Download - Earned Value analysis
Earned Value
Elements of Project Control
• Creation of a Baseline Schedule
• Measurement of Performance
• Effective Corrective Actions
Schedule Updating
1. Schedule durations and sequences often vary from actual durations and sequences
– Subcontractors might use different methods– Force Majeure events delay the project– Etc
2. Participants would like to know how the project is progressing
– Owners – When can I move in? How much should I pay this month? What milestones have been met?
– Designers – When do I release drawings– Subcontractors – when do I come on to the site?
Usefulness of frequent schedule updating
• Current state of the project is always known
• Updates provide a valuable record of project status at a given time– Can document changes, responsibilities and
delays throughout the project– Useful during claims proceedings
• Schedule is a document that can be followed
More on updates
• Schedules should be updated periodically– Especially if a major event such as a logic
change occurs
• Updates should show– New start and completion dates– Completed activities– Percentage progress on activities
Percentage Complete
Planned Vs. Actual
Updating a Precedence Diagram
0 0
Start
0 0 0
0 4
F (3)4
3 3 7
0 3
A 3
0 0 3
3 9
B (4)6
3 0 9
6 8
D 2
7 1 9
3 6
E 3
4 1 7
9 9
Finish
9 0 9
6 8
C 2
7 1 9
Earned Value
• “We have spent 60% of the time for an activity but have completed 40% of the work. We are on schedule since we have completed the most time consuming parts of the activity”
Evaluating Progress on an Activity
• Units completed– Length of pipe laid, length of trench dug
• Effort expended– Plastering = 50%, Painting = 50% effort– 3 walls plastered, two painted out of 4 walls– Percentage complete = (3x0.5+2x0.5)/4 = 62.5%
• Expert opinion• Amount spent• Time taken (?)
Project Monitoring
Project Monitoring
• Planning and scheduling play an important role in project management
• But without monitoring the project, chances of completing the project on schedule is difficult
• Two parameters are monitored– Cost– Time
• The following graph shows the Time-cost relationship for a project
Project Monitoring
• This graph shows Project Progress
Time
Cost over-run with schedule
Time over-run
IdealCurve
Project Monitoring
• Cost is not proportional to the time/man-hours spent on each activity– Eg:- Installation of a projector in a classroom
• Cost of the projector is very high• Man-hours spent on installation are not significant
• Neither expenditure nor man-hours spent can be used to measure the project progress
• Expenditure and man-hours are inputs• Progress in terms of input does not indicate progress in
terms of output
Project Monitoring
• Quantities installed can give information regarding project progress, but is limited to very few activities and cannot be applied to the entire project as it involves various activities
• Thus with the help of above mentioned parameters, it is difficult to measure the project progress.
• Hence the use of “EARNED VALUE” of time or cost
Concepts of Earned Value
Concept of Earned Value
• Consider the following example:– Wall construction
Wall is divided into 4 sectionsFor 4-sections - 100 man-hours are requiredHence if 2-sections are completed,
(2/4) × 100= 50 man-hours
– We say that 50 man-hours have been EARNED
• The actual man-hours spent to construct these two sections can be more than or less than the Earned Value of man-hours
Concept of Earned Value
– Wall construction
If 4 sections cost Rs. 1000/-then the cost of constructing 2 sections = Rs. 500/-
We say that Rs. 500/- is the EARNED value of moneyThe actual cost incurred in constructing these two
sections can be more than or less than the Earned Value of money
It is important to note that Earned Value is based on the Actual quantities installed or Actual quantity of work done
Hence output is considered in the Earned Value concept
Concept of Earned Value
• Calculation of Earned Value– Earned Value of man-hours or money for an activity can be
calculated as follows:
Example 1
Example 1
• Determination of planned % complete:• Consider the following example
Draw % complete with respect to man-hours and money.
Activity A
Activity B
300
5000
700 (man-hours)
5000 (money)
500
10000
800 (man-hours)
70000 (money)
Example 1
• Determination of planned % complete based on man-hours.
