� Provide information about the LAX United Airlines East Aircraft Maintenance and GSE Project
� Provide information on the California Environmental Quality Act (CEQA) process
� Discuss Initial Study conclusions and environmental resource areas being carried forward in the Draft EIR
� Collect community comments on the information and analyses presented in the Initial Study
Project Site and Purpose
� Consolidate existing UAL aircraft maintenance facilities into one facility on an existing UAL leasehold.
� Modernize UAL’s existing East Maintenance Facility.
Pershing Dr
Imperial Hwy
Westchester Pkwy
Sep
ulve
da B
lvd
World Way West
Century Blvd
Avia
tion
Blv
d
Lincoln Blvd
Runway 6L-24R
Runway 6R-24L
T3T1
T4 T5 T6 T7 T8
TBIT
Runway 7R-25L
Runway 7L-25R
Arbor Vitae St
Airp
ort B
lvd
98th St
96th St
T2
LAX/El Segundo
Dunes
Vista del Mar
Century Fwy
111th St
La C
iene
ga B
lvd
Manchester Ave
PacificOcean
42
PROJECTSITE
WESTCHESTER
1
405
105
PLAYA DEL REYO0 0.25 0.5
Miles
Legend UAL East Maintenance Facility UAL West Maintenance Facility LAX Property BoundarySource: CDM Smith, November 2017. Prepared by: CDM Smith, November 2017.
Figure
8LAX UAL East Aircraft Maintenance and GSE Project Proposed Floor Plan - Level 2
Source: United Airlines, FSB, July 2017.Prepared by: CDM Smith, November 2017.
NDND
Legend
AIRCRAFT MAINTENANCE
BUILDING FUNCTION
CIRCULATION
FACILITIES MAINTENANCE
GSE
OTHER
STORES
SHARED
Parking Structure F
United Airlines Cargo
Roof
HangarRoof
OPEN BELOW
Proposed Project Components � Demolish the existing buildings associated with the East Maintenance Facility
� Quonset Hut will not be affected
� Construct and operate a new aircraft and GSE maintenance facility, totaling approximately 411,000 square feet to include:
� Two wide-body aircraft hangar bays and permanent GSE maintenance facility
� Aircraft maintenance shops, aircraft parts/supplies stores, fire suppression water tank, and supportive facilities
� The new maintenance building will be designed to meet LEED Silver standards
� Relocate provisioning (i.e., storage) to a portion of the exisiting UAL Cargo building
Facility
Existing Facilities Proposed Facilities
Approximate Building Area (ft²)
Aircraft Parking Positions
Approximate Building Area (ft²)
Aircraft Parking Positions
West Maintenance Facility 593,046 15 NA NA
East Maintenance Facility 133,750 19 411,000 23
Total 728,796 34 411,000 23
Figure
7LAX UAL East Aircraft Maintenance and GSE Project Proposed Floor Plan - Level 1
Source: United Airlines, FSB, July 2017.Prepared by: CDM Smith, November 2017.
Legend
AIRCRAFT MAINTENANCE
AIRCRAFT MAINTENANCE HANGAR
BUILDING FUNCTION
CIRCULATION
EXTERIOR
FACILITIES MAINT.
GSE
OTHER
SHARED
STORES
Parking Structure F
United Airlines Cargo
United AirlinesCargoYard
GSE Yard
Stores Yard
Hangar
Avion Drive
PROPOSED LEVEL 1 FLOOR PLAN
PROPOSED LEVEL 2 FLOOR PLAN
� Apron improvements
� Replace/resurface/restripe a portion of the apron area
� Reconfigure the apron and include aircraft parking positions in the hangar
� Total of 23 future aircraft parking positions on the leasehold
� Construct a jet blast deflector (also called a blast fence)
� Relocate, remove, and install utilities
� Vacate the east-west portion of Avion Drive north of Parking Lot H
� Relocate employee parking to Parking Structure F, located at the southeast corner of Century Boulevard and Avion Drive
Proposed Project Components
CONCEPTUAL SITE PLAN
CEQA Overview
� Purpose is to inform decision-makers, agencies, organizations, and the public of the environmental effects of a project
� Applies to discretionary projects
� Identifies potential effects on the environment
� Identifies ways to avoid or reduce potential significant effects through mitigation measures or alternatives
No Impact/Less Than Significant(No Further Analysis)
Analysis Being Carried Forward in EIR
�Aesthetics �Agricultural/Forestry Resources �Biological Resources �Cultural Resources
� Archaeological Resources � Paleontological Resources
�Hydrology and Water Quality � Land Use and Planning �Mineral Resources �Noise �Population and Housing �Public Services �Recreation
�Air Quality �Cultural Resources
� Historical resources �Greenhouse Gas Emissions � Transportation/Traffic �Cumulative Impacts
�Geology and Soils �Hazards and Hazardous Materials
� Tribal Cultural Resources �Utilities and Service Systems
�Other CEQA Considerations
Schedule & Anticipated Milestones
NOP/Initial Study
Draft EIR
Final EIR
Start of Construction
Public Release December 7, 2017
Scoping Meeting December 19, 2017
Public Release Mid-2nd Quarter 2018
Late 3rd Quarter 2018
4th Quarter 2018
We Are Here
Public Comments on the NOPComments can be submitted:
� At this Scoping Meeting on comment cards � Online at: http://www.lawa.org/ourLAX/Comments.aspx � Mailed to the following contact:
Los Angeles World Airports Attention: Maritza Lee, Project Planner One World Way, P.O. Box 92216 Los Angeles, CA 90009-2216
Comments must be received by (not postmarked by) 5:00 pm, Monday, January 8, 2018