Download - Ayman Method Statements 2
-
8/3/2019 Ayman Method Statements 2
1/15
Cairo International Airport
New Hotel Airotel
METHOD OF STATEMENTS
FOR
FIRE FIGHTING SYSTEM
-
8/3/2019 Ayman Method Statements 2
2/15
TABLE OF CONTENTS
SECTION NO. DESCRIPTION
1- SCOPE
2- PURPOSE
3- REFERENCES
4- SAFETY
5- PROCEDURES
-
8/3/2019 Ayman Method Statements 2
3/15
SCOPE-1
This procedure defines the method used to ensure that the fire fighting system
all pipes, fighting, valves, reducers, expanders, nipples, vents,, expansion and
contraction devices (previously submitted), hangers, brackets, anchors,supports, sleeves, plates, and all accessories and components connected
thereto as an integrated pipe work system, installation, final connections and
workmanship, is correct and acceptable and conforms to the contract
documents and general specifications.
PURPOSE-2
This method statement covers onsite installation of pre-fabricated and site
fabricated steel pipe work, supports, and expansion and anchor points for
firefighting system
REFERENCES-3
3.1- Fire Protection Specification sections 15012, 15051, 15075, 15057,
15121, 15122, 15181, 15185, 15189
3.2- General provisions for HVAC work, pipes and pipe fittings and piping
specifications.
CONSIDERATIONSSAFETY AND ENVIRONMENTAL-44.1- Mechanical superintendent will ensure that only suitable approved, tools,
and materials are used.
4.2- All tradesmen to ensure that the area clean and free from rubbish.
-
8/3/2019 Ayman Method Statements 2
4/15
PROCEDURES-5
PREPARATION FOR INSTALLATION:
Al l materials and documentation relevant to particular section of work
will be by the construction department prior to commencement of work
ensuring that these are of correct type as reviewed by consultant.
Before commencement of any construction works, pre-inspections will be
carried out on all materials prior to them leaving the storage area. The
consultant will be invited to attend this inspection at their discretion.
Before commencement of any construction works, areas and access will beinspected to confirm that they are in a suitable condition for construction
works to commence.
METHOD:-INSTALLATION
Mechanical supervisor will be instruct the tradesmen regarding the
execution of the works and will distribute all necessary approved
construction drawings of the latest revision .The supervisor will also
check that tools and equipments available are in compliance with
the contract requirements.
-
8/3/2019 Ayman Method Statements 2
5/15
Sleeves installationSleeves will be checked and installed by the construction team as follow:-
a-Location: As per approved construction drawings.b-Material: as the sleeve type in the next table.c-Size : equal to outside pipe insulation diameter plus 25mm.d-Length :
i. Floor slabs : equal to floor slab +finish+50mm.
ii. Roof slabs : equal to floor slab + finish +100mm.
iii.Walls and partitions: equal to wall construction + finish.Packing and sealant: the construction team will use Packing Type in the next
table to fill the space between sleeve and the outside
diameter of pipPacking TypeSleeve typelocation
Incombustible, permanently plastic, waterproof, non-stainingcaulking compound or pack with fibrous glass to within 1/2"
of both construction surfaces and finish with caulking
compound as per above. For floor and roof slabs, finish is
required on top side of slab only.
Standard weight galvanizedsteel pipe
Membranewaterprooffloor,roof and wall
Oakum, hempStandard weightgalvanized steel pipe
Non-membrane
water
proof wall
Incombustible, permanently plastic, waterproof, non-staining
caulking compound or pack with fibrous glass to within 1/2"
of both construction surfaces and finish with caulking
compound as per above. For floor and roof slabs, finish is
required on top side of slab only.
#18 gauge, galvanized steel
or
Standard weight
galvanized steel pipe
Interior walls
partitions and floors
Oakum, hempStandard weight galvanized
steel pipe with a
continuously welded water
stop of 1/4" steel plate
Exterior Walls
Packed mineral wool sealed with Johns-Manville "Duxseal"
install set screw escutcheons on both sides of wall.Standard weightgalvanized steel pipeInterior fire ratedshaft wallsTable for type of sleeve & Packing
-
8/3/2019 Ayman Method Statements 2
6/15
Piping & support fabrications
Piping Painting procedures as follow:-a- Mechanical supervisor will check that the pipes surface are cleaned
With wire brush and cleaning solution by construction team.b-After cleaning, Construction team will begin to spray the painting
Material using compressor with spray gun or brush.c- Type of painting
i.(BLACK STEEL PIPING) to be painted with two coats of Zinc phosphateprimer, they are to be Finishes painted with two coats of Approved oil paint.
ii.(PIPING run in trenches, shafts, underground) to be painted with two coatsof Zinc Phosphate primer and two Coats of heavy bituminous solution paint.
