MaineDOT Projects Under Construction April 23, 2018
# of Projects: 314# of Contracts: 231
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
023011.00 Acton 023229.00 023229.00 MAINTENANCEACTON, WEARING
SURFACE REPLACEMENT
SHOEM CORP
GARY PELLETIER
Robert Mcferren
018995.11
Acton, Hollis, Buxton,
Biddeford, Dayton, Lyman,
Wells
018955.11 018995.11 HIGHWAY
PRESERVATION PAVING
CRACK SEALING 2018 -REGION 1
COASTAL ROAD REPAIR LLC.
RESIDENT?
Laray Hamilton 5/1/18 10/1/18
016871.00 Amherst 021711.00 021711.00 BRIDGE PRESERVATION
AMHERST, SUMNER BRIDGE PAINT
PANTHER INDUSTRIAL
PAINTING LLC
DAVID DOUCETTE
Devin Anderson 7/6/17 1/4/18
022409.00 Appleton, Camden, Hope
022409.00 022409.00 MAINTENANCE CLINTON, CULVERT REPLACEMENTS
PRATT & SONS, INC.
JAMIE ANDREWS
James Andrews 8/9/17
018983.00 Arundel 018996.00 018996.00 BRIDGE REHABILITATION
ARUNDEL, B&M RAILROAD BRIDGE
WEAR SURF AND PIERREHAB
T BUCK CONSTRUCTION, INC.
JOHN AUGER
Joel Kittredge 1/25/18 6/28/18
023284.00 Ashland, Castle
Hill, Mapleton 2328400 023284.00 HIGHWAY
PRESERVATION PAVING
ASHLAND, ROUTE 163,ULTRA-THIN BONDED
WEARING COURSE
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Roger Soucy 6/15/18 9/15/18
023379.00 Ashland, GarfieldPlt 023379.00 023379.00 MAINTENANCE
ASHLAND - GARFIELD, CULVERT
REPLACEMENTS
ED PELLETIER & SONS, CO.
JAMES BALL
Keith Richards
016862.00 Auburn, Lewiston
NHPP-1872(100) 018721.00 BRIDGE
PRESERVATION
LEWISTON - AUBURN, VIETNAM MEMORIAL
WEST BR PAINT
PANTHER INDUSTRIAL
PAINTING LLC
PETER BROWN
Devin Anderson 6/13/17 12/1/17
022599.00 Auburn, Lewiston
STP-2259(900)
022599.00 BRIDGE
REHABILITATION
AUBURN, REHABILITATION OF
BERNARD LOWN PEACE BRIDGE
CPM CONSTRUCTORS
DAVID SHERLOCK
Joel Kittredge 3/19/18 10/2/18
020853.00 Auburn, Turner NHPP-2085(300) 020853.00
HIGHWAY PRESERVATION
PAVING
AUBURN/TURNER ROUTE 4 MILL AND
FILL
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Guy Whittington 5/1/18 10/13/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018774.00 AugustaSTP-
1877(400) 018774.00 HIGHWAY
PRESERVATION PAVING
AUGUSTA, MILL AND FILL AND PARKING
LOT REHABILITATION, AIRPO
CROOKER CONSTRUCTION LLC
AKA HARRY C CROOKER & SONS,
INC.
KYLE MACDONALD
Douglas Coombs 7/13/18 10/1/18
018771.00 Augusta STP-1877(200)
018772.00 HIGHWAY
PRESERVATION PAVING
AUGUSTA, CIVIC CENTER DRIVE MILL &FILL; 1 1/4" OVERLAY
LANE CONSTRUCTION
CORPORATION (THE)
KYLE MACDONALD
Douglas Coombs
7/5/17 6/1/18
021712.00 Augusta 02171200 021712.00 BRIDGE PRESERVATION
AUGUSTA, CALUMET BRIDGE PAINT
SPARTAN CONTRACTING LLC
DAVID DOUCETTE
Devin Anderson 7/3/17 2/12/18
021980.00 Augusta NHPP-2198(000) 021980.00
HIGHWAY PRESERVATION
PAVING
AUGUSTA, ROUTE 3 ULTRA-THIN BONDED
WEARING COURSE
ALL STATES ASPHALT, INC.
EDITH GIGGEY
Douglas Coombs 5/15/18 9/22/18
018771.00 Augusta STP-1877(100)
018771.00 HIGHWAY
PRESERVATION PAVING
AUGUSTA, CAPITOL STREET & ARMORY STREET MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
KYLE MACDONALD
Douglas Coombs
7/5/17 6/1/18
018771.00 Augusta STP-1877(300)
018773.00 HIGHWAY
PRESERVATION PAVING
AUGUSTA, SEWALL STREET MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
KYLE MACDONALD
Douglas Coombs
7/5/17 6/1/18
023444.10 Augusta 023444.10 023444.10 BRIDGE REHABILITATION
AUGUSTA, RAMP F SUPERSTR REPL
WYMAN & SIMPSON, INC.
CANDACE THOMPSON
Joseph Stilwell
021763.00
Augusta, Richmond,
Gardiner, West Gardiner,
Bowdoinham, Waterville,
Fairfield, Benton,Clinton
021763.00 021763.00 BRIDGE PRESERVATION
CONCRETE BRIDGE COATINGS
INTERSTATE REGION 2
WYMAN & SIMPSON, INC.
MARK PINKOSKI
Joseph Stilwell 4/30/18 12/10/18
018857.00 Augusta, Winthrop
STP-2255(400) 022554.00
HIGHWAY PRESERVATION
PAVING
AUGUSTA, ROUTE 202WESTERN AVENUE
MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
MICHAEL SULLIVAN 312-2713
Shawn Smith 6/17/15 7/1/17
023183.00 Baldwin 023183.00 023183.00 MAINTENANCEBALDWIN, WEARING
SURFACE REPLACEMENT
WYMAN & SIMPSON, INC.
GARY PELLETIER
Donald Mckenna
020811.00 Bangor NHPP-2081(100) 020811.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BANGOR, RAMP IMPROVEMENTS, I-95
SB. EXIT RAMP 185.
LANE CONSTRUCTION
CORPORATION (THE)
Rhobe Moulton 5/14/18 10/20/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018966.00 Bangor 018967.00 018967.00 BRIDGE REHABILITATION
BANGOR, I-95 NB/PERRY ROAD AND
MCRR BRIDGE
WYMAN & SIMPSON, INC.
TRAVIS HAMEL
Michael Wight 8/23/18 7/25/19
018966.00 Bangor 018966.00 018966.00 BRIDGE REHABILITATION
BANGOR, I-95 SB/PERRY ROAD AND
MCRR BRIDGE
WYMAN & SIMPSON, INC.
TRAVIS HAMEL
Michael Wight 8/23/18 7/25/19
016871.00 BangorSTP-
2166(200) 021662.00 BRIDGE
PRESERVATIONBANGOR, MORSE
BRIDGE PAINT
PANTHER INDUSTRIAL
PAINTING LLC
RESIDENT?
Devin Anderson 7/6/17 12/7/17
021743.00 Bangor 2167400 021674.00 BRIDGE PRESERVATION
BANGOR, SIX MILE FALLS BRIDGE WEAR
SURF REPL
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Michael Wight 5/16/18 8/22/18
021902.00 Bangor 021902.00 021902.00 ADMINISTRATIONBANGOR - DESIGN
AND BUILD STORAGE BUILDING
RALPH MCNAUGHTON
CONSTRUCTION INC
STEVE HALL 592-7907
Richard Bradbury
020811.00 Bangor HSIP-2269(400) 022694.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BANGOR, RAMP IMPROVEMENTS, I-95
NB. ON-RAMP 185.
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Rhobe Moulton 5/14/18 10/20/18
020855.00
Bangor, Veazie,Orono, Old
Town, Alton, Argyle Twp
NHPP-2085(500)
020855.00 HIGHWAY
PRESERVATION PAVING
BANGOR - ALTON, INTERSTATE-95 NB,
ULTRA-THIN BONDED WEARING
ALL STATES ASPHALT, INC.
RESIDENT?
Shawn Smith 6/1/18 9/1/18
019197.00 Bar Harbor AC-STP-1919(700)X
019197.00 HIGHWAY CONSTRUCTION
BAR HARBOR, HIGHWAY
RECONSTRUCTION, RTE.3
SARGENT CORPORATION
DALE MAYO 592-7811
Rhobe Moulton 1/4/17 6/15/19
022674.00 Bath HSIP-2267(400) 022674.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BATH, SAFETY IMPROVEMENTS,
RTE.1 WITH HIGH ST. RAMP
PRATT & SONS, INC.
GLENN PHILBROOK
Brian Keezer 9/18/17 6/15/18
018725.00 Bath 1872510 018725.10 BICYCLE-PEDESTRIAN
BATH, CENTRE STREET CONNECTION
SIDEWALK CONSTRUCTION
T BUCK CONSTRUCTION, INC.
GLENN PHILBROOK
Joel Kittredge 2/12/18 8/24/18
018725.00 Bath STP-1872(500) 018725.00 BRIDGE
CONSTRUCTION
BATH, CENTRE STREET CONNECTION
BRIDGE DECK REPL
T BUCK CONSTRUCTION, INC.
GLENN PHILBROOK
Joel Kittredge 2/16/18 6/29/18
022626.00 Beals, Jonesport STP-2262(600)
022626.00 BRIDGE CONSTRUCTION
BEALS - JONESPORT, BEALS ISLAND BRIDGE
REPLACEMENT.
CPM CONSTRUCTORS
PHIL ROBERTS
Leanne Timberlake
9/8/17 1/11/21
022683.00 Belfast HSIP-2268(300) 022683.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BELFAST, SAFETY IMPROVEMENTS, US.
RTE.1.
LANE CONSTRUCTION
CORPORATION (THE)
STEPHEN HALL
Aurele GorneauIi 4/16/18 9/27/18
024244.00 Belfast 024244.00 024244.00 MAINTENANCEBELFAST BRIDGE
JOINT REPLACEMENTS
GORDON CONTRACTING INC.
CY ADAMS
?
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
020858.00 Belfast 022996.01 022996.01 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
BELFAST, ROUTE 1 VEHICLE
ENFORCEMENT
LANE CONSTRUCTION
CORPORATION (THE)
DEAN ROWLANDS
Stephen Bodge 6/19/17 9/1/17
018253.00 Belgrade STP-1825(300)X 018253.00 HIGHWAY
CONSTRUCTION
BELGRADE, HIGHWAY RECONSTRUCTION,
RTE.27.PRATT & SONS, INC.
ANNE LOWE
Ernest Martin 4/16/18 10/19/19
012773.00 Belgrade STP-1277(300)X 012773.00 HIGHWAY
REHABILITATION
BELGRADE, HIGHWAY REHABILITATION,
RTE.8.
PIKE INDUSTRIES, INC.
ANNE LOWE
Rhobe Moulton 3/15/18 6/3/19
020858.00 Belmont, Belfast STP-2085(800)
020858.00 HIGHWAY
PRESERVATION PAVING
BELMONT-BELFAST, ROUTE 3 1 1/4"
OVERLAY AND MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
DEAN ROWLANDS
Douglas Coombs
6/30/17 6/1/18
022482.10 Benton 022482.55 022482.55 MAINTENANCEBENTON, ROUTE 139
PMRAP PUGMILL SUPPORT
PIKE INDUSTRIES, INC.
HEATHER GROVES
?
023854.00 Benton 023854.00 023854.00 MAINTENANCE WINSLOW - ALBION DITCHING
PIKE INDUSTRIES, INC.
JAMIE ANDREWS
James Andrews 8/1/17 10/21/17
022482.10 Benton 022482.10 022482.10 HIGHWAY REHABILITATION
BENTON ROUTE 139 PMRAP BENTON-
CLINTON ROUTE 11 PMRAP
PIKE INDUSTRIES, INC.
