Migrating a Large SAP Landscape to theAmazon Cloud – A Real Life Case Study of Migrating
Joe CoyleNorth American Chief Technology Officer – Capgemini
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 2/47
[Agenda
Client Background The Vision and the Mission
The First Rule We Followed
e o u on
What we Started With
Business Case
The Target Platform / Environment
Timeline and Critical Steps
The Mi ration Process and Ke Learnin 's
Some Challenges Around Adapting SAP Landscapes to AWS
Impacts to People, Process, and Existing Infrastructure
Ada tin Traditional Enter rise Monitorin and Orchestration
Legal, Risk, and Audit Involvement
AWS Cloud Security Model Overview
Ke Lessons
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Wrap-Up
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 3/47
[3 Key Take-Aways
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 4/47
[3 Key Take-Aways
Enterprise Operationalbenefits and
challenges to an AmazonWeb Services On-Demand
and Elastic Infrastructure.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 5/47
[3 Key Take-Aways
Obtainingapprovals and
demystifying concernsaround SAP environments
Enterprise Operationalbenefits and
challenges to an AmazonWeb Services On-Demand
in the public cloud.and Elastic Infrastructure.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 6/47
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 7/47
[Client
A massive global SAP ecosystem in an outsourced environment:
B A C K G R O U N D
– ~170 SAP instances
– ~ 150 Terabytes of data across the landscape
– Many non-productive SAP instance with productive data loads used for various critical
– Single global instance strategy
Global SAP Rollouts on-going.
.
Constant Leadership pressure to speed up the rollout and cut IT spend in parallel.
Additional SAP streams of work ongoing including upgrades, BI, etc.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 8/47
[The Vision and the Mission – A True Cloud Experience
Deliver a lower cost solution than existing platform:
Migrate to a “Subscription-Based” Model.
Reduce infrastructure investment and shift costs from CAPEx to OPEx.
Deliver a lower cost solution than existing platform:
Eliminate Capacity constraints in the existing datacenters:
Get out of the IT refresh cycle.
landscapes.
Additional landscapes constantly required for new deployment /
development efforts.
Improved Business Value:
Simplify capacity management with flexibility for infrastructure resizing.
Greater Scalabilit to handle short-term and ad-hoc re uests.
Reduce Time to deployment from weeks to days.
Eliminate HW Life Cycle Management.
Standardization due to abstraction of a lication from hardware to
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
hypervisor.
Move to an overall “As A Service” model.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 9/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 10/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 11/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
esource poo ng• Location independence
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 12/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
esource poo ng• Location independence
Rapid elasticity4
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 13/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
esource poo ng• Location independence
Rapid elasticity4
Measured service5
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 14/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
esource poo ng• Location independence
Rapid elasticity4
Measured service5
But
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 15/47
[The First Rule We Followed
We want to ensure that our solution brings all five essential components ofCloud to the solution:
Broad network access2
esource poo ng• Location independence
Rapid elasticity4
Measured service5
the solution also needs to deliver Enter rise BusinessButIT capabilities around monitoring, metering, orchestration,
service desk, capacity planning, reporting, billing.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
capitalize on the components of Cloud.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 16/47
[The Solution
Migrate SAP environments to the Capgemini Orchestration Management Platform End To
End (COMPLETE) environment powered by the Amazon Web Services.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 17/47
[The Solution
Migrate SAP environments to the Capgemini Orchestration Management Platform End To
End (COMPLETE) environment powered by the Amazon Web Services.
Customer Applications/Solutions – SAP Ecosystem
Decide►Design► Build► Integrate►Migrate►Run►Support
Service Management Security and Compliance
Service Automation Usage and Accounting
L E
T E
on or ng
Platform/Virtualization
High Availability
Server, Storage, Network C O M
anagemenHardware
Cloud Infrastructure Abstraction & Aggregation Layer
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Traditional
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 18/47
[The Solution
Migrate SAP environments to the Capgemini Orchestration Management Platform End To
End (COMPLETE) environment powered by the Amazon Web Services.
