DFMC Paper No. 47/2012
(for discussion on 22.11.2012)
Southern District Council
District Facilities Management Committee
Progress Report on District Facilities Works Projects in the Southern District
(as at 8 November 2012)
Purpose
The purpose of this paper is to report on the progress of district minor works
(DMW) projects in the Southern District.
Content
2. The progress report includes –
(i) Progress Report on District Facilities Works Projects in the Southern District
(Appendix I);
(ii) Progress report and financial report on DMW projects from 2008/09 to 2011/12
(Appendix II); and
(iii) Progress report and financial report on DMW projects in 2012/13 (Appendix III);
Advice Sought
3. Members are invited to note the reports.
Secretariat, Southern District Council
November 2012
2
Appendix I
Progress Report on District Facilities Works Projects in the Southern District
(as at 8 November 2012)
Item Project TitleLead Department /
Works Agent
Tentative “Design & Build”
Works Schedule
Progress / Notes
(Updated texts are underlined)
1. Uplifting Works to Promenades
of Aberdeen Harbour and Ap
Lei Chau Main Street Area
CEDD 30 September 2011 to end 2014
(a) Decorative Lightings on
Ap Lei Chau Bridge
1st Quarter to 3rd Quarter of 2012
(b) Aberdeen Promenade
4th Quarter of 2011 to end 2012
(c) Ap Lei Chau Promenade and
Wind Tower Park Entrance
3rd Quarter of 2012 to end 2013
(d) Ap Lei Chau Main Street Area
3rd Quarter of 2013 to end 2014
Construction works commenced in September 2011 and to be
completed in phases from 2012 to 2014. As at 31 October 2012,
approximately 30% of site works have been completed.
Construction of the viewing deck and the renovation of the
footbridge near Aberdeen Centre were underway and would be
completed by end 2012 / early 2013. Construction of the
performance stage, information kiosk, cruise landing shelter and
toilet etc. commenced in May 2012 and would be ready for use by
the public by the end of 2012 / early 2013.
3
Appendix II
Progress report and financial report on DMW projects from 2008/09 to 2011/12
(as at8 November 2012)
I. DMW projects with funding approved
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
1. Construction of canopy at exit of Shek Pai Wan
Lift Tower (Yue Fai Road)
HAD /
Term Consultant
The major site works was completed in Nov 2012. Some minor rectification of defects
and testing are being carried out at site.
4
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
2. Beautification of area near bus stop at Repulse Bay
Beach
HAD /
Term Consultant
The design drawings were completed in October 2010 and submitted to HyD and TD for
comments in the same month. The reply from HyD was received on 3 November 2010,
mentioning that they would not take up the maintenance responsibility of the taxi stop
cover, railings and the pavement after completion of the works. The reply from TD was
received on 24 December 2010, mentioning that the bus companies would not take up the
maintenance responsibility of the bus stop poles after completion of the works. In
addition, TD mentioned that traffic flow would be improved, including rearrangement of
the existing bus stop locations, increasing the width of the existing pedestrian traffic light
crossing and realignment of the road curb at the taxi stop. TD informed that the works
period of the traffic improvement works would need to accommodate the slope works
nearby. The Secretariat would continue to liaise with TD on the situation. The
beautification works at the location could only commence after TD’s completion of
works and the excavation suspension period.
At the same time, the consultant has revised the design drawings of our beautification
project based on comments of DMW WG meeting on 27 June 2011 as well as TD’s
design received in early 2012 and submitted it for ACABAS’ comments. The revised
design was supported by DMW WG on 7 May 2012 and DFMC approved additional
funding rendering the total project cost to $2,984,000 at the meeting on 24 May 2012.
The consultant is preparing the detailed design.
3. Setting up of an SDC logo and a permanent festive
lighting site at the triangular lawn area near the
Hong Kong Academy of Medicine
HAD /
Term Consultant
The works contract was signed in June 2012. Site works commenced in July 2012 and
are expected to be completed by the end of 2012.
5
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
4. Widening of footpath to Stanley Main Beach from
Stanley Link Road (near Hoi Fung Path)
HAD /
Works Section
As it is not suitable to close the footpath for works during the swimming season, works
would be carried out in 2 phases. The 1st phase included widening works on the land
resumed by LandsD. The 2nd phase included improvement to the whole footpath and
railings. Site works for the 1st phase were completed in early June 2011. Stanley
Sub-office had completed the local consultation regarding the design of the works in the
2nd phase. Tender for works of the 2nd phase was invited in August 2012. It is
expected that works would commence in late-December 2012.