HEATHER GROVES
Emory Lovely 4/15/18 8/15/18
022482.10 Benton, Clinton 022484.10 022484.10 HIGHWAY REHABILITATION
BENTON/CLINTON ROUTE 11 PMRAP
PIKE INDUSTRIES, INC.
HEATHER GROVES
Emory Lovely 4/15/18 8/15/18
022104.00 Bethel 024612.00 024612.00 MAINTENANCE BRIDGE MILLING ROUTE 26
PIKE INDUSTRIES, INC.
SCOTT COOK
Robert Mcferren
022084.00
Biddeford, Kennebunkport,
Arundel, Kennebunk,
Acton, Alfred, Lebanon,
Sanford, North Berwick, Wells, South Berwick,
Berwick
022084.00 022084.00 HIGHWAY LIGHT CAPITAL PAVING
BERWICK AREA 2018 LCP LIGHT CAPITAL
PAVING
PIKE INDUSTRIES, INC.
GEORGE MORRELL
Emory Lovely 7/9/18 8/17/18
020544.00 Biddeford, Saco CM-2054(400) 020544.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BIDDEFORD - SACO, TRAFFIC SIGNAL MODIFICATIONS,
RTE.1 AND EL
A. D. ELECTRIC, INC.
DENNIS FOLSOM
441-4372
Brian Keezer 10/5/17
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
021839.00 Bingham, Concord Twp 022253.00 022253.00 MAINTENANCE BRIDGE DECK
REPLACEMENTPIKE INDUSTRIES,
INC.
SCOTT COOK 215-3533
Mark Hume
012667.00 Blaine, Mars HillNH-
1266(700)E 012667.00 HIGHWAY
CONSTRUCTION
BLAINE - MARS HILL, HIGHWAY
RECONSTRUCTION, US RTE.1
SODERBERG COMPANY, INC.
DERYLE SPONBERG
Roger Soucy 4/30/18 7/8/19
022878.00 Boothbay Harbor 022878.00 022878.00 MAINTENANCEBOOTHBAY CULVERT
REPLACEMENTHAGAR
ENTERPRISES, INC.
JAMIE ANDREWS
James Andrews
022110.00
Bradford, Orneville Twp, Milo, Levant, Kenduskeag,
Newport, Corinna,
Orrington, Dixmont,
Newburgh, Hampden, Etna,
Stetson, Pittsfield, Exeter,
Corinth, Garland, Palmyra
022110.00 022110.00 HIGHWAY LIGHT CAPITAL PAVING
STETSON AREA 2018 LCP LIGHT CAPITAL
PAVING
LANE CONSTRUCTION
CORPORATION (THE)
JARED STANLEY
Emory Lovely 8/29/18 10/2/18
018575.00 BrewerNHPP-
1864(600) 018646.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
BREWER, TRAFFIC SIGNAL
MODIFICATION, RTE.9A. D. ELECTRIC, INC.
STEVE HALL
Aurele GorneauIi 3/20/18 7/2/18
018575.00 BrewerSTP-
1857(500) 018575.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
BREWER, TRAFFIC SIGNAL
MODIFICATION, WILSON & N. MAIN
ST'S.
A. D. ELECTRIC, INC.STEVE HALL
Aurele GorneauIi 3/20/18 7/2/18
018575.00 Brewer STP-2089(700) 020897.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
BREWER, TRAFFIC SIGNAL
MODIFICATION, RTE.1A W/ THOMPSON
AND
A. D. ELECTRIC, INC.STEVE HALL
Aurele GorneauIi 3/20/18 7/2/18
019109.00 Bridgton NHP-2028(100) 020281.00
HIGHWAY PRESERVATION
PAVING
BRIDGTON, ROUTE 302 1 1/4" OVERLAY
ALVIN J. COLEMAN & SON, INC.
DAVE SHERLOCK 233-7751
Laray Hamilton 8/31/15 5/25/18
019109.00 Bridgton, Fryeburg
NH-1910(900)E 019109.00 HIGHWAY
CONSTRUCTION
FRYEBURG/ BRIDGTON, HIGHWAY RECONSTRUCTION,US
. RTE.302
ALVIN J. COLEMAN & SON, INC.
DAVE SHERLOCK 233-7751
Ernest Martin 8/16/15 3/26/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022878.00 Bristol 022880.00 022880.00 MAINTENANCE BRISTOL CULVERT REPLACEMENT
HAGAR ENTERPRISES, INC.
JAMIE ANDREWS
James Andrews
020503.00 Brownville STP-2050(300)
020503.00 BRIDGE CONSTRUCTION
BROWNVILLE, JUNCTION BRIDGE
REPLACEMENT
T BUCK CONSTRUCTION, INC.
TIMOTHY HEBERT
557-8914
Michael Wight 12/25/17 2/4/19
020860.00 Brunswick NHPP-2086(000) 020860.00
HIGHWAY PRESERVATION
PAVING
BRUNSWICK, I-295 RAMPS EXIT 28 MILL &
FILL
CROOKER CONSTRUCTION LLC
AKA HARRY C CROOKER & SONS,
INC.
RESIDENT?
Laray Hamilton 5/1/18 10/1/18
021671.00 Bucksport STP-2167(100) 021671.00 BRIDGE
PRESERVATION
VERONA-BUCKSPORT,DR. EDWARD THEGEN
MEMORIAL BRIDGE
LANE CONSTRUCTION
CORPORATION (THE)
TRAVIS HAMEL
Michael Wight 6/12/18 12/3/18
021679.00 Calais 021679.00 021679.00 BRIDGE
PRESERVATION
CALAIS, INTERNATIONAL
BRIDGE WEARING SURFACE
SEALCOATING
GORDON CONTRACTING INC.
TRAVIS HAMEL
Devin Anderson 2/20/18 5/29/18
022888.00 Camden 022888.00 022888.00 MAINTENANCE CAMDEN, CULVERT INVERT LINING
CULVERT REHABILITATION
SERVICES (DIV. OF CLH & SON)
JAMIE ANDREWS
James Andrews
018285.00 CaratunkSTP-
1828(500) 018285.00 HIGHWAY
CONSTRUCTION
CARATUNK, HIGHWAY RECONSTRUCTION,
RTE.201
ALVIN J. COLEMAN & SON, INC.
JEFFREY WALLACE 592-6143
Rhobe Moulton 10/11/16 8/1/18
024306.00 Carrabassett Valley
024404.00 024404.00 MAINTENANCECARRABASSETT
VALLEY, GUARDRAIL REPLACEMENT
C A NEWCOMB & SONS, INC.
DAVID MERRILL
?
024306.00 Carrabassett
Valley024306.00 024306.00 MAINTENANCE
CARRABASSETT VALLEY, GUARDRAIL
REPLACEMENT
C A NEWCOMB & SONS, INC.
DAVID MERRILL
Mark Hume
022935.00 Carthage 024232.00 024232.00 MAINTENANCE
CARTHAGE CATCH BASIN ADJUSTMENTS
AND CULVERT REPLACEMENTS
PRATT & SONS, INC.
TIMOTHY ANDREWS
?
020500.00 Chester, Lincoln STP-205(000) 020500.00 BRIDGE
CONSTRUCTION
CHESTER-LINCOLN, PENOBSCOT RIVER
BRIDGE DECK REPLACEMENT.
CPM CONSTRUCTORS
TIM HEBERT
Michael Wight 8/20/18 2/15/19
021770.00 China 21770.00 021770.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
CHINA, LARGE CULVERT
REPLACEMENT, RTE'S 3/202.
F C WORK & SONS, INC.
RESIDENT?
Douglas Coombs 5/30/18 9/13/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
021980.00
China, Palermo,Liberty,
Montville, Searsmont,
Morrill, Belmont
2329000 023290.00 HIGHWAY
PRESERVATION PAVING
CHINA-BELMONT, ROUTE 3 ULTRA-THIN
BONDED WEARING COURSE
ALL STATES ASPHALT, INC.
EDITH GIGGEY
Douglas Coombs 5/15/18 9/22/18
024238.00 Clinton 024238.00 024238.00 MAINTENANCE CLINTON BRIDGE RAILREPLACEMENT
C A NEWCOMB & SONS, INC.
JAMIE ANDREWS
?
024242.00 Clinton 024242.00 024242.00 MAINTENANCE CLINTON SLOPE REPAIR
F C WORK & SONS, INC.
MATTHEW WHITCOMB
?
022571.00 Corinna, Dexter STP-2257(100)
022571.00 HIGHWAY
PRESERVATION PAVING
CORINNA - DEXTER, ROUTE 7 HOT-IN-
PLACE RECYCLING
PIKE INDUSTRIES, INC.
JOSEPH GRAHAM
446-0407
Randall Barrows
4/26/17 6/8/17
022088.00
Cumberland, Yarmouth,
Falmouth, Gray,New Gloucester
022088.00 022088.00 HIGHWAY LIGHT CAPITAL PAVING
CUMBERLAND AREA 2018 LCP LIGHT CAPITAL PAVING
PIKE INDUSTRIES, INC.
GEORGE MORRELL
Emory Lovely 6/4/18 6/24/18
022106.00
Cutler, ColumbiaFalls, Addison,
Jonesport, Jonesboro,
Whiting, Machiasport, East Machias
022106.00 022106.00 HIGHWAY LIGHT CAPITAL PAVING
JONESPORT AREA 2018 LCP LIGHT CAPITAL PAVING
GENERAL CONTRACTOR
VAUGHN D. THIBODEAU II
JARED STANLEY
Emory Lovely 8/1/18 9/5/18
024302.00 Dallas Plt 024302.00 024302.00 MAINTENANCERANGELEY, GUARDRAIL
REPLACEMENT
C A NEWCOMB & SONS, INC.
DAVID MERRILL
Mark Hume
023802.00 Damariscotta 023802.00 023802.00 MAINTENANCEDAMARISCOTTA
CULVERT REPLACEMENT
HAGAR ENTERPRISES, INC.
MATTHEW WHITCOMB
James Andrews
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022094.00
Damariscotta, South Bristol,
Bristol, Jefferson, Bowdoin,
Bowdoinham, Richmond, Lewiston, Sabattus,
Lisbon, Greene,Harpswell, West
Bath, Bath, Topsham, Woolwich, Arrowsic,
Georgetown, Dresden
022094.00 022094.00 HIGHWAY LIGHT CAPITAL PAVING
BRISTOL AREA 2018 LCP LIGHT CAPITAL
PAVING
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE
Emory Lovely 8/1/18
018958.00 Day Block Twp 018958.00 018958.00 BRIDGE CONSTRUCTION
DAY BLOCK TWP, PEMBROKE BRIDGE
REPLACEMENT.
CPM CONSTRUCTORS
TRAVIS HAMEL
Michael Wight 12/27/17 7/25/18
020205.00 Dayton STP-2020(500)
020205.00 HIGHWAY CONSTRUCTION
DAYTON, ROUNDABOUT
CONSTRUCTION, RTE'S 5/35.
SHAW BROTHERS CONSTRUCTION, INC.
KYLE PLOSSAY
Laray Hamilton 3/1/18 7/13/18
018246.00 Dexter STP-1824(600) 018246.00 HIGHWAY
CONSTRUCTION
DEXTER, HIGHWAY RECONSTRUCTION,
RTE.7MAINE EARTH
HARVEY SMITH
Ernest Martin 8/7/17 11/19/18
018860.00 Dixfield STP-1886(000)
018860.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
DIXFIELD, TRAFFIC SIGNALS, RTE.2 AND
RTE.142PRATT & SONS, INC.
WILLIAM CROSBY
Aurele GorneauIi
9/12/17 4/6/18
019169.00 Dixfield AC-STP-1916(900)X
019169.00 HIGHWAY CONSTRUCTION
DIXFIELD, HIGHWAY RECONSTRUCTION,
RTE'S 2/17PRATT & SONS, INC.
