BUILDING SERVICES TWO (BLD60503)
ELECTRICAL INSTALLATION
Prepared by Tan Hee Chai
![Page 2: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/2.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Sources of Electricity
![Page 3: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/3.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 4: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/4.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 5: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/5.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 6: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/6.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 7: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/7.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 8: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/8.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 9: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/9.jpg)
BUILDING | SERVICES | TWO (BLD60503)
3 major classifications for power production in reasonably large scale are :-
1) Thermal power generation 2) Nuclear power generation. 3) Hydro-electric power generation.
![Page 10: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/10.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 11: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/11.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 12: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/12.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 13: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/13.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 14: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/14.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical supply and distribution
•Fuel converted to steam at high temperature and pressure, to drive turbines which generate electricity at 25kV alternating current.•AC changes polarity from positive to negative at 50 cycles per second (50 hertz)
![Page 15: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/15.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical supply and distribution
![Page 16: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/16.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical supply and distribution
Reasons power is supplied in Alternating Current (AC) at 50 Hertz:
•Facility of generating machines•Ease of transformation•Use of electricity powered AC motors
![Page 17: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/17.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical supply and distribution132, 275 or 400 kV: National transmission
33 000 V: Large/Heavy industries, cities, towns and railways
11 000 V: Light Industries, hospitals, towns and villages
400 V: Small industries, offices, farms etc
230 V: Housing, schools, small commercial premises.
![Page 18: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/18.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical supply and distribution
• All but 230 V is supplied with 3 phases: domestic appliances and standard office equipment are designed to operate from only one phase.
• 33 000 V, three phase supply to railway operators via sub-station where it is transformed to 25 000 V DC
![Page 19: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/19.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution-Three phase and single phase supply
![Page 20: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/20.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution-Three phase & single phase
Generators at power station are wound with three conductors.•Each generate one phase•Three phases into 3 wires
Called ‘three phase three wire’ supply
![Page 21: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/21.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution-Three phase form
At secondary side of transformer at sub-station:•Any pair of three wire is 415 volts•Any of three conductors is 240 volts
Called ‘three phase four wire; supply
![Page 22: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/22.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution
Service cable supply to external meter cupboard
![Page 23: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/23.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution
Incoming cable
![Page 24: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/24.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution Overhead cable
![Page 25: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/25.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Local distribution -TT System
![Page 26: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/26.jpg)
BUILDING | SERVICES | TWO (BLD60503)
TT System• Supplied overhead without earth terminal• Consumer to provide earth electrode.• Residual current circuit breaker (or trip switch) provided
between meter & consumer unit.• RCCB operate on imbalance between the phase or live
conductor and the neutral.• A fault will energise the core coil to effect the
electromagnetic trip.
![Page 27: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/27.jpg)
BUILDING | SERVICES | TWO (BLD60503)
TN-S System
![Page 28: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/28.jpg)
BUILDING | SERVICES | TWO (BLD60503)
TN-S System• Applied to underground supplies • Metal sheathed and/or armoured cable.• Consumer’s terminal connected to metal sheath
![Page 29: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/29.jpg)
BUILDING | SERVICES | TWO (BLD60503)
TN-C System• Earth and neutral
conductors combine to provide a protective earth and neutral (PEN) or Protective multi earthing(PME)
![Page 30: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/30.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Consumer unit
![Page 31: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/31.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical Meter
• One rate (tariff) – domestic consumers
• Off peak & on peak meters
![Page 32: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/32.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Electrical Meter•Two coils: current coil connect to phase and & voltage coil across phase & neutral•Interaction of two energises a dics which rotates at speeds proportional to power consumed•Gears driven disc effect a digital display of energy consumed in KWh
![Page 33: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/33.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Overload Protection
• Need to prevent current leaks from electrical installation due to insulation failure in the electrical circuit.
• Earth Leakage circuit breaker detects earth leakage current and makes the power supply off by opening the associated circuit breaker.
![Page 34: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/34.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Overload Protection
This can be provided by:
1. Semi-enclosed rewirable fuses2. Cartridge fuses3. Miniature circuit breakers (MCB)
![Page 35: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/35.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Overload protection
![Page 36: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/36.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Overload protection
![Page 37: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/37.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 38: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/38.jpg)
BUILDING | SERVICES | TWO (BLD60503)
![Page 39: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/39.jpg)
BUILDING | SERVICES | TWO (BLD60503)
1. Semi-enclosed rewirable fuses
• Advantages • Low capital cost• Cheap to replace element• Simple in concept• No moving parts
![Page 40: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/40.jpg)
BUILDING | SERVICES | TWO (BLD60503)
Disadvantages
•Prone to abuse. Incorrect wire can be used•Deterioration with age•Reliability can vary, with temperature & fixing method.•Cannot be tested•Cannot be replaced quickly•Fusing factor higher than current rating
![Page 41: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/41.jpg)
BUILDING | SERVICES | TWO (BLD60503)
2. Cartridge fuses
Advantages•Small and compact•No moving parts•Accurate and consistent to declared rating•Will not deteriorate in protective tube
![Page 42: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/42.jpg)
BUILDING | SERVICES | TWO (BLD60503)
2. Cartridge fuses
Disadvantages•Cannot be repaired or reset, must be replaced•Prone to abuse (with metal foil)•Much more expensive than fuse wire
![Page 43: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/43.jpg)
BUILDING | SERVICES | TWO (BLD60503)
3. Miniature Circuit breaker
Advantages•No moving parts•Accurate and consistent to declared rating•Durable•Can be reset
![Page 44: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/44.jpg)
BUILDING | SERVICES | TWO (BLD60503)
3. Miniature Circuit Breaker
Disadvantages•Cannot be repaired, must be replaced•Much more expensive than fuse wire
![Page 45: BS 2 Electrical installation 1](https://reader035.vdocuments.site/reader035/viewer/2022081507/58798ae91a28ab95318b4571/html5/thumbnails/45.jpg)
BUILDING | SERVICES | TWO (BLD60503)