5. Improvement works to the Cover at Minibus Stops
in Wah Kwai Estate
HAD /
Term Consultant
The works contract was signed on 5 July 2012. Site works commenced in late July
2012 and are targeted to be completed within November 2012, taking into account of
the extension of time due to inclement weather.
6. Improvement to steel staircase at Lee Chi Road,
Ap Lei Chau
HAD /
Term Consultant
The second-round ground investigation works were completed in early July 2012. The
consultant presented the preliminary design, rough cost estimates and the feasibility
report during the Working Group meeting on 3 September 2012. Funding application
would be submitted in November 2012’s meeting.
7. Improvement to drainage channel near no. 657
Shek O Village
HAD /
Works Section
All works were completed in October 2012.
6
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
8. Construction of a rain shelter near the access to Ap
Lei Chau Service Reservoir Playground
HAD /
Works Section
DFMC approved funding in the meeting on 21 July 2011. As the site location is
adjacent to a slope, the Geotechnical Engineering Office of CEDD expressed reservation
to the chosen site and suggested a nearby location now under the purview of WSD for
the construction of the rain shelter. Works Section has carried out site inspection to
the revised location in July 2012. Trial pit works for the revised location have been
carried out in mid-September 2012 and the results of the site investigation would be
used to ascertain the feasibility of proposed installation works, finalize the project
design and arrange tender invitation after local consultation.
9. Improvement to paving and construction of
sitting-out area along the footpath linking Mount
Davis Road and Victoria Road
HAD /
Works Section
Site investigation works were completed in March 2012. Works Section has submitted
project design in September 2012. Local consultation is in progress.
10. Installation of panels at Aberdeen Bus Terminus
(route nos. 70 & 107) and South Horizons PTI
(route no. 171)
HAD /
Works Section
Site works commenced in August 2012. The works at South Horizon PTI was
completed in October 2012. Regarding the works at Aberdeen Bus Terminus, the bus
company informed that the shelters were owned by the bus company’s advertising
agent. Installing panels onto the shelters might involve issues on insurance and
liability. Also, the bus company expressed that there were plans to install advertising
panels at the locations concerned and requested the suspension of this project, so the
works at Aberdeen Bus Terminus has already been cancelled.
7
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
11. Construction of rain shelter near the minibus stop
at Pok Fu Lam Road near Queen Mary Hospital
HAD /
Works Section
Site works commenced in late March 2012. However, the electricity company
informed us in mid-April that the foundation of the rain shelter would encroach upon
several 275kV electric cables, which would affect their emergency repair works.
According to the result of earlier trial pits works, the proposed location is the only
location with enough underground space to construct the foundation of the rain shelter.
Consequently, the current construction contract has to be cancelled. Following up
with the SDC Member of the constituency’s suggestion, the Secretariat would liaise
with the Works Section to work on the designs of rain shelters without underground
foundation and to be submitted for Members’ consideration upon completion of
preliminary feasibility study, design and cost estimates.
12. Construction of rain shelter near the minibus stop
at Cyberport Road opposite to the Hong Kong
Animal Management Centre
HAD /
Works Section
DFMC approved funding through a circulation of paper in early September 2011.
The Secretariat consulted the Member of the constituency in May 2012 on the design
prepared by Works Section. Trial pit works was carried out in late August 2012.
The results showed that there were electric cables near the proposed foundation of the
rain shelter. The Secretariat is liaising with the electricity company to understand how
this would affect the project, and will follow up with Works Section in due course.
8
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
13. Construction of rain shelter near the minibus stop
at Cyberport Road opposite the South Tower,
Residence Bel-air 2
HAD /
Works Section
DFMC approved funding through a circulation of paper in early September 2011.
The Secretariat consulted the Member of the constituency in May 2012 on the design
prepared by Works Section. Trial pit works was carried out in late August 2012.
The results showed that there were electric cables near the proposed foundation of the
rain shelter. The Secretariat is liaising with the electricity company to understand how
this would affect the project, and will follow up with Works Section in due course.
14. Improvement to footpath linking Northcote Close
and Victoria Road
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Site
investigation works were completed in late July 2012. Works Section has submitted
project design in September 2012. Local consultation is in progress. With reference
to the cashflow positions and estimated works duration, the Secretariat would liaise
with the Works Section to arrange invitation of quotations and signing of contract etc,
so that there would be adequate cash to settle the payments at various stages of works
completion.
15. Construction of rain shelter near the bus stop at
Victoria Road near Sha Wan Drive
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Trial
pit works was carried out in early September 2012. The result showed that there were
electric cables near the proposed foundation of the rain shelter. The Secretariat is
liaising with the electricity company to understand how this would affect the project,
and will follow up with Works Section in due course.
