PROPOSED CORPORATE PLAN
-
Corporate Business Plan
2 | P a g e
CORPORATE BUSINESS PLAN
Overview
The corporate business plan reflects corporate operating and capital initiatives that achieve and support
the Strategic Plan. Implementation of the corporate priorities purposefully moves the Town towards
success with the Commitment statements and Measures of Success within the Strategic Plan.
Corporate Planning Process and Timelines
The corporate planning process is a new initiative of the Town of Stony Plain to aid with streamlining the
activities of the organization with the strategic goals of the community. The following timeline sets out
the dates for preparation, consideration and approval of the 2016 2018 Corporate Plan.
Date Activity
January 2015 Council Retreat Strategic Planning session regarding the Corporate Plan
March 2015 Strategic Plan Adoption of the 2015-2017 Strategic Plan Corporate Business Planning Senior Leadership Team (SLT) and Managers identify and define corporate initiatives.
March June 2015
Department Business Planning Departments work on developing their detailed Status Quo budgets, business cases or operating and capital initiatives and service changes. Department business plans are reviewed to validate dependencies and scheduling, overall budget requirements, effort demands and capacity. Ranking and Prioritization SLT completes a detailed review and prioritization of operating and capital initiatives and proposed service changes. The prioritization is designed to enable SLT to determine the initial line for calculation of funding for above the line initiatives and service changes and for analysis of capacity.
July August 2015
Financial and Capacity Analysis Calculation and compilation of financial summaries of funding strategies for the status quo budget, new initiatives and service changes as prioritized by SLT in June. An analysis on capacity of the organization to deliver core services, new initiatives and service changes is completed.
September 2015 Finalize Recommended Corporate Plan SLT reviews and finalizes changes to status quo budgets and prioritization of service changes and initiatives based on the financial and capacity analysis. SLT reviews and finalizes the funding strategies for the recommended corporate plan.
October 23, 2015 Distribution of Recommended Corporate Plan The recommended Corporate Plan is distributed to provide members of Council and the public an opportunity to become familiar with the recommended Corporate Plan.
November 2 4, 2015
Public Corporate Plan Meetings The recommended Corporate Plan is presented to Council and amended based on Council deliberations and direction.
November 23, 2015
Corporate Plan Approval the amended Corporate Plan is presented for Councils approval.
December 2015 Staff and Public Communication of the Corporate Plan The approved Corporate Plan is reviewed with staff and communicated to the public
-
Corporate Business Plan
3 | P a g e
Corporate Priorities
This section outlines the initiatives which flow from the Strategic Plan 2015 2017. They are organized
by the Themes within the Strategic Plan.
Additional details of the new initiatives are located in the New Initiatives and Service Changes section of
this Corporate Plan document.
GOVERNANCE & PARTNERS
We Commit to:
Proactively pursue connections with, build relationships with, and advocate on behalf of our residents
to neighboring municipalities, regional partners and other levels of government to provide
infrastructure, programs and services that fit the needs of our residents and business community.
Measures of Success:
An agreement with the Government of Alberta to upgrade Secondary Highways 779 and 628
A framework that defines regional partnerships for projects and service delivery, including
funding protocols
Stony Plains interests are represented and visible through regional committees, boards and
plans
Collaboration with provincial and federal municipal associations to partner with and advocate
on behalf of our community
Provincial support to meet Family and Community Support Services funding commitments
Sufficient and meaningful Council representation on external committees relevant to town
business
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate External Operating
Office of the CAO
CE-001.1 Framework for Regional Partnerships
The Town of Stony Plain is situated in close physical proximity to the City of Spruce Grove and Parkland County. Historically, this has led to positive working relationships related to service delivery, capital building construction and inter-municipal planning. The three municipalities have numerous agreements, memorandums, funding partnerships and other formal and informal mechanisms to institutionalize municipal cooperation. This initiative is contained within the Strategic Plan, the goal is to devise and work towards an over-arching framework
Jan 2016 Dec 2016
-
Corporate Business Plan
4 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
that guides funding, service delivery and further formalize these partnerships.
Corporate Internal Operating
Office of the CAO
CI-008.1 Government Relations and Advocacy
Government relations are designed to promote Stony Plain to other levels of government to gain support for priorities and needs identified by Council. Advocacy efforts are designed to educate and work with the community, key stakeholders and policy makers on the needs of the Town in order to influence legislation, policy development and project/initiative funding that affects Stony Plain. The Town currently has a framework in place for Government Relations and Advocacy. This was completed in the past 3 years but has not been developed or utilized to its fullest potential. This initiative will develop and action the framework. Council will be asked to consider, review and direct this initiative on an annual basis as part of the Strategic Planning process.
Jan 2016 Dec 2016
We Commit To:
Cultivate a strong organizational structure and processes to support effective and efficient service
delivery.
Measures of Success:
A robust organizational structure to deliver our work and make the most efficient use of our
human, capital and financial resources
Meaningful people policies to support and invest in an engaged, productive and effective
workforce
A corporate planning process that aligns with the strategic planning and budget processes
Corporate Services, Planning and Infrastructure and Community Services reviews,
recommendations and action plans to maximize efficiency and ensure balanced service
delivery
A scalable financial planning, tracking and reporting system to facilitate transparent and
effective management of public funds
Recommendations to optimize offsite levies
A performance measures framework to align with strategic priorities
-
Corporate Business Plan
5 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate Internal Operating
Corporate Services
CI-009.1 Performance Measures Framework
The intent of such a framework would be to develop metrics that are used as an accountability mechanism showing the organizations commitment to the fulfillment of the Strategic Plan and cultivation of best practice. A consultant would be hired to help the organization to develop appropriate metrics for each department; metrics tied to the 2015 2017 Strategic Plan and local government best practices. This would enable benchmarking and reporting to Council and the community and would allow for the analysis of trends over the long term. This would facilitate better future planning and management of resources
Jan 2017 Dec 2017
Corporate Internal Operating
Office of the CAO Planning & Infrastructure
CI-010.1 OCAO/P&I Review
This initiative continues the ongoing process of structural and service review for Town departments and business units. The review will consider current and expectant service levels, anticipate growth and the inter-related nature of specific services for each area. The review will encompass the current business units in OCAO and the Planning area of the P&I Department
Jan 2017 Dec 2017
Corporate Internal Operating
Planning & Infrastructure
CI-013.1 Engineering Section Staffing Review
The engineering section is within the Planning and Infrastructure Department of the organizational structure. Prior to 2007 there was one FTE position, the Manager of Engineering. In 2007 another FTE was added for an engineering technician primarily for construction inspection of storm and sanitary sewer, water and roads installation on both private subdivision development and the towns capital works program and to coordinate the lot grading program. Two significant changes dictate that the staffing level in the engineering area needs to be reviewed Change in Process and Growth in the Community .
Jan 2018 Dec 2018
-
Corporate Business Plan
6 | P a g e
We Commit To:
Engage with our residents and stakeholders to ensure integrated decision-making and collaborative
leadership.
Measures of Success:
Implementation of our public participation strategy, toolkit and policy.
-
Corporate Business Plan
7 | P a g e
SUPPORTIVE INFRASTRUCTURE:
We Commit To:
Adopting a complete streets philosophy for street design and the promotion of alternative modes of
transportation, including preparation for a transit system, to ensure physical connectivity within our
community.
Measures of Success:
Implementation of the Boundary Road functional plan, which may include provisions for
alternative modes of transportation based on traffic volumes
A renewed and fiscally supported Trails Master Plan to maximize community connectivity
A needs assessment to determine the viability of a public transit system
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate External Operating
Planning & Infrastructure
CE-003.1 Public Transit System Assessment
The Town has endorsed a complete streets philosophy to promote alternative modes of transportation. This includes provision for a public transit service that will ensure physical connectivity within the community. Before proceeding with an implementation strategy for public transit the Town needs to carry out a feasibility and needs assessment. The social and environmental benefits as well as the financial implications need to be considered. The assessment will address a phased approach to meeting the unique transit needs of Stony Plain both internally within the community and the region
Jan 2016 Dec 2016
Corporate Capital
Planning & Infrastructure
CCP-055.1 Boundary Road Upgrading Phase I
The recommendations of the Boundary Road Functional Planning Study which involves upgrading of the existing roadway from Highway 16A to Highway 628 has been established as a priority of the organization. This is one phase of that project with the scope to be determined when the project is presented to Council.
