

No

Will the activity release emissions into the atmosphere other that exhaust

emissions

No

Will any aspect of the activity produce waste that will require a waste permit

in terms of the NEM: WA?

No

4.2.2 Waste permit

The project activities do not require any waste permit or licences.

Page 66: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

66

4.2.3 Generation of noise

Noise will be generated during vegetation clearing activities, by vehicles transporting

equipment and construction activities around the power line.

These impacts are not considered to be significant enough to warrant a formal assessment.

During operation the power line may produce a corona (low „buzzing‟ or „crackling‟ noise). A

corona can be caused by water droplets forming on a conductor resulting in the breakdown

of air molecules perceived as the crackling noise (Eskom GFS 0009 Revision 2 Document,

May 2004). However, corona rings are used by Eskom on conductors to prevent / reduce the

noise. In addition, the transformer within the substation will also produce a low level

humming noise.

There are however no significant settlements or homesteads in the immediate/close vicinity

which will be affected by this type of noise.

To ensure that the noise generated during the construction phase is minimised, the following

mitigation measures are proposed (these will be included in the Environmental Management

Programme for the project, attached as Appendix G):

All equipment used on site shall be fitted with suitable silencers to control noise

pollution;

The following will prevail:

Unless otherwise specified by the EO/ECO, normal working hours will apply (i.e. from

06h30 to 17h00, Mondays to Fridays);

Ensure that employees and staff conduct themselves in an acceptable manner while

on site, both during work hours and after hours;

No loud music will be permitted on site or in the site camp.

If blasting is required during the construction period of the 132 kV power line, the following

guidelines will be followed:

The type, duration and timing of the blasting procedures will be planned with due

cognisance of other land uses and structures in the vicinity;

Page 67: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

67

The local landowners and communities will be adequately informed ahead of any

blasting event;

The use of nitrate-free explosives will be favoured wherever possible (i.e. methods

including drilling and black powder, expanding mortar or old fashioned plugs and

feathers);

Noise mufflers and/or soft explosives will be used by staff during blasting;

Appropriate measures to limit undesired flyrock will be taken;

Audible warning of a pending blast will be given at least 3 minutes in advance of a

blast; and

All flyrock (of diameter 150mm and larger) which falls beyond the cleared

4.2.4 Energy Efficiency

The activity will not use electricity but rather distribute electricity to a substation from where it

is divided into smaller voltages for distribution to end-users.

4.2.5 Property description/physical address

The following table shows the property description

Table 13: Property description

Province Limpopo

District

Municipality

Vhembe District Municipality

Local

Municipality

Thulamela Local Municipality

Ward Number(s) 26

Farm name and

number

Dzwerani 22LT

Portion number Remainder of the Farm Dzwerani

SG Code Please refer to Appendix A0

Table 14: Land owners

Province Limpopo

District

Municipality

Vhembe District Municipality

Local

Municipality

Lim 3,4,5 Local Municipality

Page 68: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

68

Ward Number(s) 14

Farm name and

number

Maltlicatt of Murziafera 25LT

Alverton 26LT

Langverwacht 27LT)

Portion number Portion 1 of Farm Langverwacht

Remainder of the Farm Alverton

Remainder of the Matlicatt or Murzia Fera

SG Code Please refer to Appendix A0

4.2.6 Gradient of the site

The general gradient of the site falls in 1:15 – 1:10 for both the preferred and the alternative

site. The location‟s landscape is undulating.

4.3 Socio-Economic Character of the local municipality

4.3.1 Level of unemployment

According to the IDP of Makhado Municipality, it is evident that the large portion of the

economically inactive population is unemployed. 33.8% male and 63.0% female. In general

forty eight percent (48%) of the population are unemployed.

Economic profile of local municipality

4.3.2 Economic profile of local municipality

The formal economy of the Makhado Municipality can be considered as a “dual economy”, as

it comprises two distinct elements namely the sophisticated economy of the Makhado town

and surrounding farms and the informal economies of surrounding townships and rural

areas. Makhado town provides a regional function to the surrounding areas (e.g. trade

services, banking, manufacturing, storage, transport, etc), because of its size and level of

sophistication. The economy is also able to generate a significant number of direct

employment opportunities for the local communities. The economies of surrounding

townships and rural areas comprise mostly of informal activities and largely serve the

immediate consumption needs of local people

Page 69: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

69

4.3.3 Level of education

There is in general low level of formal education, vocational training and the development of

entrepreneurship. People may be aware of economic opportunities but cannot gain access to

capital. The educational level is an important indicator of the quality of the labour force and

human resource base available. The educational levels shown here, pertain to the

educational institution last attended by the population, i.e. percentages at various levels does

not indicate actual completion of educational training at the various levels.

Table 15; Level of Education

Level of education Percentage

None 11.5%

Pre-Primary / Primary School 29.0%

Secondary School 21.8%

Tertiary (Certificate / Diploma/ Degree 36.2%

Educational challenges

Inadequate provision of learning materials

Renovation of old schools including the construction of administration blocks

Additional classrooms in some of the schools

Provision of water and sanitation services to schools

4.3.4 Project spin off

The expected capital value of the activity on completion is approximately 120 million rand.

Page 70: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

70

5. CHAPTER FIVE: SPECIALIST REPORTS

The objective of this chapter is to supply specialist information regarding the proposed

activity to ensure objectivity.

5.1 Biodiversity

Mr. J. Grosel --‐(Pr.Sci.Nat) (MSc. Zoology, B.Tech. Game & VeldManagement) Biodiversity

specialist was engaged and he corroborated the assertion that the biodiversity has been

transformed due to the agricultural activities. The conservation status of this vegetation unit

is considered to be vulnerable with more than 20% already transformed by cultivation and

settlement development (Mucina & Rutherford 2006) According to the National

Environmental Management Biodiversity Act (Act 10 of 2004) (NEMBA) the vegetation type

is not listed as vulnerable (NEMBA, 2004).

Majority of the area has been transformed for agriculture, grazing, settlement and sand

mining. The proposed activity, i.e preferred Alternative A1 is in an ESA and the Alternative

A2 is in the CBA. The Biodiversity specialist was subcontracted to conduct a Biodiversity

Assessment, as shown below;

Table 16: Biodiversity planning category

Systematic Biodiversity Planning Category If CBA or ESA, indicate the reason(s)

for its selection in biodiversity plan

Critical

Biodiversity

Area (CBA)

Ecological

Support

Area

(ESA)

Other

Natural

Area

(ONA)

No Natural

Area

Remaining

(NNR)

Majority of the area has been

transformed for agriculture, grazing,

settlement and sand mining

The proposed activity, i.e preferred

Alternative A1 is in a ESA and the

Alternative A2 is in the CBA. The

Biodiversity specialist was

subcontracted to conduct a Biodiversity

Assessment

Page 71: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

71

5.1.1 Habitat condition on site

Habitat Condition

Percentage of

habitat

condition

class (adding

up to 100%)

Description and additional Comments and

Observations

(Including additional insight into condition, e.g.

poor land management practises, presence of

quarries, grazing, harvesting regimes etc).

Natural 40%

The conservation status of this vegetation unit is

considered to be vulnerable with more than 20%

already transformed by cultivation and settlement

development

Near Natural

(includes areas

with low to

moderate level of

alien invasive

plants)

30%

Over grazing, cultivation, bush tracks and wood

harvesting have compromised most part of the

habitat condition

Degraded

(includes areas

heavily invaded by

alien plants)

10%

Due to overgrazing

Transformed

(includes

cultivation, dams,

urban, plantation,

roads, etc)

20%

Cultivation

Page 72: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

72

5.1.2 Types of ecosystems

The table below shows type of vegetation, including its ecosystem status, present on the site;

and clarifies as to whether an aquatic ecosystem is present on site.

Table 17: Ecosystem types

Terrestrial Ecosystems Aquatic Ecosystems

Ecosystem threat

status as per the

National

Environmental

Management:

Biodiversity Act

(Act No. 10 of 2004)

Critical Wetland (including rivers,

depressions, channelled

and unchanneled wetlands,

flats, seeps pans, and

artificial wetlands)

Estuary Coastline

Endangered

Vulnerable

Least

Threatened NO NO UNSURE YES

N

O YES NO

5.2 Vegetation type and/or aquatic ecosystem

The proposed Mamphuli-Dzwerani EXT A power line route falls within the northern reaches

of the Granite Lowveld vegetation type (Mucina & Rutherford 2006). Its distribution is fairly

wide, stretching from Kaapmuiden and Malelane in the south to the plains south and east of

Thohoyandou in the north. Mucina & Rutherford (2006) suggests that further research may

reveal a need to differentiate the northern form from the southern form of the vegetation unit

as these areas differ slightly in dominant plant species and vegetation structure. In general,

this vegetation unit is described as tall broad-leaved shrub land with few large trees to

moderately dense low woodland on deep sandy uplands with dense thickets and open

savannah in the bottomlands.

