![Page 1: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/1.jpg)
King St. (Route 7) over I-395 Bridge Rehabilitation
November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager (703) 259–2606 [email protected]
![Page 2: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/2.jpg)
Purpose & Agenda
Purpose Review the project with community stakeholders & obtain feedback for preparing the final design
Agenda • Existing Condition Summary • Scope of Repair Work • Stages of Construction for Superstructure Work • Stages of Construction for Substructure Repair Work • Safety Improvements • Cost and Schedule
2
![Page 3: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/3.jpg)
Location Map
3
Bridge Location
![Page 4: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/4.jpg)
Aerial Map
4
Bridge Location
![Page 5: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/5.jpg)
Existing Bridge
5
Looking North from I-395
Looking South from I-395
• Built in 1970 • 5 spans totaling 410-feet in length • Rolled steel girders on a curved alignment • 6 lanes of traffic with raised median • Deck CR 6 (Good) • Superstructure CR 5 (Fair) • Substructure CR 4 (Poor) • Classified as Structurally Deficient
Looking West from Rte. 7
![Page 6: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/6.jpg)
Existing Bridge Deck Condition
6
![Page 7: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/7.jpg)
7
Existing Superstructure Condition
![Page 8: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/8.jpg)
8
Existing Substructure Condition
Pier 4
Pier 1 Pier 2
Pier 1 Before
Pier 1 After
![Page 9: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/9.jpg)
Scope of Bridge Repair Work
• Replace the existing bridge railings.
• Repair Bridge Deck including closing of the Bridge deck expansion joints at all piers and reconstructing deck expansion joints at the abutments.
• Mill Bridge deck and install Impressed Current Cathodic Protection (ICCP) System with concrete overlay.
• Clean and paint Steel beams. Replace all bearing assemblies.
• Repair deteriorated concrete in pier caps, bearing pedestals, pier columns and abutments.
• Install Impressed Current Cathodic Protection (ICCP) System in all pier caps.
• Treat all pier columns and abutments with Electrochemical Chloride Extraction (ECE).
• Minor bicycle and pedestrian improvements 9
![Page 10: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/10.jpg)
Transverse Section
10
Existing Bridge
Proposed Bridge (2’-0” increase in shoulder width on each side)
99’-0”
4” 4”
4”
![Page 11: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/11.jpg)
Bridge Railing Replacement
Fiber Optic
11
Full traffic capacity (pedestrian and vehicles) will be maintained for Stages I through IV during peak hours
• Stage I - Remove raised median (WBL) during night time closures. (Estimated Duration: 4 nights)
• Stage II - Remove raised median (EBL) during night time closures. (Estimated Duration: 4 nights)
![Page 12: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/12.jpg)
Bridge Railing Replacement
Fiber Optic
Overhead Power
12
• Stage III - Replace WBL railing by shifting traffic lanes to right. (Estimated Duration: 6 weeks)
• Stage IV - Replace EBL railing by shifting traffic lanes to left. (Estimated Duration: 6 weeks)
Full traffic capacity (pedestrian and vehicles) will be maintained for Stages I through IV during peak hours
![Page 13: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/13.jpg)
Bridge Deck Repairs Deck Joint Closure/Reconstruction, Mill & Overlay with ICCP System
13
• Stage V – Close King Street westbound lanes & I-395 ramp to westbound King Street to traffic for multiple weekends for deck joint closure/reconstruction, and deck Mill & Overlay with ICCP System.
(Estimated Duration: 5 weekends)
![Page 14: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/14.jpg)
Construction Detour (King St. WBL Roadway Closure)
14
Closure of WB King Street lanes & I-395
ramp to WB King Street
![Page 15: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/15.jpg)
Bridge Deck Repairs Deck Joint Closure/Reconstruction, Mill & Overlay with ICCP System
15
• Stage VI – Close King Street eastbound lanes & I-395 ramp to eastbound King Street to traffic for multiple weekends for deck joint closure/reconstruction, and deck Mill & Overlay with ICCP System.
(Estimated Duration: 5 weekends)
![Page 16: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/16.jpg)
Construction Detour (King St. EBL Roadway Closure)
16
Closure of EB King Street lanes & I-395
ramp to EB King Street
![Page 17: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/17.jpg)
Substructure Repair Work (I-395 Lane Shifts and Shoulder Closures)
17
Work Areas at Piers 1, 3 and Abutment B
Work Areas at Abutment A, Pier 2 and Pier 4
Estimated Duration: 25 days for each Abutment 50 days for each Pier 120 days for ECE curing period (No MOT) 4 night time lane and shoulder closures for demobilization
![Page 18: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/18.jpg)
Bicycle & Pedestrian Improvements
• Replacement of bridge railings will increase outside shoulder widths to 4’-0” which allows future on road bike accommodation.
• Reconstruct existing 4’-0” wide median sidewalk to an 8’-0” wide sidewalk centered in the median.
• Provide ADA-compliant curb ramps and pedestrian signals at Menokin Drive connecting the median sidewalk to the sidewalk on the south side of King Street.
• Provide a new pedestrian crossing of westbound King Street at the existing 30th Street South intersection, including a potential HAWK (High-intensity Activated Crosswalk) or coordinated traffic signal.
• Widen the existing sidewalk along westbound King Street between 30th Street South and Park Center Drive.
• Reconstruct the curb ramps and pedestrian signals at the King Street / Park Center Drive intersection.
• Upgrade the existing roadway lighting system to current standards. 18
![Page 19: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/19.jpg)
Bicycle & Pedestrian Improvements
19
Reconstruct Curb Ramps and Pedestrian Signals at Park Center Dr
Widen Median Sidewalk from 4’ to 8’ approaching the bridge
Provide ADA Curb Ramps and Pedestrian Signals at Menokin Dr
Provide new pedestrian crossing of WB King St at 30th Street S.
Widen the existing Sidewalk between 30th St S. and Park Center Dr
![Page 20: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/20.jpg)
Environmental and Cultural Resources Summary
• Anticipate project will meet NEPA criteria for a Programmatic Categorical Exclusion in accordance with 23 CFR 771.117
![Page 21: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/21.jpg)
Cost and Schedule
Costs • Engineering $1.4 Million • Construction $10.4 Million (unfunded) • Total $11.8 Million Schedule • Final Design Fall 2016 to Summer 2017 • Public Information Meeting could occur in Winter 2017 • Advertise Project as early as October 2017 if construction
funding becomes available • Construction: 20 to 24 months (8 to 9 months for top side
King St. Work)
21
![Page 22: King St. (Route 7) over I-395 Bridge Rehabilitation2016/11/09 · King St. (Route 7) over I-395 Bridge Rehabilitation November 9, 2016 Brian Morrison, P.E. NOVA District Project Manager](https://reader034.vdocuments.site/reader034/viewer/2022050312/5f7435a610d5bf343e47cf5c/html5/thumbnails/22.jpg)
QUESTIONS & COMMENTS
Send comments via email or comment form until December 9th to: Brian Morrison, P.E. NOVA District Project Manager (703) 259–2606 [email protected]