Customer Applications/Solutions – SAP Ecosystem
Decide►Design► Build► Integrate►Migrate►Run►Support
Service Management Security and Compliance
Service Automation Usage and Accounting
L E
T E
on or ng
Platform/Virtualization
High Availability
Server, Storage, Network C O M
anagemenHardware
Cloud Infrastructure Abstraction & Aggregation Layer
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Traditional
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 19/47
[The Solution, Continued
Customer Applications/Solutions – SAP Ecosystem
Decide►Design► Build► Integrate►Migrate►Run►Support
Service Management Security and Compliance
Service Automation Usage and Accounting
L E
T E
on or ng
Platform/Virtualization
High Availability
Server, Storage, Network C O M
anagemenHardware
Cloud Infrastructure Abstraction & Aggregation Layer
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Traditional
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 20/47
[The Solution, Continued
Customer Applications/Solutions – SAP Ecosystem
Decide►Design► Build► Integrate►Migrate►Run►Support
Service Management Security and Compliance
Service Automation Usage and Accounting
L E
T E
the best advantage of the consumption based
computing model of AWS.on or ng
Platform/Virtualization
High Availability
Server, Storage, Network C O M Targeted systems after migration should inherit the
ability to rapidly deploy, de-commission, expand,
anagemenHardware
Cloud Infrastructure Abstraction & Aggregation Layer
, .
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Traditional
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 21/47
[What We Started With – Training and Prototype
Migrate selected landscapes to theCOMPLETE platform
All SAP systems that encompassthe Prototype, Training Landscapes
Prototype Systems Landscape
Training (sandbox) Systems Landscape
Totaling 33 SAP Instances
Running on Unix, Itanium based Servers
Oracle 10/11 Database Training (classroom) Systems Landscape
Approx 25 TB of Data on Enterprise SAN
Vertex and SAP Internet Pricing
Configurator includedin landscape
Global Enterprise MPLS based Extranet
must stay intact for global access
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 22/47
[The Business Case for Migration –
Driven by Cost Savings and Speed to ValueAfter reviewing all IT costs associated with the targeted environment, thebusiness case presented itself.
Client will experience a one time savings of 8 Million dollars. Client will experience a year over year savings of 45% over existing outsourcing
.
– These savings are driven by estimating two areas of the consumption based model:
• Fixed consumption costs
– Amount of storage
– Number of backups
– Secured network
• Variable Consumption Costs
– Compute time – Bandwidth and I/O
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
the agreement that we should move forward with the project!
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 23/47
[A Few Important Points on Amazon Web Services
– Platforms like Capgemini COMPLETEenhance those SLAs for enterprise
AWS is very much a “productive”
environment! as c y an n ras ruc ure resources an
virtually endless!
AWS is no longer just Infrastructure as a
erv ce. ey are we n o e a orm asa Service model.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 24/47
[Example of AWS Compute Power and Price Points
NASA’s Jet Propulsion Laboratory (JPL) has developed the All-
Terrain Hex-Limbed Extra-Terrestrial Explorer (ATHLETE)
NASA Jet Propulsion Lab’s Desert Research and Training Studies
robot. Each of the ATHLETE’s six limbs is attached to a wheel,
enabling the vehicle to travel across various types of terrain—ranging from smooth surfaces to rolling hills to ruggedly steep
terrain. Wheels can also be locked to transform the limbs into
general purpose legs that can be used as feet. The ATHLETE
robot can also be used for loading, unloading, and transporting
cargo for long distances.
The a lication is built on Pol hon which is a modular
workflow orchestration framework designed to streamline the
process of leveraging hundreds of nodes on Amazon Elastic
Compute Cloud (Amazon EC2). By accommodating excess
ca acit on local machines and s are resources in the
supercomputing center, Polyphony meshes perfectly with Amazon’s cloud computing. Most important, Polyphony
enables the resources to work together to achieve a common
oal. B usin Amazon Sim le Queue Service Amazon SQS ,
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
JPL developers can deploy massive computations on Amazon
EC2 by writing as little as a single class.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 25/47
[Example of AWS Compute Power and Price Points
Polyphony has been delivered to the Mars Science Laboratory to serve as one of
the primary data processing and delivery pipelines that process data downloaded
from Mars.
