Monica Macedon 1 4/12/2023
DEVELOPMENT PROCESS AND PROJECT INTEGRATION MANAGEMENT
Human Resources Management System Project
Master of Science in Information Technology
TS5990 – Integrative Project
Capella University
Prepared by
Monica Macedon
Presented to
Instructor - Professor Sharon Gagnon
November 26, 2005
Monica Macedon 2 4/12/2023
Contents
Page
Abstract 3
Purpose 4
PROJECT MANAGEMENT 6
Project Scope 6
Project Plan 7
PROJECT COMMUNICATION MANAGEMENT 8
Human Resource Communication 8
PROJECT CONTROLLING 8
Integrated Change Control 8
PROJECT COST MANAGEMENT 9
Costs and Benefits 9
PROJECT QUALITY MANAGEMENT 10
Quality Control 10
PROJECT RISK MANAGEMENT 10
Project Risk Plan 10
PROJECT EXECUTION 10
Executing Processes 10
SYSTEM IMPLEMENTATION 48
Integration Plan 48
Conversion Plan 48
Monica Macedon 3 4/12/2023
APPENDICES
Appendix A: Eastern Carolina Vocational Center Business Statement 14
Appendix B: Project Charter 16
Appendix C: Scope Statement 19
Appendix D: HRMS Work Breakdown Structure 21
Appendix E: Stakeholder Communication Analysis 23
Appendix F: Status Report 25
Appendix G: HRMS Cost Estimates 26
Appendix H: Risk Management Plan 28
Appendix I: Business Requirement Use Case 29
Systems Analysis Use Case 30
Appendix J: Benefits Use Case 32
Business Activity Use Case 33
Appendix K: Organizational Structured Web Site 34
Appendix L: Network Architecture 35
Appendix M: Test Plan 36
Illustrations
Table 1. Control Change Plan … ………………………………… ………………….. 21
Table 2. Table 2. Risk Management Plan Matrix ………………………………………26
Figure 1 “Select Benefits” Use Case ……………………………………………………27
Figure 2 “Maintain Benefits” Use Case …………………………………………………27
Figure 3. Benefits Use Case Diagram …………………………………………………...31
Figure 4. Business Activity Diagram ..…………………………………………………..32
Monica Macedon 4 4/12/2023
Figure 5. Information Architecture Diagram 33
Figure 6. Network Architecture Diagram 35
Conclusion 50
References 51
Monica Macedon 5 4/12/2023
Abstract
This report outlines an integrative management process for the Human Resource
Management System Project. Managing this information technology project will provide an
automated benefits enrollment process with immediate information; conducting Human
Resource Management process through decision-making; coordinating the project plan; and
guiding the project execution and project control. Including several types of testing
documentations and testing strategies are introduced in order to understand process issues and
careful project planning.
The purpose of my project is utilizing my learning skills and knowledge; incorporating
tools, techniques and software engineering; demonstrating the ability to apply the concepts of
project management practices, including my capabilities in successfully creating and managing
this project. Fulfilling the highest quality Human Resource Management Information System
and services to Eastern Carolina Vocational Center will enable benefits personnel and the
business community to spend time on serving the employees versus data entry in a cost-effective
manner.
Monica Macedon 6 4/12/2023
Project Management
Project Scope
In the initiation phase, a kick-off meeting is held to establish the project team, assign a
project manager, identify key stakeholders, view the scope statement, and develop a project
charter. According to Paula K. Martin (2001), “…project management technology is based on
team participation and control, empowerment and a focus on deliverables instead of activities”
(Usability, par.1).
The main results (deliverables) will keep the team focused on what are important – the
outputs. The team members are very interested in the starting point of planning and identifying
the business’ long-term objectives, resources, and policies. Their interest of better service, better
performance, more information, stronger controls, and reduced costs are important factors when
it comes to the level of complexity and risks. This is where experienced technology and
technical expertise are carefully managed by the team members, and we knew exactly what we
wanted and what the system will do. See appendix A for the deliverable business statement.
The scope of the HRMS project is to analyze current and future state of the benefit process that
will bring out any process change requirements and impact to the system design, and
development.
Once all key stakeholders and the project manager agree to the project scope, a Project
Charter is created. This document recognizes the existence of a project and provides duration on
the project’s objectives and management. The project deliverable is a project charter that is
reviewed and signed by the project team members. See Appendix B for the HRMS Project
Charter.
Monica Macedon 7 4/12/2023
Project Plan
The development of the team’s project plan documents all coordinating project activities,
resources, project execution, and project control. According to Tom Mochal (2003), “The work
plan is a vital tool for ensuring that the project manager and project team know what they need to
do to complete the project” (Usability, par. 2). Common mistakes of failed projects result from
poor management practices and not updating the project plan on a regular basis. This realistic
and useful project plan establishes the initial scope in this second-key process phase, which
includes inputs from all team members. The project deliverable is an agreed-on Scope
Statement. See Appendix C for the HRMS Scope Statement.