Activity A
Activity B
300
5000
700 (man-hours)
5000 (money)
500
10000
800 (man-hours)
7000 (money)
Daily Cumulative
Total Cumulative
% Complete
300 1200 800
300 1500 2300
300 1200 300230023002300
= 1.0= 0.65= 0.13
Example 1
• Determination of planned % complete based on money.
Activity A
Activity B
300
5000
700 (man-hours)
5000 (money)
500
10000
800 (man-hours)
7000 (money)
Daily Cumulative
Total Cumulative
% Complete
5000 15000 7000
5000 20000 27000
= 1.0= 0.741= 0.185
5000 20000 90000270002700027000
Example 1
Stages
Example 1
BCWS – Man-hours
Stages 1 2 3 Total
Activity A 300 700 0 1000
Activity B 0 500 800 1300 2300
Stage Total 300 1200 800
Cumulative Total 300 1500 2300
Project % Complete 0.13 0.65 1.0
Example 1
BCWS – Money
Stages 1 2 3 Total
Activity A 5000 5000 0 10000
Activity B 0 10000 7000 17000 27000
Stage Total 5000 15000 7000
Cumulative Total 5000 20000 27000
Project % Complete 0.185 0.741 1.0
• Determination of Earned Value of Man-hour.– Consider the previous problem (man-hours)
Example 1
500 800
700300Activity A
Activity B
% Complete
0.25 0.95 1.0
0.6 0.95
Activity A
Activity B
scheduled
Example 1
• Determination of Earned Value of Man-hour.– Stage 1:
EMh (A)
EMh (B)
Total Man-hours = 2300
% complete of project:% complete = 250 / 2300% complete = 0.11
Example 1
• Determination of Earned Value of Man-hour.– Stage 2:
EMh (A)
EMh (B)
Total Man-hours = 2300
% complete of project:% complete = 1730 / 2300% complete = 0.752
Example 1
• Determination of Earned Value of Man-hour.– Stage 3:
EMh (A)
EMh (B)
Total Man-hours = 2300
% complete of project:% complete = 2235 / 2300% complete = 0.97
• Determination of Earned Value of Man-hour:
Earned Value(man-hours)
500 800
700300Activity A
Activity B
% Complete
0.25 0.95 1.0
0.6 0.95
Activity A
Activity B
scheduled
250 700 50 Man-hours
780 455 Man-hours
0.108 0.752 0.971Project - % Complete
Example 1
Example 1
• Determination of Earned Value of Man-hour.
BCWP
Stages 1 2 3
% complete
Activity AActivity B
0.250
0.950.6
1.00.95
Earned Value (man-hours)
Activity AActivity B
Stage total
2500
250
700780
1480
50455505
Activity A (cum)Activity B (cum)
2500
950780
10001235
Total cumulative 250 1730 2235
Project % complete 0.109 0.752 0.972
Example 1
• Determination of Earned Value of Man-hour:ACTUAL MAN-HOURS
Actual(man-hours)
500 800
700300Activity A
Activity B scheduled
400 500 100 Man-hours
450 1000 Man-hours
Example 1
• Determination of Earned Value of Man-hour:
ACWP
Stages 1 2 3
Activity AActivity B
4000
500450
1001000
Stage Total 400 950 1100
Cumulative Total 400 1350 2450
Example 1
• Determination of Earned Value of Man-hour:
Stage 1 Stage 2 Stage 3
BCWS SCHEDULED MAN-HOUR (Cumulative) 300 1500 2300
BCWP EARNED MAN-HOUR (Cumulative) 250 1730 2235
ACWP ACTUAL MAN-HOUR (Cumulative) 400 1350 2450
SV BCWP-BCWS -50 230 -65
CV BCWP-ACWP -150 380 -215
SPI BCWP/BCWS 0.83 1.15 0.97
CPI BCWP/ACWP 0.63 1.28 0.9122
Example 1
• Determination of Earned Value of Man-hour:Earned Value
Stages
Example 1
• Determination of Earned Value of Money– Consider the previous problem (money)
10000 7000
50005000Activity A
Activity B
% Complete
0.25 0.95 1.0
0.6 0.95
Activity A
Activity B
scheduled
• Determination of Earned Value of Money.– Stage 1:
EMh (A)
EMh (B)
Total Man-hours = 27000
Example 1
% complete of project:% complete = 2500 / 27000% complete = 0.093
Example 1
• Determination of Earned Value of Money.– Stage 2:
EMh (A)
EMh (B)
Total Man-hours = 27000
% complete of project:% complete = 19700 / 27000% complete = 0.730
Example 1
• Determination of Earned Value of Money.– Stage 3:
EMh (A)
EMh (B)
Total Man-hours = 27000
% complete of project:% complete = 26150 / 27000% complete = 0.969
Example 1
• Determination of Earned Value of Money.
