Progress and Update Report
May, June, & July, 2000
The Stainless Steel Ladder $2,100 US
Side View Top View
Guards uniforms & security
Uniform Hat Days.......Rafael Nights.....Tolentino Sundays..
Rafael
Tolentino
Luis
No Glass Containers
Pool Maintenance
Pressure wash monthly
Ordered 5 new lightsOrdered tile to fix
small damaged tilesTo regrout in
September
Wind Turbines
Installed 4 Wind Turbines on sewer vents
Act as wind powered extractors creating a negative pressure on sewer vents
Reduce odor on windy days in the condos
AC Leak on Roof.....7 South
Leaking roof 7 North
Old leak coming through AC plumbing
Fiberglassed panels on roof and side
To do similar work on South side to prevent future leak
Attic Tour...TV....OTIS
Water Meters ......16 installed
Spiral Stairs to be repainted
The Box on the side
September 16 to 23....closed
POOL AREA regrout pool replace pool lights replace glass install barrier I and II install Jacuzzi pump rewire pool room
BUILDING• clean cistern• replumb water pump• elevator, tile floor. paint
shaft. & cable repairs• paint spiral stairs• general cleaning &
painting