![Page 1: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/1.jpg)
PRESENTASI TUGAS AKHIR
PERENCANAAN PERKUATAN TANGGUL UNTUK MENANGGULANGI LONGSOR DI TEBING SUNGAI
SEGAH, JALAN BUJANGGA, BERAU
DIAN ANGGRAINI 3109100076
Dosen Pembimbing: Prof. Indrasurya B. Mochtar, M.Sc, Ph.D
JURUSAN TEKNIK SIPILFAKULTAS TEKNIK SIPIL DAN PERENCANAANINSTITUT TEKNOLOGI SEPULUH NOPEMBER
SURABAYA2013
![Page 2: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/2.jpg)
PENDAHULUAN
Kronologis TerjadinyaLongsor
Latar Belakang
Rumusan Masalah
![Page 3: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/3.jpg)
Gambar Lokasi Penelitian (Sumber: PT Kaliraya Sari )
Lokasi Terjadinya Longsor
![Page 4: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/4.jpg)
Lokasi Terjadinya Longsor
Dilaksanakan proyek pelebaran Jalan
Gambar Cross Section STA 0+050
![Page 5: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/5.jpg)
Kronologis Terjadinya Longsor
Penurunan badan jalan dantimbunan hingga 2 meter
Terjadi retakan di badan jalan dantimbunan
![Page 6: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/6.jpg)
Latar Belakang
-Merupakan jalan provinsi-Sebagai jantung ekonomi masyarakat-Satu-satunya akses ke Bandara
![Page 7: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/7.jpg)
Rumusan Masalah
1. Apa Penyebab Longsor?
2. Jenis Perkuatan Tanggul apakahyang tepat untuk menanggulangilongsor di Jalan Bujangga?
![Page 8: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/8.jpg)
METODOLOGI
Bagan Alir
![Page 9: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/9.jpg)
B
A
G
A
N
A
L
I
R
![Page 10: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/10.jpg)
ANALISA DATA TANAH DAN PERENCANAAN
Data Tanah
Data SpesifikasiBahan
![Page 11: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/11.jpg)
Data Tanah
Bor
Sondir
Uji Laboratorium
LOKASI PENGAMBILAN
SOIL INVESTIGATION
![Page 12: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/12.jpg)
Lokasi Pengambilan
![Page 13: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/13.jpg)
Data Tanah Asli
Depth (m) S-3 (STA 0+003) S-4 (STA 0+025) S-5 (STA 0+035) S-2 (STA 0+045) S-6 (STA 0+075) S-1 (STA + 115) S-7 (STA 0+150) S-8 (STA 0+190)
0 - 5
Sangat Lunak
Sangat Lunak
Sangat Lunak
Sangat LunakSangat Lunak
Sangat Lunak
Sangat LunakSangat Lunak
Lunak
MenengahKaku
Kaku
Lunak
Menengah
Lunak
Menengah
Lunak
Sangat Kaku
6 - 10 Lunak
Menengah
Lunak
MenengahMenengah Sangat Lunak Lunak
Kaku
Lunak Menengah Lunak
Kaku
Kaku
11 - 15 MenengahMenengah
Kaku
Menengah
Kaku
Kaku
16 - 20
Kaku
Sangat Kaku Sangat Kaku
Sangat Kaku
Kaku
Sangat Kaku Kaku Sangat Kaku
21 - 22
Sangat Kaku
Sangat Kaku
![Page 14: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/14.jpg)
Data Tanah Ardhana Mochtar
Depth (m) Kohesi
0 0
1 7.96
2 9.13
3 10.31
4 11.48
5 12.65
6 13.82
7 14.99