Jan 2016 Dec 2016
Corporate External Operating
Planning & Infrastructure
CE-005.1 Trails Master Plan Review
The current Trails Master Plan was prepared in 2005 by Gibbs and Brown. Based on this document the town has developed a trail system which has an outstanding reputation within the region. The Town has grown significantly since the plan was prepared and there is now a new Open Space Study that impacts some of the recommendations within the existing report. These changes create a need for a comprehensive review of the current document. The Town of Stony Plain has committed to a complete streets
Jan 2017 Dec 2017
-
Corporate Business Plan
8 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
philosophy and incorporating trails into open space and street design has been endorsed in the 2015 2017 Strategic Plan. The update will identify gaps between trails and show the next steps required to link residents to destinations to enhance the trail network as an alternate option for transportation within the community.
We Commit To:
Seeking opportunities for and making investments in infrastructure to meet the current and future
needs of our residents and stakeholders.
Measures of Success:
A funding model, operational agreement, business plan and ground breaking for a new RCMP
building
Phase III Construction of Heritage Park, and an operational plan to describe the role of the
park and how residents, visitors and community groups will be able to use the space
Infrastructure and land assembly plan to support construction of a town square in the
downtown core
Recommendations to optimize the existing community centre use and accessibility
A review of community leisure requirements for indoor ice access in collaboration with our
regional partners
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate Internal Operating
Community & Protective Services
CI-007.1 Operational Plan for Heritage Park
The Town of Stony Plain will be adding the 3
rd phase to Heritage Park in 2015. The
project will add a 2 story events building to the existing Outdoor Stage and Pavilion building. The development of and operational plan will provide the correct staffing, maintenance and operational budget resourcing to the site. The phase 3 construction is scheduled for a fall 2016 completion. The operational plan will be written for a January 1, 2017 completion. The costs for this initiative are covered off with existing staff resources.
Jan 2016 Dec 2016
Corporate External Operating
Planning & Infrastructure
CE-006.1 Town Square Design and Land Acquisition Plan
The Town Square Design and Land Assembly Plan will prepare a conceptual plan and assemble the land requirements to meet the municipal office needs and some of the community needs for programmable space in the immediate vicinity of the Town Office. The high level concept for the Town Square will support
Jan 2018 Dec 2018
-
Corporate Business Plan
9 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
the needs identified as a component of the Area Redevelopment Plan for the neighborhood and a needs assessment for municipal and cultural community requirements for office, meeting or event spaces.
We Commit To:
Being mindful of the impact of growth on our ability to maintain existing and improve new
development and services. We consider the future fiscal, social and environmental implications as we
plan.
Measures of Success:
An evaluation to determine the location and form of a municipal cemetery
Appropriate allocation of space for Family and Community Support Services
Updated Land Use Bylaw to manage growth as outlined in the Municipal Development Plan
2013
A review and recommendations for adequate space to accommodate town staff and optimize
their operations and service delivery to the community.
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate External Operating
Planning & Infrastructure
CE-002.1 Cemetery Phase II
Phase I of the Cemetery Project is budgeted for 2015. In Phase 2, limited public engagement is foreseen although a workshop with Council and some stakeholder discussions might be undertaken. This component of the study will look at the precise concept (i.e. traditional crematorium, green burial, memorial garden) as well as service delivery. Issues such as costs, land requirements, pricing bylaw and other governance factors will be examined. Due to unique factors in the Town, preliminary geotechnical work might be undertaken. Finally the actual construction is slated for 2018 and is included in the Capital Projects. The amount will vary dependent on the actual concept and requisite land. A more traditional cemetery requires extensive infrastructure and is therefore more than a crematorium and green burial approach. At this time about $2 million to include construction drawings should be set aside.
Jan 2016 Dec 2016
-
Corporate Business Plan
10 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate Capital
Community & Protective Services
CCP-056.1 Town Office Expansion
Expansion of the second floor of the Town Office as per the original buildout plans from construction in 2002.
Jan 2016 Dec 2016
Corporate Internal Operating
Planning & Infrastructure
CI-011.1 Operations Facility Study
Administration desires to initiate a comprehensive feasibility/cost analysis study to determine whether the current Public Works facility could be expanded or a new facility be constructed. In addition it may also examine the need for a satellite facility twenty five years from now as a result of growth.
Jan 2017 Dec 2017
Corporate Capital
Planning & Infrastructure
CCP-057.1 Cemetery
The recommendations of the Cemetery study will detail the form, size and location of the future cemetery. Given ground conditions in Stony Plain, it is estimated that this will also play a role in site selection and capital costs.
Jan 2017 Dec 2017
Corporate Internal Operating
Corporate Services
CI-012.1 Cemetery Module
The cemetery module will be an addition to the Towns ERP system and will record and maintain the financial records related to the cemetery.
Jan 2018
-
Corporate Business Plan
11 | P a g e
COMMUNITY DEVELOPMENT
We Commit To:
Collaborate with the community to foster and maintain a sense of belonging supported by strong,
accessible cultural and social services and programming.
Measures of Success:
Increased awareness of and participation in local art and cultural opportunities identified in
the Cultural Master Plan and put forward by the Cultural Round Table
Ongoing collaboration with Family and Community Support Services to deliver effective and
reliable programs and services within the community
We Commit To:
Enhance safety of our community and continue planning for the protection of our residents.
Measures of Success:
Installation of traffic controls to support public safety
Emergency management updates and reports shared with the community
Identification of existing rail line safety measures
Enhanced organization and community disaster resiliency
We Commit To:
Embrace the diversity of our community by offering a variety of choices to connect, live and thrive.
Measures of Success:
Integration of cultural initiatives and events into municipal planning
Renewed affordable housing strategy to reflect the current environment and community
needs
We Commit To:
Pursue partnerships with community groups and institutions to unite and expand the opportunities
for our community
Measures of Success:
-
Corporate Business Plan
12 | P a g e
Collaboration with the local school boards to proactively determine the location of future
school sites
Renewed process outlining the towns relationship with and funding opportunities related to
community groups
Collaboration with regional partners and non-profit organizations to offer affordable housing
opportunities
Enhanced community use of school sites supported by existing joint use agreements
-
Corporate Business Plan
13 | P a g e
ECONOMIC OPPORTUNITY
We Commit To:
Recognizing the importance of a strong business community and its link to a sustainable future
through local job creation and continued diversification of service sectors.
Measures of Success:
Updated Land Use Bylaw that promotes commercial growth and development along the
Highway 16A corridor
An engaged business community that sees opportunities to expand its services and product
offerings
Marketing and promotion that positions Stony Plain as a tourism destination and a business-
friendly community
Relationships with new industries that show synergies with existing, emerging and developing
industry.
Category Business Unit
Name Executive Summary Start Date
End Date
Corporate External Operating
Office of the CAO
CE-004.1 Economic Development Initiatives
In 2015 Council approved the development of a Target Sector Study & Marketing Plan. The study provided an analysis of our local economy and opportunities for investment attraction that would lead to growth of our non-residential tax base, as well as diversity the local economy with additional jobs, products and services. The study was presented to Council in September 2015 and was accepted for information. The following five key development opportunities emerged from the analysis. In many cases these opportunities are related to each other and their development will serve to reinforce the assets or qualities that draw residents and businesses to the community:
Support Activities for Energy and Extraction
Business and Professional Services
Health Care and Related Services
Local Food and Food Processing
Destination Shopping, Dining, Arts and Culture
Each of these targets is an existing or emerging sector with both immediate and long term prospects for development. In each case, Stony Plain faces competition from places in close proximity and/or more distant locations targeting similar niche
Jan 2016 Dec 2016
-
Corporate Business Plan
14 | P a g e
Category Business Unit
Name Executive Summary Start Date
End Date
opportunities, which needs to be considered in the approach. The study has provided a multi-year (2016 2020) marketing plan with recommendations for each target sector. The budget request will provide the necessary resources to begin the implementation of this study.
