![Page 1: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/1.jpg)
AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development Manager
![Page 2: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/2.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
What’s the problem ?
![Page 3: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/3.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Efficiency – Reach a defined goal with minimum resource allocation /
consumption
What’s the problem ?
Source: Enhanced Work Packaging: Design through Workface Execution (Construction Industry Institute), July 2011
33%
44% 23%
Craftsman’s Work Day
Tool Time
Idle
Travelling/gatheringmaterial
![Page 4: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/4.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
If you want to know where to go you need to know where you are
Predictability – Where are we? How are we doing? Will we make it?
What’s the problem ?
![Page 5: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/5.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Properly Implemented Work Packaging and Workface Planning
Early Project Planning that integrates Work Packaging with – Engineering – Procurement – Construction – Project Controls
How can that challenge be solved?
Source: Enhanced Work Packaging: Design through Workface Execution (Construction Industry Institute), July 2011
![Page 6: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/6.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
How can that challenge be solved?
the work and work the plan
![Page 7: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/7.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
How it can be solved
Source: COAA & CII
![Page 8: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/8.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
How does AVEVA address this? Vertical Planning
– Rough Cut Planning on the top • Create and schedule Construction Work Packages
– Workface Planning below Rough Cut Planning • Create Installation Work Packages • IWPs shall stay in within he constraints defined during rough cut
planning (time & budget)
– Execution Layer on the bottom • Provide a task list to the Forman • Check constraints • Execute work • Gather actual data and let the system roll-up
![Page 9: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/9.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
How does AVEVA address this? 4D / 5D Planning
– Link the schedule with the 3D model – Simulate construction sequence to verify correct planning – Integrate with materials management
• Materials are purchased and delivered to support construction
– Communication of tasks is improved at the workface • “a picture is worth a thousand words”
– Predictability gets increased
Visualisation – Visualise material availability – Visualise status by colour-coding objects in 3D model
![Page 10: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/10.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Vertical Planning
Project Planning
Workface Planning
Execution & Control
Rough Cut
Planning
Detail Planning
Release
Execution
Feedback
Roll-up
Reconcile
![Page 11: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/11.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Vertical Planning: Loop in the Loop
Rough Cut
Planning
Detail Planning
Release
Execution
Feedback
Roll-up
Reconcile
Reconcile
Construction Work Package
IWP
IWP IWP
IWP
![Page 12: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/12.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Application AVI
![Page 13: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/13.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Work Package Building (Kitting)
Show a 3D Model in Planning Assign objects from model to work package
Step1: Select item in the model or from a list
Step2: Assign to Work Pack
![Page 14: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/14.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Timeline Simulation
Assign objects from a 3D Model to Work Packages – Can be done on all levels (CWPs, IWPs and jobs)
Timeline Simulation – Run through the schedule and simulate construction – Verify correct construction sequence – Change sequence of work packages in schedule if required
![Page 15: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/15.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Run a Timeline Simulation
Simulate construction sequence over time
Timeline running through he schedule
Adjust speed to daily, weekly monthly
![Page 16: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/16.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Visualisation
![Page 17: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/17.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Visualisation Resource Load
– Man power, machinery
Material status – To support the execution of work on-site – Visualise material availability, i.e. give a warning if material
won’t be available on time
Project Status – Colour code objects in a 3D Model depending on their
status – Status of object gets derived from underlying work
package status
Project Performance
![Page 18: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/18.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Resource Load
![Page 19: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/19.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Material Status
Red dot indicates shortage of material
Detailed list of material for a work package
Precise list of missing items
![Page 20: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/20.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Project Status
![Page 21: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/21.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Project Performance
![Page 22: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/22.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
Summarised we’ve come pretty close to this:
Someone tells me how to put
it together…
…and where it has to be
installed …
AND I CAN RELY ON
THIS! … and I have
everything I need to do it
![Page 23: AVEVA’s Construction Management Solution - IPMA Italyipma.it/ipma_/images/J. Rizzo_Aveva.pdf · AVEVA’s Construction Management Solution Jen Rizzo July 22, 2013 Business Development](https://reader034.vdocuments.site/reader034/viewer/2022051602/5af452107f8b9a4d4d8d756c/html5/thumbnails/23.jpg)
Copyright © 2013 AVEVA Solutions Limited and its subsidiaries. All rights reserved.
What do we get?
Communication of tasks is improved at the Workface Predictability gets increased Constraints such as craft availability, material,
scaffolding and drawings are better managed Engineering is able to support the construction
sequence and schedule Vendor-supplied equipment remains on schedule Materials are purchased and delivered to support
construction