Water Supply Update
Infrastructure Services Committee
September 20, 2018
1
![Page 2: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/2.jpg)
www.scrd.ca2
Water Supply – July to September 2018
• Chaster well and Gray Creek provided 5-20% of total supply.• Combined water availability in both lakes was below 30% late August.• Siphons were online for 14 days to supplement flows from Edwards Lake.
![Page 3: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/3.jpg)
www.scrd.ca
Community Water Demand 2018
Environmental Flow requirement of 200 l/s maintained at all times
3
Year 2015 2016 2017 2018Stage 2 9-Jun 25-Jul 21-Jul 5-JulStage 3 11-Jul 26-Aug 1-Sep 13-AugStage 4 13-Aug -- 3-Oct 31-Aug
Return to Stage 2 8-Sep 19-Sep 28-Oct 14-Sep
![Page 4: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/4.jpg)
www.scrd.ca4
![Page 5: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/5.jpg)
www.scrd.ca
Comprehensive Regional Water Plan
4 Projects to increase water supply:
– Universal Metering
– Chapman Lake Infrastructure Improvement Project
– Groundwater Investigation
– Water Reservoir
5
![Page 6: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/6.jpg)
www.scrd.ca
Universal Water Metering• Installations
– Phase 1: North and South Pender Harbour – Completed (2015)– Phase 2: Other Rural Electoral Areas – Completed (2018)– Phase 3: District of Sechelt / shíshálh Nation (report on today’s
agenda)
• Water savings thus far:– Contributed to 1430 private leaks resolved – Saving approximately 3,700,000 litres per day all areas – 437 active private side water leaks (Sept 2018)
6
![Page 7: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/7.jpg)
www.scrd.ca
Chapman Lake Infrastructure Improvement Project• Applied for grant Canada
Infrastructure Program - Green Infrastructure.
• Spring 2019: Provincial Decisions expected on Park Use Permit and Water Licence
• Summer 2019: construction
• Summer 2020: fully operational
• Commitment for ongoing environmental assessments and monitoring
7
![Page 8: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/8.jpg)
www.scrd.ca
Groundwater Investigation• 2017: Phase1: Completed desk
top study
• 2018: Phase 2: Test drilling on 4 sites to determine feasibility
• Phase 3: Develop wells (incl. associated infrastructure and permitting)
8
![Page 9: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/9.jpg)
www.scrd.ca
Phase 2: Test Wells
• Objectives: Determining maximum sustainable yield
• September 17-30, drilling test wells– 3-4 days per site– Door to door correspondence in
neighborhoods
• Early October, initiate testing wells:– Pumping high volumes of water for 48-72 hrs per
site– Monitoring stations set up in surrounding wells
9
![Page 10: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/10.jpg)
www.scrd.ca
Raw Water Reservoir
Feasibility Study (Summer 2018 onwards):– Selection and assessment of potential locations
• Regulatory framework– Ecologic – Hydrology– Contamination– Public Safety– Water Quality for human consumption
• Preliminary design • Costs (construction and operation)
10
![Page 11: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/11.jpg)
www.scrd.ca
Projected Timelines
11
Project Feasibility confirmed
Authorizationsreceived (incl. land ownership)
Commence Construction
Commissioning
Chapman Lake infrastructure Improvement
Confirmed Spring 2019 Summer 2019 Late 2019
Groundwater Investigation Early 2019 2020-2022 2021-2022 2021-2022
Raw Water Reservoir 2019 2022-2024 2025-2026 2026-2027
![Page 12: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/12.jpg)
www.scrd.ca
Current Policy Development• Water Sourcing Policy
– Framework approved April 2018– Finalized Water Sourcing Policy targeted for Q2 2019
• Drought Management Plan – Annual review and updates Q2 2019
• Review Bulk Water Agreement – Town of Gibsons– Report October 11, 2018
12
![Page 13: Water Supply Update Infrastructure Services Committee ... 20 ISC... · – Phase 3: District of Sechelt / shíshálh Nation (report on today’s agenda) • Water savings thus far:](https://reader034.vdocuments.site/reader034/viewer/2022042406/5f2088a69c0d4756c83247c4/html5/thumbnails/13.jpg)
www.scrd.ca