![Page 1: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/1.jpg)
Earned Value Refresher
By Robert Perrine, PMPhttp://www.robertperrine.biz
Copyright reserved
![Page 2: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/2.jpg)
Copyright, Robert Perrine, PMP
2004 - 2006, Irvine, California, USA. Offered as is, with no warranty regarding the accuracy or
suitability of this material. Copyright reserved. Please, however free to copy and share this document with the following restrictions.
1. You may not charge for use or distribution of this material.
2. Your usage of this material is conditioned upon your compliance with the PMI Code of Ethics.
3. All distributions must be made with the intent to further the collected wisdom of humanity.
4. You may not remove my name or my copyright notices from these documents.
![Page 3: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/3.jpg)
Overview Basics of EV Work a few quick problems Apply EV to more realistic problems
![Page 4: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/4.jpg)
Basics of EV
![Page 5: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/5.jpg)
Basics of EV – EQUATIONSCost Performance Index CPI = EV / AC
Cost Variance CV = EV - AC
Earned Value (for a task) EV = PV * %Complete
Estimate To Complete ETC = EAC - AC
Schedule Performance Index SPI = EV / PV
Schedule Variance SV = EV - PV
Variance At Completion VAC = BAC - EAC
Estimate At Completion (EAC) EAC has a separate set of equations
![Page 6: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/6.jpg)
Basics of EV –Estimate At Completion
EAC = AC + ETC Re-Estimated
EAC = AC + (BAC - EV) Atypical
EAC = AC + ((BAC - EV) / CPI) Typical
EAC = BAC / CPI Typical
![Page 7: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/7.jpg)
Basics of EV – Old Vocabulary
ACWP Actual Cost of Work Performed replaced by AC
BCWP Budgeted Cost of Work Performed replaced by EV
BCWS Budgeted Cost of Work Scheduled replaced by PV
![Page 8: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/8.jpg)
Earned Value Basics of EV Work a few quick problems Apply EV to more realistic problems
![Page 9: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/9.jpg)
EV Problems – Scenario You are the project manager for a $250,000
upgrade to your company’s internet site. The current project status is shown on next slide. The next board meeting is scheduled for two
months from today. The CEO of your company will demonstrate your
new internet site to the board and to the investors attending that meeting.
![Page 10: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/10.jpg)
EV Problems – Project Status
Task Description PV EV AC
1.0.0 Operating system $25,000 $23,000 $27,000
2.0.0 Database $90,000 $85,000 $80,000
3.0.0 Web server $10,000 $9,000 $9,000
4.0.0 Firewall $8,000 $8,000 $11,000
5.0.0 Internal testing $10,000 $6,000 $2,000
6.0.0 “Beta” customers $12,000 $1,000 $2,000
7.0.0 Marketing $40,000 $5,000 $4,000
![Page 11: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/11.jpg)
EV Problems – Question 1 Use the Project Status data, show above.
Which task is on schedule?A) 1.0.0B) 2.0.0C) 3.0.0D) 4.0.0
What is your answer ? Why ?
![Page 12: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/12.jpg)
EV Problems – Question 1
Task Description PV EV AC
1.0.0 Operating system $25,000 $23,000 $27,000
2.0.0 Database $90,000 $85,000 $80,000
3.0.0 Web server $10,000 $9,000 $9,000
4.0.0 Firewall $8,000 $8,000 $11,000
5.0.0 Internal testing $10,000 $6,000 $2,000
6.0.0 “Beta” customers $12,000 $1,000 $2,000
7.0.0 Marketing $40,000 $5,000 $4,000
![Page 13: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/13.jpg)
EV Problems – Question 2 You are the project manager for a $250,000 upgrade to
your company’s internet site. The current EV data is shown in Table 1, above. The next board meeting is scheduled for two months from today. The CEO of your company will demonstrate your new internet site to the board and to the investors attending that meeting. Which task has the largest schedule variance? A) 2.0.0B) 5.0.0C) 6.0.0D) 7.0.0
What is your answer ? Why ?
![Page 14: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/14.jpg)
EV Problems – Question 2
Task Description PV EV SV
1.0.0 Operating system $25,000 $23,000 -2,000
2.0.0 Database $90,000 $85,000 -5,000
3.0.0 Web server $10,000 $9,000 -1,000
4.0.0 Firewall $8,000 $8,000 $0
5.0.0 Internal testing $10,000 $6,000 -4,000
6.0.0 “Beta” customers $12,000 $1,000 -11,000
7.0.0 Marketing $40,000 $5,000 -35,000
![Page 15: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/15.jpg)
EV Problems – Question 3 Use Table 1, shown above. What is the CPI
on task 7.0.0? A) 1.250B) 0.800C) 8000D) 0.125
What is your answer ? Why ?
