1
COUNTY GOVERNMENT OF KERICHO
DEPARTMENT OF FINANCE AND ECONOMIC PLANNING
BILL OF QUANTITES
FOR
PROPOSED ERECTION AND COMPLETION OF AN
OPERATING THEATRE
AT AINAMOI HEALTH CENTRE
FOR THE
COUNTY GOVERNMENT OF KERICHO
PREPARED BY:-
COUNTY WORKS OFFICER
P.O BOX 7-20200
KERICHO
2
NOVEMBER 2018
Item
Description Qty Unit
Rat
e
Amount
K.Sh.
PROPOSED ERECTION AND COMPLETION OF AN OPERATING
THEATRE AT AINAMOI HEALTH CENTRE, KERICHO COUNTY
0.00
ELEMENT NO. 1
SUBSTRUCTURES (ALL PROVISIONAL)
Oversite excavation 0.00
A Excavate oversite to remove top soil average 200mm deep and
keep on site for later re-use for landscaping
441 sm
Excavation
B Excavate oversite to reduce levels commencing from stripped
level exceeding 1.50 meters deep.
662 cm
C Excavate foundation trench starting from reduced level not
exceeding 1.50 meters deep.
142 cm
D Ditto for column bases starting from reduced level not
exceeding 1.50 meters deep.
58 cm
E Extra-over all excavation for excavating rock irrespective of
class
20 cm
F Return, fill-in and rum selected excavated materials around
foundations
95 cm
G Remove and cart away surplus excavated materials. 53 cm
Diposal of water
H Keeping all excavations free from all water including spring or
running water
Item 25,000.00
Planking and strutting
I Uphold the sides of all excavations Item 25,000.00
Filling
J Hardcore filling in making up levels,exceeding 300mm thick in
layers of 150mm maximum thickness
117 cm
K 50mm (average) thick quarry dust blinding to surfaces of
hardcore
389 sm
Antitermite treatment 0.00
3
L Premise 200 SC' or other equal and approved anti-termite
insecticide treatment with ten years guarantee, applied strictly
in accordance with manufacturer's instructions, to tops of fill and
foundation walls
389 sm 0.00
Carried to Collection
Concrete 0.00
A 50mm thick mass concrete class Q (1:3:6) to bottoms of
foundations
114 sm
Insitu concrete; reinforced; class 20 / (20mm); vibrated
B Foundations in trenches irrespective of thickness 28 cm
C Column bases 19 cm
D Foundations columns 6 cm
E 150mm thick bed; 389 sm
Reinforcement
Bars; high yield steel; cold worked to B.S. 4461 including bends,
hooks, tying wire and distance blocks
F 12mm ditto 2,650 kg
G 8mm ditto 2,650 kg
Fabric; B.S. 4483
H Reference A142 mesh 200 x 200 mm , weight 2.22 kgs per square
meter ( measured net - no allowance made for laps( inclunding
bends, tying wire and distance blocks
389 sm
Sawn formwork to insitu concrete as described:-
I To sides; vertical or battering of foundations, ground beams or
the like
63 sm
J To sides; vertical or battering of column bases 45 sm
K To sides; vertical or battering of columns 65 sm
0.00
L Edges of ground floor slab; 75 to 150mm wide 85 lm
Walling
M 200mm thick approved natural stone; local; roughly squared to
foundation walling; bedding and jointing in cement sand (1:3)
mortar
189 sm
4
Damp proofing
N Polythene sheet; 1000 gauge, 200mm welted laps (no
allowance made to laps), horizontal; 1 no. layer laid on
compacted quarry dust blinding
389 sm
Carried to Collection 0.00
A 200mm wide; B.S. 743 Type A bitumen hessian base 150 mm laps
(no allowance made for laps); horizontal, 1 no. layer, bedded in
cement sand (1:3) mortar
273 lm
Insitu Finishings
B 14mm thick 2 No. coatwork cement sand (1:3) render; wood
floated to concrete or blockwork base to walls; external
85 sm
Painting and Decorations
Prepare and apply three coats bituminous paint to:
C Wood floated rendered plinths over 300mm girth 85 sm
Paving Slabs.