8 16.16
9 17.34
10 18.52
11 19.69
Depth (m) Kohesi
12 20.86
13 22.05
14 23.22
15 24.40
16 25.57
17 26.74
18 27.92
19 29.09
20 30.27
21 31.44
22 32.62
23 33.80
Dibandingkandengan Data Tanah dari Rumus EmpirisArdhana Mochtar
![Page 15: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/15.jpg)
PENYEBAB LONGSOR
![Page 16: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/16.jpg)
Perencanaan Eksisting TurapTOP ELEVATION OF SHEET PILE +10.040
TOP WATER LEVEL + 8.750
LOW WATER LEVEL + 7.000
PENETRATION 15.000 M
PENETRATION 20.000 M
SEA BED
![Page 17: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/17.jpg)
Evaluasi Turap
Evaluasi Turap
Saat Pasang
Evaluasi Turapsebagai Turap
Evaluasi Turapsebagai ceruck
Saat Surut
Evaluasi Turapsebagai Turap
Evaluasi Turapsebagai ceruck
![Page 18: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/18.jpg)
Evaluasi Turap Sebagai Turap
q = 1,5 t/m2
Lapisan Pasir
? = 1,9 t/m3 F = 30 c = 0 t/m2
Lapisan Lempung Lunak ? = 1,65 t/m3 c = 1,265 t/m2 F = 0
T
1
Lapisan Lempung Lunak ? = 1,67 t/m3 c = 1,382 t/m2 F = 0
2 m
1,5 m
D
Lapisan Lempung Lunak ? = 1,68 t/m3 c = 1,499 t/m2 F = 0
Lapisan Lempung Lunak ? = 1,71 t/m3 c = 1,616 t/m2 F = 0
Lapisan Lempung Lunak ? = 1,73 t/m3 c = 1,734 t/m2 F = 0
2 m
2 m
2 m
2 m
2
3
4
5
6
7
5 t/m2
q
1,7 t/m2 2,57 t/m2
3,55 t/m23,31 t/m2
0,55 t/m2
0,08 t/m20,39 t/m2
0,86 t/m2
0,86 t/m2 11,5 + D t/m211,5 + D t/m2
Ilustrasi turap dan kondisi tanah disekitarnya
Diagram Tekanan Tanah
Kondisi Saat Air Sungai Pasang
![Page 19: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/19.jpg)
Evaluasi Turap Sebagai Turap
q
P1
P2
P3 P4
P6P5
P7
P8
P9
P10P11
Gaya-gaya yang bekerja pada turap
P Nilai P (t) Lengan (m)Momen Terhadap T
(t m)
P1 2 0 0
P2 2,4 0,67 1,6993
P3 3,855 2,75 10,60
P4 0,731 3 2,194
P5 1,094 4,5 4,923
P6 2,563 4,167 10,68
P7 0,158 6,5 1,027
P8 0,778 8,5 6,613
P9 0,861D 9,5 + 0,5D 8,1795D + 4,75D2
![Page 20: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/20.jpg)
Evaluasi Turap Sebagai Turap
Sehingga didapatkan persamaan momen:24,512 – 8,1795D – 4,75 D2 = 0Maka nilai D = 1,568 meter = 2 meter.Karena nilai safety factor yang ingin dicapai adalah 1,2, maka panjang D = 1,2x 2 = 2,4. Jadi panjang turap yang dibutuhkan adalah 11,5 + 2,4 = 13,9 14meter.
![Page 21: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/21.jpg)
Evaluasi Turap Sebagai Turap
Dengan menggunakan program SAP didapatkan momen maksimum sebesar17,51545 ton-m = 1.751.545 kg-cm. Maka nilai modulus section yang dibutuhkan, yaitu:
Sehingga bisa direncanakan turap dengan memakai U-type Sheet Pile FSP-IV dengan Section Modulus, Zx = 2.250 cm3/m
![Page 22: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/22.jpg)
Evaluasi Turap Sebagai Turap
Perhitungan turap juga dilakukan saat kondisi surut, sehingga terjadi bedaelevasi muka air.
