Project Quality ManagementBased on PMBOK 5th Edition
Abdelrahman Sheta, PMP,ITIL
1PMP - Project Quality Planfacebook.com/Sheta.Page
![Page 2: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/2.jpg)
Agenda
PMP - Project Quality Plan 2
Quality Theories
Evolution of Quality Management
8.1 Plan Quality Management
8.2 Perform Quality Assurance
8.3 Control Qualityfacebook.com/Sheta.Page
![Page 3: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/3.jpg)
Quality is the degree to which the project fulfills
requirements.
Quality Management
PMP - Project Quality Plan 3
Quality Management includes creatingand following policies and procedures
in order to ensure that a project meets the defined needs it was intended to meet.
facebook.com/Sheta.Page
![Page 4: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/4.jpg)
Joseph Juran: 80/20 principle, top management
involvement. Quality is fitness for use.
W. Edwards Deming: 14stepsof total Quality
Management, Plan-Do-Check-Act cycle.
Philip Crosby: Cost of poor quality,
prevention over inspection and zero
defects. Quality is “conformance to
requirements”
Quality Theorists
PMP - Project Quality Plan 4facebook.com/Sheta.Page
![Page 5: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/5.jpg)
Customer Satisfaction
Prevention over inspection
Continuous improvement
Management Responsibility
Cost of Quality (COQ)
ISO Compatibility
PMP - Project Quality Plan 5facebook.com/Sheta.Page
![Page 6: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/6.jpg)
Quality is:
A. Meeting & exceeding customer needs.
B. Adding extra to make customer happy.
C. Conformance of requirements and fitness of use
D. Conformance to management’s requirements
Quiz:
PMP - Project Quality Plan 6facebook.com/Sheta.Page
![Page 7: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/7.jpg)
PMP - Project Quality Plan 7facebook.com/Sheta.Page
![Page 8: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/8.jpg)
8.1 Plan Quality Management
• Identifying quality requirement and/or standards
for the project and its deliverables, and
documenting how the project will demonstrate
compliance with the relevant quality requirements.
PMP - Project Quality Plan 8facebook.com/Sheta.Page
![Page 9: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/9.jpg)
1. Project Management Plan,
includes but not limited to Scope baseline
Work Breakdown Structure
WBS Dictionary
Schedule baseline
Cost baseline
Other management Plans
Plan Quality: Inputs (1)
PMP - Project Quality Plan 9facebook.com/Sheta.Page
![Page 10: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/10.jpg)
2. Stakeholder Register
3. Risk register
4. Requirements Documentation
5. Enterprise environmental factors
6. Organizational process assets
Plan Quality: Inputs (2)
PMP - Project Quality Plan 10facebook.com/Sheta.Page
![Page 11: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/11.jpg)
1. Cost-benefit Analysis2. Cost of Quality (COQ)3. Seven Basic Quality
Tools Cause-and-Effect
Diagram Flowcharts Check-sheet Pareto Diagram Histograms Control Charts Scatter Diagram
Plan Quality: T & T
PMP - Project Quality Plan 11facebook.com/Sheta.Page
![Page 12: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/12.jpg)
4. Benchmarking5. Design of Experiments6. Statistical Sampling7. Additional Quality Tools
Brainstorming Force field analysis Nominal Group Technique Quality Management and control
tools
8. Meetings
Plan Quality: T & T
PMP - Project Quality Plan 12facebook.com/Sheta.Page
![Page 13: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/13.jpg)
The primary benefit of meeting
quality requirements is less
rework, i.e., higher productivity,
lower costs and increased
stakeholder satisfaction.
The primary cost of meeting
quality requirements is the
expenses associated with quality
management activities.