We Commit To:
Increasing awareness of the unique advantages our community offers potential investors and how to
align our efforts with regional economic initiatives.
Measures of Success:
A business sector analysis with recommendations to attract new and diverse business
opportunities to the community
Recommendations on regulatory processes, fees and taxes to maintain a competitive and
attractive climate for investment
Partnerships with local developers that market the community.
We Commit To:
Active pursuit of opportunities that support and match our priorities for a vibrant downtown core,
institutional development including, post-secondary opportunities, and cultural economy.
A decision on moving forward the Downtown Redevelopment Plan
Partnerships with local organizations such as Stony Plain & District Chamber of Commerce,
Community Futures Capital Region, and Norquest College that support and facilitate local
business vitality.
-
Corporate Business Plan
15 | P a g e
ENVIRONMENTALLY RESPONSIBLE
We Commit To:
Protect and manage our environmental impact by actively pursuing an integrated approach to our
operations.
Measures of Success:
Alignment of current development and building standards with the municipalitys
environmental initiatives.
A tool to monitor the municipalitys current environmental initiatives and determine
opportunities for enhancement and partnerships with the community
A database for brownfield development
Completion of Partners for Climate Protection: Milestone 5 which assesses the municipalitys
current environmental initiatives and provides direction for future initiatives.
We Commit To:
Working with the community to expand the reach of our efforts through education, programming and
service provisions that support a greener way of living.
Measures of Success:
Educational programming and promotion that progresses the towns environmental
initiatives.
Increased awareness of the towns water conservation programming, including the toilet
rebate program and home water kits
Enhanced inventory of community gardens
We Commit To:
The health of our natural environment and plan our growth and delivery of services to preserve and
support air quality, reduced greenhouse gas emissions, and efficient use of land, energy and water.
Measures of Success:
Implementation of development standards that require infrastructure to support multi-unit
waste collection.
Implementation of a water conservation study to support awareness building and educational
opportunities
-
Corporate Business Plan
16 | P a g e
Feasibility study in collaboration with the City of Spruce Grove and Parkland County for an
organic processing facility.
Support for dark skies and mitigation of unwanted light through corporate principles in
subdivision design and operations.
-
Corporate Business Plan
17 | P a g e
DEPARTMENT BUSINESS PLANS
Overview
The Department Business Plans reflect the activities of departments within the Town that help to fulfill
the Towns Strategic Plan and move the Town forward with effective operational services. The
operational services are guided by service delivery expectations within the Town and include
departmental operating and capital initiatives as well as service changes proposed for 2016, 2017 and
2018.
The department business plans are organized into four main departments: Office of the Chief
Administrative Officer (OCAO), Corporate Services (CS), Community and Protective Services (CAPS) and
Planning & Infrastructure (P&I).
The Office of the CAO is led by the Town Manager and oversees the Corporate Office including the
functional areas of Economic Development, Culture and Corporate Communications.
Corporate Services, Community & Protective Services and Planning & Infrastructure are led by general
managers with managers and supervisors overseeing the operations of sections within the departments.
Each department business plan includes the following components: identity statement; organizational
chart; full time equivalent (FTE) staffing summary; service changes; departmental operating and capital
initiatives and the fiscal plan.
Organizational Chart
The organizational charts represent the internal reporting structure of each department or section and
correlate to the FTE staffing summaries. The charts are not intended to reflect the level of authority and
accountability of each position or working relationships with third party agencies in the delivery of
services.
Positions that are proposed for 2016 - 2018 are reflected on the organizational charts in shaded boxes
and include the position name with the year they are proposed.
-
Corporate Business Plan
18 | P a g e
The following is the organizational structure of the Town:
Residents of Stony Plain
Town Council
Office of the CAO - Town Manager
Corporate Services
Financial Services
Legislative Services
Technology Services
Human Resource Services
Procurment & Assurance
Community & Protective Services
Community Services Programming
Facilities
Fire Services
Enforcement Services
Golf Course
Planning & Infrastructure
Planning
Engineering
Operations
Building Inspection
-
Corporate Business Plan
19 | P a g e
Identity Statement
The identity statement for each department was developed by the employees in that department during
the business planning process. The statements are intended to reflect the purpose for which the
department exists and the work they carry out on behalf of the Town.
Staffing Summary
The staffing complement associated with the delivery of services within each department is identified.
Staffing is expressed as Full Time Equivalents (FTE). The staffing summaries for each department include
proposed FTEs for 2016 2018. The Town of Stony Plain Full Time Equivalent per 1,000 residents is still
well under other municipalities in the province.
Analysis of Employees to Population - 2013
2013 2013 Population Employees/
Municipality Population FTEs per employee 1000 Pop
Devon 6,510 47 139 7.22
Morinville 8,569 63 136 7.35
Edson 8,646 64 135 7.40
Hinton 9,640 105 92 10.89
Yellowhead County 10,469 77 136 7.36
Lacombe 11,707 120 98 10.25
Wetaskiwin 12,525 107 117 8.54
High River 12,920 126 103 9.75
Brooks 13,676 91 150 6.65
Cold Lake 14,400 108 133 7.50
Beaumont 14,916 107 139 7.17
Stony Plain 15,051 95 158 6.31
Camrose 17,286 182 95 10.53
Cochrane 18,750 141 133 7.52
Okotoks 26,319 156 169 5.93
Leduc 27,241 252 108 9.25
Spruce Grove 27,875 218 128 7.82
Parkland County 30,568 209 146 6.84
Airdrie 49,560 315 157 6.36
Medicine Hat 61,180 1,074 57 17.55
St. Albert 61,466 585 105 9.52
Lethbridge 90,417 1,178 77 13.03
Strathcona County 92,490 1,319 70 14.26
Wood Buffalo 116,407 1,196 97 10.27
AVERAGE 119.94 8.97
-
Corporate Business Plan
20 | P a g e
From the Alberta Municipal Affairs website
http://www.municipalaffairs.alberta.ca/mc_municipal_profiles the latest statistics available are for
2014. The chart shows that the Town of Stony Plain has the second lowest staffing while being number
12 of 24 population wise.
In 2013, the Town of Stony Plain had 6.31 employees for every 1,000 population or stated another way,
every employee potentially served 158 residents. At todays population of 16, 127 and the FTE
employees of approximately 103.50, the population per employee shifted to 156 and there are 6.42
employees for every 1,000 population. The following chart shows the Town of Stony Plain Results in
comparison to the overall averages:
Population per employee
Employees/1,000 population
Stony Plain - 2013 158 6.31
Stony Plain 2015 156 6.42
2013 Average of municipalities under 20,000 population
126 8.18
2013 Average of entire sample 120 8.97
To come to the average of all municipalities under 20,000 population, the Town would have to add 1.86
employees for every 1,000 residents. This amounts to 30 FTE. (1.86 x 16.127).
-
Corporate Business Plan
21 | P a g e
The following schedule shows the proposed FTEs for the 2016 2018 Fiscal Plan years.
Proposed Position 2016 2017 2018 Office of the CAO Manager of Gov. Relations & Strategic Initiatives 1.0 Economic Development Assistant 1.0 Cultural Development Assistant 1.0 Corporate Services Payroll clerk from time to full time .5 Accounts Clerk 1.0 GIS Coordinator (July start) .5 .5 Staff Development Coordinator 1.0 Corporate Planner 1.0 FOIP Coordinator 1.0 Human Resources Administrative Assistant 1.0 Procurement & Assurance Clerk 1.0 Community & Protective Services Firefighter 1.0 Community Peace Officer 1.0 Community Services Program Manager 1.0 Operator I Facilities 2.0 Community Services Program Coordinator 1.0 Facilities Coordinator 1.0 Planning & Infrastructure Apprentice Mechanic Small Fleet 1.0 Operator I Roads 1.0 Integrated Pest Management Operator 1.0 Proposed Annual Increase in FTEs 5.0 9.5 6.0
-
Corporate Business Plan
22 | P a g e
The following table is a summary of the total FTEs, including proposed positions for 2016 2018.
