Download - John Osborne GS/SE 6 June 2013
CENF CIVIL ENGINEERING UPDATE :
- SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES- 3D VISUALS FOR SURFACE STRUCTURES
John Osborne GS/SE 6 June 2013
Site investigation for Near Detector and Target Area will be complete (pumping tests on-going)
• Pumping tests on cores C8,C10 & C12 • Report expected by early July
Tender documents :• Updated list of firms from MS• Instruction to Bidders• Technical Spec including :
• Descriptive• Deliverables for the phases• Safety Rules• Drawings• Geology
• Risk Matrix• Conditions of Contract• Tender Form• “Best Value for Money” Questions
& Criteria (50%/50%)• etc
Call for tender for CE Design and Contract Administration documents ready for issue
3D Visualisations for Near, Far and Taget Areas
• These artist impressions are essential for Impact Study and Building Permit submissions
• Offer from a company for :• Site visit and take base photographs• Prepare 3D wire-frame models from 2D Autocad drawings• Existing ground survey files to be prepared by CERN• Deliver images for Near, Far and Target Area by mid July
• Same company prepared all 3D images for CERN MasterPlan2030
• Estimate = 9200CHF
3D Visualisations – Example from MasterPlan : Bld 54 and Bld 30 extensions
SPARES
Phases of Services
• Phrase added top have a ’hold’ point after each phase to allow contract termination after any Phase
Lum
p S
um
Key Dates (1)
• Specification Committee Monday 29 April. HSE & Legal Service consulted at the same time. Second meeting held Friday 3 May.
• Technical documents complete
• Documents will be send around for final comments this week
• Target date for Bidders Conference is Mon 10 June• • Target closing date for receiving bids is day 28 June
• Special FC Approval in July (Accelerated Procedure required including Peers Review)
Near and Far Buildings :• Tender Design (Phase 1) complete by October 2013 (over summer months !)
• Construction Design (Phase 2) complete by end of 2013• CE construction works early 2014 – early 2015
Target areaTender Design (Phase 1) complete by March 2014• Construction Design (Phase 2) complete by July 2014• CE construction works mid 2014 – early 2016
*Junction cavern, extraction tunnel and service bld dates to be confirmed*Input from all CERN services needed to allow this firm to do detailed civil design (CV,EL, Access, Cranes etc)
Key Dates (2) (+1 month ?)November
CATIA CE model of North Hall nearly complete for Integration
Bld 887 L.Faisandel GS/SE
CENF geological survey findings
• Completed borings up till 30 April 2013: C11-C14 (near detector area)
Stratigraphy C11 and C12• 0.2m-1.2m topsoil and backfill • 1.2m to 8.0m Wurmian Moraine (clays, silts)
• Consolidated• Intra-moraine units (marly, sandy, gravely), maximum thickness of 2.2m
• Partially saturated → excavation in wet conditions• Between 6.0m and 13.0m gravels
• Compacted• Aquifer → pumping tests will be carried out to determine the properties of the aquifer
• From13.0m up to 20m Rissien Moraine
Stratigraphy C13• Entire borehole consists of Moraine, except for an intra-moraine marly and gravely unit at 5.0 – 7.2m depth
• Marly unit partially saturated → excavation in wet conditions• Aquifer in gravels
Stratigraphy C14• Entire borehole consists of Moraine, except for an intra-moraine marly and gravely unit at 5.0 – 7.2m depth
• Partially saturated → excavation in wet conditions• No well defined aquifer, but some water inflow has been noted
Initial conclusions• Geology is very heterogeneous • Groundwater levels are variable