9
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
16. Provision of tourist signage at Hung Shing Street,
Ap Lei Chau, and the intersection of Chengtu
Road and Wu Nam Street in Aberdeen
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. The
Secretariat is consulting the Tourism Commission and the Hong Kong Tourism Board
regarding the tourist signages. Works Section would arrange trial pit works based on
the comments received and would, based on the results of the site investigation, finalize
the project design, prepare drawings and arrange tender invitation after local
consultation. With reference to the cashflow positions and estimated works duration,
the Secretariat would liaise with the Works Section to arrange invitation of quotations
and signing of contract etc, so that there would be adequate cash to settle the payments
at various stages of works completion.
17. Improvement of footpath to mobile toilets in San
Wai Village, Wong Chuk Hang
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Works
Section has submitted project design and estimate in June 2012 and local consultation
was completed in July 2012. Trial pit works were carried out in early September
2012. Based on the result, Works Section will finalize project design, prepare
drawings for tender invitation. It is expected that tender could be invited in
mid-December 2012.
10
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
18. Construction of rain shelters near bus stops at both
bounds of Shek O Road near Shek O Quarry
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Works
Section has submitted project design and estimate in July 2012. Local consultation
was completed. Trial pit works were carried out in early September 2012. The
results showed that there are sufficient spaces for the proposed rain shelter installation
works at both bounds and the findings of the investigation would be used to finalize the
project design, prepare drawings for tender invitation. Tender will be invited in
mid-November 2012.
19. Reconstruction of mailboxes for Tung Ah Village,
Lan Nai Wan Village and To Tei Wan Village
along Shek O Road
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Works
Section has submitted project design and estimate in July 2012 and local consultation
was completed. It is expected that tender could be invited in mid-December 2012.
11
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
20. Improvement to footpaths and drainage channels
in San Wai Village, Wong Chuk Hang
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Works
Section has submitted project design and estimate in June 2012 and local consultation
was completed in July 2012. Phase I trial pit works were carried out in early
September 2012 and the remaining phase were completed in early October 2012. The
results showed that the proposed drainage improvement works could be carried out.
The findings of the investigation would be used to finalize the project design, prepare
drawings for tender invitation. It is expected that tender could be invited in
mid-December 2012.
21. Improvement to drainage channels near Shek O
Road Sitting Out Area
HAD /
Works Section
DFMC approved funding through circulation of paper in early September 2011. Works
Section has submitted project design and estimate in June 2012 and local consultation
was completed in July 2012. Tenders had been invited in late August 2012. Works
have been commenced in late October 2012 and were anticipated to be completed in
mid-February 2013.
12
Financial report on DMW projects from 2008/09 to 2011/12
(as at 8 November 2012)
DMW Project Project Cost ($) Note 1
Expenditure in
2008-12 ($)
Expenditure in
2012-13 ($)
1. Construction of cover at mini-bus stop at Stanley Plaza 1,276,128.77 1,061,405.33 0
2. Construction of pedestrian cover at Aberdeen Praya Road 18,500,000.00 6,867,949.79 9,858,681.64
3. Construction of cover at mini-bus stop in Wah Kwai Estate 2,650,000.00 2,623,013.93 11,028.40
4. Construction of pedestrian cover at Ap Lei Chau near Manly House 3,995,000.00 3,754,026.35 0
5. Upgrading of barbecue pits and ancillary facilities at South Bay Beach 420,000.00 376,726.54 25,366.25
6. Improvement to facilities in Shek O Village Children’s Playground 100,000 90,755.78 5,302.89
7. Construction of toilet block in Shek Pai Wan Estate Playground No. 1 2,500,000 1,270,836.00 120,532.07
8. Construction of canopy at exit of Shek Pai Wan Lift Tower (Yue Fai Road) 1,210,000.00 67,696.27 84,501.23
9. Beautification of area near bus stop at Repulse Bay Beach 2,984,000 141,120.00 0
10. Alteration works at 1/F South Horizons Neighbourhood Community Centre 1,344,676.77 1,280,826.27 0
