CON 2001
Construction MethodsTool #1 - Construction SchedulingPresented by Elia Twigg, P.E.(Prof. Ralph V. Locurcio, P.E.)
![Page 2: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/2.jpg)
CVE 4070
Construction EngineeringTool #1 - Construction SchedulingPresented by Elia Twigg, P.E.(Prof. Ralph V. Locurcio, P.E.)
![Page 3: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/3.jpg)
A little about me…
![Page 4: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/4.jpg)
Scheduling Basics
What is scheduling? Tool to plan, monitor and record
progress
What are the benefits of scheduling? Forces pre-planning of project Graphical representation of project Helps manage resources
![Page 5: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/5.jpg)
Scheduling…
Common methods: Bar/Gantt Charts Network Diagrams:
o CPM – Critical Path Methodo PERT – Program Evaluation & Review
Technique Velocity Chart or S-Curve Line-of-Balance Charts
![Page 6: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/6.jpg)
Simple Bar Chart
1. Simple and easy to read2. Does not show interdependencies or critical path
![Page 7: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/7.jpg)
Gantt Chart
1. Simple and easy to read2. Shows interdependencies 3. Can show critical path in a different view within MS Projects
![Page 8: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/8.jpg)
CPM/PERT Chart
![Page 9: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/9.jpg)
Velocity Chart or S-curve
1. Good for showing progress
2. Does not show task relationships or critical path
Excav Found Slab Struct Walls Roof Partitions Ceilings Paint CleanSchedule 100 225 275 575 975 1275 1725 1850 1950 2000Cum Hrs 88 218 268 568 768 993 1493 1493 1493 1493Plan Hrs 100 125 50 300 400 300 450 125 100 50Act Hrs 88 130 50 300 200 225 500
Simple Velocity Chart
0
500
1000
1500
2000
2500
Excav
Found
Slab
Struct
Wall
sRoo
f
Partiti
ons
Ceilin
gsPain
t
Clean
Schedule
Cum Hours
Plan Hours
Act Hours
![Page 10: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/10.jpg)
Line-of-Balance Chart
1. Used for production line activities
2. Shows inter-dependencies
3. Does not show critical path
AA
CC
BB
AA Between house numbers
BB Activity time
CC Lag time between activities
![Page 11: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/11.jpg)
Scheduling Programs…
Microsoft Project Easy to use Multi-format
o Network Diagram – shows CPMo Gantt Chartso Resource tracking
Excellent for small projects Relatively inexpensive Several other products on market
![Page 12: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/12.jpg)
Primavera Used for large projects More flexible than MS Projects Includes resource & budget Includes database for tracking submittals Requires more capable computers Generally requires trained operator
Scheduling Programs…
![Page 13: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/13.jpg)
Scheduling…
Tasks are not all consecutive Think of the WBS (major tasks and sub-tasks) Example – Road work and Drainage work
Project Managers need to: Identify tasks & timing Identify task interdependencies Identify critical path Identify slack/float and lag times Chart progress & payment
![Page 14: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/14.jpg)
Tasks & Timing… Any single, identifiable & measurable work step
in the total project WBS
A “time consuming” task
Two conventions: Activity on Arrow… AOA networks
Precedence diagrams (MS Projects)
![Page 15: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/15.jpg)
Activity on Arrow…
3 5 7
2 4
1
Activity Name Duration 1-3 Sign Contract 3 1-2 Obtain Permits 5 3-5 Excavation 7 5-7 Form Foundation 10 2-3 Survey Utilities 2 2-4 Layout Foundation 3 4-5 Deliver Forms 1 7-8 Pour Foundation 1
Sign Contract
Obtain Permits
Excavation Form FoundationSu
rvey
Util
ities
Layout Foundation
Del
iver
For
ms
3 7 10
5 2 1 1
38
Pour
Foundation
![Page 16: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/16.jpg)
Precedence diagram…
Activity Duration Float
Sign Contract 0
Obtain Permits 5 0
Survey Utilities 2 0
Excavation 7 2
Layout Foundation 3 0
Deliver Forms 1 2
Form Foundation 10 3
Pour Foundation 1 0
Signcontract
Obtainpermits
ExcavationForm
Foundation
Survey Utilities
Deliver Forms
Layout Foundation
Pour Foundation
![Page 17: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/17.jpg)
Task Interdependencies…
Finish-to-start (FS): Succeeding activity (Activity B) may not begin UNTIL the
preceding activity (Activity A) is completed Most common or conventional relationship Example…
You cannot begin constructing walls on a house until the foundation has been constructed.
