Purple Line Extension Construction Community Meeting May 19, 2016
Agenda
2
Western look ahead: Sound wall construction La Brea Piling Update La Brea Decking: Phase l, ll ,lll detours, outreach and communication Jet Grouting Schedule and Locations Fairfax Updates: Tree/median removal, sound wall/driveway
construction, traffic reconfiguration, piling La Cienega look ahead: Advance utility relocation, building demo Eat Shop Play Wilshire Question & Answer
Purple Line Extension Project Alignment
3
Section 2 and 3 Status
4
Under Construction Forecasted Schedule
Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.48 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction Activities Current - 2016 2015 - 2018 2025 - 2027
Construction 2015 - 2023 2018 - 2026 2027 - 2035
Operations 2024 2026 2035
PLE Section 1 Alignment
5 5
Local Streets
6
Project Policies for Local Streets:
• No hauling and no construction vehicles
on residential streets.
• No parking on residential streets
outside of permitted closures.
Enforcement:
• Training and take-home materials for
craft and sub contractors prior to
starting on the job.
• Signage in the yards and on local
streets.
• Flaggers strategically placed to avoid
violations.
• Stand-down meetings with construction
supervision and craft.
• Penalties for companies and employees
that violate policies.
Hard-hat sticker provided to
all craft and subs on the
project.
Examples of Mitigation Signage
7
Mitigation signage
commonly seen near
work zones.
Example of mitigation
signage installed in
staging yards. Example of mitigation signage in the La Brea yards.
Mitigation Measures
8
Example of a map provided to sub-
contractors to show approved haul routes.
A flagger at
Wilshire/Detroit
monitoring hauling
during an ongoing
closure.
8 Parking meters
restored on Wilshire
between Detroit and
Cloverdale.
Purple Line Maintenance Facility
Butterfield Property
590 S Santa Fe Avenue
• Located in Arts District downtown, near 6th St Bridge
• Continuation of Abatement work – Monday thru Saturday
– Work Hours: 7am to 4:30pm
• Design Advisory Group – Advisory group is made up of local
leaders and artists from the Arts District.
– Goal is to review and provide input on exterior design of building.
– Presentation from April 13th meeting online.
9
Tie-in at Western Station
10
Future Western Staging Yard
• Northeast corner of Wilshire and Manhattan Place one block west of Western
• Fencing and signage placed at site
• Sound wall construction anticipated for early July
Utility Investigation
Additional activities in Western area include pot holing and street restoration
• M-F, 9am-3:30pm
• Sat-Sun, 8am-6pm
Wilshire/Manhattan Place staging yard
Crenshaw Yard Staging Site Wilshire/Crenshaw
• Used throughout Section 1 utility relocation and construction
• Mitigation efforts and maintenance:
– Crenshaw Gate Entrance re-worked and improvements made
– Lorraine Gate temporarily closed until further notice
– Maintenance inside and outside of yard
Signage at the Crenshaw Yard
11
Signage and blankets at the Crenshaw Yard Entrance
La Brea Station
Rendering shows length of the La Brea underground station box
on Wilshire Blvd from Orange Dr to Detroit St 12
Purple Line Extension La Brea Schedule
13
*As of May 2016. Subject to Change
Tunneling
Station
Testing
Staging Yard Activities and Equipment
• Yard usage: 7am to 11pm, (11pm to 7am as needed).
• Wall has openings where pile installation and decking will occur
• Sound wall is 20-24 feet high
• Maintenance of equipment
• Deliveries
Mitigations
• Must comply with COLA noise requirements
• Noise Control Signage
• Low Impact Back up alarms
• Acoustical Insulation
• Metro 5 Step Noise Plan
La Brea Station La Brea Staging Yards
14
Eat Shop Play promotions and construction phase artwork
N La Brea Staging Yard Pile Work
La Brea Station Pile Installation
La Brea Pile Installation Overview On Wilshire from Orange Dr. to Detroit St. Pile installation includes:
• Rig to construct approx. 95ft (L) deep • Crane lifting approx. 95Ft (L) , 24 Inch H-piles into holes • Approx. 590 piles total • Drilling, pile installation and backfilled concrete completed
same day
Pile Installation for South side of Wilshire April 2016-Summer* • Orange Dr to Detroit St
• Work hours: 7am to 11pm with potential nighttime work hours from 11pm to 7am.
• Will require directional closures on La Brea, Wilshire and intermittent closures of Orange Dr and Sycamore.
