LHC: Overview, Status and Commissioning Plans

Mike Lamont, LHC Operations, CERN

7th May 2007

Page 2: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

MethodologyThe LHC….work in progress!

Two beams of trillions of protons will race around the 27km ring in opposite directions travelling at 0.999999991 times the speed of light…

Sometime soon!

Page 3: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Design basics

We want to collide high energy protons(let’s say 7 TeV) (for what ever crazy reasons)

We have the 27 km LEP tunnel which we’d better use

Back of an envelope calculation tells us we need strong magnets to bend the beam around

Higgs, Supersymmetry, data matter, extra dimensions

Page 4: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

2L

2L

θ

ρ

7 TeV• 8.33T• 11850A

rad 101.512322 3−×===π

ρθ l1232 magnets to get us round

in a circle

Page 5: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Superconductivity

To produce the high magnetic fields we need very high currents…

Abolish Ohm’s Law!

Use of superfluid helium which is a magic coolant and gives us some margin in the high magnetic fields

30 kTons cold mass; 120 Tons of Helium –a huge cryogenic system

Page 6: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC - dipole

B +J -J

I I

I

B

Page 7: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Niobium-Titanium Rutherford cableStrand

Filament

Cable

Total superconducting cable required 1200 tonnes which translates to around 7600 km of cable

The cable is made up of strands which is made of filaments, total length of filaments would go 5 times to the sun and back with enough left over for a few trips to the moon.

Page 8: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Critical surface of niobium titanium

Niobium titanium NbTi is the standard ‘work horse’ of the superconducting magnet business

picture shows the critical surface, which is the boundary between superconductivity and normal resistivity in 3 dimensional space

superconductivity prevails everywhere below the surface, resistance everywhere above it

Field (Tesla)Temperature (K)

Cur

rent

den

sity

(kA

.mm

-2)

Page 9: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Stuck inside…

Page 10: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Bend the beam

Momentum at collision 7 TeV / cMomentum at injection 450 GeV / cMachine Circumference 26658.883 mRevolution frequency 11.245 kHz

Number of dipoles 1232Dipole field at 450 GeV 0.535 TDipole field at 7 TeV 8.33 TBending radius 2803.95 mMain Dipole Length 14.3 m

Page 11: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC - quadrupole

Two intersecting ellipses, rotated by 90°, generate a perfect quadrupole fields

Page 12: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Focus the beam

Page 13: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Luminosity

We want to produce high luminosity at high energy so we can discover the Higgs etc.

(for high luminosity read a large number of collisions)

yx

bb

feIn

σσπ 02

2

4L =

Page 14: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

BeamMany bunches:

2808 bunches per beamHigh bunch currents:

1.15 x 1011 protons per bunchSmall beam size at the interaction points

16 µm fully squeezed

Have to keep the beam apart as much as possible

Therefore two beam pipes and for cost reasons a2 in 1 magnet design

Page 15: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Bunch configuration

Page 16: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Experiment Insertion

• Bring the beams together to produced collisions

• Squeeze the beam sizes down at the interaction point

Page 17: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Cross beams at an angle

Page 18: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC : 27 km long100m underground

pp, B-Physics,CP Violation

Heavy ions, pp

ALICE

General Purpose,pp, heavy ions

General Purpose,pp, heavy ions

CMS+TOTEM

ATLAS

Page 19: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC

Eight sectors plus:Point 1: AtlasPoint 2: Alice, injectionPoint 3: Momentum cleaningPoint 4: RFPoint 5: CMSPoint 6: Beam DumpsPoint 7: Betatron cleaningPoint 8: LHCb, injection

Page 20: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Beam energy

Two very cold, very dark, very small holes...

energy per beam up to 360 MJ

British aircraft carrier at 12 knots

Page 21: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Beam Dump

Beam has got out in case of a quench or other problem otherwise we end up with scrap metal

Page 22: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Operations

Page 23: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything
Page 24: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Nominal cycle

0

14000

-3000 -2000 -1000 0 1000 2000 3000

Time [s]

MB

cur

rent

0

1

2

3

4

5

6

7

8

9

B [T

]