D 600 x 600 x 50 mm Precast concrete class 20/20 paving slabs,
laid to falls on blinded hardcore surface and jointed in cement
and sand (1:3) mortar
119 sm
Carried to Collection
COLLECTION
From page SH/1 0.00
From page SH/2 0.00
From above 0.00
TOTAL FOR SUBSTRUCTURES CARRIED TO SUMMARY 0.00
0.00
ELEMENT NO. 2 0.00
0.00
FRAME 0.00
0.00
Insitu concrete; reinforced; class 20 / (20mm); vibrated 0.00
A Beams 19 cm 0.00
5
0.00
B Columns 15 cm 0.00
0.00
Reinforcement 0.00
0.00
Bars; high yield steel; cold worked to B.S. 4461 including bends,
hooks, tying wire and distance blocks 0.00
0.00
C 12mm Ditto 1,700 kg 0.00
0.00
D 8mm Ditto 1,700 kg 0.00
0.00
Sawn formwork to insitu concrete as described:- 0.00
0.00
E To sides and soffits of beams. 221 sm 0.00
0.00
F Vertical sides of columns 147 sm 0.00
0.00
TOTAL FOR FRAME CARRIED TO SUMMARY 0.00
ELEMENT NO. 3 0.00
0.00
WALLING 0.00
0.00
EXTERNAL WALLING 0.00
0.00
NATURAL STONE WALLING 0.00
0.00
A 200 mm thick approved local; chisel dressed both sides;
bedding, jointing and pointing in cement sand (1:3) mortar
288 sm
0.00
B 200 mm eaves filling, 200mm high including dressing between
rafters
72 lm
0.00
C Extra over horizontal and vertical pointing in 10mm thick rod in
cement and sand (1:3) mortar; one coat of bituminous paint.
288 sm
0.00
INTERNAL WALLING 0.00
0.00
NATURAL STONE WALLING 0.00
0.00
D 200 mm thick approved local; chisel dressed both sides;
bedding, jointing and pointing in cement sand (1:3) mortar
640 sm
0.00
TOTAL FOR WALLING CARRIED TO SUMMARY 0.00
ELEMENT NO. 4 0.00
0.00
6
ROOF CONSTRUCTION. 0.00
0.00
Galvanized steel box profile sheets; 28 gauge; prepainted 0.00
0.00
A Roof covering; 150mm laps on one end and one and a half
corrugation side lap; fixed to angle section purlins with and
including J-bolts, nut and neoprene washers.
508 sm
Accessories, fixing as necessary to roof sheets
B 150mm dia. Half round ridge cap 28 lm
CARPENTRY
The following in sawn celcured cypress
C 100 x 50mm purlins 564 lm
D 150 x 50mm wall plate rag-bolted at 1200mm centres with 12mm
diameter bolts (m/s) 158 lm
E 200 x 50mm ridge board 28 lm
The following sawn celcured cypress timber trusses, nailled
connections, spanning 3000 to 4000mm wide, hoisting 9.0m
above ground
F 150 x 50mm ceiling joist 306 lm
G 150 x 50mm rafters 360 lm
H 100 x 50mm struts and ties 312 lm
I 150 x 50mm king post 52 lm
0.00
J 100 x 25mm nailing plates 20 lm 0.00
0.00
Labour and material (Provisional) 0.00
0.00
K 12mm diameter rag bolt, 200mm long complete with and
including head, nut and two washers; cast into and including
mortice in stone or concrete and run with cement and sand
(1:3) mortar 133 No 0.00
0.00
L Drill 50mm thick timber to receive 12mm dia. Bolt (m/s) 133 No. 0.00
0.00
Carried to Collection 0.00
7
0.00
RAINWATER DISPOSAL 0.00
0.00
24g Galvanised mild steel sheeting; all welds ground smooth 0.00
A 150 x 100mm box gutter including soldered joints in the running
length fixed to fascia board with and including brackets at
approved centers
94 lm
B Extra; 100mm dia.outlet 100mm long 12 No
C
100mm dia. rainwater downpipe fixed with and including mild
steel straps at 900mm centres, plugged and screwed to wall
48 lm
D Extra; swanneck bend with 1135mm projection 12 No
E Extra; horse shoe bend 12 No
Painting and Decorations
Prepare and apply one zinc plumbate primer and three coats of
'CROWN SOLO' or other equal and approved super gloss oil
paint to:-
F General surfaces of gutters; over 300mm girth external 150 sm
G Small pipes 48 lm
Carried to collection 0.00
0.00
COLLECTION
From page SH/6 0.00
From above 0.00
TOTAL FOR ROOF CONSTRUCTION CARRIED TO SUMMARY 0.00
ELEMENT NO. 5
0.00
DOORS 0.00
0.00
Wrot mahogany framed frames and framings 0.00
0.00
A 150 x 50 mm; 2 No. labours; plugged door frame 203 lm
B 40 x 35 mm moulded architrave 203 lm
8
C 25 x 25mm moulded quadrants 203 lm
45mm Thick solid core flush doors to B.S 459: part 2 veneered
both sides with internal quality plywood and lipped on all edges
in approved hardwood
D Double swing door size 1740 x 2060 mm high with view panel to
Architects detail 6 No.
