Agile Estimating and Planning
October, 2013 Technion, Israel
Prof. Fabio KonUniversity of Sao Paulo, Brazil
![Page 2: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/2.jpg)
2
Non-Agile World
No
PlansExcess of
Plans---------
![Page 3: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/3.jpg)
3
How much to plan
Plan too much is waste
Plan too little = lack of organization/focus
![Page 4: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/4.jpg)
4
Some data from Chaos report(2004)
18%
29%53%
Success
failuresChallenged
![Page 5: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/5.jpg)
5
Chaos report
1994 2004Projects not completed------------ 31%
Projects succedded----- 16%
Avg. budget consumed-----------------------> 280%
Avg. time needed-----------------------> 264%
Projectos not concluded------- 18%
Projects succedded----------- 29%
Avg. budget consumed---------------> 156%
Avg. time needed-------------> 84%
![Page 6: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/6.jpg)
Disclaimer
The Chaos report is not very scientific
Use with caution
![Page 7: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/7.jpg)
Which software to develop?
Never or Rarely
Used64%
TovMeod
36%
Source: Jim Johnson, 2000
Features:
![Page 8: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/8.jpg)
8
Attention!
In real life, you can be sure of only one thing:
things will change and not follow the plan
Be prepared for that!
![Page 9: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/9.jpg)
9
Agile Approach
Individuals and interactions
Working Software
Customer collaboration
Adaptation to change is more important than following the initial plan
- - - x - - -
Plans are nothing; planning is everything
Eisenhower
![Page 10: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/10.jpg)
10
Scope of Agile Planning
Planning Onion
![Page 11: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/11.jpg)
11
Release planning
What to do
• List stories that will be developed
• Select the stories that will be included in the release
• Estimate stories
What not to do
• Assign responsibilities
• Define a sequence
• Create tasks for each story
High-level planning
![Page 12: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/12.jpg)
12
Iteration planning
• Customers, programmers, analysts, designers, etc.
• Identify needed tasks for each story
• Manage tasks using online tool or paper cards
• Estimate each task
• Do not allocate tasks to people (yet)
![Page 13: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/13.jpg)
13
Uncertainty cone
![Page 14: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/14.jpg)
14
Benefit of (good) Estimates
Reduce risk
Reduce uncertainty
Help in decision making
Establishes trust
Transmit information/knoweledge
![Page 15: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/15.jpg)
15
Why plans fail?
Planning is done task by task and added up Activities are not independent
Delays add up
Activities are never completed before the deadline Parkinson law (1993)
Many tasks in parallel decrease productivity Features are not developed in order of priority Uncertainty is normally ignored Estimates become commitments
![Page 16: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/16.jpg)
16
Preparing to estimate
Avoid false precision
Define a scale, e.g.: 1, 2, 3, 5 and 8 0, 1, 2, 4 and 8 10, 20, 30, 50, and 100
Identify Stories, Themes, and Epics
![Page 17: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/17.jpg)
17
Let’s estimate!
Size is different from Duration
1
1
2
22
2
4
4
4
4
8 16
16
2 Total = 58
![Page 18: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/18.jpg)
18
Estimating
• with Points
– Relative estimates
– Abstract
– Measures size of effort (must be converted to time)
• with Ideal Work Days
– Easier to explain
– Concrete
– My favorite when doable
![Page 19: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/19.jpg)
19
Why ideal ≠ real
Meetings Bug fixing Special projects Support Demonstration Training Revisions
Interviews Task switching Phone calls E-mails Personal issues Sicknesses Extraordinary boss
requests
1 real day = α ideal day, 0 < α < 1
![Page 20: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/20.jpg)
20
How to estimate
Major techniques: Expert opinion analogy Divide and conquer
Major problems: Availability of expert Estimator is not developer Estimate by feature and not by task
Solution: Planning Poker
![Page 21: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/21.jpg)
21
Planning Poker
![Page 22: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/22.jpg)
22
Estimating Velocity
Based on history / previous experience
Carrying out 1 iteration
![Page 23: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/23.jpg)
23
First Plan
The first iteration is likely to be very wrong.
Don’t worry, learn, and adapt, correct your estimates.
… at least, the 1st iteration is done only once ;-)
![Page 24: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/24.jpg)
24
Protection against uncertainty
Always add a buffer!
Lag in schedule
Buffer in estimates
Buffer in features
![Page 25: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/25.jpg)
25
Scheduling
Prioritize based on Business Value
Consider: Financial value of the functionality Cost of development and maintenance Development time Amount of learning and knowledge offered by the
new feature Amount of risk eliminated after developing the
functionality Technical dependencies
![Page 26: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/26.jpg)
26
Value and Risk
High
High
Low
RISK
Value
Avoid
Do Last
Do First
Do Second
![Page 27: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/27.jpg)
27
Prioritizing Customer Desires
Kano Model for Customer Satisfaction
Required features
Aggregating features
Surprising features
![Page 28: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/28.jpg)
28
Project Monitoring
Estimates will be very wrong in the beginningWill get better as team become more experienced
It’s important to monitor progress to: Know where you are Learn and then estimate better
![Page 29: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/29.jpg)
29
Release Burndown Chart
![Page 30: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/30.jpg)
30
Release Burndown Bar Chart
![Page 31: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/31.jpg)
31
12 Rules for Planning with Agility (I)
1. Involve the whole team
2. Plan in multiple levels
3. Keep size and time estimates separate (optional)
4. Consider uncertainty for features and dates
5. Replan frequently
6. Track and advertise progress
![Page 32: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/32.jpg)
32
12 Rules for Planning with Agility (II)
1. Be aware of the importance of learning
2. Work with features of the right size
3. Prioritize features
4. Base your estimates and plans in facts
5. Not plan for 100% of the time (buffer, ideal work day)
6. Coordinate planning to avoid dependencies
![Page 33: Agile Estimating and Planning October, 2013 Technion , Israel](https://reader035.vdocuments.site/reader035/viewer/2022062804/56814b24550346895db83404/html5/thumbnails/33.jpg)
33
Questions
Fabio Kon
University of São Paulo, Brazil
Bibliography:
Agile Estimating and Planning. Mike Cohn. Pearson Education. 2005.