RACHEL DAMON
Rhobe Moulton 1/31/18 10/28/19
022648.00 Dover-Foxcroft 22648.00 022648.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
DOVER FOXCROFT, LARGE CULVERT REPLACEMENT,
RTE.15
S E MACMILLAN
CARLTON PEABODY
Randall Barrows 7/18/18 11/21/18
018733.00 Dover-Foxcroft STP-1873(300) 018733.00 BRIDGE
PRESERVATION
DOVER-FOXCROFT, THIRD BRIDGE SCOURCOUNTERMEASURES
GORDON CONTRACTING INC.
CARLTON PEABODY
Michael Wight 8/9/18 12/24/18
021779.10 Dover-Foxcroft 021779.10 021779.10 HIGHWAY REHABILITATION
DOVER-FOXCROFT ROUTE 7 PMRAP
PIKE INDUSTRIES, INC.
MICHAEL IRELAND
Emory Lovely 8/6/18 9/29/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022876.00 Dresden, Richmond
022876.00 022876.00 MAINTENANCE RICHMOND CULVERT REPLACEMENTS
SUNKAZE PROJECT SOLUTIONS, INC.
JAMIE ANDREWS
James Andrews
022094.00 Dresden, Woolwich
024052.00 024052.00 MAINTENANCE SOUTH BRISTOL ROUTE 129 MILLING
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE
James Andrews
021781.00 Durham HSIP-2178(100) 021781.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
DURHAM, SAFETY IMPROVEMENTS,
RTE.125 AND QUAKER MEETING
A. D. ELECTRIC, INC.JOHN KELLEY
Catherine Rand 12/18/17
020425.00 Dyer Brook, Island Falls
NHP-2042(500)
020425.00 HIGHWAY
PRESERVATION PAVING
DYER BROOK-ISLAND FALLS INTERSTATE 95
SOUTHBOUND
LANE CONSTRUCTION
CORPORATION (THE)
JON BITHER
Shawn Smith 5/9/17 7/1/18
018734.00 E TwpSTP-
1873(400) 018734.00 BRIDGE
CONSTRUCTION
E TWP, THREE BROOKS BRIDGE
REPLACEMENT
SODERBERG COMPANY, INC.
TROY DEVOE
Michael Wight 7/2/18 11/16/18
024011.75 East Machias 024011.75 024011.75 HIGHWAY LIGHT CAPITAL PAVING
MACHIAS ADA UPGRADES
SUNKAZE PROJECT SOLUTIONS, INC.
SCOTT AUSTIN
Emory Lovely
022094.00 Edgecomb 024048.00 024048.00 MAINTENANCEEDGECOMB
MAINTENANCE LOT PAVING
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE
James Andrews
018980.00 Edgecomb 018980.00 018980.00 BRIDGE PRESERVATION
EDGECOMB, COD COVE BRIDGE REHAB
PANTHER INDUSTRIAL
PAINTING LLC
GLENN PHILBROOK
Joel Kittredge 7/6/17 4/6/18
022878.00 Edgecomb 022929.00 022929.00 MAINTENANCE EDGECOMB CULVERT REPLACEMENT
HAGAR ENTERPRISES, INC.
JAMIE ANDREWS
James Andrews
015608.00 Eliot 2185600 021856.00 BRIDGE PRESERVATION
ELIOT, STURGEON CREEK BRIDGE
PAINTINGMONOKO, LLC
BENJAMIN WALZ
Devin Anderson 1/24/18 7/11/18
014259.04 Ellsworth 14259.04 014259.04 FREIGHTELLSWORTH, BRIDGE
REHABILITATION, UNION RIVER BRIDGE
LANE CONSTRUCTION
CORPORATION (THE)
BRIAN REEVES
Brian Reeves 2/12/18 5/25/18
019196.00 Ellsworth AC-STP-1919(600)X 019196.00 HIGHWAY
CONSTRUCTION
ELLSWORTH, HIGHWAY
RECONSTRUCTION, RTE. 1A
R F JORDAN & SONS CONSTRUCTION, INC.
JEFF COFFIN 592-0743
Rhobe Moulton 6/13/16 6/1/18
018950.00 Embden, Solon 018950.00 018950.00 BRIDGE REHABILITATION
EMBDEN - SOLON, SUPERSTRUCTURE
REPLACEMENTREED & REED, INC.
RESIDENT?
Leanne Timberlake 5/1/18 4/2/19
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022832.00 Etna 023686.00 023686.00 MAINTENANCE ETNA CULVERT REPLACEMENT
GORDON CONTRACTING INC.
SCOTT AUSTIN
Joe Prescott
022092.00 Fairfield 024046.00 024046.00 MAINTENANCEFAIRFIELD
MAINTENANCE LOT PAVING
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE
James Andrews
018961.00 Falmouth 018961.00 018961.00 BRIDGE
REHABILITATION
DUNHAM ROAD BRIDGE, FALMOUTH
CULVERT INVERT LINING
DREW CORPORATION
RESIDENT?
Joseph Stilwell 5/31/18 8/23/18
020204.00 Falmouth STP-2020(400) 020204.00 HIGHWAY
CONSTRUCTION
FALMOUTH, ROUNDABOUT
CONSTRUCTION, RTE.9 / WOODS RD.
A H GROVER, INC.JIM FERGUSON
Ernest Martin 7/18/17 5/2/18
020352.00 Farmington 20352.00 020352.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
FARMINGTON, LARGE CULVERT
REHABILITATION, RTE.4
E L VINING & SON, INC.
PATRICK BRYANT
Guy Whittington 6/9/17 11/15/17
021724.00 Fort Fairfield 021724.00 021724.00 BRIDGE
PRESERVATIONFORT FAIRFIELD - BRIDGE PAINTING GEMSTONE, LLC
JAMES BALL
Benjamin Foster 9/20/17 10/23/17
021652.00 Freeport 2242400 022424.00 HIGHWAY
PRESERVATION PAVING
FREEPORT,US ROUTE1 2" MILL AND FILL
WITH 1/2" SHIM
PIKE INDUSTRIES, INC.
RESIDENT?
Laray Hamilton 6/1/18 10/1/18
021652.00 Freeport STP-2165(200) 021652.00
HIGHWAY PRESERVATION
PAVING
FREEPORT, US ROUTE1 1 1/4" OVERLAY/ 2" MILL AND FILL WITH S
PIKE INDUSTRIES, INC.
RESIDENT?
Laray Hamilton 6/1/18 10/1/18
023011.00 Fryeburg 023217.00 023217.00 MAINTENANCEFRYEBURG, WEARING
SURFACE REPLACEMENT
SHOEM CORP
GARY PELLETIER
Donald Mckenna
019415.00 Gouldsboro AC-STP-1941(500)X
019415.00 BICYCLE-PEDESTRIAN
GOULDSBORO, PEDESTRIAN SAFETY
IMPROVEMENTS, RTE.186
WELLMAN PAVING
TRAVIS SOUTHWICK
Aurele GorneauIi
3/21/18 6/22/18
018765.00 Gray NHPP-1876(500)
018765.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
GRAY, TRAFFIC SIGNAL
MODIFICATIONS, RTE.26.
A. D. ELECTRIC, INC.WILL SAVAGE
Brian Keezer 3/15/18 5/1/18
018622.10 Hallowell 18622.10 018622.10 HIGHWAY CONSTRUCTION
HALLOWELL, PIPE OUTFALLS, WATER ST.
ST. LAURENT & SON, INC.AKAMAINE
HEAVY EQUIPMENT RENTAL, INC.
RESIDENT?
Ernest Martin 11/13/17 5/31/18
018737.00 Hallowell STP-1873(700) 018737.00 BRIDGE
PRESERVATION
HALLOWELL, MILLIKENS CR BRIDGE
WEAR SURF REPL
GORDON CONTRACTING INC.
DAVE DOUCETTE 592-0302
Joel Kittredge 3/20/17 5/26/17
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018622.00 Hallowell STP-1862(200)
018622.00 HIGHWAY CONSTRUCTION
HALLOWELL, HIGHWAY
RECONSTRUCTION, RTE.201.
SARGENT CORPORATION
KAREN LIBBY
Ernest Martin 4/2/18 9/18/18
022118.00
Hamlin, Saint Agatha, PresqueIsle, Frenchville,
Madawaska, Van Buren,
Mapleton, CastleHill, Wade, Washburn
022118.00 022118.00 HIGHWAY LIGHT CAPITAL PAVING
PRESQUE ISLE AREA 2018 LCP LIGHT CAPITAL PAVING
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Emory Lovely 6/27/18 7/20/18
023712.00 Hampden, Eddington
023712.00 023712.00 MAINTENANCEEDDINGTON AND HAMPDEN SLOPE FAILURE REPAIR
SUNKAZE PROJECT SOLUTIONS, INC.
SCOTT AUSTIN 441-7425
Alden Mclaughlin
020815.00 HartlandSTP-
2081(500) 020815.00 BRIDGE
CONSTRUCTION
ATHENS-HARTLAND, CORSON CORNER BR.
CULVERT REPL.S E MACMILLAN
RESIDENT?
Michael Wight 2/17/18 10/24/18
020509.00 Haynesville STP-2050(900) 020509.00 BRIDGE
CONSTRUCTION
HAYNESVILLE, HAYNESVILLE BRIDGE
SUPERSTRUCTURE REPLACEMENT
CPM CONSTRUCTORS
TIMOTHY HEBERT
557-8914
Michael Wight 6/22/16 11/8/17
022856.00 Hebron 022890.00 022890.00 MAINTENANCE HEBRON, CULVERT REPLACEMENT
ST. LAURENT & SON, INC.AKAMAINE
HEAVY EQUIPMENT RENTAL, INC.
TIMOTHY ANDREWS
Robert Holbrook 7/15/17
018973.00 Hermon 018973.00 018973.00 BRIDGE REHABILITATION
HERMON, POND ROADDECK REPL
LANE CONSTRUCTION
CORPORATION (THE)
ROBBIN LANPHER 592-0132
Michael Wight 5/19/17 8/16/17
023318.00 Hermon, Hampden
023318.00 023318.00 HIGHWAY
PRESERVATION PAVING
HERMON-HAMPDEN, COLDBROOK ROAD,
CPR
LANE CONSTRUCTION
CORPORATION (THE)
BILL LUCAS
Randall Barrows
4/6/18 11/5/18
023011.00 Hiram 023011.00 023011.00 MAINTENANCEHIRAM, WEARING
SURFACE REPLACEMENT
SHOEM CORP
GARY PELLETIER
Donald Mckenna
021684.10 Hodgdon, Cary
Plt 021684.55 021684.55 MAINTENANCECARY-HODGDON
ROUTE 1 PUGMILL SUPPORT
STEELSTONE INDUSTRIES, INC.
ROGER BARNES
Joe Tedford
019280.00 Hollis BR-1928(100)X 019281.00 BRIDGE
CONSTRUCTION
HOLLIS, CANAL BRIDGE
REPLACEMENT PLUS OTHER INCIDENTAL
WORK.
WYMAN & SIMPSON, INC.
PETER BROWN 592-6473
Mark Parlin 4/13/15 12/22/17
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
021886.00 Hollis NHPP-2188(600)
021886.00 BRIDGE CONSTRUCTION
HOLLIS BRADBURY BRIDGE #3763
CULVERT REHABILITATION
PROSHOT CONCRETE, INC.
RESIDENT?
Joel Kittredge 6/12/18 9/4/18
022917.00 Hope, Appleton 022917.00 022917.00 MAINTENANCECAMDEN, HOPE, AND APPLETON CULVERT
REPLACEMENTSJAKE BARBOUR INC.