E Ditto; but single swing door size 840 x 2060 mm high 20 No.
F Ditto; semi-solid 4 No.
Iron mongery
Supply and fix the following to UNION catalogue or other equal
and approved
To softwood, hardwood or the like fixing with screws
G Euro cylinder mortice deadlock comprising case and Euro
profile single cylinder 6 No.
H Three lever rebated mortice lock complete with set lever
aluminium handle furniture 20 No.
J Two lever mathroom mortice lock complete with set lever
aluminium handle furniture 4 No.
K 100mm brass-plated double action butt hinges 6 prs
L 100mm brass-plated butt hinges 30 prs
M 300mm diameter D handle 24 No.
To concrete or blockwork; fixing with bolts; plugging
N Rubber door stop complete with 38 mm rawl bolt 68 No.
Glazing
O 5mm Thick obscure sheet glass panes to metal surfaces; fixing
with putty 6 sm
Carried to collection 0.00
9
Painting and Decorations 0.00
0.00
Aluminium primer or other equal and approved wood primer
before fixing: -
0.00
0.00
A Backs of frame, board, etc over 100mm but not exceeding
200mm girth
203 lm
Knot, prime and stop; prepare and apply one coat stain and
two coats of clear varnish
B General surfaces of timber doors over 300mm girth; external 143 sm
C Frames; over 200mm but not exceeding 300mm girth; internal 203 lm
D Frames not exceeding 100mm girth; internal 203 lm
0.00
Carried to Collection 0.00
COLLECTION
From page SH/8 0.00
From above 0.00
TOTAL FOR DOORS CARRIED TO SUMMARY 0.00
ELEMENT NO. 6
WINDOWS
METAL WORK 0.00
PURPOSE - MADE UNITS 0.00
Supply, assemble and fix the following purpose-made mild steel
casement windows; standard metal section from approved
manufacturer complete with frames, transomes, mullions and
with and including permanent ventilators comprising "T" bar,
gauze and 16 gauge sheet metal hood 50mm high x 50mm
projection to full width of window, coupling mullions, approved
ironmongery and one coat manufacturer's primer; all welding
ground to smooth finish.
0.00
0.00
10
Steel; for glazing with putty, lugs to two jambs, cutting and
pinning to concrete or blockwork, fixing to head and sill with
screws; plugging 0.00
0.00
A Window, overall size 3000 x 100mm high fixed lights 5 No 0.00
B Window, overall size 1800 x 2000mm high with 2No. Side-hung
openable light size 500 x 1500mm high and 1No. fixed lights
9 No 0.00
C Window, overall size 600 x 600mm high with 1No. Top-hung
openable light size 300 x 600mm high and 1No. fixed lights 4 No 0.00
Glazing 0.00
D 5mm Thick clear sheet glass panes over 0.1 but not exceeding
0.5 square meters; fixing with putty 49 sm 0.00
0.00
E Ditto; obscure 1 sm 0.00
Painting and Decorations 0.00
0.00
On Metal work 0.00
0.00
Prepare and apply three coats oil paint full gloss to Crown Solo
or other equal and approved to: - 0.00
0.00
F General window surfaces; over 300mm girth internal 50 sm 0.00
0.00
G General window surfaces; over 300mm girth external 50 sm 0.00
TOTAL FOR WINDOWS CARRIED TO SUMMARY 0.00
0.00
ELEMENT NO. 7 0.00
0.00
FINISHES 0.00
0.00
Wall finishes 0.00
0.00
Insitu finishes 0.00
0.00
Render; 15mm thick, 1 No. coatwork of cement and sand (1:3);
wood floated to concrete or blockwork base generally to: -
0.00
A Beams and columns; external 94 sm 0.00
0.00
Plaster; 15mm thick, 2 No. coatwork, 12mm first coat of cement
sand (1:3); 3mm second coat of cement and lime putty (1:9);
steel trowelled to concrete or blockwork base 0.00
11
0.00
B Walls; internal 1,843 sm 0.00
0.00
Prepare and apply one undercoat and three coats of first
quality emulsion paint to the following surfaces 0.00
0.00
C Rendered walls; external 94 sm 0.00
D Plastered walls; internal 1,843 sm 0.00
Floor finishes 0.00
0.00
Insitu Finishings 0.00
20mm thick, 2 No. coat work terrazzo; approved colour;
cement and marble chippings (1:2); machine polished; to
concrete or blockwork base generally to: - 0.00
E Floors level; internal 389 sm 0.00
0.00
F Skirtings; 150mm wide; rounded junction with wall finish and
straight junction with floor finish. 461 lm 0.00
0.00
Beds or Backings 0.00
Screed; cement and sand (1:3) 0.00
0.00
G 20mm thick one coat backings; wood floated to receive
ceramic tiles (m/s) to concrete or blockwork base; to floors
level; internal 389 sm 0.00
Carried to Collection 0.00
Ceiling finishes 0.00
0.00
Wrot cypress 0.00
0.00
A 75 x 25mm moulded cornice 461 lm
Approved sawn softwood; second grade; pressure
impregnated.
