BASIC KNOWLEDGE IN ROADCONSTRUCTION
Chungdu TsheringEngineer, CDB, MoWHS
-
8/11/2019 Road Construction Works
2/39
Types of Road in Bhutan
1. National Highways2. Dzongkhag Roads3. Farm Roads
-
8/11/2019 Road Construction Works
3/39
1. National Highways
a. Asian Highway (Currently the existing Phuentsholing-ThimphuHighway)
b. Primary National Highway (existing East-West Highway)c. Secondary National Highway (Currently District Roads)
Carriageway3500
Shoulder 1500
Shoulder 1500
L-Drain1000
Sub base = 190mmBase Course = 150mm
Hard Shoulder
Compacted Granular Soil Soling
Secondary National Highway
Subgrade CBR = 7%
Carriageway6500
Shoulder 1500
Shoulder 1500
L-Drain1000
Sub base = 210mmBase Course = 150mm
Hard Shoulder
Compacted Granular Soil Soling
Primary National Highway
Subgrade CBR = 7%
50mm DBM + 25mm AC
25mm PMC
-
8/11/2019 Road Construction Works
4/39
2. Dzongkhag Roads Currently feeder Roads Connects a Dzongkhag centre and a Dungkhag Centre etc.
Carriageway3500
Shoulder 500
Shoulder 500
L-Drain600
Sub base = 150mmBase Course = 150mm
Hard Shoulder
Compacted Granular Soil Soling
Dzongkhag Road
Subgrade CBR = 7%
-
8/11/2019 Road Construction Works
5/39
3. Farm Roads Roads that link farmland areas/villages.
Carriageway3500
Shoulder 500
Shoulder 500
L-Drain600
Sub base = 140mmBase Course = 120mm
Hard Shoulder
Compacted Granular Soil Soling
Farm Road
Subgrade CBR = 7%
Note: If the traffice is less than 10-15 vpd, single layer base course should sufice
-
8/11/2019 Road Construction Works
6/39
WHAT
WE DOIN ROAD CONSTRUCTION
-
8/11/2019 Road Construction Works
7/39
MAJOR ACTIVITIES
1. FORMATION CUTTIN G2. SUB-GRADE PREPARATION3. BASE COURSE & BLACK TOPPING
4. SHOULDER5. PERMANENT WORKS6. BRIDGES
-
8/11/2019 Road Construction Works
8/39
1. FORMATION CUTTING
SLOPEGRADIENTGEOMETRICDISPOSAL OF SPOIL
-
8/11/2019 Road Construction Works
9/39
-
8/11/2019 Road Construction Works
10/39
2. SUB-GRADE PREPARATION
In order to maintain stable and durable sub-grade, uniformconsolidation to be incorporatedSub-grade act as a cushion for other layers i.e. In order to
achieve durable road sub-grade should be strong
.Maintain proper Camber
-
8/11/2019 Road Construction Works
11/39
SUB-GRADE PREPARATION
CAMBER
-
8/11/2019 Road Construction Works
12/39
3. BASE COURSE & BLACK TOPPING
Type I (Old) Base course = 150 + 100 = 250mm thickness 150mm = 40-63mm, (Rolling) 100mm = 20-50mm, (Rolling)
Premix = 25mm + blinding material (Rolling by applying water) Sand Seal coat Resurfacing: 20mm
Type II (New) Granular Sub-Base (GSB) coarse graded (70mm below) Wet Mix Macadam (WMM) (40 mm, 20 mm, 10 mm & Soil) mix
with water Dense Bitumen Macadam (DBM) 20mm + Bitumen Asphalt Concrete 10mm + Bitumen
Thickness depends upon the actual design for a road
-
8/11/2019 Road Construction Works
13/39
-
8/11/2019 Road Construction Works
14/39
-
8/11/2019 Road Construction Works
15/39
Sub-Grade Preparation
Base Course: 150mm ( 40-63mm),Rolling
Base Course: 150mm ( 20-50mm),Rolling
Premix: 10mm + bitumen, Rollingby applying water
Sand Seal Coat
Base Course & Type - I
-
8/11/2019 Road Construction Works
16/39
Sub-Grade Preparation
Granular Sub Grade ( 70mm below),rolling
Wet Mix Macadam (WMM), 10 to40mm plus soil with water & rolling
Dense Bitumen Macadam (DBM) 20mm + Bitumen
Asphalt Concrete 10mm +Bitumen
Base Course & Type - II
-
8/11/2019 Road Construction Works
17/39
TYPE - I
-
8/11/2019 Road Construction Works
18/39
TYPE - II
-
8/11/2019 Road Construction Works
19/39
4. SHOULDER:
A hard area at the side of a main road, especially amotorway, where a driver can stop if there is a seriousproblem
Shoulder should be strong enough to resist any types
of vehicle
Maintain proper compaction as per the design
Width and thickness should be as per the specification
-
8/11/2019 Road Construction Works
20/39
SHOULDER
-
8/11/2019 Road Construction Works
21/39
PERMANENT WORKS
RETAINING WALLBREAST WALLRCC WALLCULVERTDRAIN
-
8/11/2019 Road Construction Works
22/39
Breast Wall
-
8/11/2019 Road Construction Works
23/39
RCC Wall
-
8/11/2019 Road Construction Works
24/39
Culverts
-
8/11/2019 Road Construction Works
25/39
Culverts
-
8/11/2019 Road Construction Works
26/39
-
8/11/2019 Road Construction Works
27/39
CATCH PITCATCH PIT
-
8/11/2019 Road Construction Works
28/39
3. BRIDGE CONSTRUCTIONRCC BRIDGESTEEL BRIDGEBAILEY BRIDGEWOODEN BRIDGE
-
8/11/2019 Road Construction Works
29/39
RCC Bridge
-
8/11/2019 Road Construction Works
30/39
Steel Bridge
-
8/11/2019 Road Construction Works
31/39
Bailey Bridge
-
8/11/2019 Road Construction Works
32/39
Wooden Bridge
-
8/11/2019 Road Construction Works
33/39
MATERIALS REQUIRED IN ROAD
CONSTN. CEMENT SAND BOULDER AGGREGATES (different sizes) STEEL MESH BITUMEN GEO-TEXTITLE RCC HUME PIPES
-
8/11/2019 Road Construction Works
34/39
CONSTRUCTED WITHOUT SPECIFICATION
-
8/11/2019 Road Construction Works
35/39
-
8/11/2019 Road Construction Works
36/39
WE BUILD
GOOD & DURABLE ROAD
-
8/11/2019 Road Construction Works
37/39
WE PROVIDE TO ROAD USERS
COMFORT & SAFE RIDING LESS OPERATIONAL COST IN REASONABLE TIME
-
8/11/2019 Road Construction Works
38/39
FOR THE COUNTRY
BOOST UPCOUNTRYs SOCIO
-ECONOMYDEVELOPMENT
-