Along drainage lines there is a greater diversity of plants particularly within dense riparian

thickets which also support larger trees. Combretum apiculatum is the dominant tree species

on the slopes and plains while Senegalia (Acacia) nigrescens, Dichrostachys cinerea and

Grewia bicolor dominate the thickets in the bottomlands. Terminalia sericea is the common

woody species in the deep sandy uplands.

In the northern range of this vegetation type Swazian Goudplaats Gneiss,Makhutswi Gneiss

and Nelspruit Suite (Granite gneiss and migmatite) form the basement geology. This

Archaean granite and gneiss weathers into sandy soils in the higher areas and clayey soils

with a high sodium content in the low-lying areas (Mucina & Rutherford 2006).

Page 73: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

73

The climate within the Granite Lowveld vegetation unit is typical of north-eastern Southern

Africa with summer rainfall and dry winters. The annual precipitation in this area ranges from

500mm per year in the eastern flats to about 900mm per year in the north-west and along the

escarpment. Mean monthly maximum and minimum temperatures are 38°C and 3.7°C for

January and July. The conservation status of this vegetation unit is considered to be

vulnerable with more than 20% already transformed by cultivation and settlement

development (Mucina & Rutherford 2006). Below is a regional vegetation map

Figure 9: Regional vegetation map

Page 74: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

74

Figure 10: Vegetation type found in the area of the proposed project

5.3 Cultural/Historical Features

The Phase I HIA study for the proposed Eskom Mamphuli-Dzwerani EXT A Project did not

reveal the presence of any of the types and ranges of heritage resources as outlined in

Section 3 of the National Heritage Resources Act (No 25 of 1999) in the Project Area.

A Phase 1 Heritage Impact Assessment was undertaken by a qualified archaeologist, Dr

Edward Matenga and reviewed by Professor Pikirai. (Report included in Appendix F).

Mitigation/ Management

If any heritage resources of significance are exposed during the power line construction, the

South African Heritage Resources Agency (SAHRA) and the provincial authority should be

notified immediately, all construction activities must be ceased and an archaeologist

accredited with the Association for Southern African Professional Archaeologist (ASAPA)

should be notified in order to determine appropriate mitigation measures for the discovered

finds. This may include obtaining the necessary authorization (permits) from SAHRA to

conduct the mitigation measures.

Page 75: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

75

6. CHAPTER SIX: PUBLIC PARTICIPATION

The objective of this chapter is to supply all proceedings and findings pertaining to the Public

Participation Programme.

6.1 PUBLIC PARTICIPATION PROCESS FOLLOWED

A detailed public participation process for the project was followed. This section provides a

description and summary of the results of this process. Detailed information is supplied in

Appendix E)

Public participation is a continuous two way communication process aimed at promoting full

public understanding of the processes and mechanisms through which environmental

problems and needs are investigated and solved by the responsible agents. It is aimed at

keeping the public informed about the status and progress of the studies conducted and the

implications of the project thereof as well as document all issues, comments and concerns

voiced by the public and their preferences regarding resource use and alternative

development or management strategies and any other information and assistance relative to

the decision.

The Stakeholder Engagement Process as it is referred to by the Department of Environment

and Tourism (formerly DEAT) is a “...process leading to a joint effort by stakeholders,

technical specialists, the authorities and the proponent who work together to produce better

decisions than if they had acted independently”. The process aims at improving

“...communication between stakeholders – including the proponent – in the interest of

facilitating better decision-making and or sustainable development”.

Sustainable development requires some level of trade-off between economic growth, social

equity and ecological integrity. The stakeholder engagement process provides an opportunity

for Interested and Affected Parties (I&APs) to participate in an informed bases and ensure

their needs and requirements are considered and allows the decision-making authority to

understand to what degree stakeholders are willing to accept and live with the tradeoffs

involved. The objectives of the stakeholder engagement process for the proposed project

can thus be summarized below;

to inform and provide the public with information and an understanding of the project,

issues and solutions;

identify relevant individuals, organisations and communities who may be interested in

or affected by the proposed development;

identify key issues and concerns, raised by I&APs, that should be addressed in the

subsequent specialist investigations which are part of the BA;

Page 76: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

76

identify shortcomings and gaps in existing information;

identify viable project alternatives that will assist the relevant authorities in making an

informed decision;

6.1.1 Advertisement and Notice

The newspaper advert was placed on the following newspapers informing and inviting

members of the public and any other interested and affected parties (I&APs) to comment on

the proposed project:

a) Zoutpansberger advertised on the 23 November 2019 in English (See Appendix E5)

In addition, pamphlet notices and background information documents (BID) were distributed

to the identified land owners, potential stakeholders and I&APs. (See Appendix E1).

Distribution was done on the in 5th December 2019. The site notices were placed along the

power line area and the substation

The purpose of the BID was to provide stakeholders with introductory information on the

proposed project, the BA and the stakeholder engagement process. The BID also provided

stakeholders who are interested in the project with the opportunity to register as stakeholders

by way of requesting and completing the registration sheet distributed with the BID.

Information on the registration sheet has been used to register stakeholders on a database

to receive all project-related information and invitations to meetings. The registration sheet

included a section for comments and issues, which allows stakeholders an opportunity to

provide the consultants with written comments and feedback.

See the following appendices for the contents of adverts and site notices:

. a) Appendix E1 – BID

. b) Appendix E4 – Site Notices

. c) Appendix E5 – Newspaper advert

6.1.2 Placement of advertisements and notices

To inform surrounding the public, I&APs, communities and immediately adjacent landowners

of the proposed project, site notices were placed at various sites and locations which are

visible and accessible along the route towards the proposed site on the 5th December 2019.

Site notices were placed at various points (See Appendix E4):

6.1.3 Site notice placement

The table shows the coordinates of the exact locations where the onsite notices were

displayed,

Page 77: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

77

Publication name Zoutpansberger

Date published 5th December 2019

Site notice

position

Latitude Longitude

S23004‟ 40.79‟‟

S230 07‟ 25.15‟‟

S230 06‟ 28.78‟‟

E30025‟ 38.08‟‟

E300 26‟ 03.94‟‟

E300 25‟ 19.39‟‟

Date placed 5th December 2019

Figure 11: Proof of on-site notices

6.1.4 Key stakeholders

The following key stakeholders (other than organs of state) wer identified in terms of

Regulation 54(2)(b) of GN R.543:

Table 18: Public participation key stake holders

Title, Name and

Surname

Affiliation/ key stakeholder

status

Contact details (tel number or e-

mail address)

Chief Nelwamondo NR Dzwerani-Mamphuli Village

Traditional Authority

Cel: 071 292 0959

Chief Nelwamondo KM Dzwerani-Mamphuli-Dzwerani

EXT A Village Traditional

Authority

Cel: 060 631 3625

Chief Mundalamo RJ Tshitungulwane Village

Traditional Authority

Cel: 082 958 2811

Page 78: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

78

6.1.5 Issues raised by interested and affected parties

During public consultation, the following comments were raised and the project team

responses are shown on the table below.

Table 19: Comments and responses from key stakeholders.

Comments/Issues raised Responses

Chief Nelwamondo indicated that the identified area for the proposed substation does not fall within her jurisdiction even though the substation is named after her village. The area falls under Chief R Nelwamondo of Mamphuli village.

The EAP requested for the contact details of Chief R Nelwamondo in order to schedule a meeting with him and his council. -Name was changed accordingly. The council‟s secretary was emailed a letter informing the council that their proposed name was adopted and she acknowledged.

Community members indicated that they do not have any objections against the project; however they suggest that the name of the proposed substation be changed because it is in Mamphuli village not Mamphuli-Dzwerani EXT A. They want the substation to be named after their village.

PP Consultant explained that they will write to Eskom to inform them about the request. She also requested them to put their request in writing and also include the proposed name in their request. The issue has been submitted to Eskom for consideration

Members of the council wanted to know if there will be job opportunities created.

PP Consultant explained that during construction phase Social Facilitators from Eskom will brief the community on employment and other community social issues relating to the project.

Chief Nelwamondo wanted to know how he will be compensated for his land.

It was indicated that Eskom has Negotiators who deals with compensations; they will liaise with him regarding this issue.

EAP wanted to know the whereabouts of the Maswanganyi family regarding the grave next to the proposed substation. He wanted to inform the family about the proposed development and to put them at ease since the grave will not be affected.

Chief R Nelwamondo indicated that he is not certain about the whereabouts of the family but he will take full responsibility of the grave since it is in his land.

When is the construction going to start? PP Consultant indicated that it difficult to say since we are still in the preparation phase (Environmental Authorisation); once Environmental Authorisation is granted the project still need to be advertised for the Contractor which is also a process.

As a community member I want to find out when you are going to finish with the current electrification project.

PP Consultant explained that we are appointed as independent consultants specifically for the Proposed Mamphuli-Dzwerani EXT A Substation and its powerlines. Based on this we are unable to respond to this question.

