PROJECT COST ESTIMATION
PROJECT MANAGER S
JOB
Manage it-- To the schedule- Within budget.
Identify and acquirenecessary resources.-People--Equipment-- Machineries etc, etc.
Estimate the costEstablish the budget
Plan the project
-
7/31/2019 Cost Project Estimation 2012-Lan4800
3/29
PROJECT MANAGER DILEMA
Cost is usually theboundary that cannot
be crossed
Unable to figure out
What it will take on
the cost before have
done it.
Able to determined the cost
By how much ( labour, material,
Etc. Plus how long ( schedule )
But often lack of accuracy.
continue
-
7/31/2019 Cost Project Estimation 2012-Lan4800
4/29
Project construction
1. Capital Cost 2 Operation Cost 3. Maintenance Cost
Land acquisition
Planning and feasilitiesstudies. - Operating staff
Architecture and engineering - Labour and material
design. for maintenance and repair.
Constuction + material + equipment - Insurance / tax .
+ labour. - Utilities.
Field supervision.
Insurance, bon , tax during construction. +
Client general office. ContigenciesEquipment and furnishing. Refer to the note Inspection and testing
-
7/31/2019 Cost Project Estimation 2012-Lan4800
5/29
Constructors /
contractors
Field manager
Designer
Suppliers
Craftmans
Sub Contractors
Owner / Client
CONSTRUCTION INDUSTRY
- Cost estimate involve the following entity s role
-
7/31/2019 Cost Project Estimation 2012-Lan4800
6/29
NOTE:
Allowance for contigencies / unexpected cost: -
1.Change in design development.
2. Adjustment of schedule.
3. Other requirements from government agencies / localAuthority.
PROJECT CONSTRUCTION
-
7/31/2019 Cost Project Estimation 2012-Lan4800
7/29
Understanding whats in the cost
1 . Elements of cost
- Direct Cost attribute to the project salaries
- materials.
- Payment to the sub contractor/
Consultants- Project related travel
- Indirect Cost Overhead Necessary business expenses General admin
cost.
- Facilities.
( utilities, insurance. )- Marketing.
Basic equation
Cost = Labour x Time
+ other direct cost + Indirect cost
-
7/31/2019 Cost Project Estimation 2012-Lan4800
8/29
COST ESTIMATION
Definition ...( Generic )
-The expected cost to perform a task or to acquire an item
-In another word ....
-An important output of project cost management is a
-cost estimate
COST ESTIMATOR
-- Collect and analyse data to estimate the time, money,
resources and labour.
NOTE:
Cost is a resources sacrificed or foregone to achieve a specific objective or
something given up for in exchange.
Costs are usually measured in monetary units eg ringgit, dollar
-
7/31/2019 Cost Project Estimation 2012-Lan4800
9/29
COST ESTIMATING
It is one of the most important steps in project management process.
It is one of the most fundamental component.
It represent a prediction by the estimator on the basis of available
data.
If not accurately measured, project riddle with budgetary constraint.
Effective estimating is a key to the success of a project.
Accuracy of the cost estimate reflect the information available at
the time of estimation.
Cost estimate made at the earlier stage of a project is expected
to be less accurate.
The accuracy of project estimation can have a dramatic impact
on profitability.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
10/29
COST ESTIMATION TOOLS AND TECHNIQUES
3 basic tools and techniques for cost estimates
1. Anologous or top down
- Use the actual cost of a previous, similar project as a basis for
the new estimate.
2. Definitive or Bottom up
- Estimate individual work items and sum them to get total
estimate . In other word based on complete detail of quantity,
specification and condition .
3. Parametric or top down estimate
- Use project characteristic in a mathematical model to estimate
cost.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
11/29
OTHERS......
Appropriation estimate
-Prepared from best available information to establish a budget
submitted for funding approval. ( i.e an appropriation )
Also known as budget estimate.
Rough Order of Magnitude estimate
-An approx estimate made without detail info
BEST PRACTICE TO MANAGE THEPROJECT AT SITE- COST
CONTROLBEST TECHNIQUES
FOR COSTESTIMATION
Project manager
-
7/31/2019 Cost Project Estimation 2012-Lan4800
12/29
CONSTRUCTION COST 6 FACTORS
Offer by tender is a general way used by government, local authority
and private sector to implement a construction project.
The construction cost for a project depend on several factors:
1.labour cost
2.material cost include transport + wastage
3. equipment and machineries cost.
4. Insurance.
5. Management cost
6.Profit
NOTE: Each project varies in their construction cost( scale and size, duration. Design etc )
-
7/31/2019 Cost Project Estimation 2012-Lan4800
13/29
ESTIMATING METHOD
The following are some of the rough estimating method thatcan be selected to anticipate a project cost before it being
constructed ( there is already design but contract
information has not been prepared ) :-
1. Cubic Content Method
2. Floor Area Method
3. Unit Valuation Method
4. Appropriate qualities method
5. Bill of Quantities Method
-
7/31/2019 Cost Project Estimation 2012-Lan4800
14/29
Factors that influence the method to be used : -
1. The time ( duration ) that is available to prepare
the estimate.