Piping Joints:a-Threaded fittings : for pipe sizes up to 2".b-Grooved couplings: for pipe sizes 2 1/2" and more.c-Flange adapter will be used in case of flex. Connections or flanged valves.
Jointing method for Grooved pipes:
a-Grooved type couplings (fixed & flexible coupling as manufacture StudyWhich previously submitted) with Grooved fittings at pipe ends Where
Used (size 2 1/2" and more), the constructionteam will chick the grooving
According to manufacturer's recommendation.
b-Type of groove:i. Rolling groove: for size 2 1/2'' and up to 8'
ii. Manufactures recommendations are as in following table:
Piping fabrication
as in following shown:for end of piperoll groovedmakeFirst
-
8/3/2019 Ayman Method Statements 2
7/15
in following shown:fitting aspiping withjointSecond
Jointing method for threaded pipes:a-Pipes ends shall be cut threads full and clean using sharp dies.b-Male threads shall be sealed compound, or pipe joint tape (Teflon).c-Special care shall be taken by construction team for handling
The threaded pipes
d-Tighten joint to leave not more than 3 threads exposed.e-Screwed pipe work shall meet the BS 21Flanged Site Work Joints:The construction team will match flanges within piping system, and at
Connections with valves and equipment and check that:
a- Gaskets used are 4mm thick rubber.
b- Both flange faces are cleaned.
C- Tighten bolts to provide uniformcompression of gaskets
D-No. Of flange bolts shall be meets ASMI B16.5 including bolt
size as the following table:
Bolts Diam.No. of BoltsStandard Pipe Size
-
8/3/2019 Ayman Method Statements 2
8/15
16 mm450 to 80 mm
19 mm8100 to 200 mm
Dielectric Fittings:
The construction team will install dielectric fittings where dissimilarmetals are connected together. These will be marked on the
approved shop drawings.
Pipe Hangers and Supports
Hangers supportPipes hanger work shall meet the following details and the rood size
table:
-
8/3/2019 Ayman Method Statements 2
9/15
Rod size (mm)Maximum distance between hangers (mm)Pipe diameter (mm)
10240025-3210270040
10300050
12330065
12370080
164200100
165100150
195800200
Trapeze Hangers supportTrapeze hanger &wall bracket work shall meet the following details:
-
8/3/2019 Ayman Method Statements 2
10/15
Zone control valve
The construction team will installZone control valve with type of valveand location and all accessories as the show:
-
8/3/2019 Ayman Method Statements 2
11/15
DrainsThe construction team will install drain points at the low points of
the system to drain the system when needed and to avoid traps.Automatic Air Vents:
The construction team will install the automatic air vents at the
highest points of the system, risers, pumps and equipments
Connections with DN 20 inlet connection to release trapped air.
Hydro Testing:
a- The construction team will use ambient temperature water as atesting medium.
b- The construction team will check that, the air vents which
installed at higher point of the system are working to release
trapped air; also the drain points which installed at lowest points
of the system are closed.
c- Subject piping system to hydrostatic pressure equal to 2 times
working pressure for at least 2 hours to examine piping, joints,
and all connections for leakage. Eliminate leaks by tightening,
repairing, or replacing components and repeat hydrostatic test
until there are no leaks.
d- Prepare test report and call the consultant for inspection
PREPARATIONFlashing
a- Flushing is carried out methodically from the main fire water inlet to
The end of the main branches the system.
b- The isolating valves are installed at the drain points indicated to control
The drainage for flushing.
c- All the isolating valves at the drain points are connected to the nearestDrain point by means of hoses.
d- All the drainage valves and main valve are closed.
f- Fire fighting jockey pump is ready to operate to provide the pressured
Water for flushing.
