Download - Schedule Crashing Example
PowerPoint Presentation
ST
D (7)
A(4)
B(3)C(8)
F(12)
G(2)
I(6)
E (9)
H(5)
FN
ActivityIPAsDurationESEFLSLFTFFFIFABCDEFGHI------AAB, CB, CD, ED, EF, G438791225600441212212124431211212423263009415131222252441212222224243030090111014009010001400901000030
1
Table 8.4Project Crashing and Time-Cost Trade-Off Example Problem (3 of 5)
2
Project Crashing and Time-Cost Trade-Off Example Problem (2 of 5)Figure 8.20Copyright 2010 Pearson Education, Inc. Publishing as Prentice HallCrash cost & crash time have a linear relationship:
3
Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost (2 of 2)
4
Project Crashing and Time-Cost Trade-Off Example Problem (4 of 5)
5
Project Crashing and Time-Cost Trade-Off Example Problem (5 of 5)As activities are crashed, the critical path may change and several paths may become critical.
6