JAMIE ANDREWS
James Andrews
022996.03 Howland 022996.03 022996.03 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
HOWLAND, ROUTE 6, OPERATIONAL AND
SAFETY IMPROVEMENTS
LANE CONSTRUCTION
CORPORATION (THE)
MARK AUSTIN `
Stephen Bodge 5/15/18 10/15/18
016705.00 Howland, Enfield BH-1670(500)X
016705.00 BRIDGE CONSTRUCTION
PENOBSCOT RIVER BRIDGE REPL.
REED & REED, INC.PHIL ROBERTS
557-5169
Michael Wight 3/20/15 12/29/17
018798.00 Indian Twp Res, Waite 023392.00 023392.00
HIGHWAY PRESERVATION
PAVING
INDIAN TWP-WAITE, US ROUTE 1
HIGHWAY CYCLICAL PAVEMENT RES
LANE CONSTRUCTION
CORPORATION (THE)
MICHAEL THOMAS
Randall Barrows 3/21/18 10/18/18
020425.00 Island Falls,
Crystal, Sherman
NHP-2042(800) 020428.00
HIGHWAY PRESERVATION
PAVING
ISLAND FALLS - SHERMAN
INTERSTATE 95 SOUTHBOUND
LANE CONSTRUCTION
CORPORATION (THE)
JON BITHER
Shawn Smith 5/9/17 7/1/18
022094.00 Jefferson 024050.00 024050.00 MAINTENANCEJEFFERSON ROUTE
215 MILLING
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE
James Andrews
023862.00 Jefferson 023862.00 023862.00 MAINTENANCE JEFFERSON DITCHING
NATHAN O NORTHRUP FOREST
PRODUCTS & EARTHWORK
JAMIE ANDREWS
James Andrews 8/21/17 11/2/17
018828.00 Johnson Mountain Twp
18828.00 018828.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
JOHNSON MT. TWP., LARGE CULVERT
REPLACEMENT, US. RTE.201
GORDON CONTRACTING INC.
RACHEL DAMON
Guy Whittington 7/6/18 8/30/18
018290.00 Jonesboro, Whitneyville
STP-1829(000)
018290.00 HIGHWAY REHABILITATION
JONESBORO - WHITNEYVILLE -
MACHIAS, HIGHWAY REHABILITATION,
LANE CONSTRUCTION
CORPORATION (THE)
GALEN COSTIGAN
Randall Barrows
11/29/17 9/18/18
022106.00 Jonesport 024624.00 024624.00 MAINTENANCEJONESPORT AREA 2018 LCP BRIDGE
MILLING AND PAVING
GENERAL CONTRACTOR
VAUGHN D. THIBODEAU II
JARED STANLEY
Emory Lovely
023298.00 Kennebunk,
Arundel, Biddeford
2329800 023298.00 HIGHWAY
PRESERVATION PAVING
KENNEBUNK-ARUNDEL-
BIDDEFORD, US ROUTE 1 ULTRA-THIN
BONDED WE
ALL STATES ASPHALT, INC.
RESIDENT?
Laray Hamilton 5/1/18 10/1/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
015608.00 Kennebunkport BH-1560(800)X
015608.00 BRIDGE PRESERVATION
KENNEBUNKPORT, LORDS BRIDGE
PAINTINGMONOKO, LLC
BENJAMIN WALZ
Devin Anderson 4/2/18 11/1/18
016710.00 Kittery BH-1671(000) 016710.00 BRIDGE
CONSTRUCTION
KITTERY-PORTSMOUTH, BR
#3641
CIANBRO CORPORATION
RON TAYLOR 446-2885
Jeffrey Folsom 12/25/14 5/24/18
022996.03 Lagrange, Alton 2330000 023300.00 HIGHWAY
PRESERVATION PAVING
LAGRANGE TO ALTON,ROUTE 16 ¾" OVERLAY W/
VARIABLE DEPTH SH
LANE CONSTRUCTION
CORPORATION (THE)
MARK AUSTIN
Randall Barrows 4/23/18 7/17/18
023318.00 Levant,
Glenburn, Hermon, Bangor
023388.00 023388.00 HIGHWAY
PRESERVATION PAVING
LEVANT TO BANGOR, ROUTE 222, CPR
LANE CONSTRUCTION
CORPORATION (THE)
BILL LUCAS
Randall Barrows 4/6/18 11/5/18
016862.00 Lewiston 018998.00 018998.00 BRIDGE PRESERVATION
LEWISTON, RAMP A BRIDGE PAINT
PANTHER INDUSTRIAL
PAINTING LLC
PETER BROWN
Devin Anderson 6/16/17 1/26/18
023231.00 Lewiston 023231.00 023231.00 MAINTENANCELEWISTON, BRIDGE
JOINTSGORDON
CONTRACTING INC.
GARY PELLETIER
Donald Mckenna
022599.00 Lewiston NHPP-1865(000)
018650.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
LEWISTON, AUXILIARY TURNING
LANES
CPM CONSTRUCTORS
DAVID SHERLOCK
Joel Kittredge 3/20/18 12/20/18
016862.00 Lewiston 018999.00 018999.00 BRIDGE PRESERVATION
LEWISTON, RAMP D BRIDGE PAINT
PANTHER INDUSTRIAL
PAINTING LLC
PETER BROWN
Devin Anderson 6/16/17 1/26/18
022225.00 Lincoln 022225.00 022225.00 MAINTENANCE LINCOLN MILL AND FILL
SHOEM CORP
MATTHEW CONNOR
592-1165
?
020868.00 Lisbon NHPP-2086(800) 020868.00
HIGHWAY PRESERVATION
PAVING
LISBON, ROUTE 196 MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Laray Hamilton 6/1/18 10/1/18
021712.00 Litchfield, West
Gardiner02175700 021757.00
BRIDGE PRESERVATION
WEST GARDINER, TAPPAN BRIDGE
PAINT
SPARTAN CONTRACTING LLC
DAVID DOUCETTE
Devin Anderson 7/4/17 2/13/18
023324.00 Litchfield, West
Gardiner 023324.00 023324.00 HIGHWAY
PRESERVATION PAVING
LITCHFIELD, ROUTE 9 HIGHWAY CYCLICAL
PAVEMENT RESURFACING
CROOKER CONSTRUCTION LLC
AKA HARRY C CROOKER & SONS,
INC.
ROB CLEWLEY
Douglas Coombs 4/30/18 5/28/18
023302.00 Littleton, Monticello 2330200 023302.00
HIGHWAY PRESERVATION
PAVING
LITTLETON-MONTICELLO US
ROUTE 1 ULTRA-THIN BONDED WEARING CO
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Roger Soucy 6/15/18 9/15/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022471.00 Lubec 022471.00 022471.00 MAINTENANCE LUBEC SLOPE STABILIZATION
SUNKAZE PROJECT SOLUTIONS, INC.
SCOTT AUSTIN
Joe Lacerda
021675.00 Ludlow, Houlton 021675.00 021675.00 BRIDGE PRESERVATION
HOULTON - LUDLOW, WEARING SURFACE
REPLACEMENTS
RANGER CONTRACTING INC.
CARL DODGE
Michael Wight 7/30/18 12/17/18
022501.00 Lyman NHPP-2250(100) 022501.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
LYMAN, FLASHING BEACON SIGNS, RTE.
111.
SHAW BROTHERS CONSTRUCTION, INC.
WILLIAM CROSBY
Brian Keezer 5/15/18 8/30/18
022102.00 Magalloway Plt 024512.00 024152.00 MAINTENANCE MAGALLOWAY BRIDGEMILLING AND PAVING
PIKE INDUSTRIES, INC.
SCOTT COOK
Robert Holbrook
020870.00 Mars Hill, Westfield
NHPP-2087(000) 020870.00
HIGHWAY PRESERVATION
PAVING
MARS HILL - WESTFIELD US
ROUTE 1 MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
SPENCER MAYNARD
Roger Soucy 6/14/18 8/22/18
018965.00 Masardis 018965.00 018965.00 BRIDGE REHABILITATION
MASARDIS, ST. CROIX BRIDGE DECK REPL
BMB CONSTRUCTIONLLC
TROY DEVOE
Michael Wight 3/7/18 8/8/18
022937.00 Mattawamkeag 022937.00 022937.00 MAINTENANCE
MATTAWAMKEAG MOLUNKUS
MACWAHOC, CULVERT
REPLACEMENTS
THOMAS DICENZO, INC.
JAMES BALL
Anthony Dow
023758.00 Medway 023758.00 023758.00 MAINTENANCEMEDWAY, EROSION
STABILIZATIONSUNKAZE PROJECT
SOLUTIONS, INC.
JAMES BALL
Joe Tedford
022451.00 Medway 022451.00 022451.00 MAINTENANCE MEDWAY ROOFING REPLACEMENTS
GORDON CONTRACTING INC.
JAMES BALL 592-1165
?
021765.00
Medway, Sherman,
Crystal, Island Falls, Oakfield, Smyrna, Ludlow,
Houlton
021765.00 021765.00 BRIDGE PRESERVATION
CONCRETE BRIDGE COATINGS
INTERSTATE REGION 5
GORDON CONTRACTING INC.
CARL DODGE
Joseph Stilwell 4/30/18 12/10/18
018498.00 Mexico STP-1849(800)
018498.00 BRIDGE CONSTRUCTION
PERU - MEXICO, ANDROSCOGGIN
RIVER BRIDGE REPLACEMENT
WYMAN & SIMPSON, INC.
CATHERINE METTEY
446-0683
Leanne Timberlake
12/19/16 7/23/18
019312.00 Milford STP-2050(500) 020505.00 BRIDGE
CONSTRUCTION
MILFORD, SUNKHAZE BRIDGE
REPLACEMENTREED & REED, INC.
TROY DEVOE 592-6270
Leanne Timberlake 11/30/16 3/7/18
019312.00 Milford AC-IM-1931(200)X 019312.00 BRIDGE
CONSTRUCTION
MILFORD, LOWER TRESTLE BRIDGE
REPLACEMENTREED & REED, INC.
TROY DEVOE 592-6270
Leanne Timberlake 11/30/16 3/7/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022090.00
Minot, Auburn, Lovell,
Stoneham, Albany Twp,
Otisfield, Oxford,Waterford
022090.00 022090.00 HIGHWAY LIGHT CAPITAL PAVING
OXFORD AREA 2018 LCP LIGHT CAPITAL
PAVING
PIKE INDUSTRIES, INC.
GEORGE MORRELL
Emory Lovely 8/20/18 9/21/18
023968.00 Montville, Knox 023968.00 023968.00 MAINTENANCE MONTVILLE TO KNOX, DITCHING
F C WORK & SONS, INC.
JAMIE ANDREWS
James Andrews
018285.00 Moscow NHPP-2199(600) 021996.00
HIGHWAY PRESERVATION
PAVING
MOSCOW - CARATUNK, 3/4"
OVERLAY, RTE.201
ALVIN J. COLEMAN & SON, INC.
JEFFREY WALLACE 592-6143
Guy Whittington 11/1/16 7/30/17
019197.00 Mount Desert STP-2269(900) 022699.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
MT. DESERT - SOMESVILLE,
INTERSECTION SAFETY
IMPROVEMENTS, R
SARGENT CORPORATION
DALE MAYO 592-7811
Aurele GorneauIi 12/16/16 6/29/18
021819.10 Mount Vernon 022096.00 022096.00 HIGHWAY LIGHT CAPITAL PAVING
MOUNT VERNON LCP AREA 22096.00
PIKE INDUSTRIES, INC.
SCOTT COOK
Emory Lovely 5/28/18 9/7/18
022832.00 Newburgh 022832.00 022832.00 MAINTENANCE NEWBURGH CULVERT REPLACEMENT
GORDON CONTRACTING INC.
SCOTT AUSTIN
Joe Prescott
022647.00 Newburgh 22647.00 022647.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
NEWBURGH, LARGE CULVERT
REPLACEMENT, KENNEBEC RD.