Khawaja Shams, Senior Solution Architect, explains that the application “allowed
us to process nearly 200,000 Cassini images within a few hours under $200on AWS.” Due to the lack of elasticity available internally before switching to
“ locally and spent more than 15 days on the same task.” The efficiency andcost-savings offered by AWS has proven invaluable.
,from Mars in a few
hours.
Cost on AWS $200.00.
Traditional processing
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
same task!
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 26/47
Lets Get Technical for a Few Minutes
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 27/47
[The Target Platform on COMPLETE Powered by AWS
Linux & Windows AMI customized & hardened as base for application AMI creation.
Creation of Operating System Amazon Machine Images (AMIs)
Used to launch instances and clone for different landscape needs.
Elastic Block Storage (EBS) defined, logical volumes striped, (can be resized as
re uired .
SAP Application AMIs created for each application version
EBS Snap shots to S3 to preserve golden images.
A ro riate instance size estimated – will be monitorin for resizin as re uired.
Launch of Application instances to create the 3 landscapes
Capgemini COMPLETE to manage monitoring of infrastructure, OS and Instance
operations.
Metrics, thresholds and actions to be confirmed.
management.
SAP Instances were un-coupled (MCOD/MCOS) to leverage the power of AMIs and
leverage the consumption model.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 28/47
[The AWS Target Platform, Continued
Virtual Private Cloud Infrastructure with customer defined IP addresses and
subnets.
Network Architecture
Secured access from the customer network via VPN Tunnels to customer Internet
Gateways for quick start. Secured access from the customer network by extension of MPLS backbone via
AWS Direct Connect rocess with E uinix Co-location center.
Security Groups templates for enabling only required application ports and
protocols, source and destinations at the instance level.
Internet Gateway managed by Capgemini for use to public subnet only (VPNanager, pac e everse roxy or upp er or a .
Support & Services
SAP Application support will continue to be provided as part of our existing
.
All infrastructure support services will be included in as part of the COMPLETE
service.
Existin SLAs will carr over to a lications su orted on the COMPLETE
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
platform.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 29/47
[High Level Network Architecture
Auth.Traffic
Customer Intranet
DC/CustomerLocation 1
CustomerLocation 2
CustomerLocation n
SAP-ProdSolman
Uperform
Non-ProdSolman/CUATransports
CustomerVPN Gateway
CustomerVPN Gateway
CustomerVPN Gateway
upp ers
InternetCustomer VPN
Gateway206.193.136.11
InternetGateway
R
VPN Manager10.109.7.4.
184.72.123.193
Legend
Any IPSec devicecan be used
CustomerVPN Gateway
Customer VPCPrivate subnet
10.109.6.0/24
Train 2 (2)Landscape
Train (N)Landscape
Supplier PortalReverse Proxy
DMZ/Public subnet
10.109.7.0/26
Capgemini/AWS
recommended
Cisco ASA
Site to SiteIPSec Tunnel
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Prototype (T)Landscape
As Required
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 30/47
[Customer Connectivity to AWS with MPLS
AWS Cloud
Customer
Datacenter
AWS
Customer
Site 1
Customer
MPLSDirect
Connect
Switch CustomerSite 2
CustomerSite n
MPLS CERouter
Equinix
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 31/47
[Proposed Timeline
Year
SAMPLE
Description Month 1 Month 2 Month 3 Month 4 Month 5
Complete Network and ArchitectureDesign/Financial and Risk Review
Sign-Off by customer to proceed with
m gra on
System Builds are completed (no data)
Complete Multi-tunnel Network
Connectivity
house)
Migrate Training and Prototype to the
COMPLETE Platform
Cutover Training and Prototype systems
from in-house to COMPLETE Platform
Repurpose Training and “T” HW tosupport SMI Group 3
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Task End Milestone
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 32/47
[Critical Steps
The list below tracks the tasks which need to be completed prior to approving themigration to move forward.