• Approved detour routes provided in construction notices for directional closures.
15
*Dates and work activities subject to change
Pile work at Wilshire/La Brea
Weekend Directional Closures for Piling
Weekend Directional Closures for Piling on the South Side of Wilshire April 2016-Summer* • Approved weekend directional closures start Friday
9pm-Monday 6am • Directional closures for piling on the south side of
Wilshire will include closures of southbound La Brea, northbound La Brea and eastbound Wilshire.
• La Brea directional closures use Highland, 6th St. and 8th St. as detours.
• Wilshire directional closures use Fairfax, La Brea, and 6th St. as detours.
• Work includes pot holing, pre-trenching, piling, jet grouting.
• Traffic officers dispatched to facilitate traffic movement.
16
*Dates and work activities subject to change
Pile work under a northbound directional closure on La Brea
Directional closure locations in the Wilshire/La Brea area.
Appendage Piles, South Side of Wilshire
• Appendage piles are the ancillary piles for the structures on the sides of the station box. • Located on the north and south side of Wilshire Blvd on La Brea, Sycamore, and Orange. • Appendage structures include:
• Vent shafts, exit stairwells, and station entrance at La Brea • Appendage piles are smaller and shorter (40-60ft.) than the station box piles. • Requires closures on La Brea, Sycamore, and Orange.
17 This diagram shows the appendage structure locations on the south
side of Wilshire boxed in purple.
Appendage Piles Schedule
South side of Wilshire Appendage Piles • South side appendage structures started in
May 2016
Traffic control • Sycamore and Orange will be closed to thru
traffic at Wilshire intermittently • Access from 6th, 8th, and alleys will be
maintained • Intermittent sidewalk closures • Sidewalk on the south side of Wilshire
between La Brea and Detroit closed thru July
18
Northbound Sycamore Appendage Pile Work
19
LA BREA DECKING
La Brea Station Decking Overview
Decking • On Wilshire, between Orange Dr. and Detroit St.
• Construction of a concrete deck, curb to curb
• Sidewalks be maintained, or pedestrian detours created
• Decking will serve as the temporary street surface
• Traffic will travel on the installed deck panels while the station is constructed underground
• La Brea Station:
– Approx. 1,000 feet long
– Approx. 70 feet wide
– Approx. 60 feet deep
• Will follow pile operations; anticipated to begin June 2016
• Will work closely with First Responders on emergency access and safety
• Pending Board of Public Works approval in May
• Additional activities under decking closures: jet grouting, piling, temp. civil improvements.
20
20
La Brea Station Examples of Decking
21
Full Closure of Crenshaw Blvd to install Decking
La Brea Station Examples of Decking
22
Full Closure of Crenshaw Blvd to Install Decking
La Brea Station Example of Decking Completed
23
Crenshaw Blvd and Rodeo Rd Decking
La Brea Station Decking Schedule
June 2016 through Fall 2016 Approximately 22 weekend closures (no work 4th of July or Labor Day weekends) Work is scheduled in three phases. Phase 1: Wilshire, from Detroit to La Brea Phase 1B: Wilshire, from Cloverdale to La Brea Phase 2: Wilshire/La Brea Intersection Phase 3: Wilshire, from La Brea to Highland
Traffic plan for closures • Fridays 10am: Wilshire reduced to one lane each direction
• Lane reductions at 10am will allow the design builder to start the loudest work (breaking of concrete) during day time hours.
• Friday 8pm: Full closure of Wilshire or Wilshire/La Brea intersection (Phase 2) • Monday 6am: Streets open • Work occurs 24/7
For information on closures and detours WWW.METRO.NET/PURPLELINEEXT
*Dates and work activities subject to change
La Brea Decking Phase 1 Wilshire, Detroit to La Brea
25
Essentials: • Wilshire reduced to one lane
in each direction, from Detroit to Highland, on Fridays from 10am - 8pm
• Full closure of Wilshire Blvd, Detroit to La Brea, starting at 8pm on Fridays until Mondays at 6am
• Southbound La Brea reduced to one lane between 6th and Wilshire.
Work zone on Wilshire, Detroit – La Brea
Phase 1 Detour Wilshire, Detroit to La Brea Closure
26
Westbound: Northbound La Brea to Westbound 6th St. to Southbound Fairfax Eastbound: Northbound Fairfax to Eastbound 6th St. to Southbound La Brea
La Brea Decking Phase 1B Wilshire, Cloverdale to La Brea
27
Essentials • Full closure of Wilshire, from
Cloverdale to La Brea, during
Phase 1 of decking.