Page 79: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

79

6.1.6 Authority Participation

Authorities and organs of state identified as key stakeholders are as follow;

Name

Authority/ Organ

of State

Address Cell/tel number

e-mail address

Competent

Authority

Department of

Environmental

Affairs (Head

office)

Private Bag

X447

Pretoria

0001

Tel: 012 310

3427

Mr Mulalo

Nethengwe/

Vhonani

Nethononda

Department of

Water and

Sanitation

(Limpopo)

Azmo Building

29 General

Joubert Street

Polokwane

Central, 0699

Tel: 015 290

1200

[email protected]

a

Ms Ndina Mudau /

Mr Thapelo

Machate

Department of

Agriculture,

Forestry and

Fisheries (DAFF)

(Forestry

Regulations &

Support)

Private Bag

X2413

Makhado

0920

Tel: 015 291

1200/ 015

5193300

Fax:

0155161062/

0865715711

Cel: 083 610

7122

[email protected]

a

[email protected]

Mr Rhulani

Mthombeni /

Ms LD Mojapelo

Limpopo

Department of

Economic

Development

Environment and

Tourism

Corner Suid &

Dorp Streets;

Polokwane;

0699

Tel: 015 290

7000 /

015 290 7156

Fax: 015 295

5015

[email protected]

a

[email protected].

za

Ms Molele/

Mokgadi Miyen

Department of

Rural

Development and

Reform

Private Bag x

9552

Polokwane 0700

Tel: 015 297

3539

tsmolele@ruraldevelopm

ent.gov.za

Mr Tele Maphotho Regional Land

Claims

Commission

Private Bag x

9552

Polokwane 0700

Tel:015 284

6300

Fax:015 295

7403

tamaphotho@ruraldevelo

pment.gov.za

Ntsoane S.E Department of 67/69 Biccard Tel: [email protected]

Page 80: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

80

Agriculture Street

Polokwane;

0699

0152943443

Fax:

0156326303

.gov.za

Mr D Lithole/

Mrs Vhonani

Ramalamula

Limpopo Heritage

Resources

Authority-LIHRA

Private Bag x

9549

Polokwane 0700

Tel: 015 284

4039

Cel:076 621

1113

[email protected]

v.za

Chief

Nelwamondo NR

Dzwerani-

Mamphuli Village

P.O 52

Lwamondo;

0985

Cel: 071 292

0959

N/A

Tshihwalule C

Vhembe District

Municipality

Private Bag

X5006

Thohoyandou;

0950

Tel:015 960

2117

[email protected]

ov.za

J E Joubert

Makhado Local

Municipality

P/B X2596

Louis Trichardt;

0920

Tel: 015

5193181

Cel:

0836363546

[email protected]

M.S Madi Thulamela Local

Municipality

Private Bag

X5066

Thohoyandou;

0950

Tel:015 962

7586/7705

[email protected].

za

Chief

Nelwamondo KM

Dzwerani-

Mamphuli-

Dzwerani EXT A

Village

P.O Box 477

Lwamondo;

0985

Cel:060 631

3625

N/A

Chief Mundalamo

RJ

Tshitungulwane

Village

P.O Box 121;

Vuwani, 0952

Cel:076 885

3430

N/A

Rasivhaga T Mamphuli Tribal

Council Secretary

P.O Box 3231

Thohoyandou;

0950

Cel:082 861

5886

Pastortakalanibookings

@gmail.com

Cllr. Makungo Ward Councillor P.O Box 3292

Thohoyandou;

0950

Cel:079 144

8335

makungogg@thulamela.

gov.za

Cllr. Mathoma Ward Councillor P.O Box 94

Vuwani; 0952

Cel:079 890

7380

mathomamphophineas@

gmail.com

Page 81: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

81

SD Rasimphi CDW (Makhado) P.O Box 52

Lwamondo;

0985

Cel:082 958

2811

[email protected]

SS Mahutsi SANCO Secretary P.O Box 3231

Thohoyandou;

0950

Cel:079 438

4086

[email protected]

m

6.1.7 Conclusion of public participation programme

The Consultants are confident that all reasonable actions were undertaken to ensure that the

key stakeholders were informed of the study and could place their concerns and comments

on record. The Consultants trust that all the comments and conditions raised were addressed

in a satisfactorily manner.

Page 82: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

82

7. CHAPTER SEVEN: IDENTIFIED IMPACTS AND PROPOSED MITIGATION

MEASURES

7.1 Introduction

The objective of this chapter is to describe and evaluate the expected impacts of the

proposed project on the relevant environmental components and identify applicable

mitigation measures.

Impacts that may result from the planning and design, construction, operational,

decommissioning and closure phases will be captured and the proposed mitigation measures

will be proffered.

7.2 132KV POWERLINE CORRIDOR AND THE SUBSTATION ALTERNATIVES

From the suitability criteria, Eskom and Mbofho Consulting identified two (2) feasible sites for

the location of the proposed LILO Power line and Mamphuli-Dzwerani EXT A substation. The

Alternative A1 (preferred) is about 500m away from Alternative sites A2. The Alternative A1

site is the preferred alternative and is on the north-western side of the tapping line.

Alternative Site A2 (Not preferred) is on the north side of the tapping 132kv power line.

7.2.1 Alternative S1 (Preferred)

Approximately 6 km – Loop in Loop out 132kV power lines running straight from the

connection at the existing 132kV power line at Tshitungulwana near Vuwani to the proposed

Mamphuli-Dzwerani EXT A substation. The 2x power lines runs from Tshitungulwana and

bends towards Mamphuli-Dzwerani EXT A to the north-west before crossing the river and

then proceed for about 1.8kms to the new Mamphuli-Dzwerani EXT A substation. The power

lines is in red color

Page 83: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

83

7.2.2 Alternative S2 (Optimal)

Approximately 7km – Loop in Loop out 132kV power lines also running straight from the

connection at the existing 132kV power line at Tshitungulwana near Vuwani to the proposed

Mamphuli-Dzwerani EXT A substation. The power lines runs from Tshitungulwana straight

towards alternative 2 Mamphuli-Dzwerani EXT A to the north for about total of approximately

7km. It is described in Blue color

7.2.3 General project impacts

Although the proposed project site will completely transform the site, the site is situated on

an area with little ecological value/significance. Only the new substation and powerline

alternative 2 crosses through a small portion classified as a Critical Biodiversity Area 2 as

well as a small portion classified as an Ecological Support Area (see Appendix A for

Sensitivity map), which is due to the Luvuvhu River. The rest of the area is not situated in

any sensitive ecosystem or plant/animal community and species richness of the vegetation of

the study area is relatively low. The impact of the proposed project on the ecological

resources is therefore considered to be low due to the already low current status of the area.

This project will also not result in any significant cumulative impact (low - medium) as the

vegetation type is classified as least concerned and disturbance of vegetation will be mostly

confined to the footprint of the proposed substation and the corridor.

The general Mitigation measures to reduce potential impacts:

Page 84: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

84

Strictly limit Mamphuli-Dzwerani EXT A Substation facility and associated

infrastructure construction and development to the proposed project footprint.

Use existing roads as far as possible and limit the number of additional roads

constructed.

7.3 Heritage issues

The HIA specialist identified a grave and monument dedicated to Maswanganyi is located

200m to the northwest of the site. The 200m distance is away from the site and will not be

affected by the proposed project.

7.3.1 Mitigation measures

A 200m wide buffer zone will be reserved between the Maswanganyi burial/memorial and the

proposed substation. It is also recommended that the same buffer distance be reserved

between the proposed substation and proposed cemetery. No historically or archaeologically

sensitive sites were found along the route of the power line. If any other finds were to be

made during the development phase the procedure is to approach the relevant heritage

authorities (SAHRA and/or the Provincial Heritage Resources Authority) and a heritage

expert will be called to attend.

7.4 Biodiversity issues

From Ecological point of view, the natural vegetation at the site is moderately modified. The

proposed Mamphuli-Dzwerani EXT A power line route falls within the northern reaches of the

Granite Lowveld vegetation type (Mucina & Rutherford 2006). Its distribution is fairly wide,

stretching from Kaapmuiden and Malelane in the south to the plains south and east of

Thohoyandou in the north. Mucina & Rutherford (2006) suggests that further research may

reveal a need to differentiate the northern form from the southern form of the vegetation unit

as these areas differ slightly in dominant plant species and vegetation structure. In general,

this vegetation unit is described as tall broad-leaved shrubland with few large trees to

moderately dense low woodland on deep sandy uplands with dense thickets and open

savannah in the bottomlands.

Along drainage lines there is a greater diversity of plants particularly within dense riparian

thickets which also support larger trees. Combretum apiculatum is the dominant tree species

on the slopes and plains while Senegalia (Acacia) nigrescens, Dichrostachys cinerea and

Grewia bicolor dominate the thickets in the bottomlands. Terminalia sericea is the common

woody species in the deep sandy uplands.

Page 85: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

85

In the northern range of this vegetation type Swazian Goudplaats Gneiss, Makhutswi Gneiss

and Nelspruit Suite (Granite gneiss and migmatite) form the basement geology. This

Archaean granite and gneiss weathers into sandy soils in the higher areas and clayey soils

with a high sodium content in the low-lying areas (Mucina & Rutherford 2006).

