Transcript
Page 1: Paisley Canal ‘Low Cost’ Electrification

Paisley Canal‘Low Cost’ ElectrificationYoung Railway Professional Competition 2012Brian Sweeney, Asset Engineer (Electrification), Network Rail Scotland

Page 2: Paisley Canal ‘Low Cost’ Electrification

Overview

• Introduction

• Overview of Paisley Canal Electrification scheme

– ‘Innovative thinking’ to make scheme affordable

– Staged plan for delivery

• Managing electrical safety through design

• Innovation Challenges still to meet

• Summary & Conclusions

Page 3: Paisley Canal ‘Low Cost’ Electrification

ProjectOverview

Page 4: Paisley Canal ‘Low Cost’ Electrification

Paisley Canal Line

Non-Electrified Section (8.8km)

Page 5: Paisley Canal ‘Low Cost’ Electrification

Devolution Challenge - Why Electrify?• Operated by 3 ‘trapped’ cl156 DMUs

as surrounding areas electrified

• Timetable does not work with DMU stock – 17,000 delay minutes per year, only 16% of trains right time

• Route already 33% electrified, only 8.8 additional STK of OLE required

• No additional HV switchgear needed

• “Quick Win” for Scotland’s Railway as existing DMU stock can be re-allocated elsewhere in Scotland to meet demand

• Paisley Canal service can be operated with better diagramming of existing cl314 & cl380 EMU fleets

Page 6: Paisley Canal ‘Low Cost’ Electrification

Electrification Challenges

• 12 Overbridges on route - 9 require work to achieve Special Reduced Clearances

• 3 bridges adjacent to station platforms – track lower drives full platform reconstruction

• GRIP 2 desktop study estimate £20-£28m

• Works out at (worst case) £3.2m per STK of OLE

• Innovative thinking required to reduce scheme cost to a sustainable level - BCR is only positive below £12.2m

Page 7: Paisley Canal ‘Low Cost’ Electrification

Electrification Challenges - Freight

• Route cleared to W7 for freight traffic to/from Hawkhead Oil terminal

• Route not been used for W7 traffic since 1994

• FOC aspiration for future use in medium term

• No new freight paths available from 0530 to 2330 Mon-Sat

• Electrification scheme needs to cater for future freight use – NR have made this commitment as part of Network Change Process

Page 8: Paisley Canal ‘Low Cost’ Electrification

Project Scope

• Bare minimum amount of works required to electrify the route for use by half-hourly Scotrail EMU service

• Maintaining capability for freight traffic to/from Hawkhead

• Accommodating non-multiple EMUs only – i.e. 4-car Class 380, 3-car 314, 318, 320, 334 stock

• Extending to Elderslie, re-doubling the line or making passive provision for either of these options

• Renewing any existing assets not associated with works

• Adding additional signalling, capacity, or increasing line speed

• Extending platforms for 6 car sets

• Adjusting existing 2m wide platforms (unless major works taking place – e.g. Hawkhead)

What the project is doing What the project is not doing

Page 9: Paisley Canal ‘Low Cost’ Electrification

Gauging Live OLE around a train…

W6a / W7

263mm Clear

150mm Track Lower for Special Reduced

Class 314

624mm Clear

No work forNormal Clearance

All ScotRail EMU (314,318,320,334,380)

419mm Clear

No work for Special Reduced Clearance

Page 10: Paisley Canal ‘Low Cost’ Electrification

Reduced Gauge Profile (‘E2’)

Power OffPower On4.03m

135mm saving

4.165m

Page 11: Paisley Canal ‘Low Cost’ Electrification

Bespoke Gauge Electrification

• Clear for vehicles of 3870mm and under when the OLE is live

• Clear for ANY UK Load Gauge (W7) vehicle when the power is off

• Number of bridges needing work drops from 9 to 5

• Extended neutral section placed under one bridge to avoid work

• Track lowers of 50-158mm under remaining 4 bridges

• Number of station platforms to be rebuilt drops from 3 to 1 - Hawkhead

Page 12: Paisley Canal ‘Low Cost’ Electrification

“Political” Background

“A £28m scheme for £12m”

• “Trail Blazer” project that meets many requirements outlined in the McNulty ‘Rail value for Money’

• High profile support – scheme is poster child for “alliancing”

• CEO highlighted project specifically during evidence to Transport Select Committee

• D&B Contract awarded to Babcock Rail in June 2012 to electrify by Dec 2012 timetable change…!

Page 13: Paisley Canal ‘Low Cost’ Electrification

December 2012 delivery?Stage 1: Electrification for Scotrail EMU only

• Route electrified with a wire height of 4030mm

• Restriction in the sectional appendix saying only vehicles with profile lower than 3870mm (i.e. Scotrail EMU) can use the route

• ‘Out of gauge’ Freight / Engineering trains can still access route under possession and isolation – procedure in place to manage

• Energised on 19th November for driver training!

Stage 2: The ‘Innovative’ Stuff!!