![Page 16: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/16.jpg)
EV Problems – Question 3
Task Description PV EV AC
7.0.0 Marketing $40,000
$5,000 $4,000
CPI = EV / AC = 5,000 / 4,000 = 1.250
![Page 17: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/17.jpg)
EV Problems – Question 3
Task Description PV EV AC
7.0.0 Marketing $40,000
$5,000 $4,000
CPI = EV / AC = 5,000 / 4,000 = 1.250Is Task 7.0.0 under-budget so far? YES
![Page 18: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/18.jpg)
EV Problems – Question 3
Task Description PV EV AC
7.0.0 Marketing $40,000
$5,000 $4,000
CPI = EV / AC = 5,000 / 4,000 = 1.250Is Task 7.0.0 under-budget so far? YESIs Task 7.0.0 on-schedule so far?NO, but who asked
![Page 19: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/19.jpg)
Earned Value Basics of EV Work a few quick problems Apply EV to more realistic problems
![Page 20: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/20.jpg)
EV Problems – Question 4 You are the project manager for a $250,000 upgrade to
your company’s internet site. The current EV data is shown in Table 1, above. The next board meeting is scheduled for two months from today. The CEO of your company will demonstrate your new internet site to the board and to the investors attending that meeting. The CEO has just called and asked you for the “percent completion” as of today. What is your answer? A) 45% B) 50%C) 55%D) 60%
![Page 21: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/21.jpg)
EV Problems – Question 4 Analyze the Question
What does “Percent Complete” mean? Hours worked ? Miles of highway, lines of code ?
Basic EV equation EV = PV * (%Complete) Applies to a Task Also applies to the project
![Page 22: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/22.jpg)
EV Problems – Question 4 Identify a Strategy For a task
EV = PV * (%Complete) %Complete = EV / PV When expressed as a decimal it is SPI.
For a Project %Complete = SUM(EV) / SUM(Project PV)
![Page 23: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/23.jpg)
EV Problems – Question 4 EV is based upon “A Point in Time”
SPI = EV / PV AT THIS POINT IN TIME
![Page 24: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/24.jpg)
EV Problems – Question 4 Identify a Strategy For a task
EV = PV * (%Complete) %Complete = EV / PV
For a Project %Complete = SUM(EV) / SUM(Project PV) What is the total PV for a project?
![Page 25: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/25.jpg)
EV Problems – Question 4 Identify a Strategy For a task
EV = PV * (%Complete) %Complete = EV / PV
For a Project %Complete = SUM(EV) / SUM(Project PV) What is the total PV for a project? BAC
![Page 26: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/26.jpg)
EV Problems – Question 4 Identify a Strategy For a task
EV = PV * (%Complete) %Complete = EV / PV
For a Project %Complete = SUM(EV) / SUM(Project PV) What is the total PV for a project? BAC What is the BAC for this project ?
![Page 27: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/27.jpg)
EV Problems – Question 4 Identify a Strategy For a task
EV = PV * (%Complete) %Complete = EV / PV
For a Project %Complete = SUM(EV) / SUM(Project PV) What is the total PV for a project? BAC What is the BAC for this project ? BAC = $250,000
![Page 28: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/28.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
![Page 29: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/29.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
What else do we need to find ?
![Page 30: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/30.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
What else do we need to find ? Sum(EV)
![Page 31: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/31.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
What else do we need to find ? Sum(EV) = $137,000
![Page 32: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/32.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
What else do we need to find ? Sum(EV) = $137,000
What is the ANSWER ?
![Page 33: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/33.jpg)
EV Problems – Question 4 What do we know
%Complete = Sum(EV) / BAC BAC = $250,000
What else do we need to find ? Sum(EV) = $137,000
What is the ANSWER ? %Complete = 137,000 / 250,000 = 0.548
![Page 34: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/34.jpg)
EV Problems – Question 4 You are the project manager for a $250,000 upgrade to
your company’s internet site. The current EV data is shown in Table 1, above. The next board meeting is scheduled for two months from today. The CEO of your company will demonstrate your new internet site to the board and to the investors attending that meeting. The CEO has just called and asked you for the “percent completion” as of today. What is your answer? A) 45% B) 50%C) 55%D) 60%
What is your answer ?