The climate within the Granite Lowveld vegetation unit is typical of north-eastern Southern

Africa with summer rainfall and dry winters. The annual precipitation in this area ranges from

500mm per year in the eastern flats to about 900mm per year in the north-west and along the

escarpment. Mean monthly maximum and minimum temperatures are 38°C and 3.7°C for

January and July.

The conservation status of this vegetation unit is considered to be vulnerable with more than

20% already transformed by cultivation and settlement development (Mucina & Rutherford

2006).

7.4.1 Ecological impacts

The Ecological Impact Assessment identified the perennial watercourse i.e Luvuvhu River as

well as a seasonal stream which the proposed powerline route alternatives will cross. A

water use license application may not be submitted to the Department of Water and

Sanitation due to the recommendations that the pylons should be 150m more away from the

edge of the river banks.

The general Mitigation measures to reduce potential impacts:

Ensure that no pylons are constructed within 150m of a watercourse.

Protect the integrity of all watercourses during the construction phase and do not alter the

beds and the banks or divert any watercourse.

From an ecological perspective route alternative 1 would be the most preferred and can be

utilised due to their very low negative impact on the Ecological Support Area (ESA) hence

Alternative 2 not only impact on ESA but also on Critical Biodiversity Area 2 as it crosses

through a small portion classified as a

Critical Biodiversity Area as well as a small portion classified as an Ecological Support Area

(see Appendix A for Sensitivity map) it is recommended from an ecological perspective that

route alternative 1 (preferred) be approved due to affecting a smaller portion of ESA only as

it crosses Luvuvhu River.

Page 86: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

86

7.4.2 Avifaunal habitat destruction

Clearing activities during the construction phase will remove vegetation and therefore habitat

that birds may require for breeding, foraging and roosting. While some of the impact may be

temporary in the case of construction phase, mitigation through rehabilitation of such areas is

possible; however there will also be direct long-term loss of vegetation associated with the

footprint of servitudes. It is noted though that due to the general uniformity of the broader

area, many birds (especially smaller passerines) may quite easily move off and find similar

and suitable habitat nearby. The avifaunal cumulative impacts associated with the

construction phase will not be highly significant and will range between low - medium.

Mitigation measures to reduce potential impacts:

Strictly limit power line and associated infrastructure construction and development to

the proposed project footprint.

Use existing roads as far as possible and limit the number of additional roads

constructed.

High traffic areas and buildings such as offices, batching plants, storage areas etc.

should, where possible be situated in areas that are already disturbed;

Existing roads and farm tracks should be used where possible;

The minimum footprint areas of infrastructure should be used wherever possible,

including road widths and lengths;

No off-road driving;

Environmental Control Officers to oversee activities and ensure that the

environmental management plan (EMPr) is implemented and enforced; Following

construction, rehabilitation of all areas disturbed (e.g. temporary access tracks and

laydown areas) must be undertaken and to this end a habitat restoration plan is to be

developed by a specialist and included within the Environmental Management Plan

(EMPr).

Page 87: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

87

7.4.3 Avifaunal electrocution

Electrocutions of birds may happen in two ways: (1) phase-to-phase electrocution by bridging

the air gap between two live conductors, and (2) phase-to-earth electrocution by contact

between a live conductor and earth device (pylon or pole), especially when the feathers are

wet (Bevanger, 1998). A number of factors determine the likelihood of electrocutions

including landscape features such as vegetation and topography, weather conditions, size of

the bird, behaviour of the bird, and structure and dimensions of the pylon (Smallie et al.,

2009). Most bird electrocutions occur on lower voltage electricity pylons, where the gaps

between conductors are small, and which are attractive perching and nesting alternatives to

trees in otherwise open, flat areas. More electrocutions occur in rainy and/or misty weather

conditions. Bird species that are prone to electrocution are larger perching species such as

birds of prey (including vultures, medium and large bodied raptors, and smaller raptors such

as falcon), storks and herons.

When perching on the towers of the new power line, large birds may be electrocuted if they

bridge the air gap between live components. Of particular concern are large raptors (e.g.

Martial Eagle, Black-chested Snake Eagle and White-backed Vulture) and storks, which due

to their size and nature are prone to electrocution impacts.

Mitigation measures to reduce potential impacts:

Any power line/s must be of a design that minimizes electrocution risk by using

adequately insulated „bird friendly‟ monopole structures, with clearances between live

components of 2m or greater and which provide a safe bird perch.

The pylon structures to be constructed must first be checked with an avifaunal

specialist or with the Endangered Wildlife Trust‟s (EWT) Wildlife and Energy

Programme.

The operational monitoring programme for the site must be in line with applicable

guidelines and must include regular (i.e at least every two months) monitoring of the

power line and the new associated substation for electrocution (and collision)

mortalities. Any mortalities should be reported to the EWT.

Page 88: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

88

7.4.4 Avifaunal collision with infrastructure

Collisions with large (132 kV or above) power lines are a well-documented threat to birds in

southern Africa, while smaller lines pose a higher threat of electrocution but can still be

responsible for collision. Collisions with overhead power lines occur when a flying bird does

not see the cables, or is unable to take effective evasive action, and is killed by the impact or

impact with the ground. Especially heavy-bodied birds such as bustards, cranes and

waterbirds, with limited manoeuvrability are susceptible to this impact. Many of the collision

sensitive species are also considered threatened in southern Africa.

The Red Data species vulnerable to power line collisions are generally long living, slow

reproducing species under natural conditions. Some require very specific conditions for

breeding, resulting in very few successful breeding attempts, or breeding might be restricted

to very small areas. These species have not evolved to cope with high adult mortality, with

the results that consistent high adult mortality over an extensive period could have a serious

effect on a population‟s ability to sustain itself in the long or even medium term.

Birds may collide with the new grid connection over-head power lines, particularly during

times of low light or poor visibility. The relatively low number of records of collision prone Red

Data species during the monitoring survey, suggest that this may be a less significant impact

for the project although mitigation in certain areas is still recommended.

Mitigation measures to reduce potential impacts:

Where possible, power line infrastructure should avoid sensitive avifaunal habitats.

Where possible, power line infrastructure should follow existing servitudes such as

existing power lines, roads and fences.

An avifaunal specialist must conduct a site walk through of the final power line route

and pylon positions prior to construction to determine if, and where, bird flight

diverters (BFDs) are required.

Install bird flight diverters as per the instructions of the specialist following the site

walkthrough, which may include the need for modified BFDs fitted with solar powered

LED lights on certain spans.

The operational monitoring programme for the site must be in line with applicable

monitoring guidelines and must include regular (i.e. at least every two months)

monitoring of the power line for collision (and electrocution) mortalities. Any

mortalities should be reported to the Endangered Wildlife Trust (EWT).

Page 89: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

89

7.4.5 Soil erosion

Due to the removal of natural vegetation and alteration of the landscape during the

construction phase the potential for loss of soil due to erosion is present and must be

monitored. The cumulative impact of this development is expected to be low due to the low

potential of the land in the area.

Mitigation measures to reduce potential impacts:

Ensure adequate erosion control measures are implemented to reduce the risk of soil

erosion during the operational phase.

7.4.6 Continued dust generation and emissions

Increased vehicle and machine activity will result in a significant increase in dust emissions

into the surrounding environment. Continued vehicle activity during the operational phase will

result in continued dust emissions occurring into the surrounding environment. It will be far

less significant than during the construction phase but could have a negative impact on

adjacent community as excessive dust fallout could potential have health implications. If

managed correctly the cumulative impact of vehicles on dust generation can be limited to

low.

Mitigation measures to reduce potential impacts:

Continued Dust Management as well as Traffic Management measures must be kept

in place in order to manage traffic movement in the area during the entire operational

phase and subsequently decrease undesired dust emissions

7.4.7 Visual disturbance of natural landscape and sense of place

The construction of the proposed powerlines within the landscape, of which the majority is

currently viewed as natural areas, will cause a direct visual impact on the tranquillity and

sense of place of the area to the local community though the area is characterised by sand

mining, formal and informal settlement, orchards and general grazing area. The sand mining

has transformed the area already and the introduction of a substation and 2x powerlines

would not cause too much of visual intrusion. The visual impact will however be mainly

restricted to within 3 km of the proposed project area after which the visibility will diminish.

The sloping landscape decreases the visibility distance of the proposed infrastructure and it

will therefore not significantly contribute to any cumulative visual disturbances.

Mitigation measures to reduce potential impacts:

Strictly limit powerline construction and substation development to the proposed

project footprint.

Use existing roads as far as possible and limit the number of additional roads

constructed.

Adequate planning and management of laydown areas

Page 90: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

90

7.4.8 Job creation, empowerment and skills development

There are short-term construction related employments opportunities are envisaged for the

construction phase. A local employment policy will be applied as far as possible in the

appointment of low-skilled and semi-skilled construction workers. Preference will be given to

skilled workers within the Vhembe District (Thulamela and Lim3,4,5 Municipalities) in the

Limpopo Province. In view of the very high unemployment rates in the local municipality area

these employment figures will make a significant positive contribution. The proposed project

will, along with other similar renewable energy projects in the area, cumulatively contribute to

reduction in poverty and unemployment figures in the Vhembe District and Limpopo Province

in general.