Once the project team establishes the scope plan, a project schedule is created and further
work is broken down into manageable pieces called a definition scope. This process improves
accuracy of time, cost, and resource estimates, base-lined for performance measurement, and
project control. Use of Microsoft Project 2003 ensures timely completion of the project, which
involves specific activities, activity sequencing, activity duration, schedule development, and
schedule control, which improves the project’s performance. This useful tool defines the total
scope of the project, organizes and divides the work into logical parts based on how each work
will be performed.
Total involvement and commitment from all project team members can keep the schedule
on time and using the Gantt Chart for the actual scheduled progress lists the project activities and
their corresponded start and finished dates can produce a successful project. The project high-
level deliverable is a Work Breakdown Structure (WBS) Document. See Appendix D for the
total scope of the project’s HRMS WBS.
Monica Macedon 8 4/12/2023
PROJECT COMMUNICATION MANAGEMENT
Human Resource Communication
In order to understand politics of the business and know how to use them in the project,
people resources are identified for each task in the form of roles. This process is concerned with
making effective use of the team members involved in the project that includes organizational
planning, staff acquisition, and team development. Communication is the lifeblood for a
business, and effective communication improves a business’ productivity, image, and
responsiveness.
It is important for the project manager to understand each team member’s preference for
communications and that listening is an important aspect of communications. Communication
needs should include “Sensitivity and Culture; Trust and Respect; and Accurate and Clear” when
building a strong relationship among project team members. The HRMS project team develops a
communication plan that includes communication planning, information distribution,
performance reporting, and administrative closure to coordinate the work flow. This plan will
guide the project team’s communication, which includes methods for obtaining information. The
deliverable is a Stakeholder Analysis. See Appendix E for the Stakeholder Communication
Analysis.
Project Controlling
Integrated Change Control
Continuous monitoring and reporting the project’s progress through emails, meetings,
and status reports that are honest, and accurate, create consistency with the business project
planning strategy. The project change control plan includes – cost control, quality control, risk
Monica Macedon 9 4/12/2023
monitoring and control, and schedule control to review necessary changes in the project
development.
A best-practice document is created that will assist the project team in implementing a
successful configuration management plan. See Appendix F, example of Status Report for
performance reporting of how the resources are used, and the Control Change Plan table.
PROJECT COST MANAGEMENT
Costs and Benefits
The project will be completed within the approved budget. Sunil Sharma (2002) states,
“…considering all aspects of the business touched by the IT system…conduct an analysis to
reveal all hidden costs and put a price tag on all intangible and strategic benefits” (Usability,
par.1). Utilizing a computerized tool, Microsoft Excel helps to reduce and control cost in order
to complete the project within the budget and constraints. The project deliverable is the
estimated costs and benefits analysis. See Appendix G for the HRMS Cost Estimate proposed
system solution and supporting details. Below is a list of tangible and intangible benefits the
system will provide:
Tangible Benefits
Automated processing – Internet-based electronic enrollment and benefit
management system, and reduced paper-based process
Reduced administrative costs and improved information access
Efficient transaction processed with fewer errors and lowered employee benefits rate
Respond quickly to changes by establishing new business rules.
Monica Macedon 10 4/12/2023
Intangible Benefits
Improved employee morale and efficient employee self-service functionality.
Flexible security and management reporting, better decision-making & easy to learn
and use.
PROJECT QUALITY MANAGEMENT
Quality Control
The project manager and project team begin with a culture that recognizes everyone in
the business is responsible for quality and each is committed to continuous process improvement.
The HRMS project quality plan includes identifying quality standards that are relevant to the
project; incorporating quality standards into the project design; and periodically evaluating
overall project performance (Schwalbe, Kathy 2004).
PROJECT RISK MANAGEMENT
Project Risk Plan
The project team will decide how to approach and plan the risk management activities for
the project by reviewing the project charter, WBS, roles and responsibilities, and the business’
risk management policies. The project team will ensure that the risk awareness will be an
ongoing activity throughout the project life cycle. See Appendix H for the Project Risk
Management Plan.
PROJECT EXECUTION
Executing Processes
With a supportive and organizational culture, strong leadership skills, useful guidelines and
templates, the project team’s expertise skills can incorporate a good relationship in order to
Monica Macedon 11 4/12/2023
execute the project successfully. The desired work plan will help the project team to monitor
and measure the project’s performance efficiently.
Below are the steps and deliverable output processes to execute the project plan:
1. Analyze problems, users/business’ needs and tasks – the Project Manager and
Systems Analyst will create use cases that will describe the system functions in terms
of inputs, outputs, processes, and stored data that are acceptable to the stakeholders.
