dr technologies, strategies and case studies · hvac - global temperature adjustment •gta based...

40
1 DR Technologies, Strategies and Case Studies March 3, 2011 Mary Ann Piette, Sila Kiliccote, Dave Watson, Rish Ghatikar Research Director, DRRC Deputy, Building Technologies Department Staff Scientist, LBNL [email protected]

Upload: others

Post on 21-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

1

DR Technologies, Strategies and Case Studies

March 3, 2011

Mary Ann Piette, Sila Kiliccote, Dave Watson, Rish Ghatikar

Research Director, DRRCDeputy, Building Technologies Department

Staff Scientist, [email protected]

Page 2: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

2

Concepts and Terminology Levels of Automation in DR

• Manual DR – Building operators manually turn off

switches and change set points at each device

• Labor intensive

• Poor reliability, repeatability

• Day ahead notification req’d

• Semi-Automated DR - pre-programmed DR strategies

initiated by a person via centralized control system

• Better reliability, repeatability

• Hours ahead notification req’d

• Fully-Automated DR - pre-programmed DR strategies

automatically initiated upon receipt of remote signal

• Most reliable & repeatable

• Sheds can occur within seconds

Page 3: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

3

HVAC - Global Temperature Adjustment

• GTA based DR strategies can be used:

• Manually by building operators

• Automatically based on remote signals

• GTA Signal from central EMCS server to all space

temperature controllers throughout the facility.

• GTA well suited for HVAC equipment such as:

• VAV boxes

• Fan coil units

• CAV multi-zone temperature control valves

• heat pumps & DX package units.

• Heating setpoints should remain the same or be

reduced during GTA mode.

Page 4: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

4

Auto-DR in 130,000 ft2 County Office Current Practice

Page 5: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

5

DR Field Tests from 2003, 2004 & 2005

GSA, Phillip Burton

Federal Building

Federal (San Francisco)

Office

1,424,000 ft²

2,130 kW peak

GSA, Ronald Dellums

Federal Building

Federal (Oakland)

Office

978,000 ft²

4,100 kW peak

GSA, National Archive

& Record Admin.

Federal (San Bruno)

Archive storage

238,000 ft²

280 kW peak

US Postal Service

San Jose PDC

Federal (San Jose)

Process, distribution

390,000 ft²

1,630 kW peak

Joe Serna Jr. Cal EPA

Headquarters Building

State (Sacramento)

Office

950,000 ft²

1,990 kW peak

UC Santa Barbara

Davidson Library

State (Santa Barbara)

Library

289,000 ft²

1,090 kW peak

Page 6: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

6

Typical Power Densities

– California Commercial End-Use Survey (CEUS) and eleven field test buildings (Yin et al. 2010)

– The simulation results from DRQAT are lower than field test data and CEUS, likely due to the assumed lighting densities, HVAC system efficiencies and building envelope of the prototypical building model

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

#1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 CEUS DRQAT

No

rm

ali

zed

Wh

ole

Bu

ild

ing

Pea

k D

em

an

d

(W/f

t2)

Page 7: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

7

Results using GTA (2003-2005)

Site name Area (ft2)

Cooling

Capacity

(Tons)

Strategy Used

# Days

of

Testing

Climate

Zone

Outside

temperature at

time of peak

Average

shed

(W/ft2)*

Peak shed

(W/ft2)

GSA Oakland

Federal

Building

978,000 3,840Global Temp

Adjustment4 3 88 0.30 1.10

Contra Costa

County 2350

Arnold

131,000 240Global Temp

Adjustment2 12 90 0.30 0.67

Contra Costa

County 50

Douglas

90,000 240Global Temp

Adjustment2 12 90 0.58 1.34

GSA Santa

Rosa Federal

Building

80,000 200Global Temp

Adjustment*20 2 95 1.50 2.40

Sacramento

County Building80,000 180

Global Temp

Adjustment*3 12 70 0.75 1.00

Cisco 4,354,000 24,600

Global Temp

Adjustment &

other strategies

1 4 90 0.16 0.20

Echelon 75,000 4,800

Global Temp

Adjustment &

other strategies

2 4 90 0.89 1.22

Page 8: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

8

Typical EMCS Graphical User Interface

Page 9: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

9

Normal Mode

Global

Temp

Adjustment

72 7374

7576

777879

7170

6968

6766

65

DR Modete

xt

GTA – Conceptual Implementation #1 (Absolute)