11. Setting up of an SDC logo and a permanent festive lighting site at the triangular lawn area near
the Hong Kong Academy of Medicine
3,187,000.00 184,135.50 125,608.82
12. Improvement on lighting in Hung Shing Street Rest Garden 143,000.00 137,062.40 0
13. Widening of footpath to Stanley Main Beach from Stanley Link Road (near Hoi Fung Path) 470,000 89,248.82 0
14. Ap Lei Chau Promenade – Improvement to the lighting facility 35,000.00 30,620.67 1,007.08
13
DMW Project Project Cost ($) Note 1
Expenditure in
2008-12 ($)
Expenditure in
2012-13 ($)
15. Big Wave Bay Picnic Area – Improvement to venue facilities 590,000 370,285.49 27,024.00
16. De-silting programme in the Southern District 2011-12 119,100.00 59,550.00 59,550.00
17. Grass-cutting in the Southern District 2011-12 156,612.21 82,212.21 74,400.00
18. Safety inspection, cleansing and minor improvement works to shelters and covers in the
Southern District 2011-12
162,600.00 14,600.00 147,000.00
19. Minor improvement works 2011-12 79,755.10 47,410.00 12,770.00
20. Improvement works to the Cover at Minibus Stops in Wah Kwai Estate 1,477,000 68,175.00 75,681.95
21. Improvement to steel staircase at Lee Chi Road, Ap Lei Chau 350,000 121,069.12 88,000.00
22. Ap Lei Chau Waterfront Promenade – Provision of Pet Garden by setting aside a portion of the
open space
900,000 735,250.00 63,803.87
23. Waterfall Bay Park – Installation of washing trough in the barbecue area 35,000 0 35,000.00
24. Installation of benches at the bus stops at Pok Fu Lam Road near Queen Mary Hospital 122,000.00 0 122,000.00
25. Construction of mailboxes in San Wai Village, Wong Chuk Hang 148,900.00 0 148,900.00
26. Construction of drainage channels near no. 285 and replacement of railing along footpaths in
Tai Long Wan Village
200,655.00 0 200,655.00
27. Improvement to drainage channel near no. 657 Shek O Village 146,000.00 0 146,000.00
28. Construction of rain shelter near the mini-bus stop at Sassoon Road, Pok Fu Lam 168,000.00 0 168,000.00
29. Construction of a rain shelter near the access to Ap Lei Chau Service Reservoir Playground 250,000 0 0
14
DMW Project Project Cost ($) Note 1
Expenditure in
2008-12 ($)
Expenditure in
2012-13 ($)
30. Construction of drainage channel, improvement to staircase and signage near Manly House, Ap
Lei Chau
76,600.00 0 76,600.00
31. Construction of rain shelter with seats near the bus stops at Victoria Road outside West Island
School
145,900.00 0 145,900.00
32. Improvement to paving and construction of sitting-out area along the footpath linking Mount
Davis Road and Victoria Road
1,500,000 0 43,600.00
33. Improvement to drainage channels near no. 9C Pok Fu Lam Village 3,228.20 0 3,228.20
34. Widening of footpath near RH/18C/116, San Wai Village, Wong Chuk Hang 91,820.00 0 91,820.00
35. Improvement to railings at the trail path from South Bay Close to Tsin Shui Wan Au 99,850.00 0 99,850.00
36. Construction of rain shelter with seats at the bus stop near Lee Chi Road Roundabout 132,400.00 0 132,400.00
37. Installation of panels at Aberdeen Bus Terminus (route nos. 70 & 107) and South Horizons PTI
(route no. 171)
180,000 0 0
38. Construction of rain shelter with seats at the bus stop near Residence Bel-air 1 172,300.00 0 172,300.00
39. Construction of rain shelter with seats at the bus stop near Wah Chui Street Sitting-out Area 289,000.00 0 289,000.00
40. Construction of rain shelter with seats adjacent to the bus stop near Ap Lei Chau Estate 166,535.00 0 166,535.00
41. Installation of benched near the bus stop at Tin Wan Shopping Centre and the bay of bus route
no. 77 in Tin Wan Estate
33,360.00 0 33,360.00
42. Installation of folding seats near Ocean Park Road bus stop 37,000.00 0 37,000.00
43. Wong Chuk Hang Recreation Ground – Improvement works to the cover of spectator stands 190,000 151,946.85 0
44. Addition of elderly fitness equipment in Waterfall Bay Park 221,000 0 198,500.00
15
DMW Project Project Cost ($) Note 1
Expenditure in
2008-12 ($)
Expenditure in
2012-13 ($)
45. Reclamation of flat land and installation of elderly fitness equipment in Shum Wan Road
Sitting-out Area
755,000 372,637.35 190,306.71
46. Improvement to footpath linking Sandy Bay Road and the nearby rocky shore 161,000.00 0 161,000.00
47. Construction of rain shelter near the bus stop (towards Wah Fu) at Victoria Road near Tai Hau
Wan Village
52,280.00 3,180.00 49,100.00
48. Construction of rain shelter near the minibus stop at Pok Fu Lam Road near Queen Mary
Hospital
102,500.00 3,540.00 72,530.00
49. Construction of rain shelter near the minibus stop at Cyberport Road opposite to the Hong Kong
Animal Management Centre