S E MACMILLAN
MICHAEL COMSTOCK
Randall Barrows
8/9/18 1/10/19
023318.00 Newburgh, Hampden 023326.00 023326.00
HIGHWAY PRESERVATION
PAVING
NEWBURGH-HAMPDEN, ROUTE 9,
CPR
LANE CONSTRUCTION
CORPORATION (THE)
BILL LUCAS
Randall Barrows 4/6/18 11/5/18
022413.00 Newburgh,
Orono, Bangor, Carmel
023618.00 023618.00 MAINTENANCE
NEWBURGH, CARMEL, BANGOR, ORONO
BRIDGE RAIL REPLACEMENT
GORDON CONTRACTING INC.
MATTHEW CONNOR
Joe Prescott
015608.00 Newcastle 2173800 021738.00 BRIDGE PRESERVATION
NEWCASTLE, MAIN STREET BRIDGE
PAINTINGMONOKO, LLC
BENJAMIN WALZ
Devin Anderson 1/24/18 10/3/18
022923.00 Newcastle 022923.00 022923.00 MAINTENANCE NEWCASTLE CULVERTREPLACEMENT
HAGAR ENTERPRISES, INC.
JAMIE ANDREWS
James Andrews
018745.00 Newcastle NHPP-1874(500) 018745.00 BRIDGE
PRESERVATION
NEWCASTLE, MARSH RIVER BRIDGE
WEARING SURFACE REPLACEMENT
WYMAN & SIMPSON, INC.
GLENN PHILBROOK
Devin Anderson 7/27/17 5/17/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022654.00 Newport 22654.00 022654.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
NEWPORT, LARGE CULVERT
REPLACEMENT, RTE.222
LANE CONSTRUCTION
CORPORATION (THE)
ROBBIN LANPHER
Randall Barrows
7/13/18 12/3/18
020410.10 Newport 20414.10 020414.10 HIGHWAY REHABILITATION
NEWPORT, HIGHWAY REHABILITATION,
RTE.2
PIKE INDUSTRIES, INC.
RESIDENT?
Emory Lovely 8/2/15 9/18/15
021806.00 OakfieldNHPP-
2180(600) 021806.00 MAINTENANCEOAKFIELD, HIGHWAY LIGHTING, I-95 EXIT
286.A. D. ELECTRIC, INC.
DERYLE SPONBERG
Catherine Rand 8/4/17 5/31/18
020434.00 Oakfield 20434.00 020434.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
OAKFIELD, HIGHWAY REHAB. RIVER RD.
LEE'S GENERAL TRUCKING AKA
EMERY LEE & SONS, INC.
ROGER BARNES
Roger Soucy 7/30/18 11/15/18
022996.03 Old Town 023396.00 023396.00 HIGHWAY
PRESERVATION PAVING
OLD TOWN, ROUTE 43 HIGHWAY CYCLICAL
PAVEMENT RESURFACING
LANE CONSTRUCTION
CORPORATION (THE)
MARK AUSTIN
Randall Barrows 4/23/18 7/17/18
023698.00 Orland 023698.00 023698.00 MAINTENANCE
BUCKSPORT AND ORLAND CULVERT
REPLACEMENTS AND DITCHING
WELLMAN PAVINGSCOTT AUSTIN
592-1853
Joe Prescott
023714.00 Orland, Surry 023714.00 023714.00 MAINTENANCEBUCKSPORT, ORLAND
AND SURRY SLOPE FAILURE REPAIR
SUNKAZE PROJECT SOLUTIONS, INC.
SCOTT AUSTIN 592-1853
Joe Prescott
022110.00 Orneville Twp, Palmyra, Corinna 024626.00 024626.00 MAINTENANCE STETSON AREA 2018
LCP BRIDGE MILLING
LANE CONSTRUCTION
CORPORATION (THE)
JARED STANLEY
Emory Lovely
022692.00 Orono HSIP-2269(200) 022692.00 HIGHWAY
CONSTRUCTION
ORONO, ROUTE 2 ANDRANGELEY ROAD,
ROUNDABOUT CONSTRUCTION.
GARDNER CONSTRUCTION
ENTERPRISES LLC.
WILLIAM BROWN
Rhobe Moulton 3/27/18 12/11/18
021808.00 Owls Head 21808.00 021808.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
OWLS HEAD, LARGE CULVERT
REHABILITATION, RTE.73
JAKE BARBOUR INC.RESIDENT?
Douglas Coombs 5/16/18 7/6/18
018875.00 PalmyraNHPP-
1887(500)018875.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
NEWPORT - PALMYRA,HIGHWAY LIGHTING, I-
95 EXIT 157.A. D. ELECTRIC, INC.
WILLIAM CROSBY
Catherine Rand 8/4/17 5/31/18
022618.00 Paris STP-2261(800) 022618.00 BRIDGE
CONSTRUCTIONPARIS, REHAB
BILLINGS BRIDGEWYMAN & SIMPSON,
INC.
CRAIG HURD
Joel Kittredge 3/24/18 8/1/19
019192.00 Parkman, Guilford
AC-STP-1919(200)X 019192.00 HIGHWAY
CONSTRUCTION
PARKMAN - GUILFORD, HIGHWAY RECONSTRUCTION,
RTE.150
JORDAN EXCAVATION AKA JORDAN LUMBER
COMANY
MATTHEW SWINDELLS
Rhobe Moulton 7/24/17 6/1/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
023115.00 Parlin Pond Twp 023115.00 023115.00 MAINTENANCE PARLIN POND TWP, APPROACH SLAB N F LUCE, INC.
DAVID MERRILL
Douglas Coombs
016867.00 Parsonsfield,
Porter 016867.00 016867.00 BRIDGE
PRESERVATION
PORTER - PARSONSFIELD, BRIDGE PAINTING
COPIA SPECIALTLY CONTRACTORS
GARY PELLETIER
Benjamin Foster 2/1/17 9/13/17
022622.00 PittsfieldNHPP-
2262(200) 022622.00 BRIDGE
CONSTRUCTION
PITTSFIELD, I-95 NB BRIDGE 5990 DECK
REPLACEMENT
CPM CONSTRUCTORS
ROBBIN LANPHER 592-0132
Joel Kittredge 10/29/17 6/29/18
022622.00 Pittsfield NHPP-2262(800) 022628.00 BRIDGE
CONSTRUCTION
PITTSFIELD, I-95 NB BRIDGE 5988 BRIDGE
REPLACEMENT
CPM CONSTRUCTORS
ROBBIN LANPHER 592-0132
Joel Kittredge 10/30/17 6/29/18
022622.00 Pittsfield NHPP-2264(000) 022640.00 BRIDGE
CONSTRUCTION
PITTSFIELD, I-95 NB BRIDGE 5987 DECK
REPLACEMENT
CPM CONSTRUCTORS
ROBBIN LANPHER 592-0132
Joel Kittredge 10/30/17 6/29/18
021743.00 Pittsfield, Etna 021743.00 021743.00 BRIDGE
PRESERVATIONPITTSFIELD, ETNA, WEAR SURF REPL
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Michael Wight 5/16/18 8/22/18
021764.00
Pittsfield, Palmyra, Newport,
Plymouth, Etna,Carmel,
Newburgh, Hampden,
Bangor, Orono, Old Town,
Howland, T2 R8 NWP
021764.00 021764.00 BRIDGE
PRESERVATION
CONCRETE BRIDGE COATINGS
INTERSTATE REGION 4
WYMAN & SIMPSON, INC.
MARK PINKOSKI
Joseph Stilwell 5/1/18 12/11/18
018972.00 Plymouth 018972.00 018972.00 BRIDGE REHABILITATION
PLYMOUTH, ROUTE 7 BRIDGE DECK REPLACEMENT
T BUCK CONSTRUCTION, INC.
ROBBIN LANPHER 592-0132
Michael Wight 5/1/17 10/2/17
021942.05 PortlandSTP-
2194(205) 021942.05 RAILINTL MARINE TERM RR
CAPACITY IMPROVEMENTS.
SHAW BROTHERS CONSTRUCTION, INC.
ED KARPINSKI
Joel Kittredge 3/1/18 6/29/18
022705.01 Portland 22705.01 022705.01 MARINECHEBEAGUE ISLAND,
FERRY TERMINAL REHABILITATION.
WYMAN & SIMPSON, INC.
ED KARPINSKI
Brian Keezer 2/19/18 6/13/18
021942.03 Portland 021942.03 021942.03 MARINE
INTERNATIONAL MARINE TERMINAL
PIER FENDER REPLACEMENTS.
MAINE COAST MARINE
ED KARPINSKI
Joel Kittredge 8/11/17 8/31/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018791.00 Portland NHPP-1879(100)
018791.00 HIGHWAY
PRESERVATION PAVING
PORTLAND, RIVERSIDE STREET
MILL & FILL
SHAW BROTHERS CONSTRUCTION, INC.
BRIAN MOUSSEAU
Laray Hamilton 4/16/18 6/23/18
023215.00 Portland 023215.00 023215.00 MAINTENANCEROOFING, PEAKS ISLAND TERMINAL
BUILDING
LIONEL PLANTE ASSOCIATES
GARY PELLETIER 441-8265
Donald Mckenna
020543.00 Portland STP-2054(300) 020543.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
PORTLAND, SAFETY IMPROVEMENTS, RTE.
302 (FOREST AVE.)
SHAW BROTHERS CONSTRUCTION, INC.
CHARLIE GUY
Aurele GorneauIi 8/14/17 10/5/18
022702.00 Portland, Falmouth
NHHP-2270(200) 022702.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
PORTLAND, INTERSTATE SIGNING,
I-295
ROADSAFE TRAFFIC SYSTEMS, INC.
JOHN DOUGHTY 252-5519
Brian Keezer 11/6/17 5/31/18
023223.00 Pownal 023223.00 023223.00 MAINTENANCE TIMBER DECK REPLACEMENT
NELSON COMMUNICATIONS
SERVICES, INC.
GARY PELLETIER 441-8265
Donald Mckenna
022116.00
Prentiss Twp T7 R3 NBPP, T8 R3
NBPP, T8 R4 NBPP, Danforth,Brookton Twp,
Forest Twp, Forest City Twp,
Mars Hill, Monticello
022116.00 022116.00 HIGHWAY LIGHT CAPITAL PAVING
HOULTON AREA 2018 LCP LIGHT CAPITAL
PAVING
STEELSTONE INDUSTRIES, INC.
ROGER BARNES
Emory Lovely 5/21/18 6/19/18
023327.00 Presque Isle 023327.00 023327.00 MAINTENANCEPRESQUE ISLE WING WALL REPLACEMENT
BMB CONSTRUCTIONLLC
JAMES BALL
Joe Tedford
022583.00 Presque Isle STP-2258(300)
022583.00 HIGHWAY
PRESERVATION PAVING
PRESQUE ISLE, ROUTE 163 MILL &
FILL
LANE CONSTRUCTION
CORPORATION (THE)
SPENCER MAYNARD
Roger Soucy 5/18/18 7/13/18
006462.91 Presque Isle HPP-6462(910) 006462.91 HIGHWAY
CONSTRUCTIONPRESQUE ISLE,
BYPASS.ED PELLETIER &
SONS, CO.
BEECHER WHITCOMB 592-7609
Rhobe Moulton 10/19/16 11/21/18
022583.00 Presque Isle, Fort Fairfield
STP-2259(100) 022591.00
HIGHWAY PRESERVATION
PAVING
PRESQUE ISLE-FORT FAIRFIELD, ROUTE 167
MILL & FILL
LANE CONSTRUCTION
CORPORATION (THE)
SPENCER MAYNARD
Roger Soucy 8/10/17 7/13/18
023398.00 Randolph, Chelsea 023398.00 023398.00
HIGHWAY PRESERVATION
PAVING
RANDOLPH/CHELSEA, ROUTE 226 HIGHWAY CYCLICAL PAVEMENT
RESURF
CROOKER CONSTRUCTION LLC
AKA HARRY C CROOKER & SONS,
INC.