B 50 x 50mm brandering 1,081 lm
C 50 x 50mm ditto; plugged 461 lm
PLAIN SHEET FINISHINGS
12
Chip board
D 12mm thick patterned chip-board ceiling board nailed to
timber brandering (m/s); nails punched and puttied 389 sm
Painting and Decorations
To wood surfaces
E Chip-board ceiling boards 389 sm
F Moulded cornice not exceeding 100mm girth 461 lm
Carried to Collection 0.00
COLLECTION
From page SH/11 0.00
From above 0.00
TOTAL FOR FINISHES CARRIED TO SUMMARY 0.00
SUMMARY
ELEMENT NO. TITLE PAGE NO. K.SHS.
1 SUBSTRUCTURE (ALL PROVISIONAL) SH/3
2 FRAME SH/4
3 WALLING SH/5
4 ROOF CONSTRUCTION. SH/7
5 DOORS SH/9
6 WINDOWS SH/10
7 FINISHES SH/12 0.00
TOTAL FOR BUILDERS WORK CARRIED TO GRAND SUMMARY 0.00
13
item descriptiom Qty unit rate Amount
KSh
ELECTRICAL INSTALLATIONS (ALL PROVISIONAL)
Supply install test and commission the following:-
A LIGHTING POINTS
B Lighting point wired in 3x 1.5mmsq s.c.c pvc drawn in 20mm dia
HG PVC conduits concealed inside ceiling brandering c/w all its
necessary accessories excluding switches and fitting for
a)one way switching 20 no
b)ditto but two way 10 no
C 10A moulded ivory switch plate as crabtree or approved
equivallent as follows:-
a)1gang-1way switch 12 no
b)1gang-2way switch 4 no
D LIGHTING FITTINGS
a)1200mm 1x36w fluorescent batten fitting of slim cross section
c/w clip-on cover adjustable as thorn or approved equivalent
12 no
b)1200mm 2x36w fluorescent batten fitting of slim cross section
c/w clip-on cover adjustable as thorn or approved equivalent
12 no
b) poly carbonate bulkhead fitting c/w energy saving bulbs 6 no
E SOCKET OUT LET AND POWER POINTS
F Socket outlet point wired in 3x 2.5mmsq s.c.c pvc drawn in
25mm dia HG PVC conduits concealed inside ceiling brandering
c/w all its necessary accessories excluding switches and fitting
for:-
15 no
a)13A socket outlet twin as crabtree or approved equivalent 15 no
G CONSUMER-UNIT
H 12ways consumer SP/N withflush wall mounting c/w
100A SP/N integral isolator as havells or approved equivalent 1 no
a)6A sp MCBS 4 no
b)32A as ditto 3 no
c)blanking covers 5 no
14
Total carried to collection page
A SUB-MAIN CABLES
B 2x10mmsq/6.0 mm sq s.c.c drawn in conduit to feed consumers 24 mts
a)standard cable looping box g 14 galvanized steel sheet 1 no
b)100A cut out fuse twin to KPL& standards. 1 no
C SUPPLY CABLE
D 16mmsq underground cable 2core c/w cable glends from the
nearest cable looping box
item 30,150 30,150.00
a)trench to standard depth and backfill item 5,000 5,000.00
b)approved hatari tiles item 5,000 5,000.00
LIGHTING PROTECTION SCHEME
E The following for lightening protection system
a) copper lightening arrestors air termination as FURSE CAT NO
RA605,properly mounted and fastened on the roof including
base clamps and fixing materials.
