Joint Meeting of Gloucester County School Board and Board of Supervisors
October 27, 2011
Page Middle School Discussion
R R M M A R C H IT E C T S
Since our meeting on September 20, 2011…
Option A1 – New 800 Student Middle School on Walker Road Site (6-8)
Option A2 - New 800 Student Middle School on Walker Road Site (6-8)
Option B – New 800 Student Middle School on Page Site (6-8)
Add-Ons
9th Grade House @ Walker Road Site
Geothermal Option
Administration and Operations Center @ Page Site
New Football Field @ Walker Road Site
New Softball Field @ Walker Road Site
Option C – 800 Student Renovation and Addition on Page Site (6-8)
Backup Data for Each Cost Model and Add-On
Basis of Cost (No Deductions Shown for Insurance Settlement)
R R M M A R C H IT E C T S
PAGE MIDDLE SCHOOL
COST OPTION SUMMARY
Title Brief Description Probable Total Project Cost Comments
Option A1 6-8 Middle School on Walker Rd for 800
students. $28,169,690
Option A2 6-8 Middle School on Walker Rd for 800
students. $27,937,322 Slightly better location for utilities than A1 and better
opportunity for future high school connection.
Option B 6-8 Middle School on Page Site for 800
students. $26,703,772
Add-on 1 9th Grade House at Walker Road Site $11,742,000
Add-on 2 Geothermal Option $750,000
Add-on 3 High School A-Wing Renovations $2,132,100
Add-on 4 Administration and Operations Center
@ Page $14,220,365 Includes renovation of existing auditorium, gym, lobby.
Add-on 5 New Football Field @ Walker Road 600,000 Replaces football field at Page Site. Includes lights and 25
additional parking spaces.
Add-on 6 New Softball Field @ Walker Road 185,000 Replaces softball fields at Page Site. Includes lights and 25
additional parking spaces.
Option C 6-8 Middle School Renovation/Addition
on Page Site for 800 students $22,193,780 Assumes SF/student, on-site and off-site improvements
comparable to Option B.
R R M M A R C H IT E C T S
Date: 10/27/2011
Option A1 Option B
New 6-8 for 800 Walker Road Site New 6-8 for 800 Page Site
Construction Costs (Hard Costs) Factors Unit Costs Factors Unit Costs
Exceptional Site Costs Allowance (site demo: A- note 1; B- note 2) 1 LS $343,600 1 LS $154,750
Exceptional Site Costs Allowance (Bldg. demo & hazmat removal) 1 LS $-00 1 LS $361,073
General Site Costs (Pkg, pav'g, walks, baseball, track, tennis, etc.) 1 LS $1,953,576 1 LS $1,967,218
Exceptional Site Costs Allowance (signalization) 1 LS $200,000 1 LS $200,000
Exceptional Site Costs Allowance (Turn lanes & off-site imp., etc.) 1 LS $505,000 1 LS $505,000
Exceptional Site Costs Allowance (Road Widening of TC Walker) 1 LS $800,000 1 LS $-00
Exceptional Site Costs Allowance (Water and Sewer) 1 LS $979,840 1 LS $135,000
New Middle School Building (148 SF/P x 800 students)** 118,400 $ 150.00 $17,760,000 118,400 $ 150.00 $17,760,000
Total Construction Cost $22,542,016 $21,083,041
Contingency Factor 5% PCT $1,127,101 6% PCT $1,264,982
Construction Cost Grand Total (w/ Contingency) $23,669,117 $22,348,023
Soft Costs
Prof. Services (A/E, Commissioning, Surveys, Borings, LEED, etc.) 7% PCT $1,577,941 7% PCT $1,475,813
Furnishings/Fixtures/Equipment and Technology Allowance 1 LS $1,964,446 1 LS $1,964,446
Construction Testing/Inspection, Adv./Reprod. 1 LS $137,710 1 LS $137,710
Miscellaneous Soft Costs Total $3,680,097 $3,577,969
Total Project Cost $27,349,214 $25,925,992
Total Project Cost with 3% Escalation $28,169,690 $26,703,772
Version A2 (incl. conting., soft costs & escalation) $27,937,322
