Creating value from uncertaintywww.Broadleaf.com.au
Cost and schedule risk assessment
PMI Australia Conference 2014
Presented by Dr Stephen Grey
![Page 2: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/2.jpg)
PMI Australia conference 2014
2
ThemeA lot of quantitative risk assessment is unnecessarily cumbersome and soaks up effort without adding value to a project.
The approaches used often make it very hard to think clearly and realistically about a project.
![Page 3: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/3.jpg)
PMI Australia conference 2014
3
Modelling
Reality Belief
Model
Project
∑
![Page 4: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/4.jpg)
PMI Australia conference 2014
4
Describing a model
Assumptions
Sources of uncertaintyDependencies
Cost
![Page 5: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/5.jpg)
The requirement
PMI Australia conference 2014
5
![Page 6: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/6.jpg)
PMI Australia conference 2014
Requirement
Project ∑
Target
Risk of exceeding target
Inputs $Duration
![Page 7: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/7.jpg)
The candidates
PMI Australia conference 2014
7
![Page 8: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/8.jpg)
PMI Australia conference 2014
8
Three methodsRisk events• List risks• Probability and impact (range of variation)• Add them upLine items• Line items from estimate (summary)• Range of variation in line item• Add them upRisk factors• Cost or duration estimating relationships• Uncertainty in inputs to relationships (ranges)• Simulate the effect on the base case
![Page 9: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/9.jpg)
PMI Australia conference 2014
9
Similarities
Rela onships in the model ≡ Rela onship in reality?
Is the link between inputs and reality easily understood?
Almost any attention to project risk will be beneficial
Some are more cost‐effective than others
Model
![Page 10: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/10.jpg)
Risk event model
Risk Probability Impact P x IRisk 1 P1 I1 P1 x I1Risk 2 P2 I2 P2 x I2Risk 3 P3 I3 P3 x I3Risk 4 P4 I4 P4 x I4… … …
Risk n Pn In Pn x InTotal ΣPi x Ii
Mon
te Carlo simulation
PMI Australia conference 2014
10
![Page 11: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/11.jpg)
PMI Australia conference 2014
11
Modelling based on risk events
∑
Target
Risk of exceeding target
Risk Probability Impact P x IRisk 1 P1 I1 P1 x I1Risk 2 P2 I2 P2 x I2Risk 3 P3 I3 P3 x I3Risk 4 P4 I4 P4 x I4… … …
Risk n Pn In Pn x InTotal ΣPi x Ii
Mon
te Carlo sim
ulation
![Page 12: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/12.jpg)
Line item modelling
WBS Item Labour Materials Total Contingency
Annnn $ $ $ $
Bnnnn $ $ $ $
Cnnnn $ $ $ $
Dnnnn $ $ $ $
… … … … …
Znnnn $ $ $ $
Total Σ$ Σ$ Mon
te Carlo sim
ulation
PMI Australia conference 2014
12
![Page 13: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/13.jpg)
PMI Australia conference 2014
13
Line item modelling
∑
Target
Risk of exceeding target
WBS Item Labour Materials Total Contingency
Annnn $ $ $ $
Bnnnn $ $ $ $
Cnnnn $ $ $ $
Dnnnn $ $ $ $
… … … … …
Znnnn $ $ $ $
Total Σ$ Σ$ Mon
te Carlo sim
ulation
![Page 14: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/14.jpg)
Project estimate summaryLabour Facilities Super‐
visionMaterials Sub‐
contractsServices Expenses Total
Earthworks 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Concrete 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
… 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Overheads 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Project Total ? ? ? ? ? ? ? ?
Risk factors model
Uncertainty about quantities of concrete (m3)
Uncertainty about rates for cost of concrete ($/m3)
Cost estimating relationships (e.g. Cost = Quantity x Unit rate)
PMI Australia conference 2014
14
Simulated cost = Base estimate x (1 + ΔQuantity) x (1 + ΔRate)
![Page 15: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/15.jpg)
∑
∑
PMI Australia conference 2014
15
Risk factor modelling
Target
Risk of exceeding target
Project estimate summaryLabour Facilities Super‐
visionMaterials Sub‐
contractsServices Expenses Total
Earthworks 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Concrete 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
… 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Overheads 1234567 1234567 1234567 1234567 1234567 1234567 1234567 ?