• This closure will support decking,
paving, and staging.
• The duration of this closure is
approx. 1-2 weekends
• Detour same as for Phase 1.
Work zone from Cloverdale to La Brea
La Brea Decking Phase 1B Closure Local Access for Detroit Street
• Local access for residents on Detroit
maintained via Carling Way at 6th St.
• Carling Way access from Detroit
restricted.
• Traffic facilitated by flaggers, signage.
• Door-to-door outreach for residents
and businesses prior to closure.
• South Detroit Street access from 8th
La Brea Decking Phase 2 La Brea/Wilshire Intersection
29
Essentials: • Early start lane reductions on
Wilshire, Detroit to Highland, reduced to one lane in each direction on Fridays from 10am until 8pm
• Full closure of La Brea Ave. starting at 8pm on Fridays until Monday at 6am
• Full closure of Wilshire Blvd. starting at 8pm on Fridays until Monday at 6am
Work zone, Wilshire/La Brea intersection
Phase 2 Wilshire Detour La Brea/Wilshire Intersection Closure
30
Westbound Wilshire: Westbound Wilshire to northbound Highland to westbound 6th St. to southbound Fairfax to westbound Wilshire. Eastbound Wilshire: Eastbound Wilshire to northbound Fairfax to eastbound 6th St to southbound Highland to Wilshire Local access on Wilshire for business and residents will be maintained up to the Wilshire/La Brea intersection. The farthest that westbound thru traffic can travel before needing to turn is: Wilshire/Highland. The farthest that eastbound thru traffic can travel before needing to turn is: Wilshire/Fairfax Lane reductions on Wilshire going westbound will start: Wilshire/McCadden Lane reductions on Wilshire going eastbound will start: Wilshire/San Diego Way
Phase 2 Southbound/Northbound La Brea Detour La Brea/Wilshire Intersection Closure
31
Southbound La Brea: Southbound La Brea to westbound 3rd St. to southbound Fairfax to eastbound San Vicente to southbound La Brea. Local access maintained between 3rd and La Brea Northbound La Brea: Northbound La Brea to westbound Olympic to northbound Fairfax to eastbound 3rd to northbound La Brea. Lane reductions on La Brea will start: • Southbound La Brea at 4th • Northbound La Brea at 9th
La Brea Decking, Phase 3 Wilshire, La Brea to Highland
32
Essentials: • Wilshire, from La Brea to
Highland, reduced to one lane in each direction on Fridays from 10am until 8pm
• Full closure of Wilshire Blvd. from 8pm on Friday until 6am on Monday
• Northbound La Brea reduced to one lane from 8th to Wilshire Blvd
Work zone - La Brea-Orange. Closure - La Brea-Highland to
avoid traffic on local streets
Phase 3 Detour Wilshire, La Brea to Highland
33
Eastbound: Northbound La
Brea to Eastbound 6th to
Southbound Highland to
Eastbound Wilshire
Westbound: Northbound
Highland to Westbound 6th to
Southbound La Brea to
Westbound Wilshire
Bus Detours Wilshire and La Brea
34
Phase I/II: 720/20, LADOT Dash, AVT • Eastbound/Westbound Wilshire Buses will be temporarily suspended between
Fairfax and La Brea • Nearest bus stop locations will be at Wilshire/Crescent Heights and Wilshire/
Highland. • LADOT Dash Buses will be temporarily suspended on 6th Street between Hauser
and La Brea • Antelope Valley Transit Authority (AVT) buses will also be temporarily suspended
on Wilshire • LADOT Dash and AVT Bus Detours will be coordinated with Metro bus operations.
Bus Detours Phase I: 720/20 Bus Lines
35
Eastbound: Eastbound Wilshire, to northbound Fairfax, eastbound 3rd St, to southbound La Brea, to Wilshire. Westbound: Westbound Wilshire, northbound La Brea, westbound 3rd St, southbound Fairfax to Wilshire
Bus Detour Phase II: 720/20 Bus Lines
36
Eastbound: Eastbound Wilshire, northbound Fairfax, eastbound 3rd St, southbound Rossmore to Wilshire Westbound: Westbound Wilshire, northbound Rossmore, westbound 3rd St, southbound Fairfax to Wilshire
Bus Detours Phase II: 212/312 Bus Lines (La Brea)
37
Southbound: Southbound La Brea, eastbound 3rd St, southbound Rossmore, eastbound Wilshire, southbound Crenshaw, westbound Olympic, southbound La Brea. Northbound: Northbound La Brea, eastbound Olympic, northbound Crenshaw, westbound Wilshire, northbound Rossmore, westbound 3rd St, northbound La Brea.