METHOD FLUSHING
a- Operate the jockey pump to provide the pressured water to the system
b- Open the main valve to provide water to the sprinkler pipes
-
8/3/2019 Ayman Method Statements 2
12/15
c- Open the drainage pipes gently one by one to start flushing the system.
d- Thoroughly flush the section to be cleaned with fresh water to
remove any dirt, dross and debris from pipe work.
e- Carry out the flushing until the clean water appears at the drainagePoints.
f- Remove the valves installed at the drainage points and install the
Sprinklers to fill up the system again.
g- On no account should any part of the system be drained and left wet
for any significant time after cleaning, as this will promote rapid
corrosion and possibly necessitate a re-clean.Identification:
a- Valves: A tag with chain will be attached to the valve handle,
as will as marking the ceiling tile to indicate location of valve.
b- Piping: The construction team will apply colour coded tape.
installationSprinkler
The construction team will install sprinkle with type of sprinkler an
location as show details:
-
8/3/2019 Ayman Method Statements 2
13/15
FIRE PUMPSINSTALLATION
A. Mechanical supervisor will Install packaged fire pump systems and accessoriesAs indicated in accordance with Manufacturer's written instructions, requirements of
applicable Standards and with Recognized industry practices to ensure that
installation complies with requirements and Serves intended function.
B. Coordinate as necessary to interface installation of packaged fire pump systems workwith other work.
C. Provide access space around pumps for service.D. Support piping Adjacent to pump such that no weight is carried on pump casings. For
base mounted Pumps provide supports under elbows on pump suction and discharge.
E. Provide drains for bases and seals, piped to and discharging into floor drainsF. Mount unit on vibration isolatorsG.
Provide for connection to electrical serviceH. Lubricate pumps before start-up
I. Check, align, and certify base mounted pumps by qualified millwright prior to start-up
-
8/3/2019 Ayman Method Statements 2
14/15
3.2 INSTALLATIONA. Install in accordance with manufacturer's instructions and NFPA 12
B. Ream pipe and tube ends. Remove burrs. [Bevel plain end ferrous pipe.]
Remove scale and dirt inside and outside before assembly. Blow out pipe
Before nozzles or discharge devices are installed.
C. Route piping in orderly manner, concealed, plumb and parallel to building
Structure, and maintain gradient. Install piping to conserve building space, and
Not interfere with use of space and other work.
D. Securely support piping in accordance with ANSI/ASME B31.1 with allowance
For CO2 thrust forces, and thermal expansion and contraction.E. Use grooved mechanical couplings and fasteners only in accessible locations.
Roll groove piping only.
F. Install unions downstream of valves and at equipment or apparatus connections.
G. Prepare pipe, fittings, supports, and accessories for finish painting..
H. Identify in accordance with ANSI/NFPA 12 requirements. Place directional
Arrows and system labels wherever piping changes direction and minimum 20
Feet (6 meters) on straight runs.
I. Secure cylinders as indicated on Drawings. [Where manifold, mount and
Support by rack as indicated. For each system provide same size cylinders
Containing equal amounts of liquid.]
J. In rooms with suspended ceiling tiles, clip or retain tiles within 4 foot (1.2 m)
radius of the nozzles to prevent lifting during discharge.K. Install wiring in accordance with Section 16120 & 16180 requirements.
L. Make final connections between equipment and system wiring under direct
supervision of factory trained representative of manufacturer.
M. Install engraved plastic instruction plate, detailing emergency procedures, at
control panel and at each manual discharge and abort switch location. At
control panel identify control logic units, contacts, and major circuits with
permanent nameplates.
N. At hazard area walls pack space between pipe, pipe sleeve or surface penetration
with mineral fiber with elastomeric calk to depth of 1/2 inch (13 mm). Provide
Escutcheons where exposed piping passes through walls, floors, and ceilings.
Seal pipe penetrations of fire separations.
O. Locate discharge nozzle approximately 6 inches (150 mm) above or below
ceiling and 6 inches (150 mm) below raised floors. Avoid interference with
-
8/3/2019 Ayman Method Statements 2
15/15
other piping and equipment.
P. Locate remote manual releases at one or more doors to protect area where
indicated. Locate deadman abort switch adjacent.
Q. Provide signal to building fire alarm system. Refer to Section 16721.
R. Provide interlock with automatic closing door releases.
S. Provide interlock with motorized dampers. Refer to Section 15952.
Incombustible, permanently plastic, waterproof, non-staining
caulking compound or pack with fibrous glass to within 1/2"
of both construction surfaces and finish with caulking
compound as per above. For floor and roof slabs, finish is
required on top side of slab only.