1 no
b)3mm thick x25mm wide FURSE cat NO TC030 annealed
copper tape properly saddled at 1000mm intervals
10 mts
c)junction clamps as FURSE SD115 2 no
d)test clamps as FURSE cat CT305 1 no
e)earthing comprising 12mm x1500mm as FURSE cat NO RB110
copper rod c/w clamps and concrete inspection earth pit,to
the satisfaction of the project manager.
1 no
f)32mm dia PVC H/G sleeve to protect copper tape to hide of
1500mm from ground level.
1 no
F Allow a provisional sum of Kenya shillings five hundred thousand
(500,000.00) only for ELECTRICAL INSTALLATIONS
ITEM
500,000.00
Total carried to collection page
COLLECTION
1 From page EW/I
2 From page EW/2
TOTAL FOR ELECTRICAL WORKS CARRIED TO GRAND SUMMARY
15
Description Qty Unit Rate Amount
MECHANICAL INSTALLATIONS (ALL PROVISIONAL)
SANITARY FITTINGS
Supply, deliver, install the following sanitary fittings including materials and jointing to supply, waste/soil and overflow pipes
Shires products are specified only as an indication of quality. Equal and approved appliances may be supplied. Where trade names are mentioned, the Ref. No. is intended only as a guide to the type and quality of fittings
High level water closet
Ceramic water closet suite comprising pan, heavy plastic seat and cover ceramic cistern, flush pipe”P” or “S” trap. White ideal standard studio suite
2 NO
Wash hand basins
Wash hand basin with single taphole and of size: 560mm x 435 mm in approved colour complete with “Aztec monobloc basin mixer, 32mm dia popo-up waste chrome plated, 32mm chrome plated bottle trap. As “Shires ACCORD approved equivalent.
4 NO
Stainless steel wash hand basins
Wash hand basin with 3No. taphole and of size: 1160mm x 435 mm complete with hands free basin mixer, 32mm dia pop-up waste chrome plated, 32mm chrome plated bottle trap. As “Shires ACCORD approved equivalent.
4 No
Sponge tray
Semi-recessed build in soap tray vitreous china size 305 x 150mm as
"twyfords" or equal approved
2 No
Toilet roll holder
Semi-recessed build in toilet roll holder in vitreous china size 305 x 150mm as "twyfords" or equal approved
2 No
Mirrors
6mm thick polished plate glass silver backed mirror with bevelled edges, sizes: 610x497 mm plugged and screwed to wall with 4No dome capped chrome plated screws and 5mm thick foam back rest
4 No
16
Towel rail
20mm diameter x 900mm long approved towel rail chrome plated plugged and screwed into the wall.
2 No
Shower fittings
Concealed shower fitting consisting of 15mm chrome plated riser pipe to connect the concealed shower mixer for hot and cold water to a swivel/ adjustable shower rose, chrome plated handles and stop corks and other necessary fittings & accessories. All to be as Bricon/aztec or equal and approved.
2 No
Total for Sanitary Fittings carried forward to summary Page
INTERNAL PLUMBING
Supply, deliver and install the following PPR pipework and fittings.