Page 10: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

10

Normal Mode DR Modete

xt

Global Temp Adjustment

(Relative)

“Relax” each zone

by _2_ deg.F

GTA – Conceptual Implementation #2(Relative)

Page 11: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

11

Cost to Implement GTA

• Software only – no hardware cost.

• Several (smaller) vendors already offer this feature

at no extra cost.

• Sold nationwide

• Remaining vendors can add GTA to standard product

line at a low one-time cost.

• GTA can be added to existing buildings

• Zone level DDC required

• Programming cost $2K - $10K per site

Page 12: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

12

Comfort: 1.5 deg. F° Temperature Rise at GSA (39 zone average)

68

69

70

71

72

73

74

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Zone T

em

pera

ture

[D

egre

e F

]

Actual Previous Days Average

Page 13: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

13

Comfort: Online Tennant Survey

Page 14: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

14

LBNL DR Strategies Report

•DR Control Strategies for Commercial Buildings:

DR Strategy Global Temperature Adjustment (GTA)

Definition Increase zone temperature setpoints for an entire facility.

HVAC type CAV, VAV systems. Cooling by central plant or package unit DX.

System

applicability

EMCS must have DDC control to the zone level. EMCS must have

Global Temp Adjustment feature.

Sequence of

Operation (DR)

Increase zone temperature cooling setpoints globally throughout

entire facility.

Zone temperature heating setpoints must remain unchanged or be

reduced.

Power savings in: Fans & Cooling systems

Efficiency

potential

Permanent increase in zone temperature setpoints for some zones

may be possible

Rebound

Avoidance

Gradual ramp back to normal setpoints. Lock out chillers etc.

Caution Occupant comfort. Zones will approach increased temperature

setpoints at different rates.

Page 15: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

15

Acknowledgements .......................................................................................................... iii

Executive Summary ......................................................................................................... iv

1. Introduction............................................................................................................... 1