176,000 0 0
50. Construction of rain shelter near the minibus stop at Cyberport Road opposite the South Tower,
Residence Bel-air 2
194,000 0 0
51. Improvement to footpath linking Northcote Close and Victoria Road 690,000 0 26,760.00
52. Construction of rain shelter near the bus stop at Victoria Road near Sha Wan Drive 125,000 0 0
53. Provision of tourist signage at Hung Shing Street, Ap Lei Chau, and the intersection of Chengtu
Road and Wu Nam Street in Aberdeen
55,000 0 0
54. Improvement of footpath to mobile toilets in San Wai Village, Wong Chuk Hang 40,000 0 0
55. Construction of rain shelters near bus stops at both bounds of Shek O Road near Shek O Quarry 170,000 0 0
56. Reconstruction of mailboxes for Tung Ah Village, Lan Nai Wan Village and To Tei Wan
Village along Shek O Road
220,000 0 0
57. Improvement to footpaths and drainage channels in San Wai Village, Wong Chuk Hang 200,000 0 0
16
DMW Project Project Cost ($) Note 1
Expenditure in
2008-12 ($)
Expenditure in
2012-13 ($)
58. Improvement to drainage channels near Shek O Road Sitting Out Area 67,000 0 0
59. Shek O Beach – Addition of garden benches 112,000 71,400.00 4,157.59
60. Big Wave Bay Beach – Addition of garden benches 80,000 71,279.19 0
61. Aberdeen Sports Ground – Improvement of lighting facilities 600,000 276,275.64 46,581.47
62. Installation of Flower Plaque in Aberdeen Promenade Note 2 154,000.00 107,000.00 47,000.00
Total: 51,013,201.05 20,531,234.50 13,688,342.17
Note 1: Project costs shown in italic denote the amount approved by DFMC. Otherwise, they denote the latest project cost.
Note 2: Item 62 “Installation of Flower Plaque in Aberdeen Promenade” is part of the “Southern District Literary Trail – Creative Working and Flower Plaque Making
Programme” was endorsed by SDC on 14 July 2011.
17
Appendix III
Progress report and financial report on DMW projects in 2012/13
(as at 8 November 2012)
I. DMW projects with funding approved
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
1. Beautification in the Southern District using
flower pots 2012-13
LCSD DFMC approved funding in the meeting on 9 February 2012. The beautification works
and plant maintenance service commenced in March 2012 and are expected to be
completed in February 2013.
2. De-silting programme in the Southern District
2012-13
HAD /
Works Section
DFMC approved funding in the meeting on 9 February 2012. Works commenced in
late June 2012 and are expected to be completed in early March 2013.
3. Grass-cutting in the Southern District 2012-13 HAD /
Works Section /
LandsD
DFMC approved funding in the meeting on 9 February 2012. Works commenced in
mid-August 2012 and are expected to be completed in early March 2013.
4. Safety inspection, cleansing and minor
improvement works to shelters and covers in the
Southern District 2012-13
HAD /
Works Section
DFMC approved funding in the meeting on 9 February 2012. Works commenced in
mid-August 2012 and are expected to be completed in early March 2013.
5. Minor improvement works 2012-13 HAD /
Works Section
DFMC approved funding in the meeting on 9 February 2012.
18
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
6. Repair of the footbridge near Big Wave Bay
Beach at Tai Long Wan Village – Construction of
a temporary footbridge
HAD /
Works Section
DFMC approved funding in the meeting on 24 May 2012. The Stanley Sub-Office had
finished consulting the villagers on the project design prepared by Works Section.
Tenders were invited in late July 2012. Site works commenced in late October 2012
and are expected to be completed in February 2013.
7. Thirty-seven outdoor leisure venues in the
Southern District – Improvement works for energy
saving of lighting facilities
LCSD/
EMSD
DFMC approved funding in the meeting on 24 May 2012. Site works are expected to
commence in December 2012 and to be completed in March 2013.
8. Ap Lei Chau Sports Centre – Improvement works
for energy saving of lighting facilities
LCSD/
EMSD
DFMC approved funding in the meeting on 24 May 2012. Site works are expected to
commence in December 2012 and to be completed in January 2013.
9. LCSD venues in the Southern District – Urgent
minor improvement works
LCSD/
ArchSD/
EMSD
DFMC approved funding in the meeting on 24 May 2012. Improvement works
carried/to be carried out include:
(a) Deep Water Bay Beach – Installation of 2 nos. staircase lighting($14,000) – the
works were completed in November 2012.
10. Pok Fu Lam Public Library – Improvement works
for the air conditioning system at Students’ Study
Room
LCSD/
EMSD
DFMC approved funding in the meeting on 26 July 2012. Site works commenced and
completed in early August 2012.