RESIDENT?
Douglas Coombs 5/15/18 9/22/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022935.00 Rangeley 022935.00 022935.00 MAINTENANCE RANGELEY CATCH BASIN ADJUSTMENTS
PRATT & SONS, INC.
TIMOTHY ANDREWS
Robert Holbrook
018955.00 Rangeley 018955.00 018955.00 BRIDGE CONSTRUCTION
RANGELEY, HUNTER COVE BRIDGE REPLACEMENT.
REED & REED, INC.
MICHAEL PELLETIER
Michael Wight 7/12/18 1/3/19
023464.00 Rangeley Plt 023464.00 023464.00 HIGHWAY REHABILITATION
RANGELEY PLANTATION CULVERT
REPLACEMENTSN F LUCE, INC.
TIMOTHY ANDREWS
Mark Hume 1/1/18 10/15/18
022102.00
Rangeley Plt, Sandy River Plt, Weld, Township D, Rangeley,
Byron, TownshipE, Carthage,
Lang Twp, Coplin Plt,
Eustis, Dallas Plt, Magalloway Plt, Lincoln Plt, Adamstown Twp,Lower Cupsuptic
Twp
022102.00 022102.00 HIGHWAY LIGHT CAPITAL PAVING
RANGELEY AREA 2018 LCP LIGHT CAPITAL
PAVING
PIKE INDUSTRIES, INC.
SCOTT COOK
Emory Lovely 7/9/18 9/21/18
024302.00 Rangeley,
Adamstown Twp,Lincoln Plt
024304.00 024304.00 MAINTENANCE
RANGELEY, ADAMSTOWN TWP, AND LINCOLN PLT,
GUARDRAIL REPLACEM
C A NEWCOMB & SONS, INC.
DAVID MERRILL
?
020877.00 Richmond STP-2087(700)
020877.00 HIGHWAY
PRESERVATION PAVING
RICHMOND, ROUTE 197, MILL & FILL
PIKE INDUSTRIES, INC.
RESIDENT?
Douglas Coombs
5/15/18 9/22/18
020877.00 Richmond STP-2087(800)
020878.00 HIGHWAY
PRESERVATION PAVING
RICHMOND, ROUTE 197, MILL & FILL
PIKE INDUSTRIES, INC.
RESIDENT?
Douglas Coombs
5/18/18 11/5/18
018927.00 Richmond 18927.10 018927.10 HIGHWAY CONSTRUCTION
RICHMOND, CROSSOVER
REHABILITATION, I-295
MCGEE CONSTRUCTION
MICHAEL LENKO
Shawn Smith 7/15/18 11/15/18
018927.00 Richmond,
Gardiner, West Gardiner
NHPP-1892(700) 018927.00
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
RICHMOND, LARGE CULVERT
REPLACEMENTS AND REHABILITATIONS, I-
MCGEE CONSTRUCTION
MICHAEL LENKO
Shawn Smith 7/15/18 11/15/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
021839.00
Ripley, Athens, Saint Albans, Wellington, Cambridge,
Mayfield Twp, Harmony
023031.00 023031.00 MAINTENANCE WP2017-MILLING VARIOUS BRIDGE
PIKE INDUSTRIES, INC.
SCOTT COOK 215-3533
Douglas Coombs
018376.10 Rockland 18376.10 018376.10 MARINE
PORLAND, FERRY VESSEL
CONSTRUCTION, ME. ST. FERRY TERMINAL.
WASHBURN & DOUGHTY
ASSOCIATES
STEWART ROGERS
Nathaniel Benoit 12/31/19
022946.00 Rockland 22946.00 022946.00
MAINEDOT MULTIMODAL
SYSTEM OPERATIONS
ROCKLAND, REHABILITATION,
MAINE STATE FERRY TERMINAL PARKING
JAKE BARBOUR INC.RESIDENT?
Brian Keezer 4/15/18 10/31/18
018845.10 Rockland, Rockport 018845.55 018845.55 MAINTENANCE
ROCKLAND-ROCKPORT, OLD COUNTY ROAD
PMRAP
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE 592-1239
James Andrews
018845.10 Rockland, Thomaston
018846.55 018846.55 MAINTENANCE
THOMASTON-ROCKLAND, OLD COUNTY ROAD,
PMRAP
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE 592-1239
James Andrews
021819.10 Rome, Smithfield 021819.10 021819.10 HIGHWAY
REHABILITATIONROME/SMITHFIELD, ROUTE 225 PMRAP
PIKE INDUSTRIES, INC.
SCOTT COOK
Emory Lovely 5/1/18 10/1/18
021819.10 Rome, Smithfield 021819.55 021819.55 MAINTENANCE ROME/SMITHFIELD, ROUTE 225 PMRAP
PIKE INDUSTRIES, INC.
SCOTT COOK
?
023674.00 Roque Bluffs 023674.00 023674.00 MAINTENANCE
JONESBORO AND ROQUE BLUFFS
CULVERT REPLACEMENT
HANSCOM CONSTRUCTION, INC.
SCOTT AUSTIN
Joe Lacerda
023453.00 Roxbury 023453.00 023453.00 MAINTENANCEROXBURY CULVERT
REPLACEMENT
NELSON COMMUNICATIONS
SERVICES, INC.
TIMOTHY ANDREWS 446-7765
Paul Picard
018847.00 Roxbury 18847.00 018847.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
ROXBURY, LARGE CULVERT
REPLACEMENT, RTE.120.
DREW CORPORATION
CATHERINE METTEY
Ernest Martin 2/15/18 5/10/18
023027.00 Rumford 023027.00 023027.00 MAINTENANCE RUMFORD BRIDGE LIGHTING
A. D. ELECTRIC, INC.
DOUG COOMBS
215-4051
Douglas Coombs
020879.00 Saco STP-2088(000) 020880.00
HIGHWAY PRESERVATION
PAVING
SACO, MAIN STREET, MILL & FILL
SHAW BROTHERS CONSTRUCTION, INC.
RESIDENT?
Laray Hamilton 6/1/18 10/1/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
020879.00 Saco STP-2087(900) 020879.00
HIGHWAY PRESERVATION
PAVING
SACO, INDUSTRIAL PARK ROAD, MILL &
FILL
SHAW BROTHERS CONSTRUCTION, INC.
RESIDENT?
Laray Hamilton 6/1/18 10/1/18
022086.00
Saco, Buxton, Scarborough,
Cape Elizabeth, South Portland,
Hollis
022086.00 022086.00 HIGHWAY LIGHT CAPITAL PAVING
SCARBOROUGH AREA 2018 LCP LIGHT CAPITAL PAVING
DAYTON SAND & GRAVEL CO. INC.
GEORGE MORRELL
Emory Lovely 5/14/18 6/1/18
022824.00 Saint Francis 022824.00 022824.00 MAINTENANCESAINT FRANCIS
CULVERT REPLACEMENT
ED PELLETIER & SONS, CO.
JAMES BALL
Anthony Dow
018956.00 Sandy River Plt 018956.00 018956.00 BRIDGE CONSTRUCTION
SANDY RIVER PLT, SOUTH SIDE BRIDGE
REPLACEMENT.
T BUCK CONSTRUCTION, INC.
MICHAEL PELLETIER
Michael Wight 7/3/18 12/17/18
018795.00 Scarborough, South Portland
STP-1879(500) 018795.00
HIGHWAY PRESERVATION
PAVING
SCARBOROUGH-S.PORTLAND, ROUTE
1 MILL & FILL
R. J. GRONDIN & SONS
WILLIAM BROGAN
441-2058
Laray Hamilton 3/20/17 5/19/18
023684.00 Sedgwick 023684.00 023684.00 MAINTENANCESEDGWICK DITCHING
AND CULVERT REPLACEMENT
LEE'S GENERAL TRUCKING AKA
EMERY LEE & SONS, INC.
MATTHEW CONNOR
557-5494
Joe Prescott
022112.00
Sedgwick, Lamoine, Hancock, Sullivan,
Franklin, Orland,Surry, Blue Hill
022112.00 022112.00 HIGHWAY LIGHT CAPITAL PAVING
SURRY AREA 2018 LCPLIGHT CAPITAL
PAVING
GENERAL CONTRACTOR
VAUGHN D. THIBODEAU II
JARED STANLEY
Emory Lovely 5/28/18 9/7/18
022413.00 Sidney 022413.00 022413.00 MAINTENANCE SIDNEY BRIDGE RAIL REPLACEMENT
GORDON CONTRACTING INC.
MATTHEW CONNOR
James Andrews
018948.00 Sidney 018948.00 018948.00 BRIDGE CONSTRUCTION
SIDNEY, MILL POND BRIDGE CULVERT
REPLACEMENT
MANTER CONSTRUCTION
RESIDENT?
Mark Parlin 6/9/18 8/31/18
023400.00 Sidney, Waterville
023400.00 023400.00 HIGHWAY
PRESERVATION PAVING
SIDNEY/WATERVILLE, ROUTE 104, HIGHWAY CYCLICAL PAVEMENT
RESU
PIKE INDUSTRIES, INC.
RESIDENT?
Douglas Coombs
4/24/18 5/25/18
021819.10 Smithfield,
Mercer 021828.10 021828.10 HIGHWAY
REHABILITATIONSMITHFIELD, MERCER.ROUTE 137 PMRAMP
PIKE INDUSTRIES, INC.
SCOTT COOK
Emory Lovely 6/21/18 9/9/18
018747.00 South Berwick STP-1874(700) 018747.00 BRIDGE OTHER
SOUTH BERWICK, REMOVAL OF
VARNEY'S BRIDGE
SCOTT CONSTRUCTION CORPORATION
RESIDENT?
Devan Eaton 3/21/18 6/13/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018795.00 South Portland STP-2254 (200)
022542.00 HIGHWAY
PRESERVATION PAVING
SOUTH PORTLAND, U.S. ROUTE 1 MILL &
FILL
R. J. GRONDIN & SONS
WILLIAM BROGAN
441-2058
Laray Hamilton 3/20/17 5/19/18
020485.00 South Thomaston
STP-2048(500)
020485.00 BRIDGE CONSTRUCTION
SOUTH THOMASTON, WESKEAG BRIDGE OVER WESKEAG
RIVER
REED & REED, INC.
CANDACE THOMPSON 441-5247
Mark Parlin 5/15/17 6/25/18
018845.10 South
Thomaston, Rockland
018850.55 018850.55 MAINTENANCE SOUTH THOMASTON, ROUTE 73 PMRAP
LANE CONSTRUCTION
CORPORATION (THE)
TIMOTHY PELOTTE 592-1239
James Andrews
018282.00 StandishSTP-
1828(200)X 018282.00 HIGHWAY
CONSTRUCTION
STANDISH, HIGHWAY RECONSTRUCTION,
RTE.35.
SHAW BROTHERS CONSTRUCTION, INC.
DANIEL LORING
Laray Hamilton 2/19/18 11/17/18
018947.00 Standish 018947.00 018947.00 BRIDGE
CONSTRUCTION
STANDISH, STATION 135 BRIDGE CULVERT
REPLACEMENT
NELSON COMMUNICATIONS
SERVICES, INC.
KAYLA STICKNEY
Joel Kittredge 3/1/18 9/28/18
021792.00 Statewide 2179200 021792.00 MAINTENANCE I295 MESSAGE BOARDPADS
BMB CONSTRUCTIONLLC
STERLING PAUL
Steven Hunnewell
9/30/17 10/31/17
018906.11B Statewide 018906.21 018906.21 MAINTENANCE
PROTECTIVE COATINGFOR CONCRETE FOUNDATIONS,
OVERHEAD TRUSSE
GORDON CONTRACTING INC.