1.1. Objectives and Report Organization................................................................... 1

1.2. Objectives and Report Organization................................................................... 2

1.3. Building Operations and Energy Management................................................... 2

1.4. Terminologies and Concepts............................................................................... 5

2. Demand Response Strategy Overview .................................................................... 7

2.1. HVAC System .................................................................................................... 7

2.2. Lighting Systems .............................................................................................. 11

2.3. Miscellaneous Equipments ............................................................................... 12

2.4. Advanced Control Strategies ............................................................................ 12

2.5. Strategies Used in Case Studies........................................................................ 12

3. Demand Response Strategy Detail ........................................................................ 15

3.1. HVAC Systems................................................................................................. 15

3.1.1. Global Temperature Adjustment............................................................... 15

3.1.2. Passive Thermal Mass Storage ................................................................. 18

3.1.3. Duct Static Pressure Decrease .................................................................. 19

3.1.4. Fan Variable Frequency Drive Limit ........................................................ 20

3.1.5. Supply Air Temperature Increase ............................................................. 21

3.1.6. Fan Quantity Reduction ............................................................................ 22

3.1.7. Cooling Valve Limit ................................................................................. 23

3.1.8. Chilled Water Temperature Increase ........................................................ 24

3.1.9. Chiller Demand Limit ............................................................................... 25

3.1.10. Chiller Quantity Reduction ....................................................................... 26

3.1.11. Rebound Avoidance Strategies ................................................................. 27

3.2. Lighting Systems .............................................................................................. 28

3.2.1. Zone Switching ......................................................................................... 28

3.2.2. Fixture/Lamp Switching ........................................................................... 29

3.2.3. Step Dimming ........................................................................................... 31

3.2.4. Continuous Dimming................................................................................ 32

3.3. Miscellaneous Equipments ............................................................................... 33

3.3.1. Fountain pump .......................................................................................... 33

3.3.2. Anti-sweat heater ...................................................................................... 33

3.3.3. Electric vehicle charger............................................................................. 33

3.3.4. Industrial process loads............................................................................. 33

3.3.5. Cold storage .............................................................................................. 34

3.3.6. Irrigation water pump ............................................................................... 34

3.4. Non-Component-Specific Strategies ................................................................ 35

3.4.1. Demand Limit Strategy............................................................................. 35

3.4.2. Signal-level Response Strategy................................................................. 36

Building Control Strategies Guide and Case Studies

Page 16: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

16

0

50

100

150

200

250

300

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

Wh

ole

Bu

ild

ing

Po

wer /

kW

Pre-cooling with Two Steps Temperature Set up

Baseline DR

Precooling and Thermal Mass

Evaluate the Effect of

Control Strategies

based on:

– Utility rate structure

– Peak demand savings

– Zone comfort (PPD and PMV)

0

50

100

150

200

250

300

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

Wh

ole

Bu

ild

ing

Po

wer /

kW

Pre-cooling with Exponential Tempearature Set up

Baseline DR

0

50

100

150

200

250

300

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

Wh

ole

Bu

ild

ing

Po

wer /

kW

Pre-cooling with Linear Tempearature Set up

Baseline DR

68

70

72

74

76

78

80

82

84

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

Zo

ne T

em

pera

ture /

Deg

F

Pre-cooling with Linear Tempearature Set up

Baseline DR - Linear DR - Two Steps DR - Exponential

Page 17: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

17

Load Statistical Summary (LSS)

LSS a plot of average,

minimum and

maximum points for a

given range of dates.

- Refined to display

Near-base load and

near-high load (2.5

and 97.5 percentile

values) (Price 2010)

2530 Arnold, Jul/2008

0

100

200

300

400

500

600

12

:00

:00

AM

1:0

0:0

0 A

M

2:0

0:0

0 A

M

3:0

0:0

0 A

M

4:0

0:0

0 A

M

5:0

0:0

0 A

M

6:0

0:0

0 A

M

7:0

0:0

0 A

M

8:0

0:0

0 A

M

9:0

0:0

0 A

M

10

:00

:00

AM

11

:00

:00

AM

12

:00

:00

PM

1:0

0:0

0 P

M

2:0

0:0

0 P

M

3:0

0:0

0 P

M

4:0

0:0

0 P

M

5:0

0:0

0 P

M

6:0

0:0

0 P

M

7:0

0:0

0 P

M

8:0

0:0

0 P

M

9:0

0:0

0 P

M

10

:00

:00

PM

11

:00

:00

PM

Time of Day

Wh

ole

Bu

ild

ing

Po

we

r (k

W)

Average of kW Max of kW Min of kW

2008

Jul

2530 Arnold

IKEA-EPA, Sept/2008

0

200

400

600

800

1000

1200

1400

12

:00

:00

AM

1:0

0:0

0 A

M

2:0

0:0

0 A

M

3:0

0:0

0 A

M

4:0

0:0

0 A

M

5:0

0:0

0 A

M

6:0

0:0

0 A

M

7:0

0:0

0 A

M

8:0

0:0

0 A

M

9:0

0:0

0 A

M

10

:00

:00

AM

11

:00

:00

AM

12

:00

:00

PM

1:0

0:0

0 P

M

2:0

0:0

0 P

M

3:0

0:0

0 P

M

4:0

0:0

0 P

M

5:0

0:0

0 P

M

6:0

0:0

0 P

M

7:0

0:0

0 P

M

8:0

0:0

0 P

M

9:0

0:0

0 P

M

10

:00

:00

PM

11

:00

:00

PM

Time of Day

Wh

ole

Bu

ild

ing

Po

we

r (k

W)

Average of kW Max of kW Min of kW

2008

Sept

IKEA-EPA

Page 18: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

18

Fan System Adjustment - Fan speed limit

• Applicable to fans with variable frequency drives

(VFDs).

