ID Task Name Duration Start Finish Predecessors Resource Names
1 Phase 1 10 days Mon 1/26/15 Fri 2/6/15
2 Mix concrete (mix 1) Compression
1 day Thu 1/29/15 Thu 1/29/15 Team
3 Mix tension molds for mix 1 & 28D compression
1 day Tue 2/3/15 Tue 2/3/15 Team
4 7 Day compressiontest, Mix 1
1 day Fri 2/6/15 Fri 2/6/15 Team
5 Phase 2 15 days Fri 2/6/15 Thu 2/26/15
6 Make Molds for base and seat
25 days Mon 2/9/15 Fri 3/13/15 Peter,Alyssa
7 Test tension moldsfor mix 1
1 day Wed 2/11/15 Wed 2/11/15
Andrew,Alyssa
8 Mix 2, compression and tension test(w/ chicken wire)
1 day Thu 2/12/15 Thu 2/12/15 Andrew,Alyssa
9 Test mix 2 compression test
1 day Thu 2/19/15 Thu 2/19/15 Andrew,Alyssa
10 Test Mix 2 tension mold 1
1 day Fri 2/20/15 Fri 2/20/15 Andrew,Alyssa
Team
W T F S S M T W T F S S M T
Jan 4, '15 Jan 11, '15 Jan 18, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Base Project Plan P1541
Date: Thu 4/16/15
ID Task Name Duration Start Finish Predecessors Resource Names
11 Mix 3 Compressionand Tension Molds
1 day Thu 2/19/15 Thu 2/19/15 Andrew,Alyssa
12 Phase 3 18 days Tue 3/3/15 Thu 3/26/15
13 Compresson Test Mix 3
1 day Tue 3/3/15 Tue 3/3/15 Andrew
14 Tension Test Mix 3 1 day Wed 3/4/15 Wed 3/4/15 Andrew,Alyssa
15 Mix 4 and 5 Compression and Tension molds
1 day Thu 3/5/15 Thu 3/5/15 Andrew,Alyssa
16 Compression Test Mixes 4 & 5
1 day Thu 3/12/15 Thu 3/12/15 Alyssa,Andrew
17 Tension Test Mixes4 & 5
1 day Fri 3/13/15 Fri 3/13/15 Alyssa,Andrew
18 Pour 28 day compression Test
1 day Tue 3/24/15 Tue 3/24/15 Alyssa,Andrew
19 Pour base and ringbeam molds
1 day Tue 3/24/15 Tue 3/24/15 Andrew,Alyssa
20 Phase 4 18 days Tue 3/31/15 Thu 4/23/15
21 Pour remaining molds
1 day Thu 4/2/15 Thu 4/2/15 Andrew,Alyssa,Peter
22 28 Day Compression Test
1 day Fri 4/10/15 Fri 4/10/15 Andrew,Alyssa
W T F S S M T W T F S S M T
Jan 4, '15 Jan 11, '15 Jan 18, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Base Project Plan P1541
Date: Thu 4/16/15
ID Task Name Duration Start Finish Predecessors Resource Names
23 Phase 5 20 days Mon 4/20/15 Fri 5/15/15
24 Pour extra bases 10 days Mon 4/20/15 Fri 5/1/15 Andrew,Alyssa,Peter
25 Pour Remaining molds
10 days Mon 4/20/15 Fri 5/1/15 Alyssa,Andrew,Peter
W T F S S M T W T F S S M T
Jan 4, '15 Jan 11, '15 Jan 18, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Base Project Plan P1541
Date: Thu 4/16/15
Team
Team
Team
Peter,Alyssa
Andrew,Alyssa
Andrew,Alyssa
Andrew,Alyssa
Andrew,Alyssa
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jan 18, '15 Jan 25, '15 Feb 1, '15 Feb 8, '15 Feb 15, '15 Feb 22, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Base Project Plan P1541
Date: Thu 4/16/15
Andrew,Alyssa
Andrew
Andrew,Alyssa
Andrew,Alyssa
Alyssa,Andrew
Alyssa,Andrew
Alyssa,Andrew
Andrew,Alyssa
Andrew,Alyssa,Peter
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jan 18, '15 Jan 25, '15 Feb 1, '15 Feb 8, '15 Feb 15, '15 Feb 22, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Base Project Plan P1541
Date: Thu 4/16/15
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jan 18, '15 Jan 25, '15 Feb 1, '15 Feb 8, '15 Feb 15, '15 Feb 22, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Base Project Plan P1541
Date: Thu 4/16/15
Team
Team
Team
Peter,Alyssa
Andrew,Alyssa
Andrew,Alyssa
Andrew,Alyssa
Andrew,Alyssa
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Feb 22, '15 Mar 1, '15 Mar 8, '15 Mar 15, '15 Mar 22, '15 Mar 29, '15 Apr 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: Base Project Plan P1541
Date: Thu 4/16/15
Andrew,Alyssa
Andrew
Andrew,Alyssa
Andrew,Alyssa
Alyssa,Andrew
Alyssa,Andrew
Alyssa,Andrew
Andrew,Alyssa
Andrew,Alyssa,Peter
Andrew,Alyssa
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Feb 22, '15 Mar 1, '15 Mar 8, '15 Mar 15, '15 Mar 22, '15 Mar 29, '15 Apr 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: Base Project Plan P1541
Date: Thu 4/16/15
Andrew,Alyssa,Peter
Alyssa,Andrew,Peter
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Feb 22, '15 Mar 1, '15 Mar 8, '15 Mar 15, '15 Mar 22, '15 Mar 29, '15 Apr 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: Base Project Plan P1541
Date: Thu 4/16/15
Peter,Alyssa
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Apr 5, '15 Apr 12, '15 Apr 19, '15 Apr 26, '15 May 3, '15 May 10, '15 May 17, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: Base Project Plan P1541
Date: Thu 4/16/15
Andrew
Andrew,Alyssa
Andrew,Alyssa
Alyssa,Andrew
Alyssa,Andrew
Alyssa,Andrew
Andrew,Alyssa
Andrew,Alyssa,Peter
Andrew,Alyssa
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Apr 5, '15 Apr 12, '15 Apr 19, '15 Apr 26, '15 May 3, '15 May 10, '15 May 17, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: Base Project Plan P1541
Date: Thu 4/16/15
Andrew,Alyssa,Peter
Alyssa,Andrew,Peter
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Apr 5, '15 Apr 12, '15 Apr 19, '15 Apr 26, '15 May 3, '15 May 10, '15 May 17, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: Base Project Plan P1541
Date: Thu 4/16/15