Container Terminal No. 9
![Page 2: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/2.jpg)
Container Terminal 9 - Some fast fact:
1. Site area: total 150 hectares, including 120 hectares reclaimed land
2. Other associated works: re-alignment of the approach fairway, access road, paved areas for container handling, surface drainage and storm water culvert systems
3. Reclamation method: dredging of alluvial clay, land formed mainly by sand-filling by conveyor or pump boat.
4. Source of filling materials: from marine borrow area in the west of Hong Kong.
5. Dumping location: south of Tsing Yi and Cheung Chau.
6. Compaction method:, majority by Surcharge (max 9m up to 6 months), vibro-vibration, installation of band drains and surface compaction
![Page 3: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/3.jpg)
Container Terminal 9 - Some fast fact (continue):
5. Provide 6 parking berths along 1,940m waterfront with water depth averaged 15.5m
6. Forming of the berth deck: deck frame constructed on pile top, precast plank placed on top of the deck frame (with 200mm RC topping) that formed the berth deck. The decks are sub-divided into 60m x 30m bay for easy control of construction.
7. Foundation: raking piles and vertical piles driven by driving rack mounted on barge boat
8. Other data:- Consultant – Maunsell Consultant Asia Ltd.
- Contractor – Hyundai/CCECC JV
- Contract sum – about $3.95 billion
![Page 4: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/4.jpg)
Current Layout of the Container Terminals (CT 1 to 9) in Kwai Chung Basin
![Page 5: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/5.jpg)
Overview of the Container Terminals (CT 1 to 9) in Kwai Chung
![Page 6: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/6.jpg)
Trailing Suction Hopper Dredger for doing the dredging works
![Page 7: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/7.jpg)
Layout of Container Terminal 9 and its associated supporting facilities
![Page 8: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/8.jpg)
Typical Section for Vertical Seawall and Quay Deck Structure
![Page 9: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/9.jpg)
Doing the marine piling as foundation for the quay deck
![Page 10: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/10.jpg)
Marine piling as foundation for the
quay deck
![Page 11: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/11.jpg)
Ship equipped with pumping devices for
sand filling
![Page 12: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/12.jpg)
Temporary drain pipe to discharge seawater
after the sand filling
![Page 13: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/13.jpg)
Initial completion of the land formed by sand
filling and the commencement of other
associated civil works
![Page 14: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/14.jpg)
Overview of the CT 9 site with the marine piles for the quay deck in position
![Page 15: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/15.jpg)
Filling work bounded by the seawall
![Page 16: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/16.jpg)
Dredging before the forming of the base for
the vertical seawall
![Page 17: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/17.jpg)
Filling work in progress
![Page 18: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/18.jpg)
South portal of Route 8 Nam Wan Tunnel
The southern portion of the Terminal where the interchange
to the future Route 8 located
![Page 19: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/19.jpg)
Detail showing the formation of the vertical seawall
![Page 20: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/20.jpg)
Compaction to the newly formed land by vibration
plate and vibro-compaction method
![Page 21: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/21.jpg)
Forming the box-culvert using cut-and-cover
method
![Page 22: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/22.jpg)
Forming the box-culvert using cut-and-cover method
![Page 23: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/23.jpg)
Other storm water discharge and drainage
work in the newly reclaimed land
![Page 24: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/24.jpg)
Other storm water discharge and drainage
work in the newly reclaimed land
![Page 25: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/25.jpg)
Marine piling work
![Page 26: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/26.jpg)
Completion of the marine piles pending for the erection of a temporary work
platform for the forming of the quay deck
![Page 27: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/27.jpg)
Newly formed land approaching the vertical seawall
![Page 28: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/28.jpg)
Detail showing the abutment between the
quay deck and the vertical seawall
![Page 29: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/29.jpg)
Erection of a temporary work platform to facilitate the
forming of the quay deck
![Page 30: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/30.jpg)
Erection of a temporary work platform to facilitate the
forming of the quay deck
![Page 31: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/31.jpg)
Work activities as seen on the temporary work
platform
![Page 32: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/32.jpg)
![Page 33: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/33.jpg)
![Page 34: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/34.jpg)
Erection of formwork for the forming of the framing
beams for the quay deck
![Page 35: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/35.jpg)
Formwork detail of the framing beams for the
quay deck
![Page 36: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/36.jpg)
The framing beam for quay deck as seen after the removal of the formwork
![Page 37: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/37.jpg)
Loading of surcharging material as a means of compaction
![Page 38: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/38.jpg)
Forming the quay deck by precast plank and
RC topping
![Page 39: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/39.jpg)
Forming the quay deck by precast plank and
RC topping
![Page 40: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/40.jpg)
Detail of quay deck with the steel reinforcing bar in place before concreting
![Page 41: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/41.jpg)
Completion of the phase 1 reclamation work with the first 3 berths of terminal handed over for operation
![Page 42: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/42.jpg)
Finishing and touching up of the facility before the handing over
![Page 43: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/43.jpg)
Precast channel for surface water discharge
![Page 44: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/44.jpg)
Precast channel for surface water discharge
![Page 45: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/45.jpg)
Paving works
![Page 46: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/46.jpg)
Final fitting out and phase hand-over of berth
![Page 47: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/47.jpg)
Final fitting out and setting up of other supporting facilities
![Page 48: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/48.jpg)
Final fitting out and setting up of other supporting facilities
![Page 49: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/49.jpg)
The terminal facilities under partial operation as seen in mid 2004
![Page 50: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/50.jpg)
The terminal facilities under operation as seen in late 2004
![Page 51: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/51.jpg)
Overview of the Container Terminal 9 as seen from the hill side. The unoccupied land in the foreground is reserved for use as the interchanging concourse for the future Route 8 scheduled for handing over in late 2007.
![Page 52: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/52.jpg)
Terminal facilities including the cargo handling yard under operation as seen in 2007
![Page 53: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/53.jpg)
Terminal facilities including the cargo handling yard under operation as seen in 2008
![Page 54: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/54.jpg)
Container Terminal 9 as viewed from the Stonecutter Island side
![Page 55: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/55.jpg)
Container Terminal No. 1 to 5 as seen from the Tsing Yi side
![Page 56: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/56.jpg)
Container Terminal No 7 and 8 completed for operation in late 1990s (photo taken in mid 2007)
![Page 57: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/57.jpg)
Container Terminal No 8 as seen in mid 2007 with the approach bridge heading toward Stonecutters Bridge in place
![Page 58: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/58.jpg)
Container Terminal No 9 as seen from the deck of Stonecutters Bridge
New Nam Wan Tunnel
![Page 59: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/59.jpg)
Stonecutters Bridge of Route 8 passing through Container Terminal 9 with interchanging slip road for vehicular users
![Page 60: Container Terminal No. 9 - City University of Hong Kongpersonal.cityu.edu.hk/.../container_terminal_9.pdf · Container Terminal 9 - Some fast fact (continue): 5. Provide 6 parking](https://reader036.vdocuments.site/reader036/viewer/2022081522/5f1038337e708231d448080a/html5/thumbnails/60.jpg)
End of Presentation for
Container Terminal 9