• Similar to duct static pressure setpoint reduction.

• Less predictable because of the open-loop nature of

the control.

• Fan speed limits may be useful as part of other DR

strategies such as cooling system adjustments.

Page 19: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

19

Fan System Adjustment - Fan Quantity Reduction.

• Applicable to constant air volume fan systems.

• Reduce fan energy by turning fans OFF completely.

• May be useful in common areas served by multiple

fans.

• Cooling energy in the fans that remain ON may

increase to make up for those that are OFF.

Page 20: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

20

Fan System Adjustment –Increase Supply Air temperature

• Applicable to CAV and VAV fan systems

• Saves mechanical cooling energy

• For air handlers with cooling coils, the savings will occur at the central cooling plant.

• For packaged DX units & heat pumps, the savings will be achieved at each unit.

• Avoid increased fan energy in VAV systems due to increased air flow

• Prevent this effect by limiting fan speeds to prior levels

Page 21: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

21

Fan System Adjustment - Cooling System Adjustment

• Applicable to Central Chiller plants & Packaged DX units & Heat Pumps.

• Most modern centrifugal, screw and reciprocating chillers have the capability of reducing demand for power:

• Raise chilled water supply temperature setpoint

• Limit the speed, capacity, number of stages or current draw of the chiller

• The quantity of chillers running can be reduced in some plants

Page 22: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

22

Lighting Based DR Strategies• Lighting systems offer great promise as a resource

for DR shed savings

• Lighting systems account for ~ 1/3 electric load in commercial buildings

• Lighting has no rebound effect during the transition from DR events to normal operations

• In California, most commercial buildings already have bi-level switching. 1/3 or 2/3 of the lights in a given office can be turn off.

• Pre-planned automated DR strategies make sheds more repeatable and less labor intensive.

• Technical challenges:

• Few office buildings have centralized control of lighting systems (Kiliccote, et al, 2005).

• Buildings with centralized lighting controls are not necessarily zoned to enable reduced light levels adequate for occupancy.

Page 23: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

23

Lighting Based DR Strategies

• Resolution of control is an important factor in determining the usefulness of lighting systems for DR. From highest to lowest resolution.

• Continuous Dimming.

– Allow light output to be dimmed from 100% to 10% (fluorescent) or 100% to 50% (HID).

– Gradual reductions not noticeable

– specific DR shed goals can be achieved

– Energy efficiency benefits in addition to DR

• Stepped Dimming, Lamp Switching, and Fixture Switching

– 2 or 3 light levels

– Noticeable, but manageable light levels.

– Lighting zones must be wired to ensure that all floor space remains illuminated at reduced levels.

• Zone Switching

– Applicable to zones that are unoccupied, or illuminated by windows.

– Egress light levels must be assured.

Page 24: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

24

DR Strategies: Lighting ( of )

START

Central lighting

control?

Y NCentral lighting

control?

Y N

Dimmable

ballast?

Y NDimmable

ballast?

Y N

Zone

switching

Zone

switching?

Y NZone

switching?

Y N

Bi-level

switching?

Y NBi-level

switching?

Y N

Do not try DR

at this time

Fixture

switching

Continuous

dimming

Lamp

switching

Step

dimming

Bi-level

infrastructure?

Y NBi-level

infrastructure?

