AURUM – VILLAS – Photo Report
• Key Plan showing the Camera positions, Click on the Icon to review respective status:
12
3
4
5
6
7
8
9
10 1112 13 14
15
1617
18
19
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 01
• Aurum Villas front entrance
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 02
• Package I – Road WMM completed
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 03
• Package I – Road Kerb work in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 04
• Package I – Waterproofing and Tiling in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 05
• Package I – UPVC window work in progress
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 06
• LEFT – Package 02 RIGHT – Package 01
Key Plan
12
3
45
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 07
• Package II – UPVC window work in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 08
• Package I – External painting 1st coat in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 10
• Package II – UPVC window in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 11
• Package II – UPVC window fixing in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 12
• Package II – Edge villa compound wall in progress
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 13
• Package II – UPVC window fixing in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 14
• Package II – Plastering and tile works in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 15
• Package II – internal plastering and planter work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 16
• Package II – tiles and planter work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 17
• Package II – shaft plumbing work and planter work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 18
• Package II – Road work in progress
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 19
• Package II – Tiling work in progress
Key Plan
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group A Villas – Electrical wall conduit work in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group B Villas – Waterproofing and tiling in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group D Villas – External plastering in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS WATER TREATMENT PLANT
• Cover slab beam reinforcement in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS RAIN WATER HARVESTING PIT
• Excavation in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS MOCKUP VILLA
• Front Elevation
AURUM_Photo Report - Villas
AURUM – VILLAS Aerial View
• .
AURUM_Photo Report - Villas
AURUM – VILLAS Front Entrance
• .