Next Ste s Res onsible Status
Agree on proposed network solution
Identify the number of locations for VPN Tunneltermination (configuration is required)
ss gn requ re a ress space
Capgemini to create small POC environment with a
couple of SAP instances with no data to test/prove out
network connectivity to 1 location
Confirm data load process with MDM team
Complete Financial review
Complete Risk Mitigation Review
Complete Legal Review
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 33/47
[The Migration Process
Approximately 25 TB of data will be initially migrated to the COMPLETEplatform powered by AWS:
In order to minimize bandwidth utilization (LAN/WAN/Web)
– Capgemini will provide the transportable storage devices (eSata and USB compliant)
– Ship to AWS & leverage AWS Import / Export Service to AWS S3
– Capgemini will migrate data from AWS S3 to EBS and import data
The approach for additional data migrations and updates will bedetermined based upon a number of factors:
– Size and timing of the data to be migrated – an w requ remen s vs. ava a e an w
– Complete or partial data migrations
– New Capabilities such as AWS Direct Connect
& Storage Gateway option to be investigated
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 34/47
[Key Learning’s Around Migration, Refreshes, and
Hetero eneous S stem Co ies Three acceptable SAP heterogeneous data migrations.
– SAP R3Load, Oracle Transportable Tablespaces and Oracle Export/Import Datapump.
.
Storage Striping via Software RAID recommended for I/O performance. Leverage AWS Import/Export Process.
– .
– Allocate appropriate time for
exports, shipping
and imports.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 35/47
[Some Challenges Adapting TraditionalSAP Landsca es to the Cloud Availability of Operating System options are limited to Linux & Windows.
Currently only SUSE Linux supported by SAP in AWS for “Production”.
Migration and refresh of large data sets in a timely manner.
Network Connectivity Options – Careful Planning Needed:
– Native Internet
– Internet VPN
– Direct Connect (for Enterprise WAN Connectivity)
– IP addressing & Routing
– AWS Routing Options Limited to Border Gateway Protocol (a routing protocol betweenautonomous systems)
High Availability architecture
– Traditional Cluster / RAC not supported
n y a coup e o nstance s zes supporte or ro uct on w tBenchmark.
DB/2 migrations limited to R3Load process (did not apply in this case).
•
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
.
• SAP static tuning parameters can not dynamically leverage the elastic compute
power of AWS. Plan accordingly.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 36/47
[Impacts to Existing Ecosystem (Infrastructure, Process, People)
The decision needs to be per business process, solution, or per software application:
What SLA do We need?
– What uptime do we expect (availability), backup policy and data retention needs, when do we expect
, .
Regulations / Compliance
– Government regulations that may apply such as FDA validation, special data protection rules such as
PCI Compliance or security rules beyond the standard.
– Focuses on how the solution functions, and how predictable it is. Do we need more computing
power for month-end, will we have unpredictable bursting such as a promotional website or even a
temporary environment that may have unpredictable growth.
– Although a move to the Cloud is a step toward getting out of the IT business, adjustments to your
infrastructure still need to be planned as part of the process. Areas here are around network security,
ability to connect in the Cloud, and reviewing the integration points between systems.
– Current leases, value of owned technology assets, datacenter layout today and labor costs to reducethe footprint, and possible changes around software licensing due to the migration.
People & Processes
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
– . -
– Changes in roles, processes and procedures.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 37/47
[Adapting Traditional Enterprise Monitoring and Orchestration
Landscape Uptime will match closely to real life needs / requests.
– Proposed 10 hours/day Mon-Fri & as required for
.
– Monitoring needs to understand scheduled up and down
times.
Automated Landscape startup (OS Instance &Application).
Automated Landscape Application Shutdown.
– Triggering. EBS Data Snapshots to AWS S3 & AMI creation.