q = 1,5 t/m2
Lapisan Pasir
? = 1,9 t/m3 F = 30 c = 0 t/m2
Lapisan Lempung Lunak ? = 1,65 t/m3 c = 1,265 t/m2 F = 0
T
1
Lapisan Lempung Lunak ? = 1,67 t/m3 c = 1,382 t/m2 F = 0
2 m
1,5 m
D
Lapisan Lempung Lunak ? = 1,68 t/m3 c = 1,499 t/m2 F = 0
Lapisan Lempung Lunak ? = 1,71 t/m3 c = 1,616 t/m2 F = 0
Lapisan Lempung Lunak ? = 1,73 t/m3 c = 1,734 t/m2 F = 0
2 m
2 m
2 m
2 m
2
3
4
5
6
7
Ilustrasi Turap Saat Air Sungai Surut
![Page 23: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/23.jpg)
Evaluasi Turap Sebagai Turap
Hasil Perhitungan Turap Sebagai Turap
No. UraianSaat Kondisi
Surut
Saar Kondisi
Pasang
1 Jumlah Tiang (baris/m) 3 1
2 Kedalaman Tiang (m) 18 14
![Page 24: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/24.jpg)
Evaluasi Turap Sebagai Cerucuk
Dengan metode ini turap diasumsikansebagai cerucuk. Sehingga perhitunganyang dilakukan dengan menggunakanmetode perhitungan cerucuk.
Gaya Lateral Tiang, P :Cu = 0,1307 kg/cm2
qu = 2 x Cu = 0,263 kg/cm2 = 0,27 tsfdari gambar di samping didapatkan f = 3 tcf = 0,096 kg/cm3
3
![Page 25: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/25.jpg)
Evaluasi Turap Sebagai Cerucuk
• Faktor kekakuan relatif, T :
• Mmax yang mampu ditahan oleh sheetpile :
• Panjang sheetpile di bawah bid. longsor :
L = 200 cm, sehingga:
maka dari grafik di samping, didapatkan:
FM = 1
cmx
f
EI50,246
096.0
600.41000.100.2 5
1
5
1
kgcmx
ZxModulusSectionxallow
000.600.3250.2600.1
,
81,05,246
200
T
L
![Page 26: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/26.jpg)
Evaluasi Turap Sebagai Cerucuk
Jadi, gaya lateral 1 tiang:
Kebutuhan SheetPile :
Analisa dengan XSTABL
kgxTxF
MP
M
75,604.145,2461
000.600.3
baris
xRxP
Mn R
3
479775,604.14
345.210.180
5
10
15
20
25
30
0
35
17.3220.13
Jalan selebar 8 meter
TIMBUNAN
![Page 27: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/27.jpg)
Evaluasi Turap Sebagai Cerucuk
No. Uraian Saat Pasang Saat Surut
1. Jumlah (baris) 1 7
2. Kedalaman (m) 23 25
![Page 28: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/28.jpg)
Penyebab Longsor
1. Kondisi Tanah Yang Relatif JelekKedalaman tanah lempung lunak mencapai 10-20 meter.
2. Adanya Pasang Surut Air Sungai
![Page 29: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/29.jpg)
Penyebab Longsor
3. Turap Eksisting tidak Memenuhi Syarat Overall Stability
4. Jumlah turap yang dipancang kurang
5
10
15
20
25
30
0
35
22.1320.00
Jalan selebar 8 meter
TIMBUNAN
![Page 30: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/30.jpg)
PERENCANAAN PERKUATAN TANAH
Turap Baja/ Sheet Pile
Cerucuk
Tiang Pancang Baja
![Page 31: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/31.jpg)
Perencanaan Perkuatan Tanah
STA
Perkuatan (buah/m’)
TurapMicropile Pipa
Baja25x25 32x32x32
0+000 4 66 53 6
0+025 2 33 27 3
0+050 2 22 18 3
0+075 3 37 30 4
0+100 6 94 76 9
0+125 7 119 96 11
0+150 5 74 60 7
0+175 4 56 45 5
0+195 4 60 49 6
Direncanakan perkuatan di sepanjang Jalan Bujangga dari hasil yang paling banyak dari tabel di atas
![Page 32: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/32.jpg)
Perencanaan Perkuatan Tanah dengan Subdrain
STA
Perkuatan (tiang/m’)
TurapMicropile Pipa
Baja25x25 32x32x32
0+000 2 34 27 3
0+025 1 8 7 1
0+050 1 2 1 1
0+075 2 19 16 2
0+100 5 71 58 7
0+125 6 88 80 8
0+150 3 49 40 5
0+175 2 31 25 3
0+195 1 13 10 2
Direncanakan perkuatan di sepanjang Jalan Bujangga dari hasil yang paling banyak dari tabel di atas
![Page 33: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/33.jpg)
Kombinasi Perkuatan
Contoh perhitungan kombinasi turap dengan tiang pancangbaja:Kebutuhan turap = 5,1 baris/meter, sehingga bisa dihitungseperti ini.