Approved 2015
Proposed 2016
Proposed 2017
Proposed 2018
Office of the CAO
Town Managers Office 2.0 2.0 3.0 3.0
Economic Development 1.0 1.0 1.0 2.0
Cultural Development 1.0 1.0 1.0 2.0
Corporate Communications 2.0 2.0 2.0 2.0
6.0 6.0 7.0 9.0
Corporate Services
General Managers Office 1.0 1.0 2.0 2.0
Financial Services 9.5 11.0 11.0 11.0
Legislative Services 3.6 3.6 4.6 4.6
Technology Services 3.0 3.5 4.0 4.0
Human Resource Services 3.0 3.0 4.0 5.0
Procurement & Assurance Services 1.0 1.0 1.0 2.0
21.1 23.1 26.6 28.6
Community & Protective Services
General Managers Office 2.0 2.0 2.0 2.0
Community Services Programming 2.83 3.83 3.83 3.83
Facilities 12.0 12.0 14.0 15.0
Fire Services 6.0 7.0 7.0 7.0
Enforcement Services 11.5 12.5 12.5 12.5
Golf Course 5.0 5.0 5.0 5.0
39.33 42.33 44.33 46.33
Planning & Infrastructure
General Manager 1.0 1.0 1.0 1.0
Planning 7.0 7.0 7.0 7.0
Engineering 2.0 2.0 2.0 2.0
Operations 25.0 25.0 28.0 28.0
Building Inspection 2.0 2.0 2.0 2.0
37.0 37.0 40.0 40.0
Total Full Time Equivalents 103.43 108.43 117.93 123.93
-
Corporate Business Plan
23 | P a g e
Departmental Initiatives and Service Changes
Department business plans include summaries of the departmental operating and capital initiatives,
service changes and staffing service changes that are proposed for 2016 and those planned for 2017 and
2018. Additional details of the initiatives and service changes are located in the New Initiatives and
Service Changes of this Corporate Plan document.
Fiscal Plan
The department fiscal plans include the status quo budget and revenue and expenses associated with
the delivery of services, new initiatives and service changes proposed in this corporate plan. The status
quo budget reflects the financial activities for the delivery of core services at current service levels and
current delivery methods. The following items are included in the status quo budget:
Growth related increases in materials and supplies
Growth related increases in repairs and maintenance
Capital lifecycle costs (capital lifecycle plans maintain and replace existing assets in their similar
form e.g. replacement vehicle, repaving etc.)
Inflation costs
Cost of Living adjustments
Performance based merit adjustments
Collective agreement costs
Items not included in the status quo budget:
Rate increases for taxes
Rate increases for utilities
Rate increases for other user fees
New staffing positions
-
Corporate Business Plan
24 | P a g e
Office of the CAO
The Town Manager is responsible for the financial activities of the Office of the CAO.
2015 2016 2017 2018
Budget Budget Budget Budget
Revenue
Town Manager's Office - - - -
Corporate Communications - - - -
Economic Development 60,000 - - -
Promo 20,000 20,000 20,000 20,000
Cultural Development 39,500 - - -
Total 119,500 20,000 20,000 20,000
Expenditure
Office of the CAO 674,131 771,752 934,962 1,000,889
Corporate Communications 149,800 166,700 167,355 233,014
Economic Development 114,000 146,250 118,400 120,650
Promo 30,000 30,000 30,000 30,000
Cultural Development 377,967 404,833 409,502 421,249
Total 1,345,898 1,519,535 1,660,219 1,805,802
Surplus/Deficit
Office of the CAO (674,131) (771,752) (934,962) (1,000,889)
Corporate Communications (149,800) (166,700) (167,355) (233,014)
Economic Development (54,000) (146,250) (118,400) (120,650)
Promo (10,000) (10,000) (10,000) (10,000)
Cultural Development (338,467) (404,833) (409,502) (421,249)
Total (1,226,398) (1,499,535) (1,640,219) (1,785,802)
-
Corporate Business Plan
25 | P a g e
Corporate Services
The General Manager of Corporate Services is responsible for the financial activities of this department.
2015 2016 2017 2018
Budget Budget Budget Budget
Revenue
General Manager's Office - - - -
Financial Services 346,200 51,500 51,500 51,500
Legislative Services 225,880 - 28,800 -
Human Resource Services 44,500 69,000 31,700 44,700
Technology Services 30,000 80,000 - -
Total 646,580 200,500 112,000 96,200
Expenditure
General Manager's Office 279,482 286,390 377,557 418,089
Financial Services 1,430,417 1,240,078 1,447,352 1,308,883
Legislative Services 632,669 442,357 638,574 501,333
Human Resource Services 459,365 424,439 457,040 532,768
Technology Services 538,112 755,958 762,588 765,903
Total 3,340,045 3,149,222 3,683,111 3,526,976
Surplus/Deficit
General Manager's Office (279,482) (286,390) (377,557) (418,089)
Financial Services (1,084,217) (1,188,578) (1,395,852) (1,257,383)
Legislative Services (406,789) (442,357) (609,774) (501,333)
Human Resource Services (414,865) (355,439) (425,340) (488,068)
Technology Services (508,112) (675,958) (762,588) (765,903)
Total (2,693,465) (2,948,722) (3,571,111) (3,430,776)
-
Corporate Business Plan
26 | P a g e
Community and Protective Services
The General Manager of Community and Protective Services is responsible for the financial activities of
this department.
2015 2016 2017 2018
Revenue Budget Budget Budget Budget
General Manager's Office 315,000 290,000 205,000 205,000
Programming 100,000 97,000 97,000 97,000
Community Services Capital 13,064,173 90,000 300,000 175,000
Programming Capital - 80,000 - -
Facilities 663,930 626,974 626,974 676,974
Fire Services 845,322 303,600 222,600 222,600
Fire Services Capital - 65,000 100,000 100,000
Municipal Enforcement 85,229 93,000 78,000 78,000
Municipal Enforcement Capital - 70,000 - -
Golf Course 1,709,771 1,637,300 1,642,300 1,642,300
Golf course Capital 77,500 15,000 - -
Municipal Policing 2,025,260 2,624,285 2,114,260 2,024,260
Total 18,886,185 5,992,159 5,386,134 5,221,134
Expenditure
General Manager's Office 2,498,832 2,403,671 2,424,832 2,473,817
Programming 321,546 426,825 438,979 513,223
Community Services Capital 13,164,157 90,000 300,000 675,000
Programming Capital - 80,000 - -
Facilities 2,456,269 2,812,903 3,199,619 3,239,389
Fire Services 2,360,785 1,928,908 2,114,726 2,008,785
Fire Services Capital - 65,000 100,000 100,000
Municipal Enforcement 584,501 702,254 709,678 725,791
Municipal Enforcement Capital - 70,000 - -
Golf Course 1,900,094 1,888,829 1,992,333 1,967,411
Golf course Capital 77,500 15,000 - -
Municipal Policing 3,942,602 4,563,903 4,925,169 4,928,365
Total 27,306,286 15,047,293 16,205,336 16,631,781
Surplus/Deficit
General Manager's Office (2,183,832) (2,113,671) (2,219,832) (2,268,817)
Community Services Programming (221,546) (329,825) (341,979) (416,223)
Community Services Capital (99,984) - - (500,000)
Programming Capital - - - -
Facilities (1,792,339) (2,185,929) (2,572,645) (2,562,415)
Fire Services (1,515,463) (1,625,308) (1,892,126) (1,786,185)
Fire Services Capital - - - -
Municipal Enforcement Services (499,272) (609,254) (631,678) (647,791)
Municipal Enforcement Capital - - - -
Golf Course (190,323) (251,529) (350,033) (325,111)
Golf course Capital - - - -
Municipal Policing (1,917,342) (1,939,618) (2,810,909) (2,904,105)
Total (8,420,101) (9,055,134) (10,819,202) (11,410,647)
-
Corporate Business Plan
27 | P a g e
Planning & Infrastructure
The General Manager of Planning & Infrastructure is responsible for the financial activities of this
department.