Earned Value(money)
10000 7000
50005000Activity A
Activity B
% Complete
0.25 0.95 1.0
0.6 0.95
Activity A
Activity B
scheduled
2500 7000 500 Money
10200 5950 Money
0.093 0.730 0.969Project - % Complete
Example 1
• Determination of Earned Value of Money.
BCWP
Stages 1 2 3
% complete
Activity AActivity B
0.250
0.950.6
1.00.95
Earned Value (money)
Activity AActivity B
Stage total
25000
2500
70001020017200
50059506450
Activity A (cum)Activity B (cum)
25000
950010200
1000016150
Total cumulative 2500 19700 26150
Project % complete 0.093 0.730 0.969
Example 1
• Determination of Earned Value of Money.ACTUAL MONEY
Actual(money)
10000 7000
50005000Activity A
Activity B scheduled
4500 6000 5000 Money
8500 7500 Money
Example 1
• Determination of Earned Value of Money.
ACWP
Stages 1 2 3
Activity AActivity B
45000
60008500
50007500
Stage Total 4500 14500 12500
Cumulative Total 4500 19000 31500
Example 1
• Determination of Earned Value of Money.
Stage 1 Stage 2 Stage 3
BCWS SCHEDULED MONEY (Cumulative) 5000 20000 27000
BCWP EARNED MONEY (Cumulative) 2500 19700 26150
ACWP ACTUAL MONEY (Cumulative) 4500 19000 31500
SV BCWP-BCWS -2500 -300 -850
CV BCWP-ACWP -2500 700 -5350
SPI BCWP/BCWS 0.5 0.99 0.97
CPI BCWP/ACWP 0.56 1.04 0.83
Example 1
• Determination of Earned Value of Money.Earned Value
Stages
Example 2
Example 2
• Determination of planned % complete:
Draw % complete with respect to Man-hours and Money.
MAN-HOURS
20 20 20 20 20
12.5 12.5 12.5 12.5
10 10
MONEY
8000 8000 8000 8000 8000
10000 10000 10000 10000
75000 75000
Sch. Qty. Sch. Mhrs
Flooring 400 100
Electrical 100 50
AV systems 20 20
Sch. Money
40000
40000
150000
Example 2
• Determination of planned % complete based on Man-hours:
Sch. Mhrs.
Flooring 100
Electrical 50
AV systems 20
170
20 20 20 20 20
12.5 12.5 12.5 12.5
10 10
20 20 32.5 32.5 32.5 32.5 10 10
20 40 72.5 105 137.5 150 160 170
20170
40170
72.5170
105170
137.5170
150170
160170
170170
0.118 0.235 0.426 0.618 0.809 0.882 0.941 1.0
Total Mhrs.
Cuml. Mhrs.
% complete
Stage 1 Stage 2 Stage 3 Stage 4
Example 2
• Determination of planned % complete based on money:
Sch. Money
Flooring 40000
Electrical 40000
AV systems 150000
230000
8000 8000 8000 8000 8000
10000 10000 10000 10000
75000 75000
8000 8000 18000 18000 18000 10000 75000 75000
8000 16000 34000 52000 70000 80000 155000 230000
8000230000
16000230000
34000230000
52000230000
70000230000
80000230000
155000230000
230000230000
0.034 0.069 0.147 0.226 0.304 0.347 0.673 1.0
Total Money
Cuml. Money
% complete
Stage 1 Stage 2 Stage 3 Stage 4
Example 2
• Scheduled-percentage complete
Days
Example 2
• Determination of Earned Value of Man-hour – UPDATE 1
Quantity Installed
50 70
12.5 17.5 0 0 0 0 0 0
12.5 30 30 30 30 30 30 30
0.074 0.176 0.176 0.176 0.176 0.176 0.176 0.176
Sch. Mhrs Inst. Qty.