R R M M A R C H IT E C T S
Potential Additional Costs
9th Grade House + Core Increase to Accommodate Growth* 50,000 $ 165.00 $8,250,000
Sitework for 9th Grade House 1 LS $1,250,000
Construction Contingency @ 5% 1 LS $475,000
Soft Costs at app. 15% 1 LS $1,425,000
Subtotal w/ 3% escalation $11,742,000
Geothermal Option 1 LS $750,000 1 LS $750,000
HS A-Wing Renovation Allowance 30,000 $ 60.00 $1,800,000
Soft Costs at app. 15% $270,000
Subtotal w/ 3% escalation $2,132,100
Administration and Operations Center Project
Exceptional Site (turn lane allowance) 1 LS $50,000
Exceptional Site (Bldg. demo less gym/audit/main hall.) 1 LS $291,981
Site Work 1 LS $1,348,880
Renovate Existing Gym, Auditorium, Lobby 17,536 $ 50.00 $876,800
New Administration & Operations Bldg + Transportation 67,444 $ 120.00 $8,093,280
Convert Transportation Bldg to Grounds 1 LS $383,109
Hazmat Removal (incl. in bldg. demo) 1 LS $-00
Construction Contingency (5%) 1 LS $558,161
Soft Costs 1 LS $2,204,221
Total Project Cost w/ 3% escalation $14,220,625
Replace Page Football Field @ Walker Rd. Site (w/ lights) 1 LS $600,000
Replace Page Softball Field @ Walker Rd. Site (w/ lights) 1 LS $185,000
*Increase incl. auditorium exp. 400 to 800 (4,450), 9th Gr. House (31,082), Admin (600), Media Ctr Core (200), Special Programs (3,100) + efficiency factor. **Basis for Costs - See Attachment
Note 1 - Walker Road site demo primarily clearing and grubbing of timber. Note 2 - Page site includes general clearing/demo but not the $361,073 for demo of main building noted on the next line.
R R M M A R C H IT E C T S
Site Plan
Option A1
R R M M A R C H IT E C T S
Site Plan
Option A1
R R M M A R C H IT E C T S
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs
Option A1 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Existing George Washington Highway/TC Walker Road intersection
New traffic signal ($200,000) Extend northbound right-turn lane to 200’ taper, 300’ storage ($50,000) Extend southbound left-turn lane to 200’ taper, 300’ storage ($50,000) New westbound right turn lane - 200’ taper, 200’ storage ($125,000)
R R M M A R C H IT E C T S
Option A1 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Existing TC Walker Road New westbound right turn lane at the proposed main school entrance – 200’ taper, 200’ storage ($125,000) New westbound right turn lane at the proposed bus entrance – 200’ taper, 200’ storage ($125,000) School Zone Advance Warning Speed Limit Signage Assembly and Flashing Beacons ($30,000)
Subtotal Turn Lane Improvements - $505,000
Widen existing 2-lane road to new 3-lane road for approximately 0.3 mile. Widened road would include left turn lanes into two proposed site entrances. ($800,000)
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs (cont’d)
R R M M A R C H IT E C T S
Option A1 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Water 3,000’ of new 8” or 10” fire service from site service entrance to George Washington Hwy.
($225,000) Bore and jack 80’ under George Washington Hwy. northbound lanes ($30,000) Tap existing 12” water main ($40,000) Double check detector and vault ($15,000) 3” water meter and vault ($5,000) Tap fee – County ($25,200) Tap fee – HRSD ($59,140)
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs (cont’d)
R R M M A R C H IT E C T S
Option A1 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Sewer 3,000’ of new 4” or 6” force main from site service entrance to George Washington Hwy.