Finish-to-start
Activity A
Activity B
![Page 18: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/18.jpg)
Task Interdependencies…
Start-to-start (SS): Successor (Activity B) cannot start UNTIL predecessor (Activity
A) begins Very common and useful, often includes a lag time Examples…
As soon as “Clearing & Grubbing” starts, the “Excavation” can start Voting for the President - As soon as votes start coming in, they can begin
Activity B, which is to tally the results.
Start-to-start
Activity A
Activity B
![Page 19: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/19.jpg)
Task Interdependencies…
Finish-to-finish (FF): The activity must finish at the same time as a preceding activity Infrequently used Example…
Cooking a meal – All items you cook may have different durations, however, if you want all items to be done at one time, this would represent a finish-to-finish example.
Activity A
Activity B
Finish-to-finish
![Page 20: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/20.jpg)
Task Interdependencies…
Start-to-finish: The activity may not finish until the predecessor starts Infrequently used, not really practical to schedule Example…
You have an exam scheduled for 11am. You determine you will cram for exam 3 hours before. You arrive in class and instructor showed up a bit late, you continue to cram until the test paper hit your desk. What determined the finish of your study time? The professor stating all study material must be put away.
Start-to-finish
Activity A
Activity B
![Page 21: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/21.jpg)
Critical Path Critical Path
Longest path through network Determines the duration of project Shortest amount of time necessary to complete the
project
![Page 22: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/22.jpg)
Slack/Float & Lead/Lag Times… Slack or Float - Measured within activities The difference between the latest allowable date and earliest
expected date for any given task
Lead or Lag Times - Measured between activities
Finish-to-start w/lag
Activity A
Activity B
Start-to-start w/lag
Activity A
Activity B
Finish-to-finish w/lag
Activity A
Activity B
Start-to-finish w/lag
Activity A
Activity B
![Page 23: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/23.jpg)
Slack/Float & Lead/Lag Times…
Slack or Float - Measured within activities
Lead or Lag Times - Measured between activities
![Page 24: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/24.jpg)
Bus Shelter Example
![Page 25: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/25.jpg)
Scheduling Process Steps…
1. Identify key work elements (WBS)
2. Establish logical order of tasks
3. Estimate time durations for each
4. Determine precedence/dependency
5. Display in graphical/network format
6. Enter lead or lag time
7. Check network timeline
8. Add percent complete for project status
9. Convert to PERT chart
10. Explore other variations… tutorial included with software.
![Page 26: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/26.jpg)
Identify Key Work Elements
![Page 27: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/27.jpg)
Identify work elements… Responsibility: prime vs. subs… Crew or craft: carpenters, plumbers, electrical… Use of equipment: dozer, dumps… Materials: concrete, steel, masonry… Subdivision of work: foundation, walls… Location of work: site A, site B… Breakdown in specs or for payment; i.e. CSI format Contractor’s bid & payment elements Other factors: like outage schedules, utilities
Really depends on the contract, the controls being used, and the owner’s requirements
![Page 28: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/28.jpg)
Estimate time durations for each
Establish logical order of tasks
![Page 29: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/29.jpg)
Determine precedence/dependency
![Page 30: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/30.jpg)
DoubleClick
Another way to determine precedence/dependency
Lag Time
![Page 31: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/31.jpg)
![Page 32: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/32.jpg)
100% Complete
DoubleClick
60% Complete
![Page 33: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/33.jpg)
Select Network Diagram
Red indicates the Critical Path
![Page 34: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/34.jpg)
Homework #3
Using MS Project Create a Gantt chart Follow all instruction on Assignment Bring to class for review & correction Due:
![Page 35: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/35.jpg)
Loading MS Project
![Page 36: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/36.jpg)
Test #1 - Review
![Page 37: CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)](https://reader033.vdocuments.site/reader033/viewer/2022050909/5697c0211a28abf838cd2c73/html5/thumbnails/37.jpg)
That’s all for today…BUT