2015 2016 2017 2018
Budget Budget Budget Budget
Revenue
General Manager's Office 996,316 780,450 736,950 688,650
Planning Capital 4,274,173 15,960,000 18,284,294 5,448,995
Engineering - - - -
Operations 9,293,758 10,117,220 10,977,587 11,298,794
Operations Capital 607,000 527,500 345,000 597,000
Building Inspection - - - -
Total 15,171,247 27,385,170 30,343,831 18,033,439
Expenses
General Manager's Office 1,828,491 1,719,017 2,137,983 2,146,005
Planning Capital 4,274,173 15,960,000 22,659,101 5,448,995
Engineering - - - -
Operations 17,047,839 18,827,480 20,824,029 21,925,695
Operations Capital 607,000 527,500 520,000 922,000
Building Inspection - - - -
Total 23,757,503 37,033,997 46,141,113 30,442,695
Surplus/Deficit
General Manager's Office (832,175) (938,567) (1,401,033) (1,457,355)
Planning Capital - - (4,374,807) -
Engineering - - - -
Operations (7,754,081) (8,710,260) (9,846,442) (10,626,901)
Operations Capital - - (175,000) (325,000)
Building Inspection - - - -
Total (8,586,256) (9,648,827) (15,797,282) (12,409,256)
-
Department Business Plans
28 | P a g e
Department Summaries
Office of the CAO
The Chief Administrators Office is led by the Town Manager and comprises the functions of:
Economic Development
Cultural Development
Corporate Communications
Executive support for Mayor and Council
Identity Statement
The Office of the Chief Administrative Officer is a team of creative, enthusiastic and respectful leaders,
who anticipate, collaborate, and innovate.
-
Department Business Plans
29 | P a g e
Organizational Chart
Full Time Equivalent Staffing Summary
Approved 2015
Proposed 2016
Proposed 2017
Proposed 2018
Town Managers Office 2.0 2.0 3.0 3.0
Economic Development 1.0 1.0 1.0 2.0
Cultural Development 1.0 1.0 1.0 2.0
Corporate Communications 2.0 2.0 2.0 2.0
6.0 6.0 7.0 9.0
Town Manager
Manager of Government Relations & Strategic
Initiatives (2017)
Economic Development Officer
Economic Development Assistant (2018)
Cultural Development Officer
Cultural Development Assistant (2018)
Corporate Communications Officer
Corporate Communications Assistant
Executive Assistant
-
Department Business Plans
30 | P a g e
Department Initiatives and Service Changes
Category Name Executive Summary Start Date End Date Department Operating
DP-018.1 Economic Development Strategic Plan Update
In 2012 Council approved the implementation of the Economic Development Strategy and Action Plan. This strategy provided a strong foundation and focus for economic development services. Since 2012, the strategy has been diligently implemented through administration, with guidance from the Growth and Commerce Committee, Council and community stakeholders. With an update of the Economic Development Strategic Plan in 2016, there is further opportunity to strengthen and build on the goals and outcomes of this key element of the Town services.
Jan 2016 Dec 2016
Service Changes Staffing
SCS-046.1 Manager of Government Relations & Strategic Initiatives
This position would report to the CAO and oversee the economic development, cultural development and communication functions. The growth of the community and maturation of the organization requires a greater focus on advocacy and policy development with other orders of government and our municipal partners at the sub-regional and regional basis. This position will provide leadership to the function areas within the OCAO, working with staff to create and implement functional strategies and work plans. The position will guide, support and implement the government relations and advocacy function of the organization flowing from direction of Council and CAO. The position will also play a key role in leading or supporting projects and initiatives deemed strategic and/or corporately significant. This service change will ensure clear support and leadership for high profile initiatives and function areas, furthering the Towns ability to implement key strategies and projects closely linked to the mid-term goals of Council and the long term vision of the community.
Jan 2017
Department Operating
DP-029.1 Website Redesign
The Towns website continues to be a vital tool in getting key messaging out to the residents of Stony Plain. Improving the Towns website is crucial to the Towns commitment to engaging with the public.
Jan 2018 Dec 2018
Service Changes Staffing
SCS-049.1 Economic Development Assistant
This service change is to create an additional full time person that reflects the increasing role of economic development services for the Town of Stony Plain. Economic Opportunity is one of the five themes of the Town of Stony Plain Strategic Plan 2015 2017. With the implementation of the 2012 Economic Development Strategy & Action Plan, the role of this area will continue to expand in an effort to generate commercial and industrial development.
Jan 2018
Service Changes Staffing
SCS-050.1 Cultural Development Assistant
This service change is to create an additional full time position that reflect the increasing role of cultural development services for the Town. Cultural development remains a key priority for the Town and clearly links to the community
Jan 2018
-
Department Business Plans
31 | P a g e
development that is a significant aspect of Uniquely Stony Plain. Consideration of the implementation of the Cultural Master Plan and a required update to this plan will continue to require dedicated resources above what is currently available. This position will further support ongoing tourism related initiatives that currently reside in this function.
-
Department Business Plans
32 | P a g e
Corporate Services
Corporate Services is led by the General Manager of Corporate Services and encompasses the following
functions:
Financial Services
Legislative Services
Human Resource Services
Technology Services
Procurement and Assurance Services
Identity Statement
Corporate Services exists to provide excellence in internal
and external customer service. Alignment with the strategic
priorities of the organization is fundamental to our success.
Municipal best practices are delivered with a focus on
legislative compliance, integrity and financial responsibility.
Excellent service is made possible through collaboration
and future capacity building.
From this identity statement the following objectives can be
determined which guide the work of all functional areas:
Excellence in Customer Service
Strategic Alignment
Progressive and Responsible Practices
Collaboration
Continuous Personnel Development
-
Department Business Plans
33 | P a g e
Organizational Chart
General Manager of Corporate Services
Manager of Financial Services
Financial Accounting Supervisor
Property Tax Clerk
Utilities Clerk
Accounts Payable
Clerk
Accounting Clerk (2016)
Customer Serivice Clerk (2)
Accountant (2)
Payroll Clerk (.5) Changing to full time in 2016
Manager of Legislative Services
Legislative Coordinator
FOIP Coordinator (2017)
Legislative Clerk
Corporate Recording Secretary (.6)
Manager of Human Resource Services
Human Resources Coordinator
Occupational Health & Safety Coordinator
Staff Development Coordinator (2017)
Human Resources Administrative Assistant
(2018)
Manager of Technology Services
Technology Services Coordinator
GIS Technologist (mid 2016)
IT Technician
Procurement & Assurance Coordinator
Procurement & Assurance Clerk (2018)
Corporate Planner (2017)
-
Department Business Plans
34 | P a g e
Full time Equivalent Staffing Summary
Approved 2015
Proposed 2016
Proposed 2017
Proposed 2018
General Managers Office 1.0 1.0 2.0 2.0
Financial Services 9.5 11.0 11.0 11.0
Legislative Services 3.6 3.6 4.6 4.6
Technology Services 3.0 3.5 4.0 4.0
Human Resource Services 3.0 3.0 4.0 5.0
Procurement & Assurance Services 1.0 1.0 1.0 2.0
21.1 23.1 26.6 28.6
Department Initiatives and Service Changes
Category Name Executive Summary Start Date End Date Department Operating
DP-016.1 Business Continuity and Disaster Recovery
In an effort to maintain an expected level of service to the residents, members of Council and to staff in the event of a catastrophic failure to our systems, the Town of Stony Plain should purchase an appliance that would replicate all Town data to an offsite location. Current business best practice dictates that all corporate data should be housed offsite at a location not less than 50 km from the epicenter of the main data store.
Jan 2016 Dec 2016
Department Operating
DP-017.1 Lotus Notes to Microsoft Exchange Migration
As the industry leader for email systems, Microsoft Exchange offers multiple benefits and therefore should be considered as an alternative to our existing Lotus environment. Offering easier management and control, integration with Active Directory (works as a single sign on between our network and other software), integration with other programs used by the Town, and finally simplified connectivity to the smartphones using ActiveSync. The Town would capitalize on these benefits and could see the end user experience enhanced due to familiarity.
Jan 2016 Dec 2016
Service Changes Staffing
SCS-037.1 Additional .5 FTE Payroll Clerk
This service change initiative involves increasing the hours of the payroll position to reflect the increase in the staffing of the Town of Stony Plain. As per the consultants report: The Path Forward (2015 and Beyond) An Introspective Exercise commissioned by the Town Manager and the Director of Corporate Services in early 2015, it was indicated that the payroll clerk should shift from half time to full time to maintain a ratio of one payroll staff member to every 100 150 permanent employees. This addition will be a job share situation to facilitate built in back up for absences etc.