($225,000) Tap existing 18” HRSD force main ($75,000) New on-site pump station ($250,000) Tap fee – County ($30,500)
Water and Sewer Subtotal - $979,840
Construction Cost Opinion = $2,484,840
(Does not include soft costs for surveying and design fees, right-of-way acquisition, or permit fees)
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs (cont’d)
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs
Option A1 - New 800 Student School on TC Walker Road Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Site Demolition:
Earthwork (Cut/Fill/Dispose) 24,200 CY $ 8.00 $ 193,600 $ 193,600.00
Clear & Grub 30 ACRE $ 5,000.00 $ 150,000 $ 150,000.00
Total Site Demolition $ 343,600.00
New Sitework:
Practice Field/Track Practice Field 175,000 SF $ 1.00 $ 175,000 $ 415,000
Track Running Surface/Striping 48,000 SF $ 5.00 $ 240,000
Baseball Field Field Base Fill/Drain/Surface 1 Field $ 25,000.00 $ 25,000 $ 38,600
Dug-Outs Bating Areas 2,200 SF $ 3.00 $ 6,600
Fencing 200 LF $ 35.00 $ 7,000
Hard Surface Play Area Base Pad/Asphalt Surfacing 10,800 SF $ 6.00 $ 64,800 $ 64,800
Tennis Courts Base/Surfacing 2 Court $ 45,000.00 $ 90,000 $ 130,500
Striping/Posts/Netting 2 Court $ 3,500.00 $ 7,000
Fencing/Gates 460 LF $ 25.00 $ 11,500
Lighting 4 Poles $ 5,500.00 $ 22,000
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option A1 - New 800 Student School on TC Walker Road Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Fitness Development
Soft Mulch Workout Area Pad 1,500 SF $ 10.00 $ 15,000 $ 15,000
Bus Parking/Loop with Drive Lanes
Heavy Duty Asphalt Parking 3,889 SY $ 30.00 $ 116,667 $ 181,867
Heavy Duty Asphalt Drive Lanes 667 SY $ 30.00 $ 20,000
Striping 480 LF $ 0.50 $ 240
Symbols/Directional Arrows 18 EA $ 95.00 $ 1,710
Curb & Gutters 1,700 LF $ 20.00 $ 34,000
Signage 10 EA $ 125.00 $ 1,250
Site Lighting 4 EA $ 2,000.00 $ 8,000
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option A1 - New 800 Student School on TC Walker Road Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Vehicular Parking with Drive Lanes
Light Duty Asphalt Parking 7,778 SY $ 25.00 $ 194,444 $ 334,144
Light Duty Asphalt Drive Lanes 3,000 SY $ 25.00 $ 75,000
Striping 3,750 LF $ 0.50 $ 1,875
Symbols/Directional Arrows 10 EA $ 95.00 $ 950
Curb & Gutters 2,000 LF $ 20.00 $ 40,000
Signage 15 EA $ 125.00 $ 1,875
Site Lighting 10 EA $ 2,000.00 $ 20,000
Entry Drive Lanes
Heavy Duty Asphalt Drive Lanes 4,000 SY $ 30.00 $ 120,000 $ 158,075
Striping 1,000 LF $ 0.50 $ 500
Symbols/Directional Arrows 10 EA $ 95.00 $ 950
Curb & Gutters 1,300 LF $ 20.00 $ 26,000
Signage 5 EA $ 125.00 $ 625
Site Lighting 5 EA $ 2,000.00 $ 10,000
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option A1 - New 800 Student School on TC Walker Road Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Landscaping/Seeding
Large Trees 13 EA $ 350.00 $ 4,550 $ 18,080
Medium Trees 24 EA $ 245.00 $ 5,880
Small Trees 10 EA $ 125.00 $ 1,250
Shrubs 50 EA $ 45.00 $ 2,250
Groundcover 250 EA $ 15.00 $ 3,750
Mulch Beds 10 CY $ 40.00 $ 400
Site Signage
Fire Lane Signs 12 EA $ 134.00 $ 1,608 $ 1,858
Stop/Directional/Info Signs 2 EA $ 125.00 $ 250
Concrete Walks/Pads
Concrete Walks 6,500 SF $ 4.00 $ 26,000 $ 38,500
HC Ramps/Walk Features 5 LOC $ 1,500.00 $ 7,500
Pads 1,000 SF $ 5.00 $ 5,000
Earthwork
Erosion Control 5,000 LF $ 3.00 $ 15,000 $ 296,652
Cut/Fill/Dispose 14,520 CY $ 8.00 $ 116,160
BMP w/Control Measures 7,500 CY $ 18.00 $ 135,000