– (14 day retention planned excluding golden image.)
– The S3 Snapshots replicates the data across AWS
.
– Periodic snapshot of archive logs to S3.
Weekly refresh of landscapes for Training businessneeds.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
– Flashback functionality integration / S3 Snapshots.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 38/47
[Legal, Risk, and Audit Involvement
Involved these groups early.
Engage the client directly with the Amazon security team.
Focus on dispelling the Cloud rumors early withso ac s:
– The Cloud is secure, It’s their business. – Amazon is not just “public Cloud”.
ar y up ron w a secur y s:
– Moving to a cloud solution does NOT
put the burden of security on only
the Cloud provider.
– Understand, formalize, and document
which party owns which piece
of the security ecosystem.
–
do not go away, they adapt.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 39/47
[AWS Cloud Security Model Overview
Certifications &Accreditations
PhysicalSecurity
VMSecurity
NetworkSecurity
SAS 70 Type IIMulti-Level Multi-Factor Multi-Factor Access to
Instance Firewalls can
be configured in security
groups
SOX Compliance Controlled Need-Based Access AWS Employees
Customer ControlledFirewall at Hypervisor
Level
Traffic may be restrictedby port, protocol, source
IP
ISO 27001 CertificationMgmt Admin
AccessNeighboring Instances
prevented access
Virtual Private Cloud
(VPC)
PCI DSS Level Multi-Factor Controlled Access to Host
Virtual Disk Mgmt Layer
Assure Only Owners
VPC IPSec VPN Access
to Enterprise Dataan ccess orage en ers
HIPAA Compliant
Architecture
All Access Logged
Monitored & Reviewed
Support for SSL
Endpoint Encryption for
API Calls
SharedResponsibility
–
FISMA
Access to Customer VM, Application & Data SI – Control Guest OS
SI – OS Security,
Patching & Maintenance
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
SI/Customer –
Application Level
Security
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 40/47
[Key Lessons
This is a mindset change. Not everything needs to be up and running 24x7. Match running
environment to actual user need to maximize cost savings.
Don’t be afraid to Convert Unix to Linux for some non-prod use cases.
ons an so u on arc ec ure an cos rev ew as e capa es are cons an yimproving and cost options are getting better. (Example: Reserve Instances, new instance
sizes, new support from SAP, storage gateway.)
You can and should extend traditional monitoring and security to the Cloud including
Solution Manager CCMS.
Put the time in and focus on Import / Export Data Migration Planning
Network Planning is critical. As it always is. Orchestration is key – Scripting of Launch, Start, Stop, Backup with proper Tagging.
Template/AMI creation for hardened Operating System as well as each SAP application.
Constantly Review Usage Charges – the truth will emerge.
Traditional instance stacking (MCOD/MCOS) and
virtualization don’t always make the best sense in a
consumption based cloud. Focus on usage to make
these decisions.
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
Traditional Basis decisions and processes are
the same. There is no magic here.
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 41/47
[If You Forgot Everything Else – Remember This:
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 42/47
[If You Forgot Everything Else – Remember This:
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 43/47
[If You Forgot Everything Else – Remember This:
Set it and Forget it!
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 44/47
[If You Forgot Everything Else – Remember This:
Set it and Forget it!
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 45/47
[If You Forgot Everything Else – Remember This:
Set it and Forget it!
Add intelligence to the environment to take advantage
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 46/47
[
Real Experience. Real Advantage.
© Copyright Capgemini 2012 All Rights Reserved
[
8/12/2019 2412 Migrating a Large SAP Landscape to the Amazon Public Cloud
http://slidepdf.com/reader/full/2412-migrating-a-large-sap-landscape-to-the-amazon-public-cloud 47/47
[
.Please remember to complete and return your
evaluation form following this session.
For ongoing education on this area of focus, visit the
Year-Round Community page at www.asug.com/yrc
[ SESSION CODE:
INSERT SESSION CODE
Real Experience. Real Advantage. 47