2. Accuracy that is required ( Nearest to the tender price )
3. Availability of information ( Design stage, drawings,
specification )
4. Estimator experience and skill.
5. Availability of data and cost of previous similar project.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
15/29
1. CUBIC CONTENT METHOD
1. Frequently used to calculate building cost.
2. Unit according to the building cubic meter ( m 3 )
3. The length and width of the building should be taken
from the external building surface.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
16/29
2. FLOOR AREA METHOD
1. Unit used base on the building internal floor area.
2. This method is widely used.
3. Easy to apply and there is a lot of construction data.
4. Easy to understand too, normally building construction is
referred to the floor area.
5. Reliable estimate as long as the building lan and height is
considered.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
17/29
3. UNIT EVALUATION METHOD
1. Used for early estimation.
2. Less accurate as compare to other method.
3. Can be used before the preparation of drawings and budget.
4. Comparison being made with building of the similar design,
function, characteristic etc.
5. This method provide limited application.
- for budget preparation
- To determine the project ceiling cost.
- To determine allocation for project.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
18/29
4. APPROPRIATE QUANTITIES METHOD
1. Good and almost accurate.
2. A few items will be group as one collective unit.
3. Work, material will be removed roughly from the
drawing for calculation purposes.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
19/29
5. BILL OF QUANTITIES METHOD
1The most accurate and good method.
2 Items being measured in details and each item are bill
according to the element or workmanship
4. The estimator is required to fill the price rate and its total.
5. The quantity of each element is gathered and multiply
with the price rate.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
20/29
PRICE BUILT RATE
The following section of the tender document that required
pricing :-
1. Preliminaries work - indirect cost that is taken into
consideration at the early stage. Eg insurance,
performance bond.
2. Measured works. BQ / Breakdown cost of each item.
3. Total prime cost and temporary allocation cost for special
work eg. electricity., air condition, lift carried out by
nominated sub contractor or named supplier.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
21/29
UNIT PRICE ( COST )
The price of the building / landscape material include pricing for
1. L abor.
2. Materials.
3. Usage of machineries and equipment.
4. Profit.
-
7/31/2019 Cost Project Estimation 2012-Lan4800
22/29
UNIT PRICE - LABOUR
Rate for execution of the job task is divided into :-
a ) skill labour / carpentry - RM 60 / Day
b ) Head of general labour monthly salary basis
c ) General labour daily wage of RM 30 / Day
Note : The labour rate is based on the time taken by
one labour to carry out the job task until completion.
( hr/m3 or hr /m2 )
Eg : Digging of drain not exceeding 1.5 m deep 1.5 hr /m3
To dispose the digging earth material to a distant of
less 50m - hr/m3
-
7/31/2019 Cost Project Estimation 2012-Lan4800
23/29
-
7/31/2019 Cost Project Estimation 2012-Lan4800
24/29
UNIT PRICE - USAGE OF MACHINARIES AND EQUIPMENTS
Divided into 2 types
1. Non Motorise or engine ( manual prunner, ladder, spade etc )
2. - Motorised or machinaries ( Lorries, bull dozer, excavator, crane )
- Motorised equipments ( prunner, chain saw etc )
Factors that should be taken into consideration
- Renting cost
- Deficiting cost
- Maintenance cost
- Usage of petrol and water for machinaries
-
7/31/2019 Cost Project Estimation 2012-Lan4800
25/29
UNIT PRICE PROFIT
-Rough profit consist of
-A ) Net cost
-B ) Overhead cost - staff / director salary- - office rental
- - furniture
- - electricity, water and telephone bill
- - transport allowance
- - Road tax- - supervisor, agent etc
-
7/31/2019 Cost Project Estimation 2012-Lan4800
26/29
BUILT PRICE FOR MACHINERIES / EQUIPMENTS
-Prior to the purchasing or rental of machineries, its good
to consider the following :-
1. Able to generate bigger profit or not.
2. Machineries / equipments to be rented / purchase is
able to be handled by labour or not
3. Does it can benefit on other project to be carried outlater.
Price analysis for machineries / equipments usage.
- Capital cost
- Overall cost consisting of original price and
maintenance cost
- Operating cost
-
7/31/2019 Cost Project Estimation 2012-Lan4800
27/29
Continue ...BUILT PRICE FOR MACHINERIES / EQUIPMENTS
Capital cost include
-Original price of the machineries / equipment.
-Machineries / equipment interest ( 5 % - 10 % )
-Life span of the machineries / plants.
-Repairing cost ( 1/10 of the original price )-Transportation cost ( 1 /20 of the original price )
-Operating cost include
-Warranty of the machineries / equipments
-Machineries loading capacity
-Using of the combustible material and others related
-Labour / workers wages
-
7/31/2019 Cost Project Estimation 2012-Lan4800
28/29
BUILT PRICE FOR DIGGING
-Digging method is divided into :
-a ) Manual ( spade, scoop, etc )
-b ) Machines ( excavator, back hole etc )
-Note : Digging work are measured in m3 / hr
-TYPES OF SOIL AND ADDITIONAL % OF COST TO
BE ADDED TO THE STANDARD RATE FOR DIGGING
-Sand 10 %
-Clay 20 %
-Natural earth 25 %-Rockery/stones / boulders 50 %
-
7/31/2019 Cost Project Estimation 2012-Lan4800
29/29
THANK YOU