Stabilization/Seeding 435,600 SF $ 0.07 $ 30,492
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option A1 - New 800 Student School on TC Walker Road Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Storm System w/Structures 3,000 LF $ 60.00 $ 180,000 $ 180,000
Sanitary Sewer System w/Structures 500 LF $ 40.00 $ 20,000 $ 20,000
Water System w/ Vault/Meter (in off site) $ - $ - $ -
Water System w/ Vault/Meter $ - $ - $ -
(incl. w/ off site work)
Fire Line System w/ Structures 500 LF $ 35.00 $ 17,500 $ 17,500
Offsite Utility Allowance (incl. in off site) $ - $ - $ -
Gas Service 1 LS $ 8,000.00 $ 8,000 $ 8,000
Power Service / Transformers 1 LS $ 35,000.00 $ 35,000 $ 35,000
Total New Sitework $ 1,953,576
R R M M A R C H IT E C T S
Site Plan
Option A2
R R M M A R C H IT E C T S
Site Plan
Option A2
R R M M A R C H IT E C T S
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs – Version A2
Option A2 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Existing George Washington Highway/TC Walker Road Intersection New Traffic Signal ($200,00) New Northbound right-turn lane to 200’ taper, 300’ storage ($50,000) Extend Southbound left-turn lane to 200’ taper, 300’ storage ($50,000) New Westbound right-turn lane – 200’ taper, 200’ storage ($125,000)
R R M M A R C H IT E C T S
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs – Version A2 (cont’d)
Option A2 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Existing TC Walker Road Widen existing 2-lane road to 3-lane road 500’ on either side of the easement entrance, approximately 1,000’. Widened road would include left turn lane into proposed site entrance. ($550,000) Assume 15,000 sf of wetlands impacts with road widening. Based on $180,000 per acre mitigation cost (2:1 ratio), wetlands mitigation fee approximated at $62,000. New Westbound right-turn lane at the proposed main school entrance – 200’ taper, 200’ storage ($125,000) School Zone Advance Warning Speed Limit Signage Assembly and Flashing Beacons ($30,000)
Construction Cost Opinion = $1,317,000 (Does not include soft costs for surveying and design fees, right-of-way acquisition, or permit and impact (fees)
R R M M A R C H IT E C T S
Option A2 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Water
• 800’ of new 8” or 10” fire service from site service entrance to George Washington Hwy. ($60,000)
• Bore and jack 80’ under George Washington Hwy. northbound lanes ($30,000)
• Tap existing 12” water main ($40,000)
• Double check detector and vault ($15,000)
• 3” water meter and vault ($5,000)
• Tap fee – County ($25,200)
• Tap fee – HRSD ($59,140)
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs – Version A2 (cont’d)
R R M M A R C H IT E C T S
Option A2 – New 800 Student School on TC Walker Road Site (Per attached RRMM sketch) Based on preliminary analysis, the following improvements are anticipated:
Sewer
• 800’ of new 4” or 6” force main from site service entrance to George Washington Hwy. ($60,000)
• Tap existing 18” or 24” HRSD force main ($75,000)
• New on-site pump station ($250,000)
• Tap fee – County ($30,500)
Construction Cost Opinion = $979,840 (Does not include soft costs for surveying and design fees, right-of-way acquisition, or permit fees)
Total Option A2 = $2,296,840 or $188,000 less than A1. $188,000 x 1.05 contingency = $197,400. $197,400 + $28,200 soft costs = $225,600. $225,600 x 1.03 escalation = $232,368. Thus bottom line of Option A2 is $28,244,391.