Jan 2016
Service Changes
SCS-038.1 Accounts Clerk
An Accounts Clerk position is required to provide assistance to the Utilities Clerk and Tax Clerk
Jan 2016
-
Department Business Plans
35 | P a g e
Category Name Executive Summary Start Date End Date Staffing positions to ensure that customer service levels are
maintained. This position is funded 50% by the Utilities portion of the budget and 50% by the General Tax Base.
Service Changes Staffing
SCS-039.1 GIS Coordinator
The Towns Geographic Information System (GIS) has taken a back seat to other priorities for the Town. While the GIS has now been introduced to certain departments; Corporate Services, Planning & Infrastructure and Community & Protective Services, only select individuals can either access, manipulate or view mapping information. The hiring of a GIS Coordinator would ensure that continued development and distribution of GIS would occur and information would be available to all internal and external clients.
Jul 2016
Capital CAP-061.1 Meeting Room Upgrade AV Golf Course
Part of the work of the Technology Replacement Team was to identify any needs or requirements that are currently not being served by the Town. One of the items identified was that use of Smart technology within our meeting rooms and the enhancement of the conference aspect of meeting rooms. This project would bring enhancement to the Golf Course Banquet Room.
Jan 2016 Feb 2016
Capital CAP-063.1 Meeting Room Upgrade - AV Fire Hall
Part of the work of the Technology Replacement Team was to identify any needs or requirements that are currently not being served by the Town. One of the items identified was that use of Smart technology within our meeting rooms and the enhancement of the conference aspect of meeting rooms. This project would bring enhancement to the Chief Dan Badry Training Room.
Jan 2016 Feb 2016
Capital CAP-064.1 Meeting Room Upgrade - AV Public Works
Part of the work of the Technology Replacement Team was to identify any needs or requirements that are currently not being served by the Town. One of the items identified was that use of Smart technology within our meeting rooms and the enhancement of the conference aspect of meeting rooms. This project would bring enhancement to the Annex Training Room.
Jan 2016 Feb 2016
Department Operating
DP-019.1 Capture of Corporate Images Project
This project involves the scanning and categorization of all corporate images, whether archive or current, for the purpose of record capture and easy search capability for use in Town documents, etc. This project will be a one-time contract that will facilitate images being readily available for users throughout the organization for Town-sanctioned projects. The current system of housing images on a regular computer drive does not allow for easy search capability or security of images. The Town has already experienced a corruption and loss of several images due to a virus on a staff computer. Capturing all images within the information management program and creating search indexes that will allow for easy selection of photos for projects will preserve these images and save staff time.
Jan 2017 Dec 2017
-
Department Business Plans
36 | P a g e
Category Name Executive Summary Start Date End Date Department Operating
DP-020.1 Digitalization of Subdivision Files
The project involves the scanning and indexing of Planning & Infrastructure subdivision files that were relocated to the Town Office vault from the upstairs file room. These records were moved because additional workspace was needed on the second floor and, as a result, the upstairs file room was repurposed. This project will be a one-time contract that will facilitate records being readily available for users throughout the organization, especially the Planning & Infrastructure staff.
Jan 2017 Dec 2017
Department Operating
DP-021.1 Digitalization of Public Works Files
This project involves the scanning, indexing and viewing of Public Works files such as maps, drawings and multi-media (ie. Videos) records. This project could be broken into manageable steps using a contracted service. One step is digitalization of these records for the purposes of business continuity, identification of important Town infrastructure, readily accessible information for users throughout the organization, especially Operations staff when completing repairs. Another step is to make the information that is on various multi-media readable regardless of type of medium and format.
Jan 2017 Dec 2017
Department Operating
DP-023.1 Planning Modules for ERP system
The addition of three modules to the Towns Enterprise Resource Planning software (Bellamy) will enhance the information available to the organization by using a system that is integrated with the planning processes. This allows for the sharing of data, and for the opportunity to build more effective reporting and planning capacity for the organization. The modules being considered are the Building Permits Module, the Planning Module and the Mobile Inspections Module.
Jan 2017
Service Changes Staffing
SCS-040.1 Staff Development Coordinator
The purpose of this position is strategic in nature and encompasses the concept of Workforce Planning in preparation for the future demands of a growing community. This individual would be involved in the coordination of all development opportunities for staff from initial orientating and onboarding, through workplace training, to preparation for retirement. This position would work with the Manager of Human Resource Services and the Senior Leadership Team to create a base level of employee training for the organization that embraces strategic intent and corporate culture creation. This position is suggested in response to the Strategic Plan commitment statement and measure of success as follows: We commit to.Cultivate a strong organizational structure and processes to support effective and efficient service delivery.Meaningful people policies to support and invest in an engaged, productive and effective workforce. This position is also integral to fulfillment of the
Jan 2017
-
Department Business Plans
37 | P a g e
Category Name Executive Summary Start Date End Date Human Resources Strategy 2015 2018.
Service Changes Staffing
SCS-044.1 FOIP Coordinator
This staffing initiative involves adding a FOIP Coordinator to respond to official Freedom of Information and Access to Privacy Act requests and to other information requests under the Legislative Services function. The number and magnitude of FOIP requests continues to increase with each business year.
Jan 2017
Service Changes Staffing
SCS-045.1 Corporate Planner
In 2015, the Town of Stony Plain introduced an enterprise wide Corporate Planning process. This process is being handled by the Corporate Services department. In order to give the process and the performance measures framework the attention it deserves and to allow the Director Corporate Services to participate in the process at the same level of exposure as the other Directors, a Corporate Planner is proposed for 2017. The timing of this service change for staffing will allow the Corporate Planning process to run for two full years and will allow the Corporate Planner to participate in the development of the Performance Measures Framework. This position will facilitate the Strategic Planning sessions with Council, the Business Planning sessions with Administration, the Corporate Planning prioritization process etc. This individual could also network with planners from other municipal environments to work on joint planning processes for the community. The Corporate Planner would work closely with the Finance area to facilitate development of the planning documents. The Corporate Planner would take the lead role on the Corporate Plan and the Finance area would take the lead on the Fiscal Plan.
Jan 2017
Service Changes Staffing
SCS-053.1 Human Resources Administrative Assistant
This position is proposed to provide administrative support to the Manager and three coordinators in the Human Resource Services functional team.
Jan 2018
Service Changes - Staffing
SCS-054.1 Procurement & Assurance Clerk
This position is proposed to provide support to the Procurement & Assurance Coordinator for the procurement, insurance and risk management activities of the organization.
Jan 2018
-
Department Business Plans
38 | P a g e
Community & Protective Services
Community & Protective Services is led by the General Manager of Community & Protective Services
and encompasses the following functions:
Community Services
Facilities
Fire Services
Municipal Enforcement
RCMP liaison
Golf Course
Handi Bus
Identity Statement
A diverse, progressive and dedicated team
committed to the delivery of quality, safe and
efficient programs and services that meet the
growing needs of our community.
-
Department Business Plans
39 | P a g e
Organizational Chart
General Manager of Community & Protective
Services
Program Manager (2016) Community Services
Coordinator - one more to be added in 2018
Administrative Assistant
Facilities Manager
Facilities Coordinator - one more to be added in 2018
Pool Manager
Operator II - Arena/Sportsfields
Operator I (3)
Operator II - Projects/Special Events
Operator I (4)- two more to be added in 2017
Fire Chief
Deputy Fire Chief (2)
Fire Fighter (3) one more to be added in 2016
Volunteers (40)
Peace Officer Supervisor
Peace Officers (3) one more to be added in 2016
Municipal Enforcement Clerk
Clubhouse Manager
Pro Shop Manager
Golf Course Superintendent
Assistant Superintendent
Shop Mechanic
Handi Bus Dispatcher Drivers (.83)
-
Department Business Plans
40 | P a g e
Full time Equivalent Staffing Summary
Approved 2015
Proposed 2016
Proposed 2017
Proposed 2018
General Managers Office 2.0 2.0 2.0 2.0
Community Services Programming 2.83 3.83 3.83 4.83
Facilities 12.0 12.0 14.0 15.0
Fire Services 6.0 7.0 7.0 7.0
Municipal Enforcement Services 5.0 6.0 6.0 6.0
Golf Course 5.0 5.0 5.0 5.0
Municipal Policing Staff (incl .5 Criminal Analyst) Currently Report to Federal Govt. supervisor
6.5 6.5 6.5 6.5
39.33 42.33 44.33 46.33
Department Initiatives and Service Changes
Category Name Executive Summary Start Date End Date Department Operating
DP-014.1 Regional Recreation Indoor Facility Study Rewrite
In 2008 the completion of a Regional Recreation Indoor Facility Study was completed and tabled with the Tri-Municipal Councils. The study was completed by RC Strategies and provided input for the future development of indoor recreation and culture facilities. Regional municipal partners have agreed that a rewrite of the document is required as regional priorities continue to grow.
