architecture 302_2 bicycle shelter
design brief 01
Site: Students were free to choose a site around the North Carolina State University campus or Raleigh. If the site was not on campus, transportation for the shelter would have to be considered.
Objective: Create a bike rack and/or shelter that improves the quantity and quality of available bike parking in Raleigh or on campus. For the shelter students were asked to consider weather and theft protection for bikes, but also the bike shelter’s contribution to the built environment which included overall aesthetics, ease of use and space consumption. It was desired that the bike shelter provide added amenities to the community such as seating and shade.
Schedule and Budget: The project needed to be complete by Monday, April 25th and needed to be on a budget of around $50 per person for the group of 8 ($400).
Organization: Students were allowed to develop multiple designs individually or in small teams. At a mid-project meeting students voted on a few alternatives to mock up at full scale.
project teams
ownerDavid Benson
designMia MulicMatt KellyTyler Shannon
construction 1David BensonSara MarleyEthan Sitver
construction 2Michael HobgoodScott Nelsen
02
project schedule
04/01/11 04/04/11 04/06/11 04/08/11 04/11/11 04/13/11 04/15/11 04/18/11 04/20/11 04/22/11 04/25/11
DESIGN DESIGN
RESEARCH BID PREPARATION FABRICATION AND ASSEMBLY
ADDENDUM PREPARATION OF FINAL DRAWINGS drafts due
structure complete
list of changes
punch listCONSTRUCTION
03
design team
project options
01
02
Michael Hobgood & Tyler Shannon
03Mia Mulic & Ethan Sitver
Emily Faber & Heidi Northcutt
05
working drawingsside elevation
7’-10” ABOVE GRADE
6’-6” ABOVE GRADE
1’-6” ABOVE GRADE
REFER TO DETAIL ON SHEET A2 FOR CONTSTRUCTION OF THIS 12’-0” MEMBER
06
working drawingsbench elevation
07
working drawingsplan
08
working drawingsassembly detail
09
6”x.5”x8’ OSB
6”x.5”x8’ OSB
BOLTED CONNECTION
TRHEADED ROD
renderings 10
renderings 11
constructionteam
initial bids 13
Bike Shelter Cost EstimateUnit Item Quantity Quantity TotalPrice Size per Unit Required Price
STR. MEMBERS
Material:
OSB Sheet 6.87 7/16” x 4' x 8' 4 75 128.81Subtotal 128.81
Hardware:
#44610 Threaded Rod 9.06 1/2” x 6' 1 16 144.96Loctite® 8.00 - 1 1 8.00#63449 Washers (Galv) 0.28 1/2” 1 270 75.60#67342 Hex Nuts (Galv) 0.30 1/2” 1 270 81.00#135536 Washers (Stainless) 1.09 1/2” 3 270 98.10#135639 Hex Nuts (Stainless) 1.09 1/2” 2 270 147.15Subtotal 309.56
ROOF + ATCHMTS.
Material:
#12473 Galv. Steel 12.10 24” x 8' 1 7 84.70#12540 Alum. Flashing 16.98 20” x 10' 1 5 84.90#HD82967 Lattice (Plastic) 25.97 1/2” x 4' x 8' 1 4 103.88#HD54137 Lattice (Wood) 11.97 1/2” x 4' x 8' 1 4 47.88#12779 Ondura 20.91 48” x 79” 1 4 83.64#77000 Polycarb. 31.90 26” x 12' 1 5 159.50#HD5189903 Vinyl Tiles 32.85 12” x 12” x 1/8” 45 135 98.55Subtotal 84.70
Hardware:
#102893 Steel Angle (Galv.) 2.77 2-1/2” x 5/8” 2 24 33.24Bolts (Stainless) 1.09 1/4” 2 48 26.16Hex Nuts (Stainless) 0.97 1/4” 5 96 18.62Washers (Stainless) 0.97 1/4” 5 72 13.97Washers (Rubber) 0.92 1/4” x 1/2” x 1/16” 1 48 44.16Subtotal 136.15
MISCELLANEOUS
Material:
Bench Boards (?) 4.00 2 x 4 x 10” 1 4 16.00Cross Bracing (?) 15.00 - 1 1 15.00Subtotal 31
Net Total 690.2245Tax 48.315715
Total 738.54
construction photos 14
