Download - Commissioning Plan for APS-U
Commissioning Plan for APS-U
Louis EmerySenior PhysicistArgonne National Laboratory
Beam Tests and Commissioning of Low Emittance Storage RingsKarlsruhe Institute of TechnologyFebruary 18th, 2019
APS-U Commissioniing Plan, Feb 18th, 20192
Outline
Some lattice features first
Some principles adopted
Schedule of dark time
Requirements before commissioning beam time
Beam time activities
APS-U Commissioniing Plan, Feb 18th, 20193
Hybrid 7BA Lattice Concept1 Plus Weak Reverse Bends2
Longitudinal gradient dipoles
Transversegradient dipoles
Dispersion bumpw/sextupoles (blue)
Dispersion bumpw/sextupoles (blue)
Phase advance of Δφx=3π and Δφ
y=π between corresponding sextupoles chosen to cancel geometrical sextupole kicks
Reverse bends (displaced quadrupoles) allowed the reduction of the emittance from 67 nm to 42 nm
1: L. Farvacque et al., IPAC13, 79.2: J. Delahay et al., PAC89, 1161, A. Streun, NIM A 747, 148
QuadrupolesReverse-bend gradient dipoles
APS-U Commissioniing Plan, Feb 18th, 20194
Injector Requirement
Need to extract from booster at negative off-momentumerror, say -0.6% or more
Need to inject into booster with zero momentumerror
Booster to SR synchronization
Booster frequency will vary during energy ramp according to adjustable ramp program in order to: 1) meet circumference requirement at each end of cycle2) vary path length to target one of 1296 rf buckets in the ring
APS-U Commissioniing Plan, Feb 18th, 20195
On-axis “swap-out” injection1,2,3 is an alternative to accumulation– Each injector shot replaces an existing stored bunch – brightness dips for one bunch for about two damping times
– DA only needs to accommodate the injected beam size
Pre-kicker for inflating the target stored bunch 50 turns before extraction
Swap-out Injection, Vertical plane
1: E. Rowe et al., Part. Accel. 4, 211 (1973).2: R. Abela et al., PAC91, 486 (1992).3: L. Emery et al., PAC03, 256 (2003).
IK1 IK2 IK3EK1 EK2 EK3
Pre-kicker
APS-U Commissioniing Plan, Feb 18th, 20196
Collimators and beam dumps
Vertical beam dumpin sectors 39 and 1For swap out.Also for bunch by bunch “slow”beam aborts with pre-kicker
Horizontal collimators for Touschek scatteringin sectors 36, 37, 38, 39 and 1Whole beam aborts (4400 J), which damages surface,requires refreshment
APS-U Commissioniing Plan, Feb 18th, 20197
Some principles followed
Achieve more than the “Key Performance Parameters” promised to funding agency (DOE), but plan to do a little more in the 3 months of commissioning
Full 200 mA not expected at end of three months. 50-100 mA?– don’t need fully operational LFB or Higher-harmonic Cavity (HHC)
Accelerator interlock system (ACIS) to be the last thing to install before beam (for convenience of entering the tunnels for PS testing, etc)
Presently thinking of installing and keeping IDs in the ring for the initial beam tests, as risk for damage is thought to be low
Diagnostics to be made ready as much as possible before introducing beam
In detailed plan, allot time for commissioning diagnostics along with beam or beam optics.
Allot time for feature beamlines to use synchrotron light near end of commissioning period
Invite some external machine physicists for commissioning
Select fixed one/two days of the week for tunnel intervention, if necessary. (say Monday/Thursday)
Once ACIS is implemented, control room operators (technician), two on shift, possibly a third one
APS-U Commissioniing Plan, Feb 18th, 20198
Schedule of Dark Time Tentative Start on June 2022 (just to have some reference)
9 weeks of equipment removal, slowly transitioning to ...
6 months of installation
3 month of injector beam time and storage ring beam time (start, say, March 2023)
Transition to operations June 2023 (say)– No intervening shut-down for a good start of operations!
APS-U Commissioniing Plan, Feb 18th, 20199
Equipment requirements before beam time
Goal is to make beam time efficient, i.e. no partial installations
Essential hardware were identified for preparation
Complete vacuum system installed and vacuum < 10 nT N2 equiv.. Includes HHC and LBF kicker cavities.
All magnets in SR and new parts of BTS, measurements available in control system
Main rf system and cavities (12) ready to support 30 kW/cav
Injection kickers (striplines) and DC septum
Booster to SR synchronization system operational (timing determined with beam later)
Diagnostics: – all bpms to report single pass and turn-by-turn for 1 nC.
– Beam current monitors
– Tune measurement system
– H and V diagnostics kickers
– BTS emittance diagnostics
Control system for above plus vacuum water, tunnel temperature, etc.
Alarm handlers
High-level applications (to be reviewed, re-written or created)
APS-U Commissioniing Plan, Feb 18th, 201910
Equipment requirements before beam time (cont’d)
Some way of doing slow orbit feedback using rf bpms
Tunnel air regulation 2 deg F
VC water cooling operational
IDs installed and aligned and gaps open. Gaps control after one month of commissioning
SC undulators installed and cooled down
Data loggers for EPICS PVs are running
Beam swap-out and abort systems operational
Beam dumps are installed in correct positions
MPS and ACIS are validated without beam to the extent possible, and ready to be validated with beam
Synchrotron light monitor is ready to show a beam image
APS-U Commissioniing Plan, Feb 18th, 201911
Equipment requirements for a higher current, say 10 mA
Orbit feedback ready to operate at some reasonably high bandwidth (say 100 Hz) using the rf bpms
Decoherence kicker and swap-out system fully validated
Beam-position limits detectors fully validated
RF system is conditioned and is ready to support high beam current ramp.
Beam size monitor is ready to resolve 0.4 pm Y emittance
Beam size monitor is ready to confirm 42 pm X emittance
RF cavity temperature control is ready for current ramp up
X-ray BPMs are operational
Hydrostatic leveling system is operational
Bunch lengthening cavity is ready to support ramp up to full beam current
Transverse and longitudinal bunch-by-bunch feedback is ready for commissioning with beam
APS-U Commissioniing Plan, Feb 18th, 201912
Beam time activities; tasks in rough time sequence
Booster-SR synchronization, Part A (i.e. recommission injector system (booster on momentum)
Commission new BTS line, Part A (trajectory)
Booster-SR synchronization, Part B (booster off-momentum)
Final rf frequency ramp of booster interleaved with SR first few days activities
First turn (plus rf bpm check-out), multiple turn trajectory, stored beam, one bunch (Sajaev, tomorrow)
Characterize lattice, Part A (including rf bpm offset)
Swap out single bunch
Vertical and Horizontal Collimators
Commission new BTS line, Part B (optics) – note that booster emittance Is large
Booster-SR synchronization, Part C (booster on frequency ramp)
Stored beam in many bunches (>10 mA from here on)
Test some undulator beams (shutters closed) – setup FF corrections
Fast orbit feedback
Photon diagnostics
Emittance-ratio (coupling) control
Various bunch patterns
HHC cavity check-out for some voltage generation
Condition vacuum with stored beam (target 10 A h)
Characterize lattice, Part B (same as Part A but with higher current)
TFB operational
LFB operational single rf
Undulator beams with users (feature beamlines)
HHC operational for some bunch pattern and current (optional)