7.4.9 Influx of construction workers and job seekers and risk of theft and damage to

property

It is expected that the influx of construction workers will have a relatively minor impact on the

Vuwani and Dzwerani community. This is because most of the low- skilled and semi-skilled

workers will be employed from the existing community. Moreover, the lack of basic services

and relative distances to local towns will also to some extent deter the influx of outsiders.

However, this aspect should be monitored throughout the construction phase. Because of

the location of the development near a low income community, theft and damage to

infrastructure is a concern. There will be no cumulative impact of the facility on the local

informal settlement.

Mitigation measures to reduce potential impacts:

A designated security company will be appointed to ensure the safety of the facilities.

Access control should be implemented

Security sign boards

Adequately monitor and manage the process throughout the construction phase

7.4.10 METHODOLOGY APPLIED FOR THE ASSESSMENT OF POTENTIAL IMPACTS

All impacts identified during Final Basic Assessment stage of the study will be classified in

terms of their significance. The broad significance categories are as follows:

The Nature of the impact: This will describe the cause and the effect, what would be affected

and how it would be affected.

Mitigation level: The degree to which the impact can be mitigated.

The Extent of the impact: This will be categorised as either local or regional

Page 91: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

91

The Magnitude of the impact: This will be quantified as either:

o Low: Will cause a low impact on the environment;

o Moderate: Will result in the process continuing but in a controllable manner;

o High: Will alter processes to the extent that they temporarily cease; and

o Very High: Will result in complete destruction and permanent cessation of

processes.

The Probability: which shall describe the likelihood of impact occurring and will be rated as

follows:

o Extremely remote: Which indicates that the impact will probably not happen;

o Unusual but Possible: Distinct possibility of occurrence;

o Can Occur: there is a possibility of occurrence;

o Almost Certain: Most likely to occur; and

o Certain/ Inevitable: Impact will occur despite any preventative measures put in

place.

The duration (Exposure): wherein it will be indicated whether:

The impact will be of an immediate (very short period of time);

The impact will be of a short tem (between 0-5 years);

The impact will be of medium term (between 5-15 years);

The impact will be long term (15 and more years); and

The impact will be permanent.

Reversibility/ Replaceability: The degree to which the impact can be reversed or the lost

resource can be replaced.

Table 20: Impact significant ranking

Ranking Magnitude Reversibility Extent Duration Probability

5 Very high/ don‟t

know

Irreversible Internation

al

Permanent Certain/inevitabl

e

4 High National Long term

(impact ceases

after operational

life of asset)

Almost certain

3 Moderate Reversible with

human

intervention

Provincial Medium term Can occur

2 Low Local Short term Unusual but

possible

Page 92: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

92

1 Minor Completely

reversible

Site bound Immediate Extremely

remote

0 None None None

Significance= Consequence (Magnitude+ Duration+ Extent + Reversibility) X Probability

Page 93: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

Table 21: Impact rating

IMPACTS Alternative 1: Without Mitigation Alternative 1: With Mitigation

DIRECT

Topography and Soils 7 6

Water Resources 12 6

Flora: Destruction of threatened

and protected flora species

12 6

Flora: Destruction of sensitive

pristine habitat types

12 6

Avifauna 8 7

Heritage 36 7

Waste 8 7

Dust 14 5

Noise 16 7

Land-use 10 0

INDIRECT

Flora: Species change 7 6

Flora: Surrounding

habitat/species

8 7

Social 7 6

CUMULATIVE

Flora 8 5

Page 94: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

2

Construction Phase

Alternative A2 and S2: (Mamphuli-Dzwerani EXT A substation and 2x 132kV power line from Mamphuli-Dzwerani EXT A new

substation to connect to the existing 132kV powerline at Tshitungulwana village – Construction Phase

Table 22: Construction phase

Potential impacts: Significance rating of impacts without

mitigation:

Proposed mitigation: Significance rating of impacts after mitigation:

Direct Impacts

1. Topography and Soils: The direct impact on landforms with the establishment of distribution lines and additional substation components is mainly one of disruption of surface soils. Potential erosion impacts are anticipated to be limited to the construction phase during site clearing activities.

Magnitude: 2 Reversibility: 3 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 8

Dry periods must be used for construction-, maintenance- and inspection activities in order to curb occurrence/ augmentation of erosion in areas of existing erosion.

Disturbed areas of natural vegetation as well as cut and fills must be rehabilitated immediately to prevent soil erosion.

Motor vehicles must not be allowed to cross rivers or streams in any area other than an approved crossing, taking care to prevent any impact (particularly erosion) in surrounding habitat.

Removed topsoil must be stored separately in areas where excavation/degradation takes place, and it must also be used for rehabilitation purposes in order to facilitate re-growth of species that occur naturally in the area.

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 7

2. Water Resources: Pollution of groundwater and surface water

Magnitude: 2 Reversibility: 3 Extent: 1 Duration: 2

Adequate sanitary facilities and ablutions must be provided for construction workers.

Waste water should be directed into the proper systems.

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2

Page 95: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

3

resources. Probability: 1 Significance Rating: 8

Sewage water should not be channelled through surface water bodies or be allowed to flow freely or stagnate on the soil surface.

Use and or storage of materials, fuels and chemicals which could potentially leak into the ground must be controlled.

Further detailed mitigation measures are included in the EMPr (Appendix F).

Probability: 1 Significance Rating: 6

3. Flora: Impacts include: a) Destruction of

threatened and protected flora species – physical damage or destruction of Red Data or Protected species or areas those are suitable for these species, representing a significant impact on the biodiversity of a region.

b) Destruction of sensitive pristine habitat types – The loss of pristine habitat types or habitat that are regarded sensitive as a result of restricted presence in the larger region (atypical habitat) represents a potential loss of habitat and biodiversity on a

Magnitude: 2 Reversibility: 3 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 9 Magnitude: 2 Reversibility: 3 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 8

A walk-through of the approved servitude be conducted prior to construction activities commencing. All individuals / stands of protected trees must be clearly and visibly marked prior to the start of construction or maintenance procedures.

Marking shall be done by steel stakes with tags, if required to demarcate construction areas by semi-permanent means in order to control movement of personnel, vehicles, providing boundaries for construction sites in order to prevent spread of impacts. No painting or marking of rocks or vegetation to identify locality or other information shall be allowed as it will disfigure the natural setting.

Disturbance of vegetation must be limited to areas of construction.

Removal of vegetation / plants shall be avoided until such time as soil stripping is required and similarly exposed surfaces must be re-vegetated or stabilised as soon as is practically possible during rehabilitation.

The establishment and re-growth of alien vegetation must be controlled after the

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 7 Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 7

Page 96: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

4

regional scale. removal of grass. All declared aliens must be identified and managed in accordance with the Conservation of Agricultural Resources Act, 1983 (Act No.43 of 1983).

Further detailed mitigation measures are included in the EMPr (Appendix F).

4. Avifauna: impact on birds breeding, foraging and roosting in or in close proximity of the site, through the modification of habitat.

Magnitude: 2 Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 8

The extent of the construction site should be demarcated on site layout plans (preferably on disturbed areas or those identified with low conservation importance), and no construction personnel or vehicles may leave the demarcated area except those authorised to do so. Those areas surrounding the construction site that are not part of the demarcated development area should be considered as “no-go” areas for employees, machinery or even visitors;

Bird guards may be fitted to all the tower structures;

Spans that cross drainage lines should be marked with bird flight diverters on the earth wire of the line, alternating black and white:

Pylons must be placed outside of the drainage line perimeter;

Poles should be fitted with bird perches on top of the poles to draw birds from insulators; and

The removal of large trees should be avoided.

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 7

5. Heritage: No Graves were identified along this route except one set 700m away from the

Magnitude: 2 Reversibility: 3 Extent: 2 Duration: 2

If anything is noticed, work in that area should be stopped and the occurrence should immediately be reported to a

lIHRA, preferably one at which an

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2

Page 97: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

5

substation site Probability: 4 Significance Rating: 36

archaeologist is available. The archaeologist should then investigate and evaluate the find.

Any discovered artefacts shall not be removed under any circumstances. Any destruction of a site can only be allowed once a permit is obtained and the site has been mapped and noted. Permits must be obtained from the South African Heritage Resources Agency.

Probability: 1 Significance Rating: 7

6. Waste: Waste generation during the construction phase would have a negative impact on the environment, if not controlled adequately. Waste includes: general construction rubble, hazardous waste (used oil, cement and concrete etc.).

Magnitude: 1 Reversibility: 2 Extent: 2 Duration: 2 Probability: 2 Significance Rating: 14

Efforts must be made to ensure waste on site must be recycled and reused.

Disposal of waste must be in accordance with relevant local and provincial legislative requirements.

The Contractor must familiarise themselves with the definitions of waste and the handling, storage and transport of it as prescribed in the applicable environmental legislation.

Burning of waste material would not be permitted.

Further detailed mitigation measures are included in the EMP (Appendix F).