construction photos 15
construction photos 16
construction photos 17
construction photos 18
construction cost & final product
20
STRUCTURAL MEMBERS
Material:
00.000.003200.0teehS BSO 0.00 -075114013444 10FT ROD <A> 6.57 1 0 6.57 0.51 7.08 MIKE611942039494 DWV PIPE<A> 6.17 3 0 18.51 1.43 19.94 MATT032053101052 WATERSEAL <A> 44.96 1 0 44.96 3.48 48.44 MATT075114013444 10FT ROD <A> 6.57 9 1 52.56 4.07 56.63 DAVIDSubtotal 132.10
Hardware:
655554 CUTWSHR 1/4” <A> 0.11 12 0 1.32 0.10 1.42 MIKE655414 HEXNUTUSS <A> 0.06 7 0 0.42 0.03 0.45 MIKE030699080748 COMBO PACK <A> 4.50 1 0 4.50 0.35 4.85 MIA030699080700 WASHER <A> 20.77 1 0 20.77 1.61 22.38 MIA030699084609 HEX NUTS <A> 7.97 3 0 23.91 1.85 25.76 MIA030699080700 WASHER <A> 20.77 1 0 20.77 1.61 22.38 MATT030699084609 HEX NUTS <A> 7.97 3 0 23.91 1.85 25.76 MATT030699084609 HEX NUTS <A> 7.97 0 1 -7.97 -0.62 -8.59 DAVID
38.1-76.32-6398.7>A< 1S4NTP 246825666467 -25.50 DAVID38.176.320398.7>A< 1S4NTP 246825666467 25.50 TYLER
Subtotal 92.55
ROOF + ATTACHMENTS
Material:
099137600771 UT 2.5 COR 10 <A> 14.00 2 0 28.00 2.17 30.17 SCOTT12474 ROOF 2 1/2” CORR 10' GALV 15.17 4 4 0.00 0.00 0.00 MIKE12473 ROOF 2 1/2” CORR 8' GALV 12.10 4 4 0.00 0.00 0.00 MIKE12475 ROOF 2 1/2” CORR 12' GALV 18.14 2.67 0 48.40 3.75 52.15 MIKE12475 ROOF 2 1/2” CORR 12' GALV 18.14 0.33 0 6.02 0.47 6.49 TYLERSubtotal 58.64
Hardware:
315683 STAN 1-1/2” ZN CNR BRC 4P 2.38 8 8 0.00 0.00 0.00 DAVID43428 1/4” HEX NUT ZINC COARSE 1.57 1 1 0.00 0.00 0.00 DAVID63408 HELICAL LOCK WASHERS 0.13 130 30 13.00 1.01 14.01 DAVID
00.000.050150150.0STUN XEH 10336 0.00 DAVID215897 1/4”-20-2' ALL THREAD PLAT 1.55 1 1 0.00 0.00 0.00 DAVID44584 1/4”-20-6' ALL THREAD PLA 3.10 1 1 0.00 0.00 0.00 DAVID44584 1/4”-20-6' ALL THREAD PLA 3.10 1 0 3.10 0.24 3.34 SARA44540 1/4”-20-1' ALL THREAD PLA 1.01 1 0 1.01 0.08 1.09 SARA315686 STAN 2-1/2” ZN CNR BRC 4P 2.97 9 9 0.00 0.00 0.00 SARA
Price
Quantity
Returned
Subtotal
Tax
Total
Buyer
67340 GALV 58.000.1104104211.0TUN XEH 11.85 SARA67343 GALV FLAT WASHER 0.12 40 40 0.00 0.00 0.00 SARA67343 GALV FLAT WASHER 0.10 0 100 -10.00 -0.78 -10.78 DAVID10643 USS FLAT WASHER 1” 0.18 2 0 0.36 0.03 0.39 SARASubtotal 19.90
MISCELLANEOUS
Material:
077089150032 2” WHTBRSBRSH <A> 1.15 2 0 2.30 0.18 2.48 SCOTT033287139934 1/4” TIN BIT <A> 3.97 1 0 3.97 0.31 4.28 SCOTT022367568252 GL EXT FLT <A> 19.97 2 0 39.94 3.10 43.04 SCOTT022367568252 GL EXT FLT <A> 19.97 0 1 -19.97 -1.55 -21.52 DAVID071514002293 TURNBUCKLE <A> 4.94 2 2 0.00 0.00 0.00 DAVID071514005331 3/16” SWG SLV <A> 1.69 4 4 0.00 0.00 0.00 DAVID
00.000.04497.2>A< TLOB-U 613200415170 0.00 DAVID61.100.5100305.0>A< EPOR ERIW 098964 16.16 DAVID
7001 2X4X96” TOP CHOICE STUD 2.89 7 0 20.23 1.57 21.80 MIKE7001 2X4X96” TOP CHOICE STUD 2.89 5 0 14.45 1.12 15.57 TYLERSubtotal 53.53
Net Total 387.04Tax 30
Total 417.04
COST DISTRIBUTION
Team Member Dues Paid BalanceBenson, David 52.13 20.42 31.71
52.13 82.91 -30.78Kelly, Matt 52.13 116.53 -64.40Marley, Sara 52.13 16.67 35.46
52.13 52.99 -0.86Nelsen, Scott 52.13 79.96 -27.83Shannon, Tyler 52.13 47.56 4.57
52.13 0.00 52.13Total 417.04 417.04 0.00
Hobgood, Michael
Mulic, Mia
Sitver, Ethan
Price
Quantity
Returned
Subtotal
Tax
Total
Buyer
Bike Shelter Cost Summary
final product 21
final product 22
final product 23