• Stage 1 only acceptable to FOCs as an interim measure - a quick, remotely operable, and safe way of switching the power off to allow ‘out of gauge’ trains to access the route has to be developed

• Desirable by Dec 2012, but safety case may not be in place

Page 14: Paisley Canal ‘Low Cost’ Electrification

Stage 1…

Page 15: Paisley Canal ‘Low Cost’ Electrification

Work in Progress… Kirow / MOVAX

Page 16: Paisley Canal ‘Low Cost’ Electrification

Work in Progress… Hawkhead Station

Page 17: Paisley Canal ‘Low Cost’ Electrification

Monday 19/11/12 – 10.08 GLC-PCN

Page 18: Paisley Canal ‘Low Cost’ Electrification

Managing Electrical Safety

Page 19: Paisley Canal ‘Low Cost’ Electrification

Low Wire Heights and EN50122…

EU Standard Case (3.5m) UK Special Case (2.75m)

Page 20: Paisley Canal ‘Low Cost’ Electrification

Man with umbrella…

Page 21: Paisley Canal ‘Low Cost’ Electrification

Add some Scottish weather…

Page 22: Paisley Canal ‘Low Cost’ Electrification

Suggested New “Enhanced” UK Case

Page 23: Paisley Canal ‘Low Cost’ Electrification

Stage 2…

Page 24: Paisley Canal ‘Low Cost’ Electrification

Paisley Canal Innovation Challenges

• Never been done on UK railway

• Will require interface between Electrical Controller, Driver and Signaller to manage

• Challenge is to develop a simple system that can control risk ALARP rather than spend a fortune on something that will rarely be used

• Heavily linked with on-going National Isolation review

• ORR would like to see more use of Remote Earthing facilities

• ‘Safe limit’ of 60V for working on the OLE will be much less than that required for train use…

• Talked about for years - a few challenges still to be overcome

Develop a suitable ‘Alternative Earthing System’ to switch off the

power before an ‘out of gauge’ train uses the route

Develop a method of working to allow one type of train to operate with the power on, and another

with the power off

Challenge 1 Challenge 2

WORK IN

PROGRESS!

Page 25: Paisley Canal ‘Low Cost’ Electrification

Possible options…

Option 1 – 314 & 380 Only

– Have been told not acceptable!

Option 2 – 2 Men with poles

– Labour intensive, Costs£86k per year if used 3nights per week

Option 3 – Remote Earthing with operational procedure only

– Relies solely on human judgement

– Prefer engineering controls to eliminate risk

Option 4 - Slotting with signalling

– Expensive – would be cheaper demolishing all the bridges!

Option 5 - Tagging System

– Eliminates the most risk, but expensive and overkill given low number of trains

Option 6 - Remote Earthing with Freight ‘Authority Key’

– Driver stops at noticeboard and obtains Castell key from OLE system as authority to proceed

Page 26: Paisley Canal ‘Low Cost’ Electrification

Likelihood of Single Fatality

Paisley Canal OOG Train Running - Likelihood of single fatality

Trains Per YearOperational Procedure

Authority Key System Tagging System

1 train per day 365 1 in 13.7 Years 1 in 137 Years 1 in 13699 Years

1 train per week 52 1 in 96 Years 1 in 962 Years 1 in 96154 Years

1 train per month 12 1 in 417 Years 1 in 4167 Years 1 in 416667 Years

1 train per 3 month 4 1 in 1250 Years 1 in 12500 Years 1 in 1250000 Years

1 train per 6 month 2 1 in 2500 Years 1 in 25000 Years 1 in 2500000 Years

1 train per year 1 1 in 5000 Years 1 in 50000 Years 1 in 5000000 Years

• Initial (draft) assessment using fairly conservative assumptions

• Biggest risk is a dewirement at Corkerhill station, causing wire toflail and leading to fatality of person in proximity

• Risk to train driver less than numbers above (enclosed in Faraday Cage)

Page 27: Paisley Canal ‘Low Cost’ Electrification

What it might look like…

Page 28: Paisley Canal ‘Low Cost’ Electrification

Summary

Page 29: Paisley Canal ‘Low Cost’ Electrification

Summary

• Overview of Paisley Canal Electrification scheme

– ‘Innovative thinking’ to make scheme affordable

– Scheme cost engineeredfrom £28m to £12m

– Managing electrical safety through design

• Staged plan for delivery:

– Basics before Dec 2012

– Innovation after Dec 2012

• Two areas of innovation

• Novel Operational Method:

– ALARP solution proposed

• Remote OLE Earthing System:

– Paisley Canal is ideal opportunity to develop concept

– Whole life costs of an earthing system need to be factored in

• Transferable benefits - cost savings for electrification on rural and secondary routes

– Not East Kilbride though…

Page 30: Paisley Canal ‘Low Cost’ Electrification

ScotRail EMU to East Kilbride…

Page 31: Paisley Canal ‘Low Cost’ Electrification

Thank You!


Top Related