Dordtech is partner
and overall contractor
Responsible for: –Concept
–Engineering
–Planning
–Construction and realization
–Commissioning
–Operations
–Maintenance Dorset conference
20 June 2014 Dordtech - Ecocycle project
![Page 2: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/2.jpg)
Skills of Dordtech
• Engineering and projectmanagement of sustainable energy production systems
• Producer of CHP units for alternative fuels
• Producer of gastreatment sets
• Cooperative partner for decentral power plants like biogas- and gasification plants
• Cooperative partner for using heat in driers, orc’s and absorption coolers
In the last few years Dordtech became
Overall contractor of green powerplants Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 3: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/3.jpg)
Vapour Processing System
Total Lyon
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 4: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/4.jpg)
Bio oil (animal fat) CHP head office TNT
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 5: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/5.jpg)
Biogas installation Belgium
2x 1MWe biogas and 1MWe dual fuel bio-oil CHP
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 6: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/6.jpg)
Ecocycle is a leading energy from
biomass and combined heat &
power plant developer, utilizing
operationally proven biomass
gasification technology.
Dorset conference 20 june 2014 Dordtech
- Ecocycle project
![Page 7: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/7.jpg)
General data Ecocycle
gasification plant Usk
• Design/layout Ecocycle/Dordtech
• Contractor Dordtech
• Commissioning: June/July 2014
• Fuel input: Woodchips TS 85%
• Fuel consumption 48.000 tons/y
• Power output: 6.300 kWe
• Heat output 5.000 kWth
• Operational hours/year 7.500
Dorset conference 20 June 2014
Dordtech - Ecocycle project
![Page 8: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/8.jpg)
Gasification plant in Usk (Wales)
Woodchips as fuel – power 6,3 MWe and 5 MWth
With exception of delivering the gasifier (Eco-Cycle/Torftech) Dordtech
provided: Engineering and construction; all piping and electrical
connections; Over-All control technology of all major components
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 9: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/9.jpg)
Fuel treatment
transport – cleaning – drying – storage – dosage
Syngas treatment
cleaning – cooling – ashcollecting
Syngas distribution
gasbuffer – emergency flare – CHP units
Heat distribution
boiler – dryer – absorption chiller – emergency
coolers
Gasification is complex
dedicated issues are:
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 10: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/10.jpg)
Woodchips for the gasifier need to have a TS of around 85%.
Heat from the CHP can be used for drying the feedstock
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 11: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/11.jpg)
Storage & dosing of woodchips
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 12: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/12.jpg)
Dorset belt driers TOMO 33
Dorset conference 20 june 2014
Dordtech - Ecocycle project
Capacity 4 MWth:
Input : 8t /hr @ 40% moisture
Output: 6t /hr @ 20% moisture
![Page 13: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/13.jpg)
Dorset driers are simple, robust and
excellent for drying biomass
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 14: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/14.jpg)
A screw press and elevator conveys the dried
woodchips to the fuel hopper
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 15: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/15.jpg)
Fuel hoppers and dosing screws
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 16: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/16.jpg)
Propane is used for start up phase, heating up the gasifier
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 17: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/17.jpg)
Woodchips are gasified
In the Torftech gasifier at
aproximately 700⁰C with
minimum O2.
The fuel is separated in
syngas and 3 – 5 % of ash
Syngas fuel variability
Comp. Min max
H2 8,6 61,9 vol%
CO 22,3 55,4 vol%
CH4 0 8,2 vol%
CO2 1,6 30,0 vol%
N2 + air 0,2 49,3 vol%
H2O 0 39,8 vol%
H2/CO 0,33 2,36 vol%
LHV 5,02 12,57 vol%
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 18: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/18.jpg)
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 19: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/19.jpg)
The produced Syngas needs to be cleaned and cooled
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 20: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/20.jpg)
WESP = Wet ElectroStatic Precipitator for removal of solid
particles and liquid droplets from the gas stream
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 21: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/21.jpg)
Heat from the CHP units is used for the absorption chiller to
produce water of 6°C to cool the syngas
the syngas from 800°C to 15°C
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 22: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/22.jpg)
To create a balanced system / contstant gas flow
a gasbuffer of 200 m³ is installed
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 23: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/23.jpg)
In emergency cases, or for Off – Spec
syngases a flare is installed
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 24: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/24.jpg)
Before (clean) Syngas is
brought into the CHP unit
it needs to have a
constant pressure and
temperature
Gastrain and blower isle
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 25: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/25.jpg)
DR – Guascor adapted gas engines are de-rated to 700 kWe
on syngas ( LHV 4,8 – 7 MJ/Nm3 )
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 26: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/26.jpg)
Housing for 9 CHP units
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 27: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/27.jpg)
The gensets are located in dedicated
sound – isolated canopees
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 28: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/28.jpg)
Chimneys and heat take – off
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 29: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/29.jpg)
All heat can be dump cooled
in case of emergency
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 30: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/30.jpg)
Pipe work and heat transferr
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 31: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/31.jpg)
And pipe work and heat transferr
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 32: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/32.jpg)
All the electrical connections
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 33: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/33.jpg)
All the electrical wiring
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 34: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/34.jpg)
Control technology
Dorset conference 20 june 2014
Dordtech - Ecocycle project
![Page 35: Dordtech is partner and overall contractor Responsible for · Dordtech - Ecocycle project . Vapour Processing System Total Lyon Dorset conference 20 june 2014 Dordtech - Ecocycle](https://reader033.vdocuments.site/reader033/viewer/2022043023/5f3f1202ff63e64c5a095ba7/html5/thumbnails/35.jpg)
Dorset conference 20 june 2014
Dordtech - Ecocycle project
Next project 2015 Exeter 10 Mwe engines & ORC \ WID