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs – Version A2 (cont’d)
R R M M A R C H IT E C T S
Site Plan
Option B
R R M M A R C H IT E C T S
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs
Option B – New 800 Student School on Existing Page MS Site (Per attached RRMM Sketch) Based on preliminary analysis, the following improvements are anticipated:
Proposed George Washington Highway/TC Walker Road bus entrance
New traffic signal ($200,000)
New northbound left-turn lane – 200’ taper, 300’ storage ($150,000)
New southbound right-turn lane – 200’ taper, 300’ storage ($150,000)
Existing George Washington Highway/Page MS entrance
Extend northbound left-turn lane to 200’ taper, 200’ storage ($50,000)
New south bound right-turn lane – 200’ taper, 200’ storage ($125,000)
R R M M A R C H IT E C T S
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs (cont’d)
Option B – New 800 Student School on Existing Page MS Site (Per attached RRMM Sketch) Based on preliminary analysis, the following improvements are anticipated:
Existing George Washington Highway
Replace Existing School Zone Advance Warning Speed Limit Signage Assembly and Flashing Beacons ($30,000)
Subtotal Turn Lane Improvements – ($505,000)
Water
New 8” fire service required for new school’s sprinkler system ($60,000)
Assume existing domestic water service is adequate
R R M M A R C H IT E C T S
Option B – New 800 Student School on Existing Page MS Site (Per attached RRMM Sketch) Based on preliminary analysis, the following improvements are anticipated:
Sewer
Assume existing pump station requires upgrading ($50,000)
Assume existing force main is requires relocation on site ($25,000)
Water and Sewer Subtotal – ($135,000)
Construction Cost Opinion = $840,000
(Does not include soft costs for surveying and design fees, right-of-way acquisition, or permit and impact fees)
Offsite Transportation & Utility Improvements Preliminary Opinion of Construction Costs (cont’d)
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Site Demolition:
Existing Tennis Courts 2 EA $ 1,200.00 $ 2,400 $ 2,400
Existing Roadway Pavement 10 Loads $ 500.00 $ 5,000 $ 5,000
Existing Parking Pavement 20 Loads $ 500.00 $ 10,000 $ 10,000
Earthwork (Cut/Fill/Dispose) 12,100 CY $ 6.00 $ 72,600 $ 117,600
Clear & Grub 18 ACRE $ 2,500.00 $ 45,000
Signage - EA $ - $ - $ -
Misc. Existing Building Pads and Structures-Heavy Equipment Removal-Disposal
Other Pads and Structures 10 Loads $ 500.00 $ 5,000 $ 6,500
Fencing 1 Loads $ 500.00 $ 500
Bleachers 1 Loads $ 500.00 $ 500
Tanks/Vaults 1 Loads $ 500.00 $ 500
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Unforeseen Underground Services 1 LS $ 5,000.00 $ 5,000 $ 5,000
Utility Removal (Disposal Costs) `
Storm 5 Load $ 500.00 $ 2,500 $ 3,500
Sanitary 1 Load $ 500.00 $ 500
Water 1 Load $ 500.00 $ 500
Site Lighting 18 Pole $ 250.00 $ 4,500 $ 4,500
Landscaping 1 LS $ 250.00 $ 250 $ 250
Total Site Demolition $ 154,750.00
Main School Structure Demo (incl. Hazmat) 91643 $ 3.94 $ 361,073 $ 361,073
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
New Sitework:
Practice Field/Track
Practice Field 175,000 SF $ 1.00 $ 175,000 $ 415,000
Track Running Surface/Striping 48,000 SF $ 5.00 $ 240,000
Baseball Field
Field Base Fill/Drain/Surface 1 Field $ 25,000.00 $ 25,000 $ 38,600
Dug-Outs Bating Areas 2,200 SF $ 3.00 $ 6,600
Fencing 200 LF $ 35.00 $ 7,000
Hard Surface Play Area
Base Pad/Asphalt Surfacing 10,800 SF $ 6.00 $ 64,800 $ 64,800