11. Construction of drainage channels near Tai Long
Wan Village public car park
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. Site investigation and
surveying works were expected to be carried out in November 2012.
19
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
12. Construction of rain shelter near the bus stop at St.
Stephen’s College Preparatory School, Stanley
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. As the proposed rain
shelter is in close proximity with the Tung Tau Correctional Institution, the Hong Kong
Correctional Services said that it might pose security threat. Thus, the project would
be stopped.
13. Construction of rain shelter near the bus stop
opposite to Chun Ma House, Ma Hang Estate,
Stanley
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. Site investigation
works are expected to commence in November 2012.
14. Installation of benches at Seaview Promenade,
Repulse Bay
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. Works Section has
submitted project design. Local consultation was completed. It is expected that
tender could be invited in mid-December 2012.
15. Replacement of chain-link fencing by Type II
railings
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. To increase cost
effectiveness, the project “Replacement of chain-link fence by Type II railings near
Consort Rise at Victoria Road” approved in May 2012 and the project “Replacement of
chain-link fencing by Type II railings (Phase II)” approved in July 2012 will be included
in this project for implementation. Works Section has submitted project design.
Local Consultation was in progress. Tender will be invited in mid-November 2012.
20
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
16. Repair of the footpath behind Chi Fu Fa Yuen to
Hong Kong Trail
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012.
17. Improvement works to drainage channels near
light post no. 49066 in Kau Wai Village, Wong
Chuk Hang
HAD /
Works Section
DFMC approved funding in the meeting on 27 September 2012. Works Section has
submitted project design. Local consultation is in progress. Tender will be invited in
mid-November 2012.
18. Installation of flower pots on the railing near
Baguio Villa, Victoria Road
HAD/
Works Section
DFMC approved funding in the meeting on 27 September 2012. Works Section has
submitted project design in September 2012. Local consultation is in progress.
Tender will be invited in mid-November 2012.
19. Widening of the staircase linking Baguio Villa and
Cyberport Road
HAD/
Term Consultants
DFMC approved funding in the meeting on 27 September 2012.
20. Construction of a staircase linking Yue Kwong
Road, Shek Pai Wan Estate to Aberdeen Praya
Road (Jing Hui Garden Block 1)
HAD/
Term Consultants
DFMC approved funding in the meeting on 27 September 2012.
21. Shum Wan Road Sitting-out Area - Improvement
to venue facilities
LCSD/
ArchSD
DFMC approved funding in the meeting on 27 September 2012. Site works are
expected to commence in November 2012 and to be completed in February 2013.
21
Item Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
22. Two leisure venue “Stanley Promenade and
Amenity Area at Stanley Village Road” / roadside
amenity plots in the District – Beautification of
soft landscape
LCSD DFMC approved funding in the meeting on 27 September 2012. Site works are
expected to commence in January 2013 and to be completed in February 2013.
23. Hong Fu Playground – Installation of fans inside
male and female toilets
LCSD/
ArchSD
DFMC approved funding in the meeting on 27 September 2012. Site works are
expected to commence in December 2012 and to be completed in January 2013.
22
II. DMW projects with agreement in principle
Priority Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
1. Construction of landmarks for the Literary
Trail in the Southern District
- Stray Birds 31; and
- The Journey of Eileen Chang
HAD/
“Design and Build”
contract
Members agreed to speed up the construction of two landmarks located in Repulse Bay at
CATC’s meeting held on 3 September 2012. The Working Group recommended DFMC
to write to HAD to clarify on the assignment of works agent.
2. Repair of the foot bridge near Big Wave
Bay Beach at Tai Long Wan Village
HAD /
Works Section
DFMC endorsed-in-principle and approved funding for the construction of a temporary
bridge during the meeting held on 24 May 2012. Please refer to the above section
regarding the progress of “Repair of the footbridge near Big Wave Bay Beach at Tai Long
Wan Village – Construction of a temporary footbridge”.
3. Extension of backstops in Ap Lei Chau
Service Reservoir Playground
LCSD/
ArchSD
DFMC endorsed-in-principle during the meeting held on 24 May 2012. The preliminary
design was submitted to WSD for comment in August 2012. ArchSD had further revised
the design according to WSD’s comments and the revised design was submitted to WSD for
comment.
4. Construction of landmarks for the Literary
Trail in the Southern District
- Tic Tac Toe;
- Xu Dishan Plain; and
- Stroll The Past.