Including characteristics and constraints that are defined and may restrict the
development project. See Appendix I for the Business Requirements Use Case and
Systems Analysis Use Case.
2. Identify in-house solution for the new system – a system proposal is produced that
will fulfill business requirements identified in the Business Statement (Appendix A).
From the Project Manager, Systems Analyst, and the Chief Financial Officer’
analysis, technically, the solution will be practical; operationally, the solution will
fulfill the users’ requirements; economically, the solution is cost-effective; and can
be designed and implemented within the acceptable time period.
3. Design the system – the approach is to facilitate usage-centered development in
modeling the system requirements. The Systems Analyst and IT team will create a
use case and activity diagrams using Poseidon UML and Visual Paradigm tools to
determine what the system is required to do from the user and stakeholder
perspective. This Tool will capture functional requirements, provide functional
specifications for designing user and system interfaces, and provide a baseline for
test plans and test cases. See Appendix J for the Benefits Use Case and Activity Use
Case diagrams.
Monica Macedon 12 4/12/2023
4. Design Application Architecture – the Systems Analyst and System Designer will
design the information architecture in a site outline that will be used to guide the
development of the site. The design work will be based on the site requirements,
content, and user testing. See Appendix K for the Organizational Structured Web
Site.
5. Design Database – the System Designer, Database Administrator, and Systems
Analyst will develop the database design specifications for the in-house software. A
Data Flow Diagram (DFD) will be created and used as a system design tool and
serves as a blueprint for system construction and implementation. See Appendix L
for the physical data flow of the Network Architecture Diagram.
6. Web Interface – the System Designer and Database Administrator will create input
designs of Web pages using Macromedia Dreamweaver MX. Usability and
accessibility will be incorporated to establish a well-structured site, as well as
performing user testing. The live site will be presented in the next step of the testing
process.
7. Testing – the testing team will create a test plan that will record the business
transactions in terms of data entry and program documentation created for testing
data. See Appendix M for a detailed description of the Test Plan. The test cycle will
provide business requirements to be implemented by the programs and the project
team will assume overall responsibilities for the program design strategy, standards,
and construction:
Unit test – identify system outputs and review logical requirements. Output
designs (web pages) that are simple to read and easy to interpret. Ensure
Monica Macedon 13 4/12/2023
input controls are entered accurately and protected against intentional errors
and abuse. Input designs (web pages) with effective navigation controls for
user review and testing. This test will be driven by the human engineering
concerns that will support the ways in which the system users work. For
security considerations, system users will be authenticated and established to
perform certain actions and access privileges.
Integration testing – Integrate output and input designs that will establish the
dialogue between the user and the computer. Web-based user interfaces
(forms) will blend well into the user’s workplace environment where the user
can test these forms to see if they work or not.
System testing – The integrated set of programs will run through tests to
make sure one program is properly accepted as inputs and outputs of other
programs. Ensuring that the application programs written and tested work
properly when they are integrated into the total system.
User acceptance testing – System users will experiment and test the interface
design before extensive programming and actual implementation begins.
Providing the opportunity to perform testing in accepting or rejecting the
system.
Monica Macedon 14 4/12/2023
Appendix A Eastern Carolina Vocational Center Business Statement
Redesigning of the benefits process will increase employee self-service
functionality and efficient employee enrollment process. Immediate confirmations and
processing of information increase greater accuracy with fewer problems. Greater
integration with the company’s HR System and the Business Information System will
allow for real time processing and consolidation into one database. Simplifies audits and
reconciliation processes, which enhances timeliness.
Summary and discussion of facts and details
The system must be designed to comply with business’ entities, process
requirements, and policy rules. Integrating a comprehensive business solution will allow
the business to use current technology to significantly expand system functionality and
dramatically increase in value. Eastern Carolina Vocational Center’s current business
processes:
1. Employee completes paper form for multiple benefit plans;
2. Submits applications to HR;
3. HR reviews forms, then photo copies forms for employee file;
4. Sends paperwork to payroll for premium deductions;
5. Payroll reviews forms and calculates deductions amount;
6. Reconciles and mails payment to insurance carrier; and
7. Distributions of deduction reports, edit reports, and mismatch statement.
ECVC’s current systems have a series of fragmented HR/Payroll business
processes that either don’t interact with one another or that require extensive manual
effort to connect. The current process is frustrating and problematic when employees
Monica Macedon 15 4/12/2023
with families have to file manual paperwork for family/dependent/beneficiary data.
There is also resulting lag time in submitting the information to the carrier. Notification
of employee/retiree status changes are not adjusted or updated on a timely basis.
