Download - 1. 2 Kinds of Production Environments LO1: Describe the different kinds of production environments
1
2
Kinds of Production Environments
LO1: Describe the different kinds of production environmentsLO1: Describe the different kinds of production environments
3
Production Environments• Job shops and Job costing
Customized products in small lots Shipyards, custom-built houses
High traceability of many costs Overhead is an exception
• With small batches and make-to-stock The batch is the unit of analysis
Has distinct job number All units move as one through the production process
Job is either complete or not Cost therefore either in COGM or in WIP
LO1: Describe the different kinds of production environmentsLO1: Describe the different kinds of production environments
4
Production Environments• Process shops and process costing
Similar products in large lots Chemicals, fertilizer
Limited traceability of costs to individual units Units in the same batch might be at different levels of
completion Need to allocate costs between COGM and WIP
• Operations costing Aspects of both job and process costing
Garment manufacturing
LO1: Describe the different kinds of production environmentsLO1: Describe the different kinds of production environments
5
a) an oil refinery.
b) a paper company.
c) a custom-home builder.
d) a car dealership.
Test Your Knowledge!The most logical business which would use job order costing would be:
A maker of custom ordered items would most likely use job order costing.
A maker of custom ordered items would most likely use job order costing.
6
Cost Flows Through Accounts
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
7
Cost Flows• Regardless of environment, flow of costs through
the inventory accounts is similar• Job shops
Individual job is the “unit of analysis” Can trace materials and labor to individual job Have to allocate overhead
Account balances are sum of costs if individual jobs
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
Beginning WIP = Value of jobs unfinished at start of accounting periodBeginning WIP = Value of jobs unfinished at start of accounting period
Ending WIP = Value of jobs unfinished at end of accounting periodEnding WIP = Value of jobs unfinished at end of accounting period
COGM = Value of jobs completed during the accounting periodCOGM = Value of jobs completed during the accounting period
8
a) Finished goods inventory.
b) Work-in-process inventory.
c) Cost of goods manufactured.
d) Raw materials inventory.
Test Your Knowledge!In a job-order costing system, direct labor costs are shown as an increase to what account?
Direct labor costs increase work-in-process inventory.Direct labor costs increase work-in-process inventory.
9
Cost Flows in a Job Shop: Magna
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
10
Inventory Accounts
(12/1): Magna
11
Analyzing Materials
• Materials flow through the inventory accounts Might separate accounts by kind of material
• For direct materials, keep track of which job materials were issued to Examples: Components
• For indirect materials, put into overhead control account Examples: Supplies
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
12
Analyzing Materials: Magna
13
Analyzing Labor Costs
• Accumulated in control account Avoids having to deal with salary, bonus, and other
benefits as separate items Avoids having to deal with separate wage rates for
different workers (e.g., due to seniority)
• If direct labor, charge out to individual jobs
• If indirect labor, charge out to overhead control
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
14
Analyzing Labor: Magna
LO2: Explain the flow of costs in a job LO2: Explain the flow of costs in a job shopshop
15
Analyzing Overhead
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
16
Pre-Determined Overhead Rates
• Calculate Rate at start of accounting period Use estimated costs and denominator volume
• Use this rate to apply overhead to individual jobs Overhead applied to Job N = driver units in job N * pre-
determined rate Normal costing
• Triggers end of period adjustments
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
17
• Suppose: Predetermined variable overhead rate = $0.30 per
direct labor dollar. Predetermined fixed overhead rate = $1.20 per
direct labor dollar.
Overhead Costs: Magna
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
18
Analyzing WIP Accounts
We get the data for individual amounts for materials, labor and overhead for each job from the prior analyses
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
19
Flow Through the WIP Account
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
20
Flow Through The FG Account: COGS
LO3: Apply overhead to jobs using predetermined LO3: Apply overhead to jobs using predetermined ratesrates
21
Under LIFO, all 2,200 units would be sold from December’s production. Thus, 2,200 x $68 = $149,600.
Under LIFO, all 2,200 units would be sold from December’s production. Thus, 2,200 x $68 = $149,600.