Cost-benefit Analysis
PMP - Project Quality Plan 13facebook.com/Sheta.Page
![Page 14: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/14.jpg)
Cost of Quality
PMP - Project Quality Plan 14facebook.com/Sheta.Page
![Page 15: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/15.jpg)
Cost of Quality
PMP - Project Quality Plan 15facebook.com/Sheta.Page
![Page 16: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/16.jpg)
Cause and Effect DiagramTrace the problem’s source back to its
“actionable root cause”
PMP - Project Quality Plan 16facebook.com/Sheta.Page
![Page 17: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/17.jpg)
FlowchartingA graphical representation of a process showing the
relationships among process steps.
PMP - Project Quality Plan 17facebook.com/Sheta.Page
![Page 18: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/18.jpg)
Tally Sheets
PMP - Project Quality Plan 18facebook.com/Sheta.Page
![Page 19: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/19.jpg)
Pareto Diagram
PMP - Project Quality Plan 19facebook.com/Sheta.Page
![Page 20: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/20.jpg)
Histogram
PMP - Project Quality Plan 20facebook.com/Sheta.Page
![Page 21: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/21.jpg)
Graphic displays of the results, over time, of a process; used to assess whether the process is “in control”
Rule of Seven – Run of seven points toward upper or lower control limit may indicate that process is out of control
Assignable causes – Variations may be caused by differences in machines, workers overtime, etc. Identify the root cause.
Control Charts
PMP - Project Quality Plan 21facebook.com/Sheta.Page
![Page 22: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/22.jpg)
Control Chart – contd.
PMP - Project Quality Plan 22facebook.com/Sheta.Page
![Page 23: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/23.jpg)
Scatter Diagram
PMP - Project Quality Plan 23facebook.com/Sheta.Page
![Page 24: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/24.jpg)
Benchmarking involves comparing actual
or planned project practices to those of
other projects in order to generate ideas
for improvement and to provide a
standard by which to measure
performance.
These other projects may be within the
performing organization or outside of it,
and may be within the same or in another
application area.
Benchmarking
PMP - Project Quality Plan 24facebook.com/Sheta.Page
![Page 25: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/25.jpg)
Design of Experiment
• Design of experiments is a statistical method
• that helps identify which factors might
influence specific variables. It also plays a role
in the optimization of products or processes.
PMP - Project Quality Plan 25facebook.com/Sheta.Page
![Page 26: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/26.jpg)
Statistical sampling involves choosing part of a population of interest for inspection (e.g., selecting 10 samples of 75 electronic components).
Appropriate sampling can often reduce the cost ofquality control.
There is a substantial body of knowledge on statistical sampling; in some application areas, it is necessary for the project management team to be familiar with a variety of sampling techniques.
Statistical Sampling
PMP - Project Quality Plan 26facebook.com/Sheta.Page
![Page 27: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/27.jpg)
1. Quality Management Plan
2. Process Improvement Plan Process Boundaries
Process Configuration
Process Metrics
Targets for Improved Performance
3. Quality Metrics
4. Quality Checklist
5. Project Documents Updates
Plan Quality Management: Outputs
PMP - Project Quality Plan 27facebook.com/Sheta.Page
![Page 28: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/28.jpg)
Training costs are part of:
A. Prevention costs
B. Appraisal costs.
C. Internal failure costs.
D. External failure costs.
Quiz:
PMP - Project Quality Plan 28facebook.com/Sheta.Page
![Page 29: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/29.jpg)
1. Auditing the quality requirements and the
results from quality control measurement
to ensure that appropriate quality
standards and operational definitions are
used.