HAD/
“Design and Build”
contract
DFMC endorsed-in-principle during the meeting held on 24 May 2012. As requested by
Members, the Secretariat had issued a letter to the Principal of the St. Stephen’s Collage to
comment on the 4 proposed locations of “Tic Tac Toe”. The Principal replied that they
prefer the landmark to be constructed near their school entrance. On the other hand, the
Secretariat was informed that the Chinese Christian Cemetery in Pokfulam would not
construct “Xu Dishan Plain” on ground level of their new columbarium, and needed to
search another location for the landmark.
23
Priority Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
5. Construction of a rain shelter with seats
near minibus stop nos. 4A & 4S, opposite to
Pik Luk House, Shek Pai Wan Estate
HAD/
Works Section
DFMC endorsed-in-principle during the meeting held on 24 May 2012. Works Section
jointly with the Secretariat have carried out site inspection to assess the site constrains and
feasibility of draw up the preliminary project design in July 2012.
Construction of a rain shelter near minibus
stop at Tung Yip House, Lei Tung Estate
HAD/
Works Section
Construction of a rain shelter near the drop
off point at Lee Chi Road, Ap Lei Chau
HAD/
Works Section
6. Installation of a rain shelter with seats near
the Sandy Bay Drainage Services
Department Sewage Screening Plant at Sha
Wan Drive
HAD/
Works Section
Construction of a pedestrian cover from
South Wave Court to the Club, Shum Wan
Road
HAD/
Term Consultants
The Working Group discussed the funding application of the preliminary feasibility study
of this project during its Meeting on 3 September 2012. The Working Group suggested
that early stage trial pits works be carried out in order to understand the underground
utilities situation of the proposed location.
Construction of a pedestrian cover from
South Wave Court to the Club, Shum Wan
Road – early stage trial pits works
HAD/
Works Section
With reference to cashflow positions, total project commitments and manpower, the
Secretariat would liaise with the Works Section to carry out cost estimates according to
the priorities for these projects. Please refer to the above section regarding the progress
of “Construction of a pedestrian cover from South Wave Court to the Club, Shum Wan
Road”.
24
Priority Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
7. Construction of a rain shelter near bus stop
of Chi Fu Fa Yuen blocks 1-6, Chi Fu Road
HAD/
Works Section
DFMC endorsed-in-principle during the meeting held on 24 May 2012. With reference to
cashflow positions, total project commitments and manpower, the Secretariat would liaise
with the Works Section to carry out technical feasibility studies, preliminary designs and
cost estimates according to the priorities for these projects. Works Section jointly with
the Secretariat have carried out site inspection to assess the site constrains and feasibility
of draw up the preliminary project design in July 2012.
Construction of a rain shelter at the bus
terminus (North) in Wah Fu Estate
HAD/
Works Section
Construction of rain shelter near bus stop at
Lee Tung Market, Lei Tung Estate
HAD/
Works Section
8. Beautification to railings of pavement along
Chengtu Road, Aberdeen
HAD/
Term Consultants
DFMC endorsed-in-principle during the meeting held on 24 May 2012. With reference to
cashflow positions, total project commitments and manpower, the Secretariat would liaise
with the Works Section to carry out technical feasibility studies, preliminary designs and
cost estimates according to the priorities for these projects.9. Construction of a hiking trail along Yuk
Kwai Shan, Ap Lei Chau
HAD/
Term Consultants
10. Construction of a pet garden near Consort
Rise at Victoria Road
LCSD/
Term Consultants
DFMC endorsed-in-principle during the meeting held on 24 May 2012. With reference to
cashflow positions, total project commitments and manpower, the Secretariat would liaise
with the Works Section to carry out technical feasibility studies, preliminary designs and
cost estimates according to the priorities for these projects. In addition, the Secretariat is
waiting for the decision on whether the site concerned would be utilised as a drop off area.
25
Priority Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
11. Improvement to the covered walkway
linking Ap Lei Chau Estate and Lee Chi
Road
HAD/
Works Section
DFMC endorsed-in-principle during the meeting held on 26 July 2012. With reference to
cashflow positions, total project commitments and manpower, the Secretariat would liaise
with the Works Section to carry out technical feasibility studies, preliminary designs and
cost estimates according to the priorities for these projects.12. Improvement to the staircase linking Yue
Kwong Road (near Yuk Fai House) and Old
Main Street, Aberdeen
HAD/
Works Section
13. Improvement to the drainage channel near
no. 42 (near Toilet B) in Pok Fu Lam
Village
HAD/
Works Section
14. Installation of mailboxes at Shui Choi Tin
Village
HAD/
Works Section
15. Addition of play equipment for children at
Ap Lei Chau Wind Tower Park
LCSD/
ArchSD
16. Construction of a rain shelter near the bus
stop at Pok Fu Lam Fire Station Officers
Married Quarters at Victoria Road
HAD/
Works Section
Construction of rain shelters near the
minibus stops at both bounds of Cyberport
Road near Cyberport Arcade
HAD/
Works Section
26
Priority Project Title
Lead Department /
Works Agent
Progress / Notes
(Updated texts are underlined)
16. Construction of a rain shelter near the
minibus stop opposite Aberdeen Kai-fong
Welfare Association Social Service Centre
at Yue Fai Road
HAD/
Works Section
DFMC endorsed-in-principle during the meeting held on 26 July 2012. With reference to
cashflow positions, total project commitments and manpower, the Secretariat would liaise
with the Works Section to carry out technical feasibility studies, preliminary designs and
cost estimates according to the priorities for these projects.