Bus Detours Phase III: 720/20 Bus Lines
38
Eastbound: Eastbound Wilshire, Southbound La Brea, Eastbound Olympic, Northbound Crenshaw, Eastbound Wilshire Westbound: Westbound Wilshire, Southbound Wilshire, Westbound Olympic, Northbound La Brea, Westbound Wilshire
La Brea Station Decking Community Outreach
39
I-405 Freeway Closure “Carmageddon”
• Robust Marketing Campaign • Social Media: Facebook, Twitter, Nextdoor • Advertising: print, radio, online (English, Spanish, Korean)
• 10 local papers • 15 radio stations
• Media Coverage: Press event, press releases • Business and resident outreach • Door to Door outreach – La Brea area • Community Meetings
• July 21, Petersen Automotive Museum • September 15, TBD
• Marketing Items • Trifold, postcard, bus drop, TAP outreach
• Landing page on PLE homepage • Decking Overview • Detour Maps • Photos/videos • Construction Notice updates
• Board of Public Works Approval – May 27 (tentative)
Communications and Outreach
La Brea Decking Outreach August – December 2015 • 65 Meetings/Briefings • 68 Construction Notices
• Sent via eblast, posted on website and social media • Community Meeting notices walked to 30,000 residents/businesses
Since 2016 • 78 Meetings/Briefings • 133 Construction Notices • 90,000+ flyers distributed • Construction Community Meetings: January 21, March 17, May 19 • Wilshire/La Brea Business Meeting: June 2 • Email Distribution List: 2,300+, Facebook 5,000+ likes, Twitter: 4,000+ • Weekly emails to community leader for NCs, HOAs, Apartments
Tower Crane at Wilshire/La Brea
41
Tower cranes in New York City on the World Trade Center
project
Rendering of the tower crane in the north La Brea yard at Wilshire/La Brea
• Tower approx. 100 ft.
• Boom approx. 180ft.
• Expected to arrive Summer 2016 in the
north La Brea yard at Wilshire/La Brea.
• Function is to support station
excavation and tunneling excavation.
Jet Grouting
● Jet grouting is a construction process that uses high-pressure air
and grout to create a deep soil-concrete block.
● The purpose of jet grouting is to reinforce and strengthen the soil with concrete to support tunneling and cross-passage excavation.
42
Examples of jet grouting at Wilshire and Detroit behind K-rail
Jet Grouting Locations
• Jet Grouting will occur at 16
locations along Wilshire between La Cienega and Western.
• There will be no more than two
jet-grouting operations being performed at one time.
• Approximately 6 weeks at each
location.
43
1. On Wilshire between Rossmore and Arden
2. On Wilshire between Arden and Lucerne
3. On Wilshire between Citrus and Mansfield
4. On Wilshire between Highland and McCadden Pl
5. On Wilshire between Cochran and Cloverdale
6. On Wilshire between Plymouth and Windsor
7. On Wilshire between Norton and Bronson
8. On Wilshire between St Andrews and Grammercy
9. On Wilshire between Crenshaw and Lorraine
10. On Wilshire between Wilton and Van Ness
11. On Wilshire between La Jolla and Sweetzer (x2)
12. On Wilshire between Crescent Heights and La Jolla
13. On Wilshire between Burnside and Dunsmuir
14. On Wilshire between Spaulding and Ogden
15. On Wilshire between Fairfax and Crescent Heights
*Dates and work activities subject to change
Jet Grouting Activities and Layout
Work Activities • Potholing, street level excavation ,
vertical drilling , trucking, cement silos, pumps, generators
Layout • Concrete Barriers placed on the
middle lanes of Wilshire Blvd • Lanes reduced to two lanes each
direction at Jet grouting locations • Bus stops will be temporarily
relocated as required • Wilshire BRT lane not enforced in
these areas during jet grouting
44
Jet Grout Schedule
Jet Grouting Jet grouting will continue behind concrete barriers at Wilshire/Detroit.