2. The key benefit of this process is that it
facilitates the improvement of quality
processes
8.2 Perform Quality Assurance
PMP - Project Quality Plan 29facebook.com/Sheta.Page
![Page 30: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/30.jpg)
PMP - Project Quality Plan 30facebook.com/Sheta.Page
![Page 31: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/31.jpg)
1. Quality Management Plan
2. Process Improvement Plan
3. Quality Metrics
4. Quality Control Measurements
5. Project Documents
Perform Quality Assurance: Input
PMP - Project Quality Plan 31facebook.com/Sheta.Page
![Page 32: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/32.jpg)
1. Quality Management and Control Tools
Affinity Diagrams Process Decision Program Charts Interrelationship Digraphs Tree Diagrams Prioritization Matrices Activity Network Diagram Matrix Diagrams
2. Quality Audits
3. Process Analysis
Perform Quality Assurance: T & T
PMP - Project Quality Plan 32facebook.com/Sheta.Page
![Page 33: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/33.jpg)
Affinity Diagrams
PMP - Project Quality Plan 33facebook.com/Sheta.Page
![Page 34: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/34.jpg)
Process Decision Program Charts (PDPC)
PMP - Project Quality Plan 34facebook.com/Sheta.Page
![Page 35: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/35.jpg)
Interrelationship
Digraph
Tree Diagrams
PMP - Project Quality Plan 35facebook.com/Sheta.Page
![Page 36: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/36.jpg)
PMP - Project Quality Plan 36facebook.com/Sheta.Page
![Page 37: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/37.jpg)
1. Change Requests
2. Project Management Plan Updates
3. Project Documents Updates
4. Organizational Process Assets
Perform Quality Assurance: Output
PMP - Project Quality Plan 37facebook.com/Sheta.Page
![Page 38: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/38.jpg)
Who is responsible of the quality
management in the project:
A. Project Quality Manager.
B. Project Manager
C. Project Team members.
D. Quality Assurance Department.
Quiz:
PMP - Project Quality Plan 38facebook.com/Sheta.Page
![Page 39: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/39.jpg)
Perform Quality Control is the process of
monitoring and recording results of
executing the quality activities to assess
performance and recommend necessary
changes
The key benefits of this process include
Identifying the causes of poor quality
Validating that project deliverables and
work meet the requirements
8.3 Control Quality (1)
PMP - Project Quality Plan 39facebook.com/Sheta.Page
![Page 40: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/40.jpg)
Important Quality terms
Prevention (Keeping errors out of the
process) vs. Inspection (Keeping errors out
of the hands of the customer).
Attribute sampling (either conform or doesn't) vs.
Variables sampling (degree of conformity)
Tolerance (range of acceptable results) and control
limits (thresholds which may indicate out of control)
8.3 Control Quality (2)
PMP - Project Quality Plan 40facebook.com/Sheta.Page
![Page 41: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/41.jpg)
PMP - Project Quality Plan 41facebook.com/Sheta.Page
![Page 42: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/42.jpg)
1. Project Management Plan
2. Quality Metrics
3. Quality checklists
4. Work Performance Data
5. Approved Change Requests
6. Deliverables
7. Project Documents
8. Organizational Process Assets
Control Quality: Input
PMP - Project Quality Plan 42facebook.com/Sheta.Page
![Page 43: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/43.jpg)
1. Seven Basic Quality Tools
2. Statistical Sampling
3. Inspection
4. Approved Change Request Reviews
Control Quality: T & T
PMP - Project Quality Plan 43facebook.com/Sheta.Page
![Page 44: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/44.jpg)
1. Quality Control Measurements
2. Validated Changes
3. Verified Deliverables
4. Work Performance Information
5. Change Requests
6. Project Management Plan Updates
7. Project Document Updates
8. Organizational Process Assets Updates (Completed
checklists, lessons learned documentation, etc.)
Control Quality: Output
PMP - Project Quality Plan 44facebook.com/Sheta.Page
![Page 45: Pmp 05 Project Quality Management](https://reader037.vdocuments.site/reader037/viewer/2022100221/557d5a02d8b42abf3d8b4aea/html5/thumbnails/45.jpg)
Quiz:
• When a process considered to be in control, it:
A. Should not be adjusted
B. May not be changed to provideimprovements.
C. Shows differences caused by expected causes.
D. Should not be inspected or reworked for any reason.