Jan 2016 Dec 2016
Department Operating
DP-015.1 Rotary Park Master Plan
Rotary Park is the gateway to the community. The park is in need of a modernization and improvement plan. The park is a well-used asset and has the potential to provide enhanced service to the community.
Jan 2016 Dec 2016
Service Change Staffing
SCS-034.1 Firefighter
The Stony Plain Fire Department (SPFD) has been built on the hard work and dedication of our Paid on Call (POC) firefighters. As a customer service focused organization, which strives satisfy the needs of internal and external clients, the system has served the community well. Today with increased demands for service, training and safety requirements; the system has some strain. Another full time fire fighter would balance the crew system and ensure minimum staffing of 5 responders during the daytime hours when POC responders are limited. The goal of adding FT staff at regular intervals is not to replace the current POC system but to enhance and provide relief to the POC firefighters during day time response. By taking some of the daytime load off of the current POC responders, it will allow them to extend their service careers by reducing potential burnout, thus maintaining the current composite department that serves the community today, while still guaranteeing sufficient number of firefighters to
Jan 2016
-
Department Business Plans
41 | P a g e
Category Name Executive Summary Start Date End Date respond to increasing calls for service.
Service Change Staffing
SCS-035.1 Community Peace Officer
This service change initiative involves increasing the Enforcement Services by one Community Peace Officer level 1 position. As a result of a meeting with the consultant currently conducting a review of the Community Services department, it was suggested a municipality this size should have 2 more Community Peace Officer than it currently employs.
Jan 2016
Service Change Staffing
SCS-036.1 Community Services Program Manager
The delivery of program service by the Community Services department is increasing and demand for additional service will increase as the community grows in population. Efficiency of department activities will be improved with the addition of this new position. It will allow the department to increase the efficiency of the organizational management and provide a higher level of internal and external customer service
Jan 2016
Capital CAP-058.1 Enforcement Services Control Vehicle
The Town of Stony Plain is a growing community. Currently 4 officers are sharing 2 patrol vehicles, an additional vehicle will provide additional patrol coverage; will maintain at least 2 in service patrol vehicles (scheduled service, breakdowns). Included in the 2016 corporate planning is the addition of a Community Peace Officer Level 1 position. The additional position will require the purchase of a third patrol vehicle to support enforcement activities and provide operational efficiencies.
Jan 2016 Dec 2016
Capital CAP-062.1 Old Fire Hall Roof Replacement
In 2006, administration retained a consultant team to perform a condition report of the Old Fire Hall and identify approximate cost estimates to upgrade the facility where deficient, dependent on future use. The original building was constructed in 1954. The existing building area is approximately 4,315 square feet. The roof structure is open web steel joists with a wood deck and minimal `strammit` type insulation, which provides minimal insulating value. At some point, additional blow in insulation was added to increase the R value of the roof structure. At that time a new metal roof was added to the building. At the time of the condition report, there was some water leakage at the penetrations through the metal roof. Many roof repairs have been undertaken in the ten years since the initial condition report. The roof is now beyond repair state and requires replacement.
Jan 2016 Dec 2016
Service Changes Staffing
SCS-047.1 and SCS 048.1 Operator I Facilities (2)
The addition of the events facility at Heritage Park will require additional staff resources to manage the maintenance and delivery of event services at the building. The facilities division of the Community and Protective Services department will expand their overall role with the maintenance of Town owned facilities
Jan 2017
Capital CAP-068.1 Stony Plain Fire Training
This project will see the creation of a fire training grounds for the Stony Plain Fire Department
Jan 2017 Dec 2017
-
Department Business Plans
42 | P a g e
Category Name Executive Summary Start Date End Date Ground Phase I (SPFD). SPFD strives to meet and maintain NFPA
1001 standards: currently at 67% compliance. Currently training is done through an agreement with Parkland County Fire Services (PCFS). The County Services Building has a small area dedicated to fire training with props and a smoke house trailer that we use on a regular basis. PCFS is moving its training operations to the Acheson Fire Hall. This increases travel distance and response times. The department has grown to a level where training grounds are a necessity to maintain current skills and develop new ones. This will ensure that the department is able to deliver the highest and safest level of response to our residents. Phase one is for site preparation and grading, installation of a water line, compaction, gravel, paving, roadway access and portable washroom facilities.
Service Changes Staffing
SCS-051.1 Community Services Program Coordinator
The Town plays an active role in the delivery of programs to the community. The current program delivery is event based. In the next two years the department is trending to providing more direct programs to meet community needs. An additional FTE will meet the planning and programming service levels anticipated in 2018.
Jan 2018
Service Changes Staffing
SCS-052.1 Facilities Coordinator
The Community and Protective Services departments facilities branch will be assuming the maintenance management of all Town owned buildings in the next two (2) years. Two (2) facility operations teams will be developed with separate areas of focus, facility operations and events and projects. An additional Facilities Coordinator position will lead one (1) of the two (2) operations teams.
Jan 2018
Capital CAP-073.1 Stony Plain Fire Training Ground Phase II
This project will see the continuation from Phase I of the project. Phase two is for additional training equipment, fencing, concrete, mobile home; seas can storage and VE pad.
Jan 2018 Dec 2018
Capital CAP-074.1 Glenn Hall Parking Lot Paving
This project will add asphalt to the gravel parking area of the Glenn Hall Arena. The asphalt surface will improve the drainage of the site, improve the customer experience during wet weather and assist with the cleanliness of the building and integrity of the ice and flooring surfaces. The addition of asphalt will also assist with the maintenance of dust and debris during the summer season improving the cleanliness of the surrounding residential area and ball diamond complex.
Jan 2018 Dec 2018
-
Department Business Plans
43 | P a g e
Planning & Infrastructure
Planning & Infrastructure is led by the General Manager of Planning & Infrastructure and encompasses
the following functions:
Municipal Planning
Engineering
Operations
Identity Statement
Our Department wants to be:
Forward thinking and masters of change, both in terms of
the communitys physical growth and development as well
as in our professional environment.
Problem solvers who are able to evaluate, provide options,
formulate recommendations and promptly make decisions.
The model of a collaborative, respectful and safe group,
known for consistency, integrity and reliability. We take
pride in our work and enjoy what we do.
Mindful of employee health and welfare as well as
providing training and education.
The purpose of the Planning and Infrastructure Department is:
To protect the public interest while guiding and facilitating
the physical and social development and maintenance of
the community.
To provide meaningful and appropriate customer service
for both co-workers and external customers. We strive to
do this through the provision of public education.
To be process managers who develop efficient systems
and procedures for core competencies.