Jet Grouting on Wilshire Blvd Start summer 2016 • First three locations
• Wilshire between Rossmore and Arden (approx. 6 weeks) • Wilshire between Arden and Lucerne (approx. 6 weeks) • Wilshire between Citrus and Mansfield (approx. 6 weeks)
• Construction notices will be sent and outreach will be conducted for each location
45
*Dates and work activities subject to change
Deck Openings What: • Deck openings are openings of the street-deck for
the purpose of delivering materials for underground construction.
• Deck openings will be done at locations of the deck that are designed to open and close.
• Deck openings will occur periodically, as needed • Deck panels are 8ftx14ft
When: • Following La Brea decking, late 2016 • Throughout the duration of the project
How: • Off-peak hour (M-F, 9am-3:30pm) lane closures
46
Example of a deck opening
from underneath the deck
Deck Openings
Construction Activities • Concrete placement
• Maintenance of deck beams, panels and utilities • Deliveries into excavation/station - rebar, struts,
lumber, MEP equipment, shoring and formwork panels, construction equipment, ventilation, utilities, waterproofing
• Station backfilling
• Installation of new and replacement utilities
47
Example of a beam delivery through a deck
opening as seen from street level.
Fairfax Station
Rendering shows length of the Fairfax underground station box
on Wilshire Blvd from west of Fairfax to just west of Ogden Dr. 48
Fairfax Station Schedule
*Schedule is subject to change. Updated as of May 2016.
35
Fairfax Station Advance Utility Relocation
• Potholing continues
• Work hours:
o Monday thru Friday: 9am-3:30pm
o Saturday-Sunday: 8am-5pm
o Night work (if necessary): 9pm-6am
50
Utility investigation during pot holing at Wilshire/Fairfax.
Fairfax Station Activities at Ogden Staging Yard
51
• Sound wall and driveway construction • Mobilization of equipment in advance of k-rail
installation
Equipment for jet grouting stored in the Ogden yard.
Sound wall pile installation underway in the Ogden Yard .
Ogden Staging Yard Sound Wall Construction
• Construction of sound wall and driveways
• Work hours: 7am-5pm
• Sound wall is 20-24 ft
• Sidewalk closure on east side of Orange Grove (yellow highlighted area)
• Eat Shop Play promotions and construction phase artwork will be added to the walls
52
Ogden Yard Safety Measures & Mitigations
.
Examples fromWilshire/La Brea Staging Yard
53
Fairfax Tree and Median Removal
• Tree removal in the medians complete • Median removal, ongoing thru May • Work hours: 9:00am-3:30pm M-F, 8:00am-6:00pm Sat/Sun • 62 agave plants were saved and donated to local recipients. • 38 street trees will be removed.
• Trees replaced at a ratio of 2:1 at the end of the project • Banner highlighting future landscape will be placed on Ogden sound wall
• 2.5 medians to be removed from Fairfax to Spaulding.
54
Students at Carthay Center School for
Environmental Studies watering donated
agave plants on campus
Fairfax Median Removal Locations
55
Future Landscape Medians at Fairfax/La Brea
56
Median design at Wilshire/ Ogden facing west (left rendering)
Median design at Wilshire/ Cloverdale facing west (right rendering)
Wilshire/Fairfax Bus Stop Relocations
57
• New bus stop locations in the Wilshire/Fairfax area
• Safely outside of construction zones
Fairfax Traffic Reconfiguration Piling Preparation
• Anticipated start is June 2016
• Start date depends on DWP cable pulling, 3rd party relocations.
• Install traffic reconfiguration over a single weekend.
• Wilshire will be reduced to two lanes in each direction from
Spaulding to San Diego Way.
• Ogden crosswalk to shift from west leg to east leg.
• Potential off-peak lane reductions to one lane in each direction.
• Left turn pockets will remain open at Wilshire and Fairfax during
north side pile operations only.
58
Fairfax Station Pile Installation Overview
47
• Pile installation includes:
– Rig to construct 95ft (L) deep
– Crane lifting 95Ft (L) , 24 Inch H-piles into holes
– Approx. 490 piles
– Drilling, pile installation and backfilled concrete completed same day
• Piling anticipated to start on north side of Wilshire between Ogden to just west of Fairfax.
• Operation anticipated to take approximately 4-6 months on each side of the street.
• Typical work hours 7am-11pm with potential nighttime work hours from 11pm to 7am.
• Wilshire is reduced to two lanes in each direction.
• Directional closures on Fairfax and Wilshire will take place on weekends.