Magnitude: 1 Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

7. Dust: Dust emissions would vary from day to day depending on the phase of construction, the level of activity, and the prevailing meteorological conditions. The following possible sources of fugitive dust have been identified as

Magnitude: 2 Reversibiity:2 Extent: 1 Duration: 2 Probability: 2 Significance Rating: 7

Frequent and effective dust-suppression is advised, particularly along dirt roads, especially during dry periods by the regular application of water. Water used for this purpose must be used in quantities that will not result in the generation of run-off.

Magnitude: 2 Reversibility: 1 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 6

Page 98: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

6

activities which could potentially generate dust during construction operations at the site: vehicle activities associated with the transport of equipment to the site; preparation of the surface areas which may be required prior to the set up of new infrastructure; and the removal of construction equipment from site after the set up of new equipment.

8. Noise: During the construction phase there is likely to be an increase in noise pollution. The following possible sources of noise could potentially generate noise pollution during construction: construction activities (excavating and site clearing); construction vehicles; and construction staff.

Magnitude: 2 Reversibility: 1 Extent: 1 Duration: 1 Probability: 2 Significance Rating: 10

Notification of adjacent landowners must be done on any envisaged noisy construction activities eg Blasting.

Provide all equipment and vehicles with standard silencers that are continuously maintained.

It must be noted that when the noise exceeds 85 dBA employees should wear ear protection equipment

Magnitude: 2 Reversibility: 1 Extent: 1 Duration: 1 Probability: 1 Significance Rating: 5

9. Land-use: The construction of the distribution line is within the approved vacant servitude and could not

Magnitude: 1 Reversibility: 1 Extent: 1 Duration: 1 Probability: 1

No mitigation proposed as the power line runs within the approved vacant servitude - However, the footprint of the proposed pole structure to be used is small (i.e. approximately 1 m x 1 m) and would thus have a localised

Magnitude: 1 Reversibility: 1 Extent: 1 Duration: 1 Probability: 1

Page 99: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

7

potentially have a very any impact on agricultural activities in the area.

Significance Rating: 4

impact. As agricultural activities can still continue to a large degree below the powerline, the impact on the use of land for agricultural purposes is anticipated to be low.

Significance Rating: 4

10. Social: Loss of grazing land and impact on landowners sense of place.

Magnitude: 2 Reversibility: 1 Extent: 2 Duration: 1 Probability: 1 Significance Rating: 6

The negotiation process with landowners must include compensation for the temporary loss of grazing land where necessary.

After completion of the construction activities rehabilitation activities must be done to ensure that the land is returned in the same condition as prior to the construction activities.

Mitigation measures should be implemented to avoid any negative impact on animals (e.g. fencing off the construction area).

Rehabilitation of the grazing area to their original grazing conditions should be done to ensure that cattle can continue to graze in the area once they are returned to that area.

Where the area cannot be rehabilitated to its original condition within a reasonable period of time, Eskom or its appointed contractor(s) should provide funding to obtain alternative food sources to the farmer for the time period required for natural rehabilitation to occur within the grazing area.

Magnitude: 1 Reversibility:1 Extent: 2 Duration: 1 Probability: 1 Significance Rating: 5

Indirect Impacts

1. Flora: a) Floristic species

changes subsequent to development.

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2

Invaders and exotic weeds and that might establish on the re-vegetated areas should be controlled to allow the grasses to properly establish.

Magnitude: 1 Reversibility: 2 Extent: 1 Duration: 2

Page 100: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

8

b) Impacts on surrounding habitat/ species.

Probability: 1 Significance Rating: 7 Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 2 Significance Rating: 14

Monitoring the potential spread of declared weeds and invasive alien vegetation to neighbouring land and protecting the agricultural resources and soil conservation works are regulated by the Conservation of Agricultural Resources Act, No. 43 of 1983 and should be addressed on a continual basis.

Probability: 1 Significance Rating: 6 Magnitude: 2 Reversibility: 1 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 6

a) Alien vegetation encroachment associated with the abovementioned disturbances.

Magnitude: 2 Reversibility: 2 Extent: 1 Duration: 2 Probability: 2 Significance Rating: 14

Provision of adequate stormwater measures and controls during construction.

The establishment and re-growth of alien vegetation must be controlled after the removal of grass. All declared aliens must be identified and managed in accordance with the Conservation of Agricultural Resources Act, 1983 (Act No.43 of 1983).

Magnitude: 1 Reversibility: 1 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 5

2. Social: Limited opportunities do, however, exist for manual labour for unskilled tasks, where the appointed contractor would be required to make use of local workers (e.g. for bush clearing and the digging of foundations).

Magnitude: 2 Reversibility: 1 Extent: 1 Duration: 1 Probability: 2 Significance Rating: 10

It is recommended that local labour should be utilised as far as possible to avoid conflicts with local communities who also need employment opportunities.

Magnitude: 3 Reversibility: 1 Extent: 1 Duration: 2 Probability: 7 Significance Rating: 49

Cumulative Impacts

1. Flora: Increase in local and regional

Magnitude: 2 Reversibility: 2

Cumulative impacts associated with this type of development would lead to initial,

Magnitude: 2 Reversibility: 2

Page 101: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

9

fragmentation/ isolation of habitat -

Extent: 1 Duration: 2 Probability: 1 Significance Rating: 7

incremental or augmentation of existing types of environmental degradation, including impacts on the air, soil and water present within available habitat. Pollution of these elements might not always be immediately visible or readily quantifiable, but incremental or fractional increases might rise to levels where biological attributes could be affected adversely on a local or regional scale. In most cases are these effects are not bound and is dispersed, or diluted over an area that is much larger than the actual footprint of the causal factor.

Extent: 1 Duration: 2 Probability: 2 Significance Rating: 14

Summary of Impacts and Average Points allocated to each Proposed Distribution Line during the Construction Phase

Table 23: Summary of impact rating

IMPACTS Alternative 1: Without Mitigation Alternative 1: With Mitigation

DIRECT

Topography and Soils 7 6

Water Resources 12 6

Page 102: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

10

Flora: Destruction of threatened

and protected flora species

12 6

Flora: Destruction of sensitive

pristine habitat types

12 6

Avifauna 8 7

Heritage 36 7

Waste 8 7

Dust 14 5

Noise 16 7

Land-use 10 0

INDIRECT

Flora: Species change 7 6

Flora: Surrounding

habitat/species

8 7

Social 7 6

CUMULATIVE

Flora 8 5

Operational Phase

Page 103: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

11

Alternative A1 and S1: (Mamphuli-Dzwerani EXT A substation and 2x 132kV power line from Mamphuli-Dzwerani EXT A new

substation to connect to the existing 132kV powerline at Tshitungulwana village– Operational Phase

Table 24: Operational phase

Potential impacts: Significance rating of impacts:

Proposed mitigation: Significance rating of impacts after mitigation:

Direct Impacts

1. Access Roads: Access roads used for maintenance might impact on vegetation and water bodies.

Magnitude: 1 Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

Use should be made of existing roads as far as possible, ensuring proper maintenance/upgrade. Alternative methods of construction / access to sensitive areas are recommended.

No vehicles should be allowed to cross rivers or streams in any area other than an approved crossing, taking care to prevent any impact (particularly erosion) in surrounding habitat.

Vehicular traffic shall not be allowed in permanently wet areas, no damage shall be caused to wet areas. Where necessary, alternative methods of construction shall be used to avoid damage to wet areas.

Any work or access near or in a permanent drainage system may have implications in terms of the National Water Act, 1998 (Act No. 36 of 1998), and therefore may well require the application of a Water Use License. Therefore, the contractor must in consultation with the ECO, assess all areas along the alignment well in advance in order to ensure the relevant Water Use License is applied for where required.

Magnitude: 1 Reversibility: 1 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 6

2. Avifauna: Magnitude: 2 Please refer to Appendix for a visual Magnitude: 1

Page 104: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

12

a) Line would impact on vegetation and habitat types, water resources and impact on threatened species.

Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 8

representation to aid the marking of the distribution line with bird deterrent devises.

Reversibility:2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

3. Waste: Waste generation during the operation phase would have a negative impact on the environment, if not controlled adequately. Waste includes: general waste or hazardous waste (used oil etc.).

Magnitude: 2 Reversibility: 2 Extent: 2 Duration: 2 Probability: 2 Significance Rating: 16

Where possible, construction waste on site must be reused or recycled.

Disposal of waste must be in accordance with relevant legislative requirements.

The Contractor must familiarise themselves with the definitions of waste and the handling, storage and transport of it as prescribed in the applicable environmental legislation.

Burning of waste material would not be permitted.

Further detailed mitigation measures are included in the EMP (Appendix F).

Magnitude: 1 Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

Indirect Impacts

1. Flora: Surrounding areas and species present in the direct vicinity of the study area could be affected by indirect impacts resulting from operation activities.

Magnitude: 1 Reversibility: 1 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 6

No mitigation proposed.

2. Socio-economic: The proposed new 66 kV distribution line would decrease the existing power shortages experienced in the

Magnitude: 1 Reversibility:2 Extent: 2 Duration: 2 Probability: 1

No mitigation proposed.