Tennis Courts
Base/Surfacing 2 Court $ 45,000.00 $ 90,000 $ 130,500
Striping/Posts/Netting 2 Court $ 3,500.00 $ 7,000
Fencing/Gates 460 LF $ 25.00 $ 11,500
Lighting 4 Poles $ 5,500.00 $ 22,000
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Fitness Development
Soft Mulch Workout Pad Area 1,500 SF $ 10.00 $ 15,000 $ 15,000
Bus Parking/Loop with Drive Lanes
Heavy Duty Asphalt Parking 3,889 SY $ 30.00 $ 116,667 $ 181,867
Heavy Duty Asphalt Drive Lanes 667 SY $ 30.00 $ 20,000
Striping 480 LF $ 0.50 $ 240
Symbols/Directional Arrows 18 EA $ 95.00 $ 1,710
Curb & Gutters 1,700 LF $ 20.00 $ 34,000
Signage 10 EA $ 125.00 $ 1,250
Site Lighting 4 EA $ 2,000.00 $ 8,000
Vehicular Parking with Drive Lanes
Lite Duty Asphalt Parking 7,778 SY $ 25.00 $ 194,444 $ 334,144
Lite Duty Asphalt Drive Lanes 3,000 SY $ 25.00 $ 75,000
Striping 3,750 LF $ 0.50 $ 1,875
Symbols/Directional Arrows 10 EA $ 95.00 $ 950
Curb & Gutters 2,000 LF $ 20.00 $ 40,000
Signage 15 EA $ 125.00 $ 1,875
Site Lighting 10 EA $ 2,000.00 $ 20,000
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Entry Drive Lanes
Heavy Duty Asphalt Drive Lanes 4,000 SY $ 30.00 $ 120,000 $ 158,075
Striping 1,000 LF $ 0.50 $ 500
Symbols/Directional Arrows 10 EA $ 95.00 $ 950
Curb & Gutters 1,300 LF $ 20.00 $ 26,000
Signage 5 EA $ 125.00 $ 625
Site Lighting 5 EA $ 2,000.00 $ 10,000
Grounds/Transportation Pavement Rework/Addition
Heavy Duty Asphalt Drive Overlay 13,333 SY $ 5.00 $ 66,667 $ 85,642
Striping 2,800 LF $ 0.50 $ 1,400
Symbols/Directional Arrows 10 EA $ 95.00 $ 950
Curb & Gutters 800 LF $ 20.00 $ 16,000
Signage 5 EA $ 125.00 $ 625
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Landscaping/Seeding
Large Trees 13 EA $ 350.00 $ 4,550 $ 18,080
Medium Trees 24 EA $ 245.00 $ 5,880
Small Trees 10 EA $ 125.00 $ 1,250
Shrubs 50 EA $ 45.00 $ 2,250
Groundcover 250 EA $ 15.00 $ 3,750
Mulch Beds 10 CY $ 40.00 $ 400
Site Signage
Fire Lane Signs 12 EA $ 134.00 $ 1,608 $ 1,858
Stop/Directional/Info Signs 2 EA $ 125.00 $ 250
Concrete Walks/Pads
Concrete Walks 6,500 SF $ 4.00 $ 26,000 $ 38,500
HC Ramps/Walk Features 5 LOC $ 1,500.00 $ 7,500
Pads 1,000 SF $ 5.00 $ 5,000
Earthwork
Erosion Control 5,000 LF $ 3.00 $ 15,000 $ 296,652
Cut/Fill/Dispose 14,520 CY $ 8.00 $ 116,160
BMP w/Control Measures 7,500 CY $ 18.00 $ 135,000
Stabilization/Seeding 435,600 SF $ 0.07 $ 30,492
R R M M A R C H IT E C T S
Onsite Costs Improvements
Preliminary Opinion of Construction Costs (cont’d)
Option B - New 800 Student School on Existing Page MS Site
Section Descriptions Qty Unit Cost per Unit Total Section Total Cost
Storm System w/Structures 1,800 LF $ 60.00 $ 108,000 $ 108,000
Sanitary Sewer System w/Structures 500 LF $ 40.00 $ 20,000 $ 20,000
Water System w/ Vault/Meter $ - $ - $ -
(incl. w/ off site work)
Fire Line System w/ Structures 500 LF $ 35.00 $ 17,500 $ 17,500
Gas Service 1 LS $ 8,000.00 $ 8,000 $ 8,000
Power Service / Transformers 1 LS $ 35,000.00 $ 35,000 $ 35,000
Total New Sitework $ 1,967,218
R R M M A R C H IT E C T S
Option C
New 6-8 for 800 Page Site
Construction Costs (Hard Costs) Factors Unit Costs
Exceptional Site Costs Allowance (site demo)* 1 LS $154,750
Exceptional Site Costs Allowance (Bldg. demo & hazmat removal)** 1 LS $153,951
General Site Costs (Pkg, pav'g, walks, baseball, track, tennis, etc.) 1 LS $1,982,218
Exceptional Site Costs Allowance (signalization) 1 LS $200,000
Exceptional Site Costs Allowance (Turn lanes & off-site imp., etc.) 1 LS $505,000