5,1 = 5 turap + digunakan tiang pancang baja
Maka tiang pancang baja yang dibutuhkan:
0,1
'/113,086
1,0mtiangx
Jadi dihasilkan kombinasi perkuatan dengan 5 baris turapdan 1 baris tiang pancang
![Page 34: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/34.jpg)
Kombinasi Perkuatan
Rekomendasi kombinasi perkuatan :
Kombinasi Turap Cerucuk TiangPancang25x25 32x32x32
Kombinasi 1 5 - - 1
Kombinasi 2 5 2 - -
Kombinasi 3 5 - 2 -
Kombinasi 4 - 6 - 7
Kombinasi 5 - - 6 7
![Page 35: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/35.jpg)
Perhitungan RAB
No. Jenis Perkuatan Jumlah Harga
1. Pemancangan Sheet Pile Rp 58,500,000,000.00
2. Pemancangan Cerucuk 25x25 Rp 83,655,000,000.00
3. Pemancangan cerucuk 32x32x32 Rp 53,955,200,000.00
4. Pemancangan Pipa Baja Rp 51,948,000,000.00
5. Kombinasi 1 Rp 53,836,575,000.00
6. Kombinasi 2 Rp 50,239,312,500.00
7. Kombinasi 3 Rp 49,806,588,000.00
8. Kombinasi 4 Rp 50,017,500,000.00
9. Kombinasi 5 Rp 48,691,760,000.00
Kombinasi 5 rencana anggaran biayanya paling murah
![Page 36: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/36.jpg)
Analisa Jangka Panjang
Disarankan relokasi jalan di tempat yang aman dan jauh daritepi sungai karena:1. Lokasi yang lama rawan terhadap gerusan2. Harga pemindahan jalan (Rp 5.850.000.000,00) lebih
murah jika dibandingkan dengan harga pemancanganperkuatan (Rp 48 Milyar)
![Page 37: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/37.jpg)
KESIMPULAN
![Page 38: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/38.jpg)
Kesimpulan
1. Penyebab longsor di Jalan Bujangga, yaitu:a. Kondisi tanah yang relatif jelekb. Adanya pasang surut air sungai yang memiliki beda elevasi
air hingga 4 meter.c. Turap eksisting yang dipancang di Jalan Bujangga terletak
di atas bidang longsor.d.Turap yang dipancang seharusnya sebanyak 7 baris, namun
yang ada di lapangan hanya 1 baris saja.
![Page 39: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/39.jpg)
Kesimpulan
2. Alternatif yang dipilih untuk menanggulangilongsor pada tebing Sungai Segah sepanjang JalanBujangga adalah dengan menggunakan kombinasiturap baja dengan micropile 32 x32 32 denganbiaya Rp 48 Milyar.
3. Dalam perencanaan ini disarankan untuk solusijangka panjangnya adalah dengan melakukanrelokasi jalan yang aman dan jauh dari pinggirsungai.
![Page 40: PRESENTASI TUGAS AKHIR - digilib.its.ac.iddigilib.its.ac.id/public/ITS-paper-34314-3109100076-Presentation.pdfDilaksanakan proyek pelebaran Jalan Gambar Cross Section STA 0+050. Kronologis](https://reader030.vdocuments.site/reader030/viewer/2022033120/5d36995688c993f1228e1151/html5/thumbnails/40.jpg)
TERIMA KASIH