Bidders must allow in their pipework prices for all the male /plastic adopters, sockets bends etc
PP – R- Pipes
20mm diameter 40 Lm
32 mm – ditto 16 Lm
Extra –over PP-R pipe work for the following :-
Bends
20mm dia threaded bend 9 No
20 mm dia bend 9 No
32 mm -ditto 6 No
Tees
32mm dia tee 4 No
32/20mm reduced tee 12 No
32/3/4” male threaded tee 12 No
23X3/4” male threaded tee 12 No
Sockets
20mm dia sockets 12 No
25mm – ditto 15 No
32mm dia sockets 12 No
Unions
32mm – ditto 12 No
17
20mm – ditto 6 No
Transition fittings
20X1/2” Round –male transition piece 12 No
20X1/2” – Ditto 12 No
Total carried forward to collection Page MW/4
Gate valves
20mm diameter “Pegler” gate valve 28 No
30mm – ditto 12 No
Ball valves
20mm – ditto 4 No
Flexible connections
15mm diameter, flexible connections 12 No
Roofs tanks
2300 litres 990x680x360mm High UPVC rectangular tanks with lids 2 No
Total carried to collection Page below
COLLECTION
From Page MW/ 3
From above
Total for Internal Plumbing carried forward to summary page
INTERNAL DRAINAGE
Supply, deliver and install the following PVC and muPVC soil and waste pipework. Bidders must allow un their prices for all the various sizes of connectors, adopters etc, required for the satisfactory functioning of the drainage system
uPVC and PVC pipes
100mm dia heavy duty golden brown pipe class “D” 150 Lm
50mm – ditto - 52 Lm
32mm- ditto 12 Lm
18
Extra –over uPVC and muPVC pipework for the following:
100mm dia WC connectors 12 No
10mm dia single branch 12 No
100mm dia vent cowl and weathering site/apron 2 No
100x50mm dia boss connector 12 No
100x50mm dia floor trap 10 No
100mm dia long radius bend 12 No
100mm dia short radius bend 12 No
100mm dia gully trap c/w cover and grating 4 No
32mm dia bends 8 No
32mm dia sweep tee 8 No
50mm – ditto 8 No
Total for Internal Drainage carried forward to summary page
FIRE PROTECTION SERVICES
Supply, deliver and install the following fire fighting equipment
Water /C02 Extinguisher
9 Litre water/CO2 gas portable fire extiquisher complete with car washer, siphon tube CO2 Cartridge and flexible rubber hose nozzle fully charged
2 No
Co2 Gas fire extinquisher
5 Kg dry Co2 gas portable extinquisher complete with squeeze grip operating head and discharge nozzle, fully charged
2 No
Manual Bell
“9” (225mm) wall mounted manual bell 1 No
Allow a provisional sum of Kenya shillings five hundred thousand (500,000.00) only for MECHANICAL INSTALLATIONS
ITEM 500,000.00
Total for fire fighting equipments carried forward to summary page
19
SUMMARY PAGE
Total cost for sanitary fittings Page MW/1
Total cost for internal plumbing Page MW/3
Total cost for internal drainage Page MW/4
Total cost for fire fighting equipments Page
MW/5
TOTAL FOR MECHANICAL WORKS CARRIED TO GRAND SUMMARY
Item Description Qty Unit Rate Amount K.Sh.
PRIME COSTS & PROVISIONAL SUMS
PROVISIONAL SUMS
The following provisional sums are to be measured on
completion and priced in accordance with the rates
contained in these bills of quantities or prorata thereto
or deducted in whole if not required
A Allow a provisional sum of Kenya shillings one hundred
thousand (100,000.00) only for compliance with N.C.A
and N.E.M.A regulations
ITEM 100,000.00
B Allow a provisional sum of Kenya shillings Two fifty
Thousand (250,000.00) only for Project Managers
Expenses on Meetings, Stationery e.t.c
ITEM 250,000.00
C Allow a provisional sum of Kenya shillings five hundred
thousand (500,000.00) only for joinery and fittings
ITEM 500,000.00
D Allow a provisional sum of Kenya shillings Five Hundred
Thousand (500,000.00) only for Contingencies
ITEM 500,000.00
TOTAL FOR P.C. & PROVISIONAL SUMS CARRIED TO GRAND SUMMARY 1,350,000.00
20
PROPOSED ERECTION AND COMPLETION OF AN OPERATING
THEATRE AT AINAMOI HEATH CENTRE
GRAND SUMMARY
ITEM DESCRIPTION Page No.
FOR TENDERER USE ONLY
FOR OFFICIAL USE ONLY
K.SHS. K.SHS.
A BUILDERS WORK SH/13
B ELECTRICAL INSTALLATIONS EW/2
C MECHANICAL INSTALLATIONS MW/5
D PRIME COST & PROVISIONAL SUMS PS/1 1,350,000.00
GRAND TOTAL CARRIED TO FORM OF TENDER
Amount in words: Kenya shillings …………………………………………………………………………………………………..
………………………………………………………………………………………..Cents ……………………………………………………
Tenderer’s Signature ………………………………………………………………………………………………………………….
Address …………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………….
Date …………………………………………………………………………………………………………………………………………..
Witness Signature ………………………………………………………………………………………………………………………………..
Address ………………………………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………………………………
Date ………………………………………………………………………………………………………………………………………………
21