Clean TeQ Sunrise
CCC Meeting – 29 August 2019
Clean TeQ Sunrise
Project Update
Community Engagement Update
Environmental Management Update
CCC Member Questions
Summary
CCC Meeting Presentation – 29 August 2019 Page 2
Project Update
Page 3
Clean TeQ Sunrise
Project Update
CCC Meeting Presentation – 29 August 2019 Page 4
• Clean TeQ Sunrise front end engineering
and design progressing steadily,
approximately 43% complete
• Fluor appointed Project Management
Contractor for Sunrise Project
• Vegetation screens planted early August
on ML1770 and Fifield Bypass
– Establishment works ongoing (e.g.
watering)
Vegetation
Screens
Community Engagement Update
Page 5
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 29 August 2019 Page 6
• Building relationships across the community
– Christmas in July dinner at the Fifield Hotel
– Provided project update to Forbes Rotary and Condobolin
Probus
– Representation at associated Rural Fire Service AGM
meetings
• Actively participating in our community
– Supported the Condobolin Women’s Wellness Expo, providing
local coffee cart for the event
– Parkes coffee cart held to celebrate the office move-in.
Catering provided by Parkes Public School P&C.
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 29 August 2019 Page 7
• Actively participating in our community
– Joined in the fun of celebrating the 50th anniversary of the Apollo
moon landing with an interactive window display – #WINNING
display
– Showtime! Have attended and sponsored Tullamore, Trundle,
Condobolin and Parkes shows and will attend Forbes
– Look forward to attending the Trundle Bush Tucker, next Saturday
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 29 August 2019 Page 8
• Education and Investment
– Launched the Little Bang Science Club at Forbes Learning Ladder.
The program aims to inspire 3 to 5 year olds to start thinking
scientifically. Science kit purchased using the Matched funding
program
– Provided matched funding to the St Josephs Primary School Trivia
night – fundraising event with funds being directed towards a new
Covered Outdoor Learning Area (COLA)
– Supporting the Condobolin Primary School 2019 Schools Spectacular
participants through the Aim High program
Clean TeQ Sunrise
Keeping people informed
CCC Meeting Presentation – 29 August 2019 Page 9
• Community newsletter
– Published in July, next edition late September
– Distributed through newspapers, mailbox and e-delivery
– Lisa Andrews profiled in the July edition. We would like to
profile members alphabetically.
• Updated fact sheets
– About us, air quality, road transport, noise management
• Facebook – posts reached over 9,000 impressions attracting
more than 1,700 engagements
• Website
– Complaints register published, zero complaints received
YTD
• Shop fronts
– Continue to operate in Condobolin & Trundle
Environmental Management Update
Page 10
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities” and will be revised
for re-approval before commencement of any works after this stage
• All EMPs submitted to the DPIE for review
• The following EMPs (incorporating Modification 4) have been approved
by the DPIE:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– Noise Management Plan
– Heritage Management Plan
– Rehabilitation Management Plan
– Biodiversity Management Plan and Revegetation Strategy
– Traffic Management Plan
Environmental Management Plans
CCC Meeting Presentation – 29 August 2019 Page 11
Clean TeQ Sunrise
Environmental Monitoring – Air Quality Monitoring
CCC Meeting Presentation – 29 August 2019 Page 12
• Construction phase air quality
monitoring – particulate matter (PM2.5
and PM10) and dust deposition
• Dust deposition gauges
– operating
• Real time particulate matter monitors
– EPA approved - Teledyne API T640x
– To be installed Q4 2019
• Meteorological monitoring station
– operating
Clean TeQ Sunrise
• Construction phase noise monitoring
– quarterly attended monitoring
consistent with Environment Protection
Licence and Noise Management Plan
• Attended monitoring
– conducted in June 2019; results
demonstrated no exceedances
– next round September 2019
Environmental Monitoring – Noise Monitoring
CCC Meeting Presentation – 29 August 2019 Page 13
Clean TeQ Sunrise
• Groundwater monitoring
– undertaken during July
– standing water levels from all bores
– water quality from minesite bores
Environmental Monitoring – Groundwater Monitoring
CCC Meeting Presentation – 29 August 2019 Page 14
CCC Member Questions
Page 15
Clean TeQ Sunrise
1. Has the pipeline agreement been finalised?
2. How much vegetation (i.e. Trees and native bush) will be removed on the length of the pipeline and do
they have to have offsets?
3. Given the water situation in Fifield where the Lachlan Council has been carting water to the village for
several months to date will Clean TeQ give an undertaking to negotiate an acceptable agreement with
Lachlan and Forbes Councils to make water available to the villages of Fifield and Ootha when the
pipeline is completed?
CCC Member Questions
CCC Meeting Presentation – 29 August 2019 Page 16
Clean TeQ Sunrise CCC Meeting Presentation – 29 August 2019