Romania

17 months (Oct 07-Feb 09)

12 pilot sites in 5 counties

Needs assessment / Landscape analysis

Test training approaches

Engage government

Ukraine

11 months (Nov 07-Oct 08)

Needs assessment

Organizational assessment of library association

Advocacy strategizing

Gauge government interest

Planning Grants by the Numbers

Page 3: Global Libraries - Review of IREX Planning Grants 2007 2009

EQUIPMENT

ASSOCIATION DEVELOPMENT

TRAINING

POLICY

Helping libraries better serve their

communities through  training and technology

Page 4: Global Libraries - Review of IREX Planning Grants 2007 2009

• Government support• Association building• Librarians and their communities

LESSONS LEARNED

Page 5: Global Libraries - Review of IREX Planning Grants 2007 2009

Government support

Initial assumption: key to success is national government embraces program goals

•Commited ownership needed from national government

•The way to foster participation was through steering committees

Page 6: Global Libraries - Review of IREX Planning Grants 2007 2009

Local government

• Immediate and direct connection to impact are local

• Local officials can serve as national advocates

• Costs are not prohibitive for local budgets

SUPPORT

Page 7: Global Libraries - Review of IREX Planning Grants 2007 2009
Page 8: Global Libraries - Review of IREX Planning Grants 2007 2009

Average startup costs: $4172

Internet costs: average $257/month ($25-$500)

Page 9: Global Libraries - Review of IREX Planning Grants 2007 2009
Page 10: Global Libraries - Review of IREX Planning Grants 2007 2009

Library Association

Networking

Systems standardization

Impact data

Training

Advocacy

Best practices

Page 11: Global Libraries - Review of IREX Planning Grants 2007 2009

Initial assumption: IREX would help associations develop integrity and credibility

Reality: The main program challenge is building a member-driven national association

Page 12: Global Libraries - Review of IREX Planning Grants 2007 2009

Association Challenges

Page 13: Global Libraries - Review of IREX Planning Grants 2007 2009

Reach members

Develop professional structures

Create valuable services

Ownership

Page 14: Global Libraries - Review of IREX Planning Grants 2007 2009

• Initial assumption: Librarians would need to be pulled into reform efforts.

• Reality: Librarians are embracing change.

Page 15: Global Libraries - Review of IREX Planning Grants 2007 2009
Page 16: Global Libraries - Review of IREX Planning Grants 2007 2009
Page 17: Global Libraries - Review of IREX Planning Grants 2007 2009
Page 18: Global Libraries - Review of IREX Planning Grants 2007 2009

Top Related