Project Total ? ? ? ? ? ? ? ?
Uncertainty about quantities of concrete (m3)
Uncertainty about rates for cost of concrete ($/m3)
Simulated cost = Base estimate x (1 + ΔQuantity) x (1 + ΔRate)
∑
![Page 16: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/16.jpg)
Making it work
PMI Australia conference 2014
16
![Page 17: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/17.jpg)
PMI Australia conference 2014
17
Risk event
No effect
Probability = 33%
Probability = 67%
Likely=$4MMin =$2M Max=$8M
Variation in costif the event occurs
No effect
Probability = 33%
Probability = 67%
Likely=$4MMin =$2M Max=$8M
Variation in costif the event occurs
Project ∑Inputs Outputs
![Page 18: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/18.jpg)
PMI Australia conference 2014
18
Risk event model
Project ∑Inputs OutputsProject ∑Inputs Outputs
Project ∑Inputs OutputsProject ∑Inputs Outputs
Project ∑Inputs OutputsProject ∑Inputs Outputs
Project ∑Inputs OutputsProject ∑Inputs Outputs
Project ∑Inputs Outputs
Target
Risk of exceeding target
Common factors, overlaps and interactions
![Page 19: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/19.jpg)
PMI Australia conference 2014
19
Line item range
Inputs Outputs∑
Cost line item
![Page 20: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/20.jpg)
PMI Australia conference 2014
20
Line item model
Target
Risk of exceeding target
Common dependencies and correlations
![Page 21: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/21.jpg)
PMI Australia conference 2014
21
Risk factor model
Inputs Outputs∑
Cost drivers
Risk factors
Riskfactor
Target
Risk of exceeding target
![Page 22: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/22.jpg)
Risk factor example (partial)Small IT development project
Professional services $
Software scale
Team productivity
Professional services rates
Duration
Overhead rates ($/month)
Overhead $
Market rates for licenses
Number of users
Design decision
Option 1
Option 2
Installed license cost $Contingency assessment
methods & trends
22
![Page 23: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/23.jpg)
Electrical & instrumentation
Steel, mechanical & piping
Concrete
Earthworks
Risk factor example (partial)Mineral processing plant construction
Earthworks direct labour $
Earthworks quantity
Labour productivity
Labour rates
Lump sum valueDesign decision
Option 1
Option 2
Major equipment item cost $
Bulk material rates $/m3
Bulk material cost $
Contingency assessment methods & trends
23
![Page 24: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/24.jpg)
Assessing input parameters
PMI Australia conference 2014
24
![Page 25: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/25.jpg)
PMI Australia conference 2014
25
Describing a rangeCommon practice
Outcome1 23
1. Start in the middle and work out
2. Explain reason for choosing numbersAnchoring bias
Confirmation bias
![Page 26: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/26.jpg)
PMI Australia conference 2014
26
Describing a rangeGood practice
1. Establish context
• Assumptions
• Sources of uncertainty
• Pessimistic and optimistic scenarios
2. Start with the extremes and work in
Pre‐empt confirmation
Break anchoring
![Page 27: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/27.jpg)
PMI Australia conference 2014
27
Describing a rangeCommon practice
Outcome12 3
Assumptions
Sources of uncertainty
Scenarios
![Page 28: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/28.jpg)
PMI Australia conference 2014
28
SummaryModelling using risk factors is generally simpler and more realistic than using structures based on risk events or line item ranging
Context setting and methods to limit anchoring are required to get realistic assessments of uncertain values’ ranges
It need not be hard work!
![Page 29: Cost and schedule risk modelling - Range analysis](https://reader034.vdocuments.site/reader034/viewer/2022051314/557904add8b42a675b8b5271/html5/thumbnails/29.jpg)
PMI Australia conference 2014
29
ContactDr Stephen GreyAssociate [email protected]+61 412 223 256
If you would like further information about this topic please contact us.