Concerto
Ethelred tower blocks - low carbon refurbishment Challenges and successes
Jon Lissimore Environment Manager
![Page 2: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/2.jpg)
Council policy - promote sustainable design and construction
Design for energy efficiency -reducing C02 & fuel poverty
Promote use of environmentally friendly materials -reducing pollution and environmental damage
Require sustainable accredited timber -avoids deforestation / loss of biodiversity, etc
![Page 3: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/3.jpg)
Ethelred tower blocks• Ward, Brittany and
Elkington • Required major
improvements• Decent homes work
needed
![Page 4: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/4.jpg)
Ethelred’s problems
• Spalling concrete• Ineffective heating and ventilation • Generic heating and hot water
charge for residents but high energy costs for Lambeth as landlord
• Socio-economic study May 2009:– 53% of respondents suffered
condensation– 38% could not keep their homes
comfortably warm due to draughty windows.
![Page 5: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/5.jpg)
Funding
• Lambeth had prior experience of carbon reduction projects
• Positive track record on sustainability helped us secure additional funding– Government Office London £6.8m
![Page 6: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/6.jpg)
Sustainable design and construction
Holles house refurbishment- proven 50% energy use reduction via a range of sustainability measures
![Page 7: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/7.jpg)
Sustainable legal timber
Fairfax House – the first construction project in Britain to be independently certified by the Forest Stewardship Council for its use of sustainable timber.
![Page 8: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/8.jpg)
Boatemah Walk
![Page 9: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/9.jpg)
Before…
![Page 10: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/10.jpg)
After!
![Page 11: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/11.jpg)
![Page 12: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/12.jpg)
![Page 13: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/13.jpg)
Ethelred tower block refurbishment
• New double glazed windows• Insulated external cladding• 63KWp Solar PV• New Communal boilers• CHP plant (310KWe)• New wet radiators with room
thermostats and heating
programmers
![Page 14: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/14.jpg)
Green roofsSedum roofs • Promoting Biodiversity• Reducing storm water run- off• Improving air quality• Insulation / cooling benefits
![Page 15: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/15.jpg)
Challenges
• PV system output
• Cladding - delays
![Page 16: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/16.jpg)
Challenges
Working with residents in occupation
![Page 17: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/17.jpg)
Successes
• Significantly improved conditions for residents
• 80% CO2 reduction in landlords footprint
• Reduced energy costs for residents and Lambeth• Blocks renewed to give a minimum 30 years of further life
![Page 18: Concerto Ethelred tower blocks - low carbon refurbishment Challenges and successes Jon Lissimore Environment Manager](https://reader030.vdocuments.site/reader030/viewer/2022032606/56649eac5503460f94bb1d29/html5/thumbnails/18.jpg)
The new look towers