![Page 35: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/35.jpg)
EV Problems – Question 4 You are the project manager for a $250,000 upgrade to
your company’s internet site. The current EV data is shown in Table 1, above. The next board meeting is scheduled for two months from today. The CEO of your company will demonstrate your new internet site to the board and to the investors attending that meeting. The CEO has just called and asked you for the “percent completion” as of today. What is your answer? A) 45% B) 50%C) 55%D) 60%
What is your answer ? C
![Page 36: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/36.jpg)
Earned Value Basics of EV Work a few quick problems Apply EV to more realistic problems
Here’s another one
![Page 37: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/37.jpg)
EV Problems – Question 5 You are the project manager for a $250,000 upgrade to
your company’s internet site. The current EV data is shown in Table 1, above. The next board meeting is scheduled for two months from today. The CEO of your company will demonstrate your new internet site to the board and to the investors attending that meeting. The CFO has just called and asked for your revised estimate on the total cost of the project. You review the data and realized that, aside from some hardware price increases initially, the remainder of the project plan is accurate. What is your revised estimated total project cost?A) $252,000 B) $250,000C) $248,000D) $246,350
![Page 38: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/38.jpg)
EV Problems – Question 5
Analyze the Question What is the EV name for
“revised estimated total project cost”?
![Page 39: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/39.jpg)
EV Problems – Question 5
Analyze the Question What is the EV name for
“revised estimated total project cost”? EAC “Estimate At Completion”
![Page 40: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/40.jpg)
EV Problems – Question 5
Analyze the Question What is the EV name for
“revised estimated total project cost”? EAC “Estimate At Completion” What are the formulas for EAC ?
![Page 41: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/41.jpg)
EV Problems – Question 5 EAC
EAC = AC + ETC Re-Estimated
EAC = AC + (BAC - EV) Atypical
EAC = AC + ((BAC - EV) / CPI) Typical
EAC = BAC / CPI Typical
![Page 42: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/42.jpg)
EV Problems – Question 5 EAC
EAC = AC + ETC Re-Estimated
EAC = AC + (BAC - EV) Atypical
EAC = AC + ((BAC - EV) / CPI) Typical
EAC = BAC / CPI Typical
Which one fits this problem ? Why ?
![Page 43: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/43.jpg)
EV Problems – Question 5 EAC
EAC = AC + ETC Re-Estimated
EAC = AC + (BAC - EV) Atypical
EAC = AC + ((BAC - EV) / CPI) Typical
EAC = BAC / CPI Typical
Which one fits this problem ? Why ?
![Page 44: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/44.jpg)
EV Problems – Question 5 EAC
EAC = AC + ETC Re-Estimated
EAC = AC + (BAC - EV) Atypical
EAC = AC + ((BAC - EV) / CPI) Typical
EAC = BAC / CPI Typical
Which one fits this problem ? Why ?What do we need to find ?
![Page 45: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/45.jpg)
EV Problems – Question 5 Totals
Task Description PV EV AC
1.0.0 Operating system $25,000 $23,000 $27,000
2.0.0 Database $90,000 $85,000 $80,000
3.0.0 Web server $10,000 $9,000 $9,000
4.0.0 Firewall $8,000 $8,000 $11,000
5.0.0 Internal testing $10,000 $6,000 $2,000
6.0.0 “Beta” customers $12,000 $1,000 $2,000
7.0.0 Marketing $40,000 $5,000 $4,000
SUM 137,000 135,000
![Page 46: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/46.jpg)
EV Problems – Question 5 Calculate the Answer
EAC = AC + (BAC - EV) = 135,000 + (250,000 – 137,000)
= 135,000 + 113,000 = 248,000
![Page 47: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/47.jpg)
EV Problems – Question 5 Find Your Answer A) $252,000
B) $250,000C) $248,000D) $246,350
![Page 48: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/48.jpg)
EV Problems – Question 5 Find Your Answer A) $252,000
B) $250,000C) $248,000D) $246,350
![Page 49: Earned Value Refresher By Robert Perrine, PMP Copyright reserved](https://reader036.vdocuments.site/reader036/viewer/2022062620/551ab493550346856e8b5081/html5/thumbnails/49.jpg)
Earned Value – Summary A few formulas to memorize Know the vocabulary – new and old EAC has a few variations