Page 105: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

13

area. The reliable power source would also open the door to new industries, within the area, in turn contributing to an increase in GDP.

Significance Rating: 7

3. Electromagnetic Fields: Magnetic fields that naturally emanate from sources such as distribution lines are directly proportionate to the amount of current flowing through the distribution lines at any given time. A higher loading condition such as may be present in hot summer months would result in increased magnetic field levels. According to the World Health Organisation (WHO) it has become increasingly unlikely (based on the existing body of research) that exposure to Electromagnetic Fields (EMFs) constitutes a serious health hazard, although some uncertainty remains. .

Temporal: Long-term (-3) Magnitude: 1 Reversibility:2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

In general, it is not recommended that humans should live under power lines due to the effects of EMF. However, the radiation decreases with an increase in distance from the source. The EMFs are insignificant on the servitude border.

Magnitude: 1 Reversibility: 2 Extent: 1 Duration: 2 Probability: 1 Significance Rating: 6

Page 106: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

14

4. Safety: There is the potential risk of electrocution (people and livestock) if access to the site is not controlled.

Magnitude: 1 Reversibility: 1 Extent: 2 Duration: 1 Probability: 3 Significance Rating: 15

It is recommended that the landowners and affected community members be contacted in advance to ensure that they are forewarned of the construction and maintenance activities planned in the area. In addition, the local community must be educated about the dangers of high voltage electricity. Safety and security issues should be addressed as a priority by Eskom.

Magnitude: 1 Reversibility: 1 Extent: 2 Duration: 1 Probability: 1 Significance Rating: 5

5. Visual: The visual impact of the proposed 66 kV distribution line would depend on the structures used and visual qualities of the structures, and on the nature of the receiving environment.

Magnitude: 1 Reversibility: 2 Extent: 2 Duration: 2 Probability: 1 Significance Rating: 7

No mitigation is proposed as this line is the preferred route.

Cumulative Impacts

None.

Summary of Impacts and Average Points allocated to each Distribution Alternative during the Operational Phase

Table 25: Operational impact rating

IMPACTS Alternative 1 : Without Mitigation Alternative 1: With Mitigation

DIRECT

Access Roads 12 6

Avifauna 8 7

Page 107: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

15

Waste 10 5

INDIRECT

Flora 8 -0

Socio-economic 8 0

Electromagnetic

Fields

12 6

Safety 12 7

Visual 14 8

CUMULATIVE

None

Page 108: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

7.4.11 No-go alternative (compulsory)

The following are the impacts for no-go alternative

7.4.11.1 Direct Impacts:

No prospects for Mine expansion in future

Power outraging will continue

Causing disruptions at the mine

Affecting mining operation

No new electrification of households

No employment opportunities will be created (i.e. no construction phase).

7.4.11.2 Indirect Impacts:

No new job opportunities due to mine failing to expand

Mining companies lose profit due to on-going disruptions due to power outages

Local suppliers and contractors will not benefit from the business opportunities

relating to construction

No new business ventures due to lack of electricity

Power outages and uncertain power supply to the area

Use of firewood, paraffin and anthracite being a danger to households

7.4.11.3 Cumulative Impacts:

Economic stagnation of the area

Positive impact - Small reduction of carbon dioxide emissions from power station as

no new connections will alleviate the use of coal and reduce greenhouse gas

emissions into the atmosphere.

On the contrary, the current use of firewood and anthracite also emits greenhouse

gasses into the atmosphere

7.4.12 Environmental impact statement

Alternative 1 Mamphuli-Dzwerani EXT A substation and 2 x 132kV powers line from

Mamphuli-Dzwerani EXT A new substation to connect to the existing 132kV powerline at

Tshitungulwana village Preferred)

Page 109: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

2

7.4.13 Heritage

The HIA specialist identified a grave and monument dedicated to Maswanganyi is located

200m to the northwest of the site. The 200m distance is away from the site and will not be

affected by the proposed project.

Phase 1 Heritage Impact Assessment did not identified any graves along the proposed

project area except a clear grave in 200m north- west of the substation. Although there are

no graves identified along the proposed route, the graves may be found during construction

phase underground.

The Archaeologist did not identify any archaeological or heritage resources such as graves,

material and artifacts of cultural significance, but however, the specialist highly

recommended that should any material or artifacts of cultural significant unearthed during

excavation, all activities must cease and SAHRA and/or Archaeologist or LIHRA be informed

of the accidentally discoveries.

From Heritage point of view, the proposed route is viable as it will not impact on any graves,

graveyards and/or heritage resources. Therefore the significance is regarded as very low.

From Ecological point of view, the natural vegetation at the site is moderately modified. The

proposed Mamphuli-Dzwerani EXT A power line route falls within the northern reaches of the

Granite Lowveld vegetation type (Mucina & Rutherford 2006). Its distribution is fairly wide,

stretching from Kaapmuiden and Malelane in the south to the plains south and east of

Thohoyandou in the north. Mucina & Rutherford (2006) suggests that further research may

reveal a need to differentiate the northern form from the southern form of the vegetation unit

as these areas differ slightly in dominant plant species and vegetation structure. In general,

this vegetation unit is described as tall broad-leaved shrub land with few large trees to

moderately dense low woodland on deep sandy uplands with dense thickets and open

savannah in the bottomlands.

Along drainage lines there is a greater diversity of plants particularly within dense riparian

thickets which also support larger trees. Combretum apiculatum is the dominant tree species

on the slopes and plains while Senegalia (Acacia) nigrescens, Dichrostachys cinerea and

Grewia bicolor dominate the thickets in the bottomlands. Terminalia sericea is the common

woody species in the deep sandy uplands.

Page 110: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

3

In the northern range of this vegetation type Swazian Goudplaats Gneiss, Makhutswi Gneiss

and Nelspruit Suite (Granite gneiss and migmatite) form the basement geology. This

Archaean granite and gneiss weathers into sandy soils in the higher areas and clayey soils

with high sodium content in the low-lying areas (Mucina & Rutherford 2006).

The climate within the Granite Lowveld vegetation unit is typical of north-eastern Southern

Africa with summer rainfall and dry winters. The annual precipitation in this area ranges from

500mm per year in the eastern flats to about 900mm per year in the north-west and along the

escarpment. Mean monthly maximum and minimum temperatures are 38°C and 3.7°C for

January and July.

The conservation status of this vegetation unit is considered to be vulnerable with more than

20% already transformed by cultivation and settlement development

(Mucina & Rutherford 2006).

7.4.14 Avi-faunal

7.4.14.1 DESCRIPTION OF EXPECTED IMPACTS

Because of their size and prominence, electrical infrastructures constitute an important

interface between wildlife and man. Negative interactions between wildlife and electricity

structures take many forms, but two common problems in southern Africa are electrocution of

birds (and other animals) and birds colliding with power lines. (Ledger and Annegarn 1981;

Ledger 1983; Ledger 1984; Hobbs and Ledger 1986a; Hobbs and Ledger 1986b; Ledger,

Hobbs and Smith, 1992; Verdoorn 1996; Kruger and Van Rooyen 1998; Van Rooyen 1998;

Kruger 1999; Van Rooyen 1999; Van Rooyen 2000; Anderson 2001; Shaw 2013).

7.4.14.2 Electrocutions

Electrocution refers to the scenario where a bird is perched or attempts to perch on the

electrical structure and causes an electrical short circuit by physically bridging the air gap

between live components and/or live and earthed components (Van Rooyen, 2004). The

electrocution risk is largely determined by the pole/tower design. The tower design that has

been proposed for this project is the steel monopole.

Page 111: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

4

7.4.14.3 Steel monopole

Clearance between phases on the same side of the 132kV pole structure is approximately

2.2m for this type of design, and the clearance on strain structures is 1.8m. This clearance

should be sufficient to reduce the risk of phase – phase electrocutions of birds on the towers

to negligible. The length of the stand-off insulators is approximately 1.6m. If very large

species attempts to perch on the stand-off insulators, they are potentially able to touch both

the conductor and the earthed pole simultaneously potentially resulting in a phase – earth

electrocution. This is particularly likely when more than one bird attempts to sit on the same

pole, which is an unlikely occurrence, except occasionally with vultures. Vultures have not

been recorded and are unlikely to occur regularly within the study area, but sporadic

occurrence cannot be ruled out. The only envisaged high risk scenario would be when a

carcass becomes available within a few hundred metres of the line, attracting White-backed

Vultures which may cluster on a few poles. This is likely to be an irregular event in the study

area.

In summary it is concluded that the risk of electrocution posed to avifauna by the steel

monopole design is likely to be of LOW significance and restricted to vultures. It should be

mentioned that the pole design holds no inherent electrocution risk for other large solitary

raptors such as eagles, as they almost never perch together in large numbers on the same

structure.

7.4.14.4 Collisions

Collisions are probably the biggest single threat posed by transmission lines to birds in

southern Africa (van Rooyen 2004; Shaw 2013). Most heavily impacted upon are bustards,

storks, cranes and various species of water birds. These species are mostly heavy-bodied

birds with limited manoeuvrability, which makes it difficult for them to take the necessary

evasive action to avoid colliding with power lines (Van Rooyen 2004; Anderson 2001; Shaw

2013).