RAMP DOWNSTART RAMP

PHYSICS

PREPAREPHYSICS

BEAM DUMP

PREINJECTIONPLATEAU

INJECTION

T0 Tinj

SQUEEZE

PHYSICS

Ramp down ≈ 18 MinsPre-Injection Plateau 15 Mins

Injection ≈ 15 MinsRamp ≈ 28 Mins

Squeeze < 5 MinsPrepare Physics ≈ 10 Mins

Physics 10 - 20 Hrs

I ~ t2

I ~ et

I ~ t

Page 25: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

So that’s the idea…

- Bend & Focus - Produce the components- Install them- Get them working and test them - Put some beam in

Page 26: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Components: dipoles

Page 27: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Last one down

Page 28: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Installation: magnets

The magnets are now in.

Page 29: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

InterconnectsVacuum, bellows, RF contacts plus leak checksCryogenics, thermal shield, heat exchangerBus bars

– superconducting splices x 10,000 (induction welding)Corrector circuits

– splices x 50,000 (ultrasonic welding)

Joining everything up 1700 times

Huge, painstaking & industrialized

Clearly on the critical path

Page 30: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Check the wiring

Page 31: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Beam vacuum 10-10 Torr

27 km (x ~2 +): warm, cold, transitions, valves, gauges etc.

The vacuum group are very, very busy…

Vacuum(~3 million molecules/cm3), want to avoid collisions with gas molecules

Page 32: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Miscellaneous

Potential aperture restrictions!

Page 33: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Installation: RF - point 4

Page 34: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Installation: junction of TI8 injection line

Page 35: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Installation: Summary May 07

All dipoles, arc and special SSS have been delivered

• Interconnection on-going in 6 sectors• Last sector Arc 1-2 magnets are in place• Installation of beam pipe and vacuum elements

– Ongoing (procurement difficulties and co-activities…)

• Critical issues: low-β triplets…

Page 36: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Following installation we have in situ hardware tests….

Page 37: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything
Page 38: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Inner triplets

Experimental insertions in points1, 2, 5, 8 contain low-beta triplets.

In total, eight triplets are installed.

Page 39: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

The LHC low-β triplet

MQXA MQXB MQXAMQXB

6.37 5.5 5.5 6.37

MCBXA MCBXMQSX

TASB

MCBX

Q3 Q2 Q1

MCSOX

DFBXLBX

D1

IR 1 and 5, D1 is a normalconducting dipole.

DFBX

Triplets were designed and built bya collaboration of five laboratories:BNL, CERN, Fermilab, KEK, LBNL.

Page 40: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC low-β triplet – Q2

External heat exchangerGRP spider

MQXB quadrupoles

Page 41: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC low-β triplet – warm assembly

Page 42: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

LHC low-β triplet – DFBX

Page 43: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Inner triplet problem

Page 44: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

FAQs (c/o Fermilab)

Did magnets explode during the pressure test?– No. Nothing exploded. The longitudinal force applied during the test

caused a quadrupole magnet to move, stretching the pipe connecting it to the adjoining magnet. The pipe ruptured, making a loud noise and releasing helium gas.

Was anyone hurt?No. Safety precautions were followed and no one was injured.

Did a mistake in mathematics cause the magnet failure?No. In an engineering oversight, Fermilab magnet designers failed to take into account the strength of longitudinal forces on the magnet in designing the magnet’s support structure.

Page 45: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

1R

2L

5L

2R

5R

8L

1L

8R

No access

Inner triplets repairs18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

May June July August September

Fixes Interconnection Leak test

Q1-Q3 H

Q1-Q3 H

Fixes

Fixes

Transport

Transport

2L - Transport

Fixes and repairs

Q3 Q1Q3

Q1-Q3

Q1 Q1Q2

Q3 Q3

Q1-Q2 & DFBX-D1 electrical

M1M2 -H

Alignment IT pressure test

Page 46: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Cool down and hardware commissioning

Page 47: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

ATLAS ALICE

SECTOR 1-2

LSS.

L2

LSS.