LEWIS BENNER
Steven Hunnewell
018906.11A Statewide 018906.31 018906.31 MAINTENANCE
PROTECTIVE COATINGFOR CONCRETE FOUNDATIONS, REGIONS 1, 2, 3
COPIA SPECIALTLY CONTRACTORS
LEWIS BENNER 242-2047
Steven Hunnewell
022217.00 Stetson 022217.00 022217.00 MAINTENANCE STETSON STRUT WIDENING
STETSON & WATSON,J. V.
MATTHEW CONNOR
557-5494
?
016665.00 Stockton SpringsSTP-
1666(500) 016665.00 BRIDGE
CONSTRUCTION
STOCKTON SPRINGS, CAPE JELLISON BR
SUPERSTR REPL
T BUCK CONSTRUCTION, INC.
GUY HEWS
Leanne Timberlake 9/15/17 8/28/18
018852.00 Stockton Springs 018852.00 018852.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
STOCKTON SPRINGS, LARGE CULVERT
REPLACEMENT, RTE.1
F C WORK & SONS, INC.
STEPHEN HALL
Douglas Coombs 9/11/17 8/1/18
018286.00 Strong, Avon STP-1828(600) 018286.00 HIGHWAY
CONSTRUCTION
STRONG - AVON, HIGHWAY
RECONSTRUCTION, RTE.4
E L VINING & SON, INC.
PATRICK BRYANT
357-7330
Rhobe Moulton 3/24/17 12/9/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022112.00 Surry, Blue Hill, Franklin
024628.00 024628.00 MAINTENANCE BRIDGE MILLING
GENERAL CONTRACTOR
VAUGHN D. THIBODEAU II
JARED STANLEY
Emory Lovely
022927.00 Swanville 022927.00 022927.00 MAINTENANCE SWANVILLE CULVERT REPLACEMENT
LEE'S GENERAL TRUCKING AKA
EMERY LEE & SONS, INC.
JAMIE ANDREWS
James Andrews 8/21/17
019236.00 T14 R6 WELS, T15 R6 WELS
STP 1923(600)X 019236.00 HIGHWAY
CONSTRUCTION
T14 R06, HIGHWAY RECONSTRUCTION,
RTE.11
SODERBERG COMPANY, INC.
PETER OUELLETTE 215-5657
Ernest Martin 11/14/16 11/11/18
020884.00
T24 MD BPP, T30 MD BPP,
Day Block Twp, Wesley, T26 ED
BPP
NHPP 2088(400) 020884.00
HIGHWAY PRESERVATION
PAVING
T24 MD-WESLEY, ROUTE 9 HOT IN-PLACE RECYCLED
LANE CONSTRUCTION
CORPORATION (THE)
MICHAEL THOMAS
Randall Barrows 3/21/18 10/18/18
021755.00 T6 R8 WELS STP-2175(500) 021755.00 BRIDGE
REHABILITATION
TWP06 R8 WELS, WEARING SURFACE
REPLACEMENT
BMB CONSTRUCTIONLLC
CARL DODGE
Michael Wight 3/14/18 8/15/18
018798.00 Talmadge 022996.02 022996.02 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
STATEWIDE, VEHICLE ENFORCE US ROUTE
1 REST AREA CONSTRUCTI
LANE CONSTRUCTION
CORPORATION (THE)
MICHAEL THOMAS
Stephen Bodge 6/1/18 9/15/18
018953.00 Temple 018953.00 018953.00 BRIDGE REHABILITATION
TEMPLE, BRIDGE STRENGTHENING ANDDECK REPLACEMENT
WYMAN & SIMPSON, INC.
CATHERINE METTEY
Douglas Coombs 6/6/18 10/6/18
017890.00 Thomaston STP-1789(000) 017890.00 HIGHWAY
CONSTRUCTION
THOMASTON, HIGHWAY
RECONSTRUCTION, RTE'S 1/131
LANE CONSTRUCTION
CORPORATION (THE)
SETH WILLS 592-1392
Ernest Martin 4/19/16 9/14/18
015608.00 Thomaston NHPP-1875(000) 018750.00 BRIDGE
PRESERVATION
WARREN, JAMES ANDREW BRIDGE
PAINTINGMONOKO, LLC
BENJAMIN WALZ
Devin Anderson 1/24/18 11/14/18
016871.00 Thorndike 01687100 016871.00 BRIDGE
PRESERVATION
THORNDIKE, SAYWARD BRIDGE
PAINT
PANTHER INDUSTRIAL
PAINTING LLC
DAVID DOUCETTE
Devin Anderson 7/6/17 1/18/18
018798.00 Topsfield 018853.00 018853.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
TOPSFIELD US ROUTE 1
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Roger Soucy 8/27/18 10/5/18
023021.00 Turner 023021.00 023021.00 MAINTENANCETURNER BRIDGE
WEARING SURFACE REPLACEMENT
SHOEM CORPDAVID MERRILL
557-5494
Douglas Coombs
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
020853.00 Turner 2302600 023026.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
TURNER, ROUTE 4 SLOPE
STABILIZATION/PROTECTION
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Rhobe Moulton 5/1/18 9/30/18
021712.00 Turner 02175400 021754.00 BRIDGE PRESERVATION
TURNER, TURNER CENTER BRIDGE
PAINT
SPARTAN CONTRACTING LLC
DAVID DOUCETTE
Devin Anderson 7/3/17 2/12/18
023021.00 Turner 023023.00 023023.00 MAINTENANCETURNER BRIDGE
WEARING SURFACE REPLACEMENT
SHOEM CORPDAVID MERRILL
557-5494
Douglas Coombs
018749.00 TurnerSTP-
1874(900) 018749.00 BRIDGE
CONSTRUCTION
TURNER, NORTH PARISH BRIDGE REPLACEMENT
T BUCK CONSTRUCTION, INC.
CRAIG HURD
Joseph Stilwell 2/28/18 12/19/18
020853.00 Turner NHPP-2088(600) 020886.00
HIGHWAY PRESERVATION
PAVING
TURNER ROUTE 4 MILL AND FILL
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Guy Whittington 6/12/18 10/26/18
020853.00 Turner 02299605 022996.05 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
TURNER, ROUTE 4 WEIGH STATION IMPROVEMENTS
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Guy Whittington 5/15/18 10/15/18
022856.00 Turner 022856.00 022856.00 MAINTENANCETURNER, CULVERT
REPLACEMENT
ST. LAURENT & SON, INC.AKAMAINE
HEAVY EQUIPMENT RENTAL, INC.
TIMOTHY ANDREWS
Robert Holbrook 7/15/17
020853.00 Turner, Livermore 2088500 020885.00
HIGHWAY PRESERVATION
PAVING
TURNER/LIVERMORE ROUTE 4 1 1/4'
OVERLAY
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Guy Whittington 6/8/18 10/24/18
016871.00 Unity 021756.00 021756.00 BRIDGE PRESERVATION UNITY, BRIDGE PAINT
PANTHER INDUSTRIAL
PAINTING LLC
DAVID DOUCETTE
Devin Anderson 7/6/17 1/18/18
022092.00
Unity, Palermo, Oakland,
Waterville, China, Morrill,
Benton, Albion, Burnham, Freedom, Winslow,
Montville, Knox,Brooks, Troy
022092.00 022092.00 HIGHWAY LIGHT CAPITAL PAVING
ALBION AREA 2018 LCP LIGHT CAPITAL
PAVING
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Emory Lovely 8/6/18 9/28/18
018978.00 Vassalboro 018978.00 018978.00 BRIDGE PRESERVATION
VASSALBORO, SEVEN MILE BROOK BRIDGE
PAINT & REHAB
WYMAN & SIMPSON, INC.
DAVE DOUCETTE
Devin Anderson 10/11/17 2/28/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022975.00 Verona Island 023672.00 023672.00 MAINTENANCE VERONA ISLAND DITCHING
F C WORK & SONS, INC.
MATTHEW CONNOR
557-5494
Joe Prescott
022623.00 Verona Island NHPP-2262(300)
022623.00 BRIDGE PRESERVATION
PROSPECT - VERONA, PENOBSCOT
NARROWS BRIDGE WEAR SURF REPL
LANE CONSTRUCTION
CORPORATION (THE)
TRAVIS HAMEL 215-7312
Michael Wight 4/28/17 6/30/17
018798.00 Waite,
Talmadge, Topsfield
STP-1879(800) 018798.00
HIGHWAY PRESERVATION
PAVING
TOPSFIELD - WAITE, US ROUTE 1 MILL &
FILL
LANE CONSTRUCTION
CORPORATION (THE)
MICHAEL THOMAS
Roger Soucy 5/25/18 10/26/18
021819.10 Waldo 023270.00 023270.00 ENVIRONMENTAL IMPROVEMENTS
SMITHFIELD, ROUTE 137 DRAINAGE
IMPROVEMENTS
PIKE INDUSTRIES, INC.
SCOTT COOK
Peter Newkirk 7/1/18 7/30/18
023966.00 Waldo, Swanville 023966.00 023966.00 MAINTENANCE WALDO TO SWANVILLE, DITCHING
F C WORK & SONS, INC.
JAMIE ANDREWS
James Andrews
018971.00 Waldoboro 018971.00 018971.00 BRIDGE
CONSTRUCTION
WALDOBORO WINSLOWS MILLS BR
SUPERSTR REPL
WYMAN & SIMPSON, INC.
GUY HEWS
Devan Eaton 7/30/18 12/31/18
020887.00 Waldoboro NHPP-2088(700) 020887.00
HIGHWAY PRESERVATION
PAVING
WALDOBORO US ROUTE 1 1 1/4"
OVERLAY
PIKE INDUSTRIES, INC.
DEAN ROWLAND
Douglas Coombs 5/15/18 10/31/18
022120.00
Wallagrass, Fort Kent, Saint John
Plt, Saint Francis, Allagash
022120.00 022120.00 HIGHWAY LIGHT CAPITAL PAVING
FORT KENT AREA 2018LCP LIGHT CAPITAL
PAVING
LANE CONSTRUCTION
CORPORATION (THE)
RESIDENT?
Emory Lovely 7/30/18 8/29/18
022233.00 Waltham 022233.00 022233.00 MAINTENANCE WALTHAM, WEARING SURFACE REPAIR
BMB CONSTRUCTIONLLC
MATTHEW CONNOR
?
020887.00 Warren 2299606 022996.06 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
WARREN, ROUTE 90 OPERATIONAL &
SAFETY IMPROVEMENTS
PIKE INDUSTRIES, INC.
DEAN ROWLANDS
Douglas Coombs 5/15/18 10/31/18
020887.00 Warren 22472.00 022472.00 HIGHWAY
PRESERVATION PAVING
WARREN ROUTE 1 1 1/4" OVERLAY &
SHOULDER WIDENING
PIKE INDUSTRIES, INC.
DEAN ROWLANDS
Douglas Coombs 5/15/18 10/15/18
020887.00 Warren STP-2088(800) 020888.00
HIGHWAY PRESERVATION
PAVING
WARREN ROUTE 90 MILL & FILL
PIKE INDUSTRIES, INC.
DEAN ROWLANDS
Douglas Coombs 5/15/18 10/31/18
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
023858.00 Washington 23858.00 023858.00 MAINTENANCEWASHINGTON DOMED
ROOFING REPLACEMENT
JARR MANAGEMENT, INC.
JAMIE ANDREWS
?
018951.00 Waterville 018951.00 018951.00 BRIDGE REHABILITATION
WATERVILLE, GILMAN STREET BRIDGE DECK
REPLACEMENT
T BUCK CONSTRUCTION, INC.