In a recent PhD study, Shaw (2013) provides a concise summary of the phenomenon of

avian collisions with power lines:

Page 112: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

5

“The collision risk posed by power lines is complex and problems are often localised. While

any bird flying near a power line is at risk of collision, this risk varies greatly between different

groups of birds, and depends on the interplay of a wide range of factors (APLIC 1994).

Bevanger (1994) described these factors in four main groups – biological, topographical,

meteorological and technical. Birds at highest risk are those that are both susceptible to

collisions and frequently exposed to power lines, with waterbirds, gamebirds, rails, cranes

and bustards usually the most numerous reported victims (Bevanger 1998, Rubolini et al.

2005, Jenkins et al. 2010).

In the present instance, the most likely potential candidates for collision mortality on the

proposed power line are Secretarybird, Lanner Falcon and Abdim‟s Stork. None of the Red

List waterbird species are likely to be at risk of collisions because the alignment does not

cross any major waterbodies or rivers. A large proportion of the proposed power line occurs

in savanna habitat where the risk of collisions are likely to be few and far between, as there

are no specific areas where one would expect a concentration of birds. Vultures would be

most at risk if they descend to a carcass near the line, which is not likely to be a regular

event, given the fact that the occurrence of vultures are likely to be the exception rather than

the rule. Abdim‟s Stork will be most at risk in agricultural clearings, where they can occur in

large flocks, especially on freshly ploughed fields and irrigated crops. In summary, the risk of

collision posed to avifauna by proposed power line is likely to be of LOW significance

7.4.14.5 Displacement due to habitat destruction and

disturbance

Page 113: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

6

During the construction phase and maintenance of power lines and substations, some

habitat destruction and transformation inevitably takes place. This happens with the

construction of access roads, the clearing of servitudes and the levelling of substation yards.

Servitudes have to be cleared of excess vegetation at regular intervals in order to allow

access to the line for maintenance, to prevent vegetation from intruding into the legally

prescribed clearance gap between the ground and the conductors and to minimize the risk of

fire under the line, which can result in electrical flashovers. These activities have an impact

on birds breeding, foraging and roosting in or in close proximity of the servitude through

transformation of habitat, which could result in temporary or permanent displacement. In the

present instance, the risk of displacement of Red List species due to habitat destruction is

likely to be fairly limited given the low reporting rate for Red List species in the study area,

the small footprint of the proposed project and the presence of existing power line

infrastructure routed on either side of the proposed 132kV power line.

Apart from direct habitat destruction, the above mentioned construction and maintenance

activities also impact on birds through disturbance; this could lead to breeding failure if the

disturbance happens during a critical part of the breeding cycle. Construction activities in

close proximity could be a source of disturbance and could lead to temporary breeding failure

or even permanent abandonment of nests. The very low reporting rates for Red List species

in the study area are an indication that they are not regularly utilising the area for breeding.

The impact of disturbance is therefore likely to be LOW and temporary as far as Red List

species are concerned. However, if the alignment is authorised, a detailed inspection would

be required to establish if there are any breeding Red List species that could be disturbed. In

such an event, appropriate mitigation measures would need to be implemented (such as

postponing the construction of the line to avoid peak breeding season).

Recommendations from Avi-faunal point of view:

The project can proceed subject to the recommendations made below.

The correct pole structure must be utilized to avoid electrocution

In addition to this, the normal suite of environmental best practices should be applied,

such as ensuring strict control of staff, vehicles and machinery on site and limiting the

creation of new roads as far as possible.

Page 114: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

7

7.4.15 Visual

Visual impacts are generally anticipated to be of low significance due to the fact that the

proposed power line would be ensconced between the two existing power lines. So the two

existing power lines will blend well with the new proposed power line. However, the proposed

route is considered as viable options. It is strongly recommended that the mitigation

measures mentioned in the EMPr be implemented to minimise the potential negative visual

impacts.

7.4.16 Current and Existing Land Use

The area traversed by the proposed power line is generally being utilised for agricultural

purposes, though the route alignment is within the vacant servitude. The land use is for

electrical power line

Two alternative sites for the Substation were assessed as Alternative A1 and A2. Also the

powerlines alternatives were assessed as Alternative line S1 and S2. Both alternative lines

will cross watercourse I,e Luvuvhu river (perennial) as well as one non-perennial

watercourse. Impacts have been identified and mitigation measures were provided.

Alternative A2 and S2will have more negative impacts as compare to the preferred

alternatives and the limitations are as follows:

The proposed alternative A2 Mamphuli-Dzwerani EXT A substation is found at the

Critical Biodiversity Area 2 (CBA2). The powerline crosses the same for about 800m

and also crosses the Luvuvhu River The alternative power line S2 crosses a small

koppie. The drilling of a koppie to provide the foundation for the pylons might have a

negative impacts on the koppie environment

The alternative powerline S2 traverse through the established private farms (orchard).

The powerline will have adverse impacts on socio-economic of the area. Local

community members who make the living from the Orchard might lose their income if

part of the orchard is impacted by the powerlines

7.4.17 No-go alternative (compulsory)

Page 115: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

8

The no go option entails the non -construction of the power line. Although this option would

result in fewer impacts on the biophysical environment. It should be noted that most of the

study area has already been impacted upon by practices such as over grazing, wood

collection and urbanisation.

Electricity has become a fundamental need and precursor of development and improvement

of people‟s quality of life. If the proposed establishment of new power lines cannot go on, the

option would greatly affect the future electricity supply to the area and the future mines.

When the project is finished, it would further help ensure that there is continuous power

supply to the area, Vuwani town, its surrounding rural communities and the entire Municipal

area. The reliable electricity source would open the door to new economic opportunities,

within the general area, in turn contributing to an increase in the local GDP. Otherwise the

loss of electricity, power outages and associated negative ripple effects on the communities,

local businesses and the environment e.g. increased wood harvesting and air pollution

caused by the usage of fossil fuels. The significance of negative impacts posed by utilising

the no-go option can therefore be considered as high.

Direct impacts:

No additional electricity to the local community;

No new mines

Frequent power outages; and

No employment opportunities will be created.

Indirect impacts:

Negative impact on local enterprises and educational facilities;

Negative impact on the environment as people would rely on fuelwood and other

natural sources for heat and energy;

Pollution from the burning of fossil fuels to create energy;

Time wasted on looking for alternative energy sources; and

Limited development would take place in the area without reliable supply of electricity.

Cumulative impact

Diminishing productivity and quality of life in the local community

Page 116: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

9

7.5 RECOMMENDATION OF PRACTITIONER

Potential impacts of the proposed development have been identified and where necessary

mitigation measures have also been proposed for ensuring that adverse impacts are

strategically taken care of. The identification of mitigation measures is just one step of the

process for addressing adverse impacts, commitment and putting in place systems during

the construction and operational phase of the proposed development also remain key.

Therefore Eskom will have to ensure that appropriate measures have been taken to ensure

that precautionary steps are taken to avoid adverse impacts on people, economy and

environment. Where challenges have been encountered during construction or operation,

relevant mitigation measures must be implemented under the supervision of trained and

competent personnel.

During the EIA process, an extensive public participation process was conducted to ensure

that all Interested and Affected Parties were consulted and given time to raise their concerns

or provide comments. All issues identified during the public participation have been

sufficiently addressed to the satisfaction of the relevant stakeholders.

The following general recommendations will be taken care of during implementation of the

proposed development:

It is recommended that should any material or artefacts of cultural significance found

during exaction, all activities should cease and SAHRA and/ or an Archaeologist be

informed immediately

It is also recommended that mitigation measures for the proposed activity throughout

the project life-cycle are included in the Environmental Management Programme

(EMPr) attached to this document.

It is further recommended that Eskom should appoint an independent ECO to monitor

the compliance to the EMPr and the EA conditions

A copy of the EMPr must always be available on site.

Page 117: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

10

Based on the facts presented in the specialist reports, Mbofho Consulting and Project

Managers (MCPM) is of the opinion that no fatal flaws were identified and that the impacts

identified can be successfully mitigated to an acceptable level. In identifying, evaluating and

comparing impacts associated with the proposed new powerline and substation alternatives,

it has been concluded that Alternative 1 (A1) for the proposed new powerline as well as

Alternative 1 (S1) for the Substation are the preferred and recommended alternatives for

the proposed project.

Page 118: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

11

Appendixes

The following appendixes will be attached:

Appendix A: Maps

Appendix B: Photographs

Appendix C: Facility illustration(s)

Appendix D: Specialist reports (including terms of reference)

Appendix E: Public Participation

Appendix F: Impact Assessment

Appendix G: Environmental Management Programme (EMPr)

Appendix H: Details of EAP and expertise

Appendix I: Specialist‟s declaration of interest

Appendix J: Additional Information

Page 119: DRAFT BASIC ASSESSMENT REPORT FOR THE PROPOSED … Draft BAR...eskom holdings (soc) limited, limpopo operating unit (lou) draft basic assessment report for the proposed power line

12