R1

Bake-out

Hardware Commissioning:qualification of circuits to

7 TeV – not trivial

Cool-down

Page 48: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Cool downOne sector: 3.3 km - 154 dipoles ++

Page 49: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

1.9 K cool down along the arc

Page 50: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Not without a cryogenic wrestling match

• Power (400V failure on 30Mar’07)– cascade effect on cooling water, control networks, mobile vacuum

pumping units• Progressive set-up of procedures to pump-down to 15mbar, while

keeping DFB’s with 4.5K conditions• Continued upgrades in instrumentation

– (Level gauges, Heaters, …) but more efforts required to improve reliability and availability

• Test of magnet temperature control loops for 1.9K operation• 1.8K Refrigeration unit trips (frequency drive) - difficulties to restore

1.9 K conditions after a stop

• plus valves, Helium inventory…but…..

Huge system

Page 51: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Things are looking better…

This is major achievement

Page 52: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Hardware commissioning

• Just starting – some 60 A correctors powered• Detailed program of hardware tests to be performed:

– Electrical quality assurance– Quench protection system– Energy extraction– Power Interlocks– Powering tests:

• Current in magnets ramped very carefully• Recall huge energies involved.

• ~9 weeks per sector

Page 53: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Teachers

Page 54: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

So…

• Feverish activity everywhere • Sector 7-8 cold• Hardware commissioning just starting.• Some problems, for example:

– Inner triplets– Quadrupole circuit earth fault– Suspect dipole sector 7-8 to be replaced– …

There is a lot left to do.

Page 55: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

XMAS 2007

NOW

Page 56: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Go straight to 7TeV (with IT repairs & interc.)

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

.

.

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

12 23 34 45 56 67 78 81

5/10/2007 K. Foraz TS-IC-PL

Sector test

Machine Check-out

Beam Commissioning

Page 57: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

2008 (briefly)

ATLASlow lumi.

Page 58: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Staged commissioning plan for 7TeV

III

No beam Beam

ShutdownMachine checkout

7TeV

Beam setup 25ns ops I

Install Phase II and MKB

Stage I II III

No beam Beam

Hardware commissioning

7TeV

Machine checkout

7TeV

Beam commissioning

7TeV

43 bunch operation 75ns ops 25ns ops I Shutdown

2008

2009

Page 59: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Total [days]1 Injection and first turn 6

2 Circulating beam 3

3 450 GeV - initial 5

4 450 GeV - detailed 12

5 450 GeV - two beams 2

6 Snapback - single beam 4

7 Ramp - single beam 8

8 Ramp - both beams 3

9 7 TeV - setup for physics 2

10 Physics un-squeezed -

TOTAL to first collisions 4511 Commission squeeze 6

12 Increase Intensity 6

13 Set-up physics - partially squeezed. 2

14 Pilot physics run 30

Given reasonable machine availability might expect first7 TeV collisions in around 2 months

RHIC 2000:- First beam April 3rd

- First successful ramp: June 1st

- First collisions June 12th

Full commissioning to 7 TeV

Page 60: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Beam commissioning

-20

-15

-10

-5

0

5

10

15

20

1500 1750 2000 2250 2500 2750 3000 3250 3500 3750 4000 4250 4500 4750 5000 5250 5500 5750 6000S [m]

N σ X aperture

Horizontal plane8 σ oscillation

Commission: instrumentation, RF, beam dump, collimators etc,

Page 61: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

7 TeV beam commissioning

• Around 2 months elapsed time to establish first collisions– Mostly pilot++, low intensity, single beam, simple machine– No crossing angle– No squeeze

Leading into a period of “Pilot Physics” plus continuing machine commissioning

Page 62: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Schedule

• Some delays are accumulating– Inner triplets clearly haven’t helped

• A new schedule will be presented in May 2007

• A 450 GeV run this year is off

• A sector test this year is on

Page 63: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

Sector test 2007

Page 64: LHC: Overview, Status and Commissioning Plans · – superconducting splices x 10,000 (induction welding) Corrector circuits – splices x 50,000 (ultrasonic welding) Joining everything

ConclusionsInstallation, Cool-down, HWC

– Despite the problems, this is going remarkably well– However, delays have accumulating

2007: Sector test

2008: 7 TeV– 6-8 weeks single/two beam machine commissioning– Pilot physics

The next 18 months is going to be a lot of fun.