Flooring 100 120
Electrical 50
AV Systems 20
170
Actual Man-hours
20 20
20 20 0 0 0 0 0 0
20 40 40 40 40 40 40 40
Earned Mhrs.
Cuml. Earned Mhrs.
% complete
Total Mhrs.
Cuml. Mhrs.
• Update 1
Example 2
Stages
Example 2
• Determination of Earned Value of Man-hour – UPDATE 2
Quantity Installed
50 70 80 80
25 30
12.5 17.5 32.5 35 0 0 0 0
12.5 30 62.5 97.5 97.5 97.5 97.5 97.5
0.074 0.176 0.368 0.574 0.574 0.574 0.574 0.574
Sch. Qty. Sch. Mhrs Inst. Qty.
Flooring 400 100 280
Electrical 100 50 55
AV Systems 20 20
170
Actual Man-hours
20 20 30 30
15 15
20 20 45 45 0 0 0 0
20 40 85 130 130 130 130 130
Earned Mhrs.
Cuml. Earned Mhrs.
% complete
Total Mhrs.
Cuml. Mhrs.
Example 2
• Update 2
Days
Example 2
• Determination of Earned Value of Man-hour – UPDATE 3
Quantity Installed
50 70 80 80 90 30
25 30 35 10
12.5 17.5 32.5 35 40 12.5 0 0
12.5 30 62.5 97.5 137.5 150 150 150
0.074 0.176 0.368 0.574 0.809 0.882 0.882 0.882
Sch. Qty. Sch. Mhrs Inst. Qty.
Flooring 400 100 400
Electrical 100 50 100
AV Systems 20 20 0
170
Actual Man-hours
20 20 30 30 30 15
15 15 15 15
20 20 45 45 45 30 0 0
20 40 85 130 175 205 205 205
Earned Mhrs.
Cuml. Earned Mhrs.
% complete
Total Mhrs.
Cuml. Mhrs.
Example 2
• Update 3
Days
Components of Earned Value
Components of Earned value Analysis
• Budgeted Cost of Work Scheduled (BCWS)– It is the budgeted cost of work scheduled to be performed– It is also called the Planned Value (PV)– It tells how much work have been completed
Components of Earned value Analysis
• Budgeted Cost of Work Performed (BCWP)– It is the budgeted cost of work actually performed– The Earned Value for the work actually completed– It tells how much work is actually completed
Components of Earned value Analysis
• Actual Cost of Work Performed (ACWP)– It is the amount actually spent on the work completed– This could be more or less than the Earned Value
Components of Earned value Analysis
• Scheduled Variance (SC)
– It compares work completed vs work planned– It helps to identify whether the project is ahead or behind
schedule– Negative value indicated that the project is behind schedule
Components of Earned value Analysis
• Scheduled Performance Index (SPI)
– It helps to identify whether the project is ahead or behind schedule
– Less than 1 indicates that the project is behind schedule– It can be used to forecast how long it will take for the project to
complete
Components of Earned value Analysis
• Cost Varience (CV)
– It compares what was planned to be spent on the work completed vs. what was actually spent
– It helps to identify whether the project is ahead or behind schedule
– Negative value indicates that the project is over budget
Components of Earned value Analysis
• Cost Performance Index (CPI)
– It helps to identify weather the project is above or below budget– Less than 1 means the project is over budget– It can be utilised to forecast how much amount will be required
to complete the project
Components of Earned value Analysis
• Budget at Completion (BAC)– It is the amount that was originally budgeted to complete the
project
Components of Earned value Analysis
• Estimate at Completion (EAC)– It is the estimated amount required to complete the project
Components of Earned value Analysis
http://www.iceincusa.com/16CSP/content/4_ev/gifs/image1.gif (17.01.2007)