PHOTO
59 Piling at the N. La Brea yard.
La Cienega Station
Rendering shows length of the La Cienega underground station
box on Wilshire Blvd from La Cienega to Tower Dr. 60
La Cienega Utility Relocation 30 Months
*Schedule is subject to change. Updated as of May 2016
61
La Cienega Station Advanced Utility Relocation
• Water and telecommunication work continues along the alignment on Wilshire from La Cienega to San Vicente.
Photo of recent AUR work for the La Cienega Station
62
La Cienega Station Advanced Utility Relocation
Current AUR activities continue during daytime and evening hours.
Days and Hours*
o Monday thru Friday: 7am – 4pm
o Saturday or Sunday: 8am – 6pm
o Night Time Hours:
• 8pm – 6am or
• 12am – 7am
* Hours vary for events at The Saban Theatre
Photo of recent AUR work on Wilshire at La Cienega
63
La Cienega Station Gale Yard
• Demolition of buildings on Gale and Wilshire Summer 2016
• Future Gale Staging Yard
• Beverly Hills Fire Department may use abated properties for fire drill exercises prior to demolition
• Updates will be provided to the community when drills are scheduled
64
La Cienega Station La Cienega Yard
• Future La Cienega Staging Yard
Buildings to be demolished, anticipated in Summer 2016
65
La Cienega Station Weekend Work
Photo
66
• Weekends, Friday thru Sunday
• Detours and turning restrictions will depend on location of construction.
• Wilshire, at least one lane open in each direction
• La Cienega, at least one lane open in each direction
• Days and Hours
o Start: Friday 10pm or 12am*
o End: Sunday by 6pm
*start time depends on the Saban Theatre performance schedule
Intersection at Wilshire and La Cienega
Eat, Shop, Play Wilshire ESP Spotlight- West Segment
67 67
Lunch Meet Up Friday May 20th, 2016 11:30am- 1:00pm Book My Lot- Food Trucks 5800 block of Wilshire Blvd Los Angeles, CA 90036 Across from LACMA (Between Spaulding and Stanley) Book My Lot brings internationally diverse and gourmet cuisine to the Miracle Mile on a daily basis by organizing and scheduling some of the best food trucks LA has to offer- on site 7 days a week For more Information: Visit www.bookmylot.com or email: [email protected]
logoloedian
Eat, Shop, Play Wilshire ESP Spotlight- East Segment
68 68
Beauty Bar Los Angeles 5115 Wilshire Suite B, Los Angeles, CA 90036
$3.00 off for a Manicure or Pedicure on Mondays, Tuesdays, or Wednesdays only! Beauty Bar Los Angeles is a nail salon located a few blocks from Wilshire and Highland. Services include a nails salon, facials, eyelash extensions and waxing.
69
Eat Shop Play Wilshire In The Community
Design Build contractor and Metro
PLE team at the Miracle Mile La
Brea business stroll
Spare Tire Kitchen and Tavern Lunch Meet up Crews buying lunch from Jack in the Box
Prospect Gourmand located on
La Cienega Lunch Meet up
70
Eat, Shop, Play Wilshire Quarterly Drawing Winners
$1,000 winner from Milk Jar Cookies
5466 Wilshire
$500 winner from Next Gen Video Games
5360 Wilshire
$250 winner from Beauty Images
678 S Cloverdale
71
Eat, Shop, Play Wilshire Fortune Fridays
• Support local businesses & spread the word on social media about your positive experience for a chance to win $50!
Participation is easy! • Use “#EatShopPlay” and
“#Wilshire” in your positive social media posts.
• “Like” & “Follow” our pages to see the winner announcements every Friday!
72
Upcoming BIF Workshops
Purple Line Extension, Phase 1
Wednesday, June 29, 2016
11:30am-12:30pm
BREATHE LA (1st Floor, Conference Room)
5858 Wilshire Blvd., Los Angeles, CA 90036 *Street Parking Only
73
For more information visit www.pcrcorp.org or contact Angela
Winston, Program Manager at 213.739.2999, ext 223
Next Meeting
74
Section 1 Construction Community Meeting Thursday, July 21, 2016
6:00-8:00pm Petersen Automotive Museum
6060 Wilshire Blvd, 4th Floor Los Angeles, CA 90036
Agenda: La Brea decking update Fairfax piling update Art Program: Resources Needed!
Stay in Touch
www.metro.net/purplelineext
twitter.com/purplelineext
facebook.com/purplelineext
213.922.6934
75