-
Department Business Plans
44 | P a g e
Organizational Chart
General Manager of Planning & Infrasrtructure
Manager of Planning
Senior Development Officer
Development Officer
Planning & Development Coordinator
Administrative Assistant
Reception Clerical
Sustainability Planner
Manager of Engineering Engineering Technician
Manager of Operations
Operations Supervisor Utilities/Roads
Operator II
HD Equipment Operator (4)
Utility Tech (6)
Operator I - Roads (2017)
Operatings Supervisor Parks/Horticulture
Operator II (2)
Operator I (5)
Recycle Center Staff (2)
Integrated Pest Managment Operator (2017)
HD Auto Mechanic (2) Apprentice Mechanic Small
Fleet (2017)
Administrative Assistant (2)
Senior Building Safety Codes Officer
Building Safety Codes Technician
-
Department Business Plans
45 | P a g e
FTE Staff Summary
Approved 2015
Proposed 2016
Proposed 2017
Proposed 2018
General Manager 1.0 1.0 1.0 1.0
Planning 7.0 7.0 7.0 7.0
Engineering 2.0 2.0 2.0 2.0
Operations 25.0 25.0 28.0 28.0
Building Inspection 2.0 2.0 2.0 2.0
37.0 37.0 40.0 40.0
Department Initiatives and Service Changes
Category Name Executive Summary Start Date End Date Capital CAP-059.1 2016
Infrastructure Rehabilitation Project
The Town recognizes the need to protect the investment it has in its existing municipal infrastructure including storm and sanitary sewer systems, water main network, roads and sidewalks. The condition of these facilities deteriorates with age or cannot provide the capacity needed to adequately service the needs of the community. In 2010, the Town developed a 10 year Infrastructure Rehabilitation Program in order to prioritize repairs or replacement of the existing systems to maintain the acceptable level of service required. Since 2010, the program has been the basis for establishing the annual capital rehabilitation projects. The priorities that are identified in the 10 year Capital Program for 2016 are:
Asphalt surface overlay 44th
Avenue (43
rd Street to St. Andrews Drive)
Concrete Sidewalk curb and gutter - miscellaneous spot repairs on 44
th Ave.
Storm Sewer 44th
Avenue (43 St. to Whispering Waters Creek)
Sanitary Sewer 44th
Avenue (45th
Street to Whispering Waters )
Jan 2016 Dec 2016
Capital CAP-060.1 - Electronic Messaging Signage
This initiative seeks the purchase of two electronic messaging signs. The electronic message sign boards would be used to inform the public of various maintenance/operational activities requiring their cooperation or just for information.
Jan 2016 Dec 2016
Department Operating
DP-022.1 Urban Forestry Program
The urban forest is a key component of the infrastructure of a modern municipality. Trees are an asset that requires planning, maintenance, protection and investment. There are many trees on municipal property that are the responsibility of the municipality. The trees provide many benefits to the Town and the residents over a long period of time if they are maintained, protected and managed.
Jan 2017 Dec 2017
-
Department Business Plans
46 | P a g e
Category Name Executive Summary Start Date End Date This initiative calls for the services of a consultant to develop and identify the resources needed for the start-up of an active system of professional management of the trees on public property within the Town of Stony Plain as well as a public education and awareness program. As with other assets, the urban forest requires that we first understand what we currently have, then determine a vision for where we want to go and identify actions and goals that will assist in getting to the vision. Finally, we will need to implement the actions through a service change in staffing in order to properly care for the urban forest of Stony Plain.
Department Operating
DP-024.1 Area Redevelopment Plan for Areas of Transition
The Municipal Development Plan identifies three Areas of Transition that need a plan that states the communitys future goals and objectives for the areas and will guide redevelopment decision-making and municipal investment in infrastructure. The Area Redevelopment Plan is a key to implementing the Municipal Development Plans policies regarding the future development of Stony Plain. The Areas of Transition have the oldest properties in Stony Plain that have the greatest potential for redevelopment. The Town will be faced with making decisions regarding the redevelopment of these properties increasingly over the next 20 years and will be required to re-invest in infrastructure and facilities to accommodate growth. The Area Redevelopment Plan will provide a broad plan for guiding decision-making regarding redevelopment of private land and investment in infrastructure and facilities so that the Town achieves the goals and vision set forth in the Uniquely Stony Plain Municipal Development Plan 2013 and the Strategic Plan 2015 2017.
Jan 2017 Dec 2017
Department Operating
DP-025.1 Glenn Hall Arena and Park Area Masterplan
This project would prepare a masterplan for the enhancement, improvements and expansion of the parks and recreation facilities on the Towns property on and around the Glenn Hall Arena, ball diamonds, curling rink, outdoor pool and spray park over the next 10-15 years.
Jan 2017 Dec 2017
Department Operating
DP-026.1 Work Flow Process
Eventually the Planning function of the department would like to offer online access to apply, pay for and receive building permits 24/7 through e-Permitting. Typically such a system offers:
Online access to apply, pay for and receive building permits 24/7
Automated inspection scheduling by phone or computer
Comprehensive permit tracking and data
Jan 2017 Dec 2017
-
Department Business Plans
47 | P a g e
Category Name Executive Summary Start Date End Date collection
Electronic plan submission and review The most effective systems recognize the actual processes within the department which are unique to each organization. The purpose of this project is to identify and document the actual work flow and to provide an opportunity for staff to contribute to improving the process efficiencies. In the next phase, efficiencies are sought.
Department Operating
DP-027.1 Tri-Region Recycling Center Feasibility Study
This study would parallel the feasibility study reviewing a regional organic waste processing facility for the Tri-Region but for shared recycling center. The study would review the current situation for recycling collection in each of the three municipalities in the Tri Region and assess the feasibility of a single shared site to provide for the collection of recycling including costs associated with the current situation as well as any it may propose.
Jan 2017 Dec 2017
Department Operating
DP-028.1 TCA Background Data Collection
This corporate initiative includes the comprehensive assessment of the Towns existing infrastructure to coincide with the TCA, GIS and Bellamy data base systems. By forensically examining the existing assets the Town can have accurate up to date records on the condition/location and cost of the current infrastructure. This perpetually increases the accuracy and efficiency for the Town to execute a ten year capital plan by mitigating risk and maximizing return on capital value. With the background data collection the Town is now also able to prioritize infrastructure rehabilitation more effectively and have proper documentation to categorize to the applicable section.
Jan 2017 Dec 2017
Service Change
SC-033.1 Town Snow Dump Study
This service change initiative involves examining the feasibility of constructing a permanent engineered snow dump within the Town. With the Town growing at a fast pace geographically and density wise, it is time to look at a long term and environmentally sustainable approach. This study will include, but not limited to: key site design considerations, capacity, soil characteristics, grading, access, and potential melt water treatment solutions. Some other key considerations outlined will focus on: operations and maintenance, environmental monitoring and environmental remediation, if so required. The need for this study is warranted to make an educated decision on the feasibility of a snow dump site.
Jan 2017 Dec 2017
Service Change Staffing
SCS-041.1 Integrated Pest Management Operator I
Integrated Pest Management is a system which seeks to balance policy and operational activities in an over-arching holistic manner in areas related to public space service delivery. A dedicated Public Works staff member is required
Jan 2017
-
Department Business Plans
48 | P a g e
Category Name Executive Summary Start Date End Date to conduct integrated pest management. As a specialist position, the duties would reflect the service delivery requirement for pest management, especially in the area of weed control, while working in tandem with the Parks and Horticulture crews. This position would also assume the enforcement role of Weed Inspector.
Service Change Staffing
SCS-042.1 Apprentice Mechanic Small Fleet
Additional staff Is being requested for the function of Common Services. This function includes the operations of the mechanical shop. With the large inventory of equipment, two heavy duty mechanics are constantly performing repairs and maintenance on the heavy equipment and the regular maintenance and repair of small fleet is being delayed. What is being requested is a third/fourth year apprentice mechanic to perform work on the small fleet.
Jan 2017
Service Change Staffing
SCS-043.1 Operator I Roads
Additional staff is being requested for the function of Roads. A recent survey of three municipalities of relative size in terms of population, Infrastructure inventory, number of dwellings and geographical area shows that the Towns Roads crew is below the average (six staff) of those municipalities.
Jan 2017
Capital CAP-065.1 Downtown Redevelopment Plan Phase I
The Downtown Redevelopment Plan is intended to address two areas of concern:
1. To replace the existing aging underground sewer and water system and the Town of Stony Plain has been working to gradually replace all of the sewer and water lines that service the Downtown area. Due to age, the existing pipes are undersized and in poor condition.
2. The importance of a strong business community and vibrant downtown has been recognized in the 2015 2017 Strategic Plan. In 2012 the Downtown Streetscape Master Plan proposed street and landscaping improvements on Main Street and the immediate surrounding ar