Exceptional Site Costs Allowance (Water and Sewer) 1 LS $135,000
Renovation of Existing Page (hazmat removal in portion to remain) 52,569 $ 1.95 $102,510
Renovation of Existing Page 52,569 $ 70.00 $3,679,830
New Middle School Building (148 SF/P x 800 students)*** 65,831 $ 150.00 $9,874,650
Total Construction Cost $16,787,909
Contingency Factor 6% PCT $1,007,275
Construction Cost Grand Total (w/ Contingency) $17,795,183
Soft Costs
Prof. Services (A/E, Commissioning, Surveys, Borings, LEED, etc.) 10% PCT $1,678,791
Furnishings/Fixtures/Equipment and Technology Allowance 1 LS $1,964,446
Construction Testing/Inspection, Adv./Reprod. 1 LS $108,940
Miscellaneous Soft Costs Total $3,752,176
Total Project Cost $21,547,359
Total Project Cost with 3% Escalation $22,193,780
Geothermal Option 1 LS $750,000 *Page Site includes clearing and demo but not the $153,951 for demo of tornado damaged area.
**Based on actual bid + monitoring of 39,074 sf being demo'd. Does not include front bldg. portion.
***Square footage based on 118,400 sf (800 x 148 sf/student) less existing52,569 sf of renovation. Thus,
new addition of est. 65,831 sf.
R R M M A R C H IT E C T S
Middle Schools and High Schools – Oct. 2011
Basis of Costs – Costs included below are construction costs (Bid Costs) and
do not include soft costs, construction contingencies, FFE and the like. Bid
prices vary depending on site conditions, required site work, complexity,
quality, size, schedule and many other factors but most importantly the market
activity at the time of bid. Costs shown are averages and tempered by current
market conditions.
Costs are also preliminary and are averages from across the state within
varying economic zones, schedule constraints, quality standards and many
other factors. See attached Dept. of Education cost data used as a resource.
R R M M A R C H IT E C T S
Office Building
Recommend $140/sf.
(RS Means Construction Cost Data)
Middle School
09-10 avg. – $142.17.
6 year avg. costs = $171.91
2011 to date – no projects.
Budget Recommendation –
$175 ($150 building, $25 site) + escalation to bid date (3%)
6 year average SF/Student =148 Recommend 148 sf/student
High School
09-10 avg. – $0. No High Schools built.
08-09 avg. - $209.05
5 year avg. costs = $186.16
2011 to date – $210.39
Budget Recommendation - $195 ($165 building, $30 site)
6 year average SF/Student = 152
2011 average SF/Student = 164
Recommend 160 sf/student
R R M M A R C H IT E C T S
R R M M A R C H IT E C T S
Football and Softball Field Cost Breakdown
Football Field:
Football Field = $150,000
Football Field Lights at 10 LOC/$5,000 EA = $50,000
Bleachers at 2000 Seats = $ 220,000
Parking Spaces at 25 @ $2,000/EA = $50,000
Fencing 8' High at 4,000 LF = $60,000
Total = $530,000
$530,000 x 1.1 for design/contingency = $583,000
$583,000 x 1.03 for escalation = $600,490
App. $600,000
R R M M A R C H IT E C T S
Football and Softball Field Cost Breakdown (cont’d)
Softball Field:
Softball Field = $25,000
Softball Field Lights at 8 LOC/$5,000 EA = $40,000
Bleachers at 300 Seats = $ 33,000
Parking Spaces at 25 @ $2,000/EA = $50,000
Fencing 8' High at 1,000 LF = $15,000
Total = $163,000
$163,000 x 1.1 for design/contingency = $179,300
$179,300 x 1.03 for escalation = $184,679
App. $185,000
R R M M A R C H IT E C T S
Joint Meeting of Gloucester County School Board and Board of Supervisors
October 27, 2011
Page Middle School Discussion