Y N

Page 25: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

25

Comparison of End-Use Strategies

HVAC Lighting Other

Building use Glo

bal t

em

p. adju

stm

ent

Duct sta

tic p

res. In

cre

ase

SA

T Incre

ase

Fan V

FD

lim

it

CH

W tem

p. In

cre

ase

Fan q

ty. re

ductio

n

Pre

-coolin

g

Coolin

g v

alv

e li

mit

Boile

r lo

ckout

Slo

w r

ecovery

Exte

nded s

hed p

eriod

Com

mon a

rea li

ght dim

Offic

e a

rea li

ght dim

Turn

off li

ght

Dim

mable

balla

st

Bi-le

vel s

witc

hin

g

Non-c

ritic

al p

rocess s

hed

ACWD Office, lab X X X X X X X

B of A Office, data center X X X X X

Chabot Museum X X

2530 Arnold Office X X

50 Douglas Office X X

MDF Detention facility X

Echelon Hi-tech office X X X X X X X X

Centerville Junior Highschool X X

Irvington Highschool X X

Gilead 300 Office X

Gilead 342 Office, Lab X X

Gilead 357 Office, Lab X X

IKEA EPaloAlto Furniture retail X

IKEA Emeryville Furniture retail X

IKEA WSacto Furniture retail

Oracle Rocklin Office X X

Safeway Stockton Supermarket X

Solectron Office, Manufacture X X

Svenhard's Bakery X

Sybase Hi-tech office X

Target Antioch Retail X X

Target Bakersfield Retail X X

Target Hayward Retail X X X X

Walmart Fresno Retail X X

Global temperature

reset migrated to

State Energy Code

Page 26: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

26

Global Temperature AdjustmentGlobal Temperature Adjustment Amounts for Auto-DR sites

68.0

69.0

70.0

71.0

72.0

73.0

74.0

75.0

76.0

77.0

78.0

79.0

80.0

81.0

82.0

Customer

Tem

pera

ture

(F

)

Normal

Moderate

High

CPP

Ave. temp. increase (mod): 2.75 F

Ave. temp. increase (high): 1.88 F

DBP

Ave. temp. increase: 2.3 F

DBP CPP one-level GTACPP two-level GTA

Reta

il

Museum

Offic

e 1 Reta

il 1A

Offic

e 3

Govern

ment 1

Reta

il 2

School

Lab/O

ffic

e2

Govern

ment 2

Govern

ment 3

Govern

ment 4

Reta

il 3

Offic

e 4

Lab/O

ffic

e

Avera

ge

Avera

ge

Avera

ge

Page 27: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

27

Aggregated Demand, 6/26/2006 (OAT: 89 °F) - Zone 2, 8 sites

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Po

wer

[MW

]

ACWD B of A Chabot 2530 Arnold 50 Douglas

MDF Echelon Gilead 300 Gilead 342 Gilead 357

IKEA EPaloAlto Oracle Rocklin Target Hayward Adj OAT Reg BL CPP BL

Moderate Price High Price

Aggregated AutoDR Results – June 26, Zone 2

Moderate High Moderate High Moderate High

ACWD 78 91 28% 32% 1.53 1.78

B of A 478 604 9% 12% 0.67 0.85

2530 Arnold 102 140 20% 29% 0.78 1.07

50 Douglas 57 94 13% 22% 0.63 1.04

MDF 90 155 17% 30% 0.52 0.90

Echelon -2 80 0% 22% -0.02 1.07

Oracle Rocklin 85 60 17% 14% 0.85 0.60

Target Hayward 59 56 15% 15% 0.45 0.43

Aggregated 946 1281 11% 16% 0.65 0.88

Average kW Average % Average W/ft²

1.3 MW reduction

during high price

period

Page 28: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

28

Consistent Multi-Year Field Performance Automating DROpenADR Application Impacts 2003-2009

PG&E CPP Test Day (all participants)

7/9/2008

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

12:0

0 A

M

1:0

0 A

M

2:0

0 A

M

3:0

0 A

M

4:0

0 A

M

5:0

0 A

M

6:0

0 A

M

7:0

0 A

M

8:0

0 A

M

9:0

0 A

M

10:0

0 A

M

11:0

0 A

M

12:0

0 P

M

1:0

0 P

M

2:0

0 P

M

3:0

0 P

M

4:0

0 P

M

5:0

0 P

M

6:0

0 P

M

7:0

0 P

M

8:0

0 P

M

9:0

0 P

M

10:0

0 P

M

11:0

0 P

M

12:0

0 A

M

Wh

ole

Bu

ild

ing

Po

wer

(kW

)