CANDACE THOMPSON
Joel Kittredge 4/15/18 11/9/18
018129.10 Waterville 21203.00 021203.00 Unknown
WATERVILLE, BRIDGE REHABILITATION, TRAFTON ROAD
BRIDGE
SARGENT CORPORATION
MATTHEW SWINDELLS
Melanie Redd
018800.00 Waterville 018800.10 018800.10 MAINTENANCE BRIDGE# 2268LANE
CONSTRUCTION CORPORATION (THE)
ROBERT CLEWLEY
Douglas Coombs
018800.00 Waterville,
FairfieldSTP-
1880(000) 018800.00 HIGHWAY
PRESERVATION PAVING
WATERVILLE-FAIRFIELD ROUTE 104
1 1/4" OVERLAY
LANE CONSTRUCTION
CORPORATION (THE)
ROBERT CLEWLEY
Douglas Coombs 6/21/17 6/1/18
020814.00 Wells STP-2081(400) 020814.00 BRIDGE
CONSTRUCTION
WELLS, CAPELL BRIDGE
REPLACEMENT
WYMAN & SIMPSON, INC.
JOHN AUGER
Joel Kittredge 2/26/19 6/7/19
018983.00 Wells 018983.00 018983.00 BRIDGE REHABILITATION
WELLS, MERRILAND BRIDGE REHAB
T BUCK CONSTRUCTION, INC.
JOHN AUGER
Joel Kittredge 3/27/18 9/5/18
023814.00 West Gardiner 023814.00 023814.00 MAINTENANCE WEST GARDINER BUILDING DEMOLITION
PLUMMER FOREST PRODUCTS AND
EXCAVATION
JAMIE ANDREWS
Maurice Hinkley
018954.00 West Gardiner, Litchfield 018954.00 018954.00 BRIDGE
CONSTRUCTION
WEST GARDINER - LITCHFIELD,
BURNHAM BRIDGE REPLACEMENT
WYMAN & SIMPSON, INC.
MACKENZIE KERSBERGEN
Leanne Timberlake 2/7/18 11/28/18
018288.00 Whiting STP-2170(800)
021708.00 BRIDGE CONSTRUCTION
WHITING, BRIDGE REPLACEMENT, RTE.1
SARGENT CORPORATION
RESIDENT?
Andrew Lathe 1/26/18 6/14/19
018288.00 Whiting,
Edmunds TwpSTP-
1828(800) 018288.00 HIGHWAY
CONSTRUCTION
WHITING - EDMUNDS TWP, HIGHWAY
RECONSTRUCTION, US. RTE.1
SARGENT CORPORATION
JEFFERY COFFIN
Rhobe Moulton 2/28/18 6/22/20
022329.20 Wilton 22329.20 022329.20 MAINTENANCEWILTON BUILDING
RENOVATIONS
BLANE CASEY BUILDING
CONTRACTOR
MIKE SULLIVAN
?
022886.00 Winslow 022886.00 022886.00 MAINTENANCE
WINSLOW, ALBION, AND BENTON
CULVERT REPLACEMENTS
PIKE INDUSTRIES, INC.
JAMIE ANDREWS
James Andrews
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
018962.00 Winslow 018962.00 018962.00 BRIDGE REHABILITATION
WINSLOW, CHAFFEE BRIDGE CULVERT REHABILITATION
CULVERT REHABILITATION
SERVICES (DIV. OF CLH & SON)
RESIDENT?
Joel Kittredge 6/24/18 9/14/18
020213.00 Winthrop HSIP-2021(300)
020213.00 HIGHWAY SAFETY
AND SPOT IMPROVEMENTS
WINTHROP, INTERSECTION
IMPROVEMENTS, US. RTE.202 / MAIN ST.
PRATT & SONS, INC.
WILLIAM CROSBY
Brian Keezer 4/3/17 4/30/18
023243.00 Wiscasset, Alna, Jefferson 023245.00 023245.00 MAINTENANCE
WP2017-MILLING CENTER LINE ON ROUTE 218 FROM
WISCASSET TO
CROOKER CONSTRUCTION LLC
AKA HARRY C CROOKER & SONS,
INC.
TIMOTHY PELOTTE
James Andrews
022104.00
Woodstock, Newry, Grafton Twp, Upton, Greenwood,
Bethel
022104.00 022104.00 HIGHWAY LIGHT CAPITAL PAVING
BETHEL AREA 2018 LCP LIGHT CAPITAL
PAVING
PIKE INDUSTRIES, INC.
SCOTT COOK
Emory Lovely 5/29/18 7/3/18
018238.00 Yarmouth SR-1823(810) 018238.10 BICYCLE-
PEDESTRIAN
YARMOUTH, SIDEWALK
IMPROVEMENTSREED & REED, INC.
RESIDENT?
Leanne Timberlake 10/16/17 12/30/19
018238.00 Yarmouth 018238.00 018238.00 BRIDGE CONSTRUCTION
YARMOUTH, MAIN STREET BRIDGE REPLACEMENT
REED & REED, INC.PETER BROWN
Leanne Timberlake
10/16/17 12/30/19
020545.10 Yarmouth STP-2054(510) 020545.10
HIGHWAY SAFETYAND SPOT
IMPROVEMENTS
YARMOUTH, INTERSECTION
IMPROVEMENTS, US. RTE.1 WITH I-295 NB
CPM CONSTRUCTORS
MARK HAAS
Brian Keezer 8/25/17 2/28/18
018957.00 York 018957.00 018957.00 BRIDGE
CONSTRUCTIONYORK, BARRELL BR
REPLWYMAN & SIMPSON,
INC.
JOHN AUGER
Devan Eaton 7/18/18 1/16/19
020116.57 020116.57 020116.57 MAINTENANCEREGION 5,
EXCAVATORS 15HOULTON RENTAL
CENTER
GAIL ILER
?
023874.00 023874.00 023874.00 MAINTENANCE PALERMO DITCHING PIKE INDUSTRIES, INC.
JAMIE ANDREWS
James Andrews 8/1/17 10/21/17
022355.00 022355.00 022355.00 MAINTENANCE
MILLINOCKET, T3 INDIAN PURCHASE TWP, PROTECTIVE
COATING
COPIA SPECIALTLY CONTRACTORS
JAMES BALL
?
022102.00 024158.00 024158.00 MAINTENANCE RANGELEY AREA 2018 LCP BRIDGE MILLING
PIKE INDUSTRIES, INC.
SCOTT COOK
Robert Mcferren
024408.04 024408.04 024408.04 MAINTENANCECARRABASSETT VALLEY SLOPE STABILIZATION
SUNKAZE PROJECT SOLUTIONS, INC.
DAVID MERRILL
?
MaineDOT Projects Under Construction April 23, 2018
Contract No. Town(s)Federal
Proj-NumProject ID Program Route(s) Description Prime Contractor
Resident/ Phone/
Fax
Project Manager
Construction Begin
AnticipateComplete
022353.00 022353.00 022353.00 MAINTENANCE EASTON, GRAVEL SURFACE MCGILLAN, INC.
JAMES BALL
?
022233.00 022241.00 022241.00 MAINTENANCESTEUBEN, WEARING
SURFACE REPAIRBMB CONSTRUCTION
LLC
MATTHEW CONNOR
?
BRIDGE PROGRAMName Title Phone LocationWayne Frankhauser Program Manager 624-3491 CentralEric Shepherd Assistant Program Manager/Construction 592-7825 CentralJeff Folsom Assistant Program Manager/Design 624-3491 CentralJoel Kittredge Sr. Project Manager 624-3550 CentralMike Wight Sr. Project Manager 624-3435 CentralLeanne Timberlake Design Build Project Manager 624-3422 CentralDevin Anderson Area Construction Manager 624-3402 CentralMike Redmond Concrete Quality Specialist 624-3271 Central
CAPITAL RESOURCESName Title Phone LocationGeorge Macdougall Contracts Engineer 624-3353 CentralKevon Hanlon Document Review Manager 624-3343 CentralLeonard Lidback Document Review/ Project Closeout 624-3502 CentralNorma Gilman Document Review/ Project Closeout 624-3495 CentralRoxane Cleaves Document Review/ Project Closeout 624-3533 CentralGuy Berthiaume Field Manager 624-3534 CentralJean Tukey Sub-Contractor/Testing Mins 624-3514 CentralRebecca Snowden Contractor payments 624-3515 CentralDiane Barnes Electronic Bidding/Web Page/Bid Tabs 624-3503 CentralSonya Everett Elations/Prequal 624-3519 CentralSusan Merriman Bid Openings/Amendments 624-3408 Central
HIGHWAY PROGRAMName Title Phone LocationBradford Foley Program Manager 624-3539 Central
MaineDOT Projects Under Construction April 23, 2018
Stephen Bodge II Assistant Program Manager /Design 441-6850 CentralScott Bickford Assistant Program Manager/Construction 215-3857 CentralBrian Luce Paving/Pavement Mixes/Construction
Support 446-0360 Central
Denis Lovely Sr. Project Manager/Construction Support 446-1978 CentralShawn Smith Sr. Project Manager/Construction Support 557-1663 CentralDerek Nener-Plante CE II - Construction Support 215-0849 CentralRob Betz Sr. Project Manager 215-4051 Region 1Meredith Kirkman Sr. Project Manager 557-0672 Region 2Guy Whittington Sr. Project Manager 562-4228 Region 3Randy Barrows Sr. Project Manager 592-2800 Region 4Roger Soucy Sr. Project Manager 215-8739 Region 5Ernest Martin Jr. Sr. Project Manager 624-3381 CentralRhobe Moulton Sr. Project Manager 624-3391 Central
MULTI MODAL PROGRAM
Name Title Phone LocationJeff Tweedie Program Manager 624-3473 CentralNate Benoit Assistant Program Manager 624-3555 CentralAurelle Gorneau II Sr. Project Manager 624-3550 CentralBrian Keezer Sr. Project Manager 624-3612 CentralCathrine Rand Project Manager I 624-3451 CentralJohn Rodrigue Project Manager I 592-0428 CentralJen Paul Construction Manager 446-3316 Central
REGIONAL ENGINEERSName Title Phone LocationKyle Hall Regional Engineer 592-3418 Region 1James Andrews Regional Engineer 446-1768 Region 2Mark Hume Regional Engineer 557-2609 Region 3John Devin Regional Engineer 592-5943 Region 4Brent Bubar Regional Engineer 557-3886 Region 5Brian Burne Highway Maintenance Engineer 624-3571 Central
REGIONAL MANAGERSName Title Phone Location
MaineDOT Projects Under Construction April 23, 2018
Doug Carlson Regional Manager 885-7000 Region 1Michael Burns Regional Manager 624-8200 Region 2Norman Haggan Regional Manager 562-4228 Region 3Steven Thebarge Regional Manager 990-2667 Region 4Robert Watson Regional Manager 764-2060 Region 5
SAFETYName Title Phone LocationDwight Doughty Safety 592-6646 Central
TESTING & LABSName Title Phone LocationRick Bradbury Testing Engineer 624-3482 CentralKevin Cummings Quality Assurance Engineer 624-3429 CentralNancy Bradbury TIMS Manager 215-7217 Region 4Mark Alley Central Lab Engineer 941-4526 Region 4James R. Robinson Freeport Lab Supervisor 865-0164 Freeport
TRAFFIC SERVICES
Name Title Phone LocationStephen Landry State Traffic Engineer 624-3624 Central
Region Main Office Phone Region 1 885-7000 Region 2 624-8200 Region 3 562-4228 Region 4 941-4500 Region 5 764-2060
*Note: Construction Begin date is based on forecast or actual dates. If there is no actual date, the forecast date is used.
List is filtered on contracts with an Advertise actual date entered, Project status = 'Active' and projects have no Final Records Submitted date entered.
Contact: Phone numbers for project residents listed or offices listedSource: Departmental contract and project management systemsRefresh Cycle: WeeklyLast Refresh: April 23, 2018
MaineDOT Projects Under Construction April 23, 2018
<---------------------End of Report------------------------>