Avance de obra al 15-03-2010
Torre 7
Torre 8
Torre 9 - 10
ACTIVIDADES DE CONTROL E10 E9 E8 E7
ARMADO, VACIADO PILOTES. EDIF. 100% 100% 100% 100%
ARMADO , VACIADO Y RELLENO DE VIGAS EDIF. 100% 100% 100% 100%
CONCRETO VACIADO PLACAS, MUROS 100% 100% 100% 2%
VACIADO MUROS INTERNOS 100% 88% 0% 0%
VACIADO ANTEPECHOS Y BALCONES 100% 100% 4% 0%
CENTRAL VACIADO ESCALERAS 100% 64% 0% 0%
INST. ELECTRICAS 50% 0% 0% 0%
INST. SANITARIAS 92% 42% 0% 0%
INST. ELECTROMECÁNICAS (ASCENSOR) 0% 0% 0% 0%
INST. GAS (65% APTO+35% MONT) 65% 50% 0% 0%
MARCOS INTERNOS APTOS. 42% 0% 0% 0%
BLOQUE APTO. 89% 8% 0% 0%
BLOQUE DE VENTILACIÓN APTO 72% 0% 0% 0%
FRISO APTO. 28% 0% 0% 0%
ACABADOS RESANEO DE MUROS INTERIORES 53% 0% 0% 0%
TABLILLA FACHADA 63% 0% 0% 0%
IMPERMEABILIZACION DE TECHOS 0% 0% 0% 0%
MODULO BLOQUE MOD.ASCENSOR 50% 0% 0% 0%
BLOQUE. VENTILAC. MOD.ESC. 92% 0% 0% 0%
BAJANTES DE BASURA 83% 0% 0% 0%CENTRAL
EXTERNOS
ALBAÑILERÍA
INSTALACIONES
ESTRUCT.
INFRAESTRUCT
Avance de obra al 15-03-2010
Torre 11
Torre 12
ACTIVIDADES DE CONTROL E12 E11
ARMADO, VACIADO PILOTES. EDIF. 100% 100%
ARMADO , VACIADO Y RELLENO DE VIGAS EDIF. 100% 100%
CONCRETO VACIADO PLACAS, MUROS 100% 100%
INST. ELECTRICAS, SANITARIAS 100% 100%
INST. ELECTROMECÁNICAS (ASCENSOR) 100% 50%
INST. GAS (65% APTO+35% MONT) 100% 83%
MARCOS INTERNOS APTOS. 100% 95%
BLOQUE APTO. Y DE VENTILACIÓN, FRISO APTO 100% 100%
PUERTA PRINCIPAL , CERRADURA 100% 99%
NIVEL I ENCAMISADO , PORCELANA , CERÁMICA APTO 100% 95%
ALAMBRADO+ CABLEADO APTO. 100% 92%
PIEZAS SANITARIAS, ELECTRICAS, BATEA 92% 50%
PINTURA MARCOS INTERNOS + PTA PPAL 99% 89%
ALUMINIO Y VIDRIO 70% 33%
IMPERMEABILIZACION DE TECHOS, TABLILLA FACHADA 100% 50%
FRISO Y ENCAMISADO EN PASILLOS 100% 100%
CERÁMICA EN MÓDULO CENTRAL 100% 83%
BARANDAS ESCALERAS Y BLACONES 100% 100%
BAJANTES DE BASURA 100% 83%
CENTRAL LAMINAS EN TECHOS (carbolux) , EXTRACTORES 100% 100%
ACABADOS
ALBAÑILERÍA
INSTALACIONES