17. Beautification of the roundabout at Tung
Tau Wan Road, Stanley
LCSD DFMC endorsed-in-principle during the meeting held on 26 July 2012. Funding
application would be submitted in November 2012’s meeting.
18. Construction of a sitting out area with grass
at the roof of Victoria Road Fresh Water
Service Reservoir at Sassoon Road
LCSD/
Term Consultant
DFMC endorsed-in-principle during the meeting held on 26 July 2012.
27
Financial report on DMW projects in 2012/13
(as at 8 November 2012)
DMW Project Project Cost ($) Note 1
Expenditure in
2012-13 ($)
1. Beautification in the Southern District using flower pots 2012-13 177,600 88,533.60
2. De-silting programme in the Southern District 2012-13 200,000 0
3. Grass-cutting in the Southern District 2012-13 200,000 0
4. Safety inspection, cleansing and minor improvement works to shelters and covers in the Southern District 2012-13 200,000 0
5. Minor improvement works 2012-13 250,000 0
6. Repair of the footbridge near Big Wave Bay Beach at Tai Long Wan Village – Construction of a temporary footbridge 150,000 0
7. Thirty-seven outdoor leisure venues in the Southern District – Improvement works for energy saving of lighting
facilities
465,102 0
8. Ap Lei Chau Sports Centre – Improvement works for energy saving of lighting facilities 122,800 0
9. LCSD venues in the Southern District – Urgent minor improvement works 200,000 0
10. Pok Fu Lam Public Library – Improvement works for the air conditioning system at Students’ Study Room 10,000 0
11. Construction of drainage channels near Tai Long Wan Village public car park 800,000 0
12. Construction of rain shelter near the bus stop at St. Stephen’s College Preparatory School, Stanley 130,000 0
13. Construction of rain shelter near the bus stop opposite to Chun Ma House, Ma Hang Estate, Stanley 180,000 0
14. Installation of benches at Seaview Promenade, Repulse Bay 140,000 0
28
DMW Project Project Cost ($) Note 1
Expenditure in
2012-13 ($)
15. Replacement of chain-link fencing by Type II railings 1,100,000 0
16. Repair of the footpath behind Chi Fu Fa Yuen to Hong Kong Trail 2,000,000 0
17. Improvement works to drainage channels near light post no. 49066 in Kau Wai Village, Wong Chuk Hang 160,000 0
18. Installation of flower pots on the railing near Baguio Villa, Victoria Road 30,000 0
19. Widening of the staircase linking Baguio Villa and Cyberport Road 300,000 0
20. Construction of a staircase linking Yue Kwong Road, Shek Pai Wan Estate to Aberdeen Praya Road (Jing Hui Garden
Block 1)
490,000 0
21. Shum Wan Road Sitting-out Area - Improvement to venue facilities 450,000 0
22. Two leisure venue “Stanley Promenade and Amenity Area at Stanley Village Road” / roadside amenity plots
in the District – Beautification of soft landscape
80,000 0
23. Hong Fu Playground – Installation of fans inside male and female toilets 15,000 0
Total: 7,850,502.00 88,533.60
Note 1: Project costs shown in italic denote the amount approved by DFMC. Otherwise, they denote the latest project cost.
29
Abbreviations
Government Departments Statutory / Advisory Bodies
ArchSD Architectural Services Department
CEDD Civil Engineering and Development Department
DevB Development Bureau
DSD Drainage Services Department
EMSD Electrical and Mechanical Services Department
EPD Environmental Protection Department
HAD Home Affairs Department
HKPF Hong Kong Police Force
HyD Highways Department
LandsD Lands Department
LCSD Leisure and Cultural Services Department
SDO Southern District Office
WSD Water Supplies Department
TD Transport Department
ACABAS Advisory Committee on Appearance of Bridges and Associated
Structures
DFMC District Facilities Management Committee
DMW WG Working group on District Minor Works Projects
SDC Southern District Council