Truesdale LakeLake Management Plan
Truesdale Lake AssociationSouth Salem, NY
![Page 2: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/2.jpg)
Truesdale Lake Evaluation
Introduction to
Land-Tech Consultants, Inc. Project overview Summary of findings Questions
![Page 3: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/3.jpg)
Project Objectives
Conduct bathymetry study Collect sediment for analysis Review Citizens Statewide Lake Assessment
Program (CSLAP) Findings (monitoring since 1999)
Evaluate data and provide management recommendations
![Page 4: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/4.jpg)
Watershed
83 Acre lakeCreated in 1927
Receives water from surface runoff and primary streams
Discharges to 200 ft wide dam with spillway
2,380 Acre Watershed
![Page 5: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/5.jpg)
Sediment
11+ feet deep 0-1.5 ft sediment
accumulated since 1956
Sediment68% Gray Sand
29% Silt
3% Gravel
![Page 6: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/6.jpg)
Water Quality
Class B water (recreation, fishing) High phosphorous (0.018-0.084 mg/l) High chlorophyll a (37.1 ug/l) Secchi disk - average= 1.15 m Eutrophic High sediment phosphorous
![Page 7: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/7.jpg)
Weed Control
Curly-leaf pondweed (Potmogeton crispus) Leafy pondweed (P. foliosus) Filamentous algae Nitella found in southern cove Aquathol K and copper sulfate treatments Effective control Long use of copper sulfate (45 years) – concern Recommend copper and fish monitoring
![Page 8: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/8.jpg)
Summary Of Existing Conditions
High landscape, scenic and recreational values Managed system Sedimentation concerns High phosphorous and chlorophyll a levels Effective weed and algal control program
![Page 9: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/9.jpg)
Recommendations
A -Shoreline Buffer Install adequate shoreline vegetative buffers of
native shrubs and grasses 15-25 foot wide buffer Slow down overland runoff Uptake of nutrients – compete for nutrients
![Page 10: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/10.jpg)
Vegetative Buffer
![Page 11: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/11.jpg)
Dense buffer
![Page 12: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/12.jpg)
Recommendations
B – Aquatic buffer Introduce rooted emergents along shoreline
– Take up and compete for nutrients– Increase aesthetics– Create escape cover for fish
![Page 13: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/13.jpg)
Typical Plants
Pickerel weed (Pontederia cordata) Bur-reed (Sparganium sp.) Three-square rush (Scirpus pugens) Common arrowhead (Sagittaria latifolia) Sweet flag (Acorus calamus) Blue flag (Iris versicolor) Soft rush (Juncus effusus)
![Page 14: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/14.jpg)
RecommendationsC – Fertilizer Use Test soil for nutrient content Apply minimal fertilizer based on nutrient needs Water soluble – minimize use near open water and
prior to heavy rain Apply only needed amounts of phosphorous Mulch grass clippings Use organic slow release fertilizer Apply annually
![Page 15: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/15.jpg)
Recommendations
D – Control Phosphorous Sources Maintain septic systems Discourage Canada geese use on lawns
![Page 16: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/16.jpg)
Recommendations
E – Address “Hot Spots” #1 South end of lake – 18” discharge pipe #2 Catch basin at Truesdale Lake Drive and
Lakeshore Drive #3 Beach along eastern shoreline #4 Channel under Boway Road #5 Inlet watercourse #6 Discharge channel at western shoreline
![Page 17: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/17.jpg)
Area #1 Relocate end of pipe
further from lake Create plunge pool Create semi-circular
forebay in lake Introduce aquatic
vegetation Provide routine
maintenance (sediment removal)
![Page 18: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/18.jpg)
Area #2 Remove section of
pipe and replace with vegetated channel
Construct a small sediment basin and install rip rap channel to lake
Routine maintenance (sediment removal, erosion repair)
![Page 19: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/19.jpg)
Rip Rap Swale
![Page 20: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/20.jpg)
Sediment Basin
![Page 21: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/21.jpg)
Area #3 Clean out & vegetate
southern channel Construct settling
basin and forebays Remove un-used pipes Riprap northern
channel, add forebay Introduce aquatic
emergent vegetation Repair eroded areas Routine maintenance
![Page 22: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/22.jpg)
Area #4 Remove sand bars Construct multiple
sediment basins where accessible
Reconstruct channel – improve flow, protect from erosion, enhance appearance
Routine maintenance
![Page 23: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/23.jpg)
Area #5
Open up mouth Construct crescent-
shaped forebay Deepen brook Introduce aquatic
emergents Routine maintenance
![Page 24: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/24.jpg)
Area #6
Construct rip rap channel from pipe over steep slopes
Construct sediment basin in level area
Construct forebay in lake
Routine maintenance
![Page 25: Truesdale Lake Lake Management Plan](https://reader035.vdocuments.site/reader035/viewer/2022062421/56812a4c550346895d8d9080/html5/thumbnails/25.jpg)
Stone Filter – if needed