CPP MA Baseline

Cumulative Shed on 7/9/08

Martinez, CA Office Building Electricity Use with & without AutoDR

June 21, 2006

0

100

200

300

400

500

600

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10

:00

11

:00

12

:00

13

:00

14

:00

15

:00

16

:00

17

:00

18

:00

19

:00

20

:00

21

:00

22

:00

23

:00

Wh

ole

Bu

ild

ing

Po

wer

[kW

]

0

20

40

60

80

100

120

OA

T (

Ou

tsid

e A

ir T

em

pera

ture

)

Actual Building Electricity Use with DR Estimated Building Electricity Use without DR OAT

Moderate

Price

High

Price

Normal

Price

Normal

Price

Price Change Signal Sent

Building automatically reduces electricity

use

Page 29: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

29

SMT Test_1, 3/3/2009 (Min OAT: 43 °F)

0

1000

2000

3000

4000

5000

6000

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10

:00

11

:00

12

:00

13

:00

14

:00

15

:00

16

:00

17

:00

18

:00

19

:00

20

:00

21

:00

22

:00

23

:00

Wh

ole

Bu

ildin

g P

ow

er

[kW

]

Actual Baseline (OAT Regression) 3/10 Baseline

Moderate

Price

High Price

Demand Profiles from Test Events

Seattle Municipal Tower, 9/11/2009 (Max OAT: 83 °F)

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10

:00

11

:00

12

:00

13

:00

14

:00

15

:00

16

:00

17

:00

18

:00

19

:00

20

:00

21

:00

22

:00

23

:00

Wh

ole

Bu

ild

ing

Po

we

r [k

W]

Actual Baseline 3/10 BL

Test Period

Page 30: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

30

Technical Coordination Concept - Automation

• Initially hand-holding customers through the

automation process including DR strategy

development and technology integration done by

LBNL researchers.

• Identified as an important role for successful

commercialization.

• Control vendors identified as ideal candidates.

• Tested with the Demand Response Integration

Services Company (DRISCO) concept in 2006

• Utilized in 2007 Auto-DR (Hands-on vs. Hands-off)

Page 31: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

31

DR Enablement Process

Analyze load shapes

Analyze operations,

systems, and end uses

Assess DR

Option

Implement Strategies

Evaluate Effectiveness

1

2

3

4

5

Historical data used for various purposes:

1. Visual analysis

2. Develop Load Statistical Summary

3. Evaluate Load Variability and Weather Sensitivity

Collect information on end uses, systems, controls and

operations

What kind of DR program works for the facility? Mapping

load shapes onto rates and programs

Semi- or fully-automated

Calculate shed - is it acceptable? Variable?

Page 32: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

32

Installation and TC Costs for 2007 AutoDR

$-

$50.00

$100.00

$150.00

$200.00

$250.00

1 10 100 1000 10000

Demand Reduction (kW)

Insta

llati

on

an

d T

C c

osts

per

sit

e ($

/kW

)

496 274 5175 100 156 295 7587.5

Industrial1

Industrial2

Office1

Office2

Bakery

Retail2

Museum

Average of New

Commercial Cust.

Average of Legacy

Commercial Cust.Average of New

Industrial Cust.

