Planning inproduction systems

MRP systems, MRP II, JIT

Slovak University of TechnologyFaculty of Material Science and Technology in Trnava

Page 2: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Material Requirements Planning (MRP)

MRP is a software based production planning and inventory control system used to manage manufacturing processes.

MRP is a calculation method geared toward determining how much of which raw materials are required and roughly when they should be ordered to fulfill a set of product orders.

Page 3: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

An MRP system is intended to

simultaneously meet three objectives:

Ensure materials and products are available for production and delivery to customers.

Maintain the lowest possible level of inventory. Plan manufacturing activities, delivery schedules

and purchasing activities.

Page 4: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

MRP generally consists of four steps: Bill of Materials Explosion - looking backward

from each product, determine which intermediates and raw materials are required, and in what quantities.

Netting - compare the above quantities against current inventory.

Lot Sizing - determine how the needed materials will be purchased or produced.

Start Date Determination - based on cycle time information, determine when each order should start production.

Page 5: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

MRP system structure

Page 6: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Level of stock

Page 7: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Manufacturing Resource Manufacturing Resource PlanningPlanning (MRP II)

orientation to production sources planning all information current, planning function

and production control integrate to one logical chain cross material current,

using continuous planning principles - production process hierarchy support.

Page 8: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Automated production

Page 9: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

JIT (Just in Time) base idea – to optimized buffering stocks, which

help us to control supplies level; high supplies level = small effectiveness,

more then supplies control – philosophy based on continual deficit finding out and elimination on all organizations levels.

Page 10: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

JIT can see as:

philosophy or full access to production technics which are used for production system

design and operation beam house control system - kanban = dispatch

note.

Page 11: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Objective of JIT Produce only the products the customer

wants. Produce products only at the rate that the

customer wants them. Produce with perfect quality Produce with minimum lead time. Produce products with only those features the

customer wants.

Page 12: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

JIT Principles Create flow production

one piece flow machines in order of processes small and inexpensive equipment U cell layout, counter clockwise multi-process handling workers easy moving/standing operations standard operations defined

Establish “TAKT” time rate at which the customer buys a product

Build Pull Product use of kanban system

Page 13: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

By decreasing supplies level we cansee hidden problems with two sources:

extern – mistakes in delivery - customers relations

intern – mistakes which reach as consequence of quality deficient (material, production engineering, production process organization, work power, goods and technical documentation design)

Page 14: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Solutions

extern problems source

- build reliable stable delivers chain and reliable customers

intern problems source

- complex quality increasing and monitoring – TQM (Total Quality Management), active production process quality assurance – SPC (Statistical process control); it try to do ZD (zero defects).

Page 15: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Aim of JIT

1. Dodge to generality

2. Avoid the loss

3. Continuing improvement

Page 16: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

1. Dodge to generality

by the customers – fast change of claim and preferences – although we need to retain adequate costs, offer palette of goods and short delivery dead-lines

by the delivers – first step in production; important in storage nonexistence to achieve quality and right supplies or blank in right time

Page 17: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

by the workers absence and another problems can be reduced with

right workers motivation, increasing the work claim, work organization, higher work motley and easy identification their portion to making good

workers education - achieve decreasing level of goods mistakes

preference before making simply monotone operations continuously by many workers have to be making complex operations by one workers

by claim of trade – is not anytime constant

Page 18: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

2. Avoid the loss Overproduction Idle time and production storages Transporting Mistakes

Page 19: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

3. Continuing improvement effective increasing, looses elimination,

indemnity for reliability, making production discipline etc. (unending process)

KAIZEN philosophy - sense to have trying achieve production without mistakes for all goods, because mistakes destroying continuous production current (continuously increasing process).

Page 20: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

JIT Advantages Shortened lead time Reduced time spent on non-process work Reduced inventory Better balance between different processes Problem clarification

Page 21: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Limitations of JIT

Preconditions to JIT trust must be present

labor/management suppliers/consumers

recognition of processes familiarity with problem solving quality at the source agreement over value and waste

Page 22: Planning in production systems MRP systems, MRP II, JIT Slovak University of Technology Faculty of Material Science and Technology in Trnava

Limitations of JIT

Right Settings applicable in growth to maturity phases of

Product Life Cycle standard product

Steinway and JIT standard/fixed pay-rate

problems with piece-rate scheme

Universal agreement that change needed