22
• Use of estimated rates means a difference between the inflows and outflows into the overhead control accountActual overhead = Amount of overhead costsApplied overhead = Allocate to products by a pre-determined rate
• We can charge out too much or too little. IF
• Generally,
End of Period Adjustments
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
Under or Over-applied
Overhead=
Actual Overhead
–Applied
Overhead
Actual Rate < Pre-determined Rate
Under-applied overhead
Actual Rate > Pre-determined Rate
Over-applied overhead
23
Calculations for Magna
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
Actual fixed overhead costs $76,582 (Given)
Applied fixed overhead cost $83,544 (120% of $69,620)
Overapplied fixed overhead $ 6,962
Check To See Why
Actual labor cost $69,620
Actual fixed overhead rate for the month
___________
Predetermined overhead rate $1.20 per labor $
Error in rate ___________
Error in rate × actual labor cost ___________
24
$78,582
$69,620
$1.10 / labor $
$83,544
$6,962 (over-applied)
$6,962
$0.10 higher
25
Disposition
• Three methods permitted Write off entire amount to COGS Prorate (i.e., allocate) among WIP, FG and
COGS accounts Re-compute the rates
• All three methods comply with GAAP All methods essentially allocate the
under- / over-applied overhead Differ in the accounts charged for the error
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
26
$4,623,800
11
Add under-applied overhead and subtract overapplied overhead to determine the adjusted COGS as $4,629,450.
11
$4,629,450
27
Disposition: Comparison
• Write off is least correct Assumes entire error relates to COGS
• Proration is better Assumes error is proportional to end of period value Should be proportion to current period overhead in the
account
• Correcting rates is most accurate
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
WIP Inventory
FG Inventory
COGS
Write off to COGS X
Proration (allocation) X X X
Actual rates (assignment) X X X
28
Which Method To Use?
• Write off to COGS is the easiest method. OK if amount is not large Easy to implement. Most inaccurate.
• Proration (i.e., allocating among) is common. Uses of end of year balances as the basis Most commonly used
• Re-computing rates is most accurate. Easy if system is computerized
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
29
Examples• If overhead is under-applied, we have used “smaller than
actual” rates. Thus, inventory accounts are under-valued. The adjustment therefore increases inventory values and cost of goods sold. Opposite reasoning of over-applied overhead. The adjustment
decreases inventory values and COGS.
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
Unadjusted cost of goods sold (Jan-Nov) $4,245,000
Cost of goods sold 378,000
Total unadjusted cost of goods sold $4,263,800
- Over-applied variable overhead for the year 25,689
+ Under-applied fixed overhead for the year 15,963
= Adjusted cost of goods sold $4,614,074
30
Example: Proration• Proration allocates the under- or over-applied
overhead to WIP, FG and COGS accounts
• Uses end of year balances as the allocation basis
LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead. LO4: Perform end-of-period adjustments for disposing of under- or overapplied overhead.
WIP Inventory
FG Inventory
COGS
Unadjusted balance as of 12/31 $21,000.00 $285,500.00 $4,623,600.00
% of total 0.4% 5.8% 93.8%
Unadjusted balance as of 12/31 $21,000.00 $285,500.00 $4,623,600.00
- Over-applied variable overhead 1,014.42 1,487.58 24,092.00
+ Under-applied fixed overhead 67.99 924.37 14,970.63
= Adjusted values $20,958.57 $284,936.79 $4,614,648.63
31
Basic job costing (LO2) Tubbs and Company manufactures custom motorcycles. Tubbs uses a job-cost system and provides the following information related to the work-in-process account for the month of January:
Required:Determine the cost of goods manufactured during January.
Exercise 14.26
January 1 balance $22,500
Direct material used 25,000
Direct labor incurred 24,000
Manufacturing overhead applied 36,000
Tubbs applies manufacturing overhead based on direct labor cost. Job No. 232 was the only job still in process at the end of January. As of January 31, this job, which was started in January, contains direct materials of $4,250 and direct labor of $2,500.
32
Exercise 14.26 (Continued)Determine the cost of goods manufactured during January.
We can use the inventory equation for the WIP account to answer the question.
Beginning WIP + (materials + labor + applied overhead) = COGM + Ending WIP.
We know the items on the left hand side. But, we need to calculate Ending WIP, which will be the costs charged to job 232.
We can use the inventory equation for the WIP account to answer the question.
Beginning WIP + (materials + labor + applied overhead) = COGM + Ending WIP.
We know the items on the left hand side. But, we need to calculate Ending WIP, which will be the costs charged to job 232.
Direct materials $4,250
Direct labor $2,500
Mfg. overhead $3,750 $2,500 × $1.50 per labor $
Ending WIP $10,500
33
Exercise 14.26 (Concluded)Determine the cost of goods manufactured during January.
Direct materials $4,250
Direct labor $2,500
Mfg. overhead $3,750 $2,500 × $1.50 per labor $
Ending WIP $10,500
(We use the total amounts charged to WIP to calculate the overhead rate as $36,000 applied overhead /$24,000 labor $ = $1.50 per labor
dollar.)
(We use the total amounts charged to WIP to calculate the overhead rate as $36,000 applied overhead /$24,000 labor $ = $1.50 per labor
dollar.)
Thus, we have:
COGM = $22,500 + (25,000+24,000 + 36,000) - $10,500 = $97,000.
Thus, we have:
COGM = $22,500 + (25,000+24,000 + 36,000) - $10,500 = $97,000.