Lab/Office2B

Gov1 Lab/Office2A

Office4School

Lab/Office1

Retail1B

Retail4

Gov2

Office4

Office6

Retail1A

Gov

4

Office5

Retail3Gov

4

$210.00

Legacy Commercial New Commercial Legacy Industrial New Industrial

Page 33: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

33

Demand Side Management and Automated DR Future

OpenADR

Daily

Energy

Efficiency

Daily

Time-Of-

Use

Energy

(TOU Rates)

Dynamic

Peak Load

Management

(Dynamic

Rates)

Scheduled

Demand

Response

Real-Time

Demand

Response

(Ancillary

Reserves)

Regulation

(Ancillary

Services)

Service Levels

Optimized

Time of Use

Optimized

Service Levels

Temporarily Reduced

Increasing Levels of Granularity of Control

Increasing Speed of Telemetry

Increasing Interactions with Grid (OpenADR & Smart Grid)

Resources Sold Back to Grid

OpenADR

Page 34: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

34

Ideal start - good commissioning, retro-

commissioning, advanced/new controls

HVAC - Direct digital control (DDC) global temperature adjustment

• In process for California Building Code

• Closed loop

Lighting Continuum - Zone Switching, Fixture Switching, Lamp Switching, Stepped Dimming, Continuous Dimming

Maybe you “can” use a strategy every day?

Desire to try

DR

Global temp.

adjustment

DDC zone

control?

Y N

Global temp.

Adjustment

capability?

Y N

Central plant

control

Air

distribution

control

Air distribution

System DDC?

Y N

Can program

GTA?

Y N Central plant

DDC?

Y N

Do not try DR

at this time

Desire to try

DR

Global temp.

adjustment

DDC zone

control?

Y NDDC zone

control?

Y N

Global temp.

Adjustment

capability?

Y NGlobal temp.

Adjustment

capability?

Y N

Central plant

control

Air

distribution

control

Air distribution

System DDC?

Y NAir distribution

System DDC?

Y N

Can program

GTA?

Y NCan program

GTA?

Y N Central plant

DDC?

Y NCentral plant

DDC?

Y N

Do not try DR

at this time

Linking DR and Energy Efficiency

Page 35: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

35

Parameters for Evaluating Load Shapes – also useful for Retro-commissioning

• Near-Base Load (kW): 2.5th

percentile of daily load.

• Near-Peak Load (kW): 97.5th

percentile of daily load.

• High-Load Duration (Hours):

Duration for which load is closer

to near-peak load than to near-

base load.

• Rise Time (Hours): Duration for

load to go from near-base load

to the start of the high-load

period.

• Fall Time (Hours): Duration for

the load to go from the end of

the high-load period to the near-

base load.

Page 36: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

36

Future DirectionsDR strategies as a “Modes” in Optimized Control

• Orchestrate modes using schedules, signals, optimization algorithms:

– Occupied/Unoccupied

– Maintenance/Cleaning

– Warm up/Cool down

– Night purge/Pre-cooling

– Low power DR mode

• Intelligence needed for decision making

• Financial feedback systems need to present operational value

• Embed DR communications client in EMCS – work toward codes, support BACnet and LON interoperability

See http://drrc.lbl.gov/ for publications

KWH

Page 37: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

37

Summary of EIS State of Technology

* Vendor list and evaluations can be downloaded from: http://eis.lbl.gov/

Page 38: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

38

Potential Collaboration– Web-Based EnergyInformation Systems

Problem Optimal energy performance requires high quality, granular building performance data, more timely analysis than monthly utility bills

Projects1. Review of Energy Information Systems (CEC Funded,

complete) • Defined a characterization framework• Evaluated state of the technology – 30 EIS• Conducted user case studies to identify energy savings2. Handbook on Energy Information Applications (DOE

Funded, underway)• Technical Advisory Group to select key applications• Evaluated state of the technology• Conducted user case studies to identify energy savings

38

Data Information Action

Page 39: DR Technologies, Strategies and Case Studies · HVAC - Global Temperature Adjustment •GTA based DR strategies can be used: •Manually by building operators •Automatically based

39

Results and Next Steps

• Shown how key owners use EIS-need to disseminate best practices and accelerate adoption

• Strong interest in movement toward utility incentives, developing specification for DOE Commerical Building Energy Alliances.

• Partnering/interest from vendors, Consortium for Energy Efficiency, USGBC, Utilities, ASHRAE Standard

• Web site: eis.lbl.gov

39