Methods Standards and Procedures:
Incorporate Project Management best practices
Software Technology (development environment- HTML, ASP JavaScript, ASP
VBScript & CGI Script)
Interface Technology (Macromedia Dreamweaver MX 2004)
Manage requirements
Use component-based architecture (database engine-VLESQL Server, platform-
Windows XP, Open Database Connection with Microsoft Access)
Visually model software and verify software quality
Monitor and control progress/changes to software
Progress reporting – every week, consistent with business project planning
strategy
Scope analysis – documentation changes
Schedule analysis – create project timeline processes and activities
Final conclusion
The benefits process redesign should be accomplished in a way that enhances a
smooth transaction for the employees and minimizes any negative results for the end-
users of this system.
Monica Macedon 16 4/12/2023
Appendix B Project Charter
Project Title: Project Management HRMS Project
Project Start Date: October 11, 2005
Projected Finish Date: December 18, 2005
Project Manager: Monica Macedon, 252-341-7763, [email protected]
Budget Information:
Project Justification: Dan LeRoux, President of Eastern Carolina Vocational
Center Inc. requested this project to support the business strategic goals. Redesigning of
the Human Resource Management System will give employees self-service access via
Web for enrollment, company information, and links to third-party Websites with
benefits-related information. It will also perform accurate data transaction and electronic
transmission to insurance carriers, while improving overall processes and results in better
service to the employees, as well as increase web-based self-service usage by 50%.
The budget for this project is $144,575. An additional $11,255 will be required
for operational expenses after the project is completed. Estimated benefits are $200,000
each year. It is important to focus on the system paying for itself within one year.
Project Objectives:
Develop a web-based self-service as the primary method for employees to
transact their benefit updates and allow an alternative method, such as gatekeeper
authority to reduce internal processes, and overcome management information issues.
The HRMS project will provide an online enrollment site that will add the ability to track
dates/actions used to manage benefit enrollments. Examples, an electronic notification
via one-way workflow, a 31 day window for new hire to enroll in benefit plans, and
Monica Macedon 17 4/12/2023
automate price and premium deductions. Provide a communication and connectivity
platform that will supply benefit choices and information to employees. Example, an
employer-branded Website that educates employees about their benefit options, view
plan information, selects and makes changes to benefits.
Approach:
Analysis approach to collect information on processing requirements (interviews).
Identification of sensitive information and an outline of steps to take for data
protection.
Analyze software for in house-development that both fulfill requirements and will
be user friendly to its end users. Prepare technical design specifications for a
database such as inputs, outputs, and interface dialogues that are adaptable for
future requirements and expansion.
Provide direct connectivity with carriers, as well as with HR/Payroll system that
allows the end-users to manage enrollment.
Lower employee benefits rate to be more cost effective.
Design the system to comply with business entities, process requirements, and
policy rules.
Provide online training and administrative support.
Roles and Responsibilities
Role Name Organization/Position Contact Information
Sponsor Dan LeRoux ECVC, President [email protected]
Project Manager Monica Macedon ECVC, Project Manager [email protected]
Team Member John Salisbury ECVC, Human Resource Manager [email protected]
Monica Macedon 18 4/12/2023
Team Member Beth Davis ECVC, Chief Financial Officer Business Department
Team Member Charles Buck ECVC, System Designer IT Department
Team Member Ellen Jackson ECVC, Database Administrator [email protected]
Team Member Doug Bonds ECVC, Quality Manager [email protected]
Team Member Crystal Talmadge ECVC, Systems Analyst [email protected]
Team Member Tina Wainwright ECVC, Payroll Department [email protected]
Sign-off:Dan LeRoux John Salisbury Charles Buck Doug Bonds Crystal TalmadgeMonica Macedon Beth Davis Ellen Jackson Tina Wainwright
Monica Macedon 19 4/12/2023
Appendix C - Scope Statement
Project Title: Project Management HRMS Project
Date: October 10, 2005
Prepared by: Monica Macedon, Project Manager, (252) 341-7763 [email protected]
Project Justification: Dan LeRoux, CEO of Eastern Carolina Vocational Center Inc., requested
this project to support the business strategic goals. Some of the business’ current HR/Payroll
business practices are the outcome of seven years of modifications put in place to satisfy related
business processes and particular needs. Redesigning of the HRMS will give employees self-
service access via Web for enrollment, company information, and links to third-party Websites with
benefits-related information. The system will stream-line the current business processes, improves
efficiency, reduce costs, and maximize returns with the use of project management knowledge,
templates, tools, and techniques to the company’s work force.
Product-related deliverables:
1. Business use case – will identify and describe the necessary system processes from the
users’ perspective.
2. Application design – prepares a technical design specification for a database that will be
adaptable for future requirements and expansion.
3. User interface design – develops inputs, outputs, and dialogue specifications that is easy to
learn and easy to use for the new system.
4. System modeling – develops an Intranet-based computing architecture that will integrate the
business processes and HR/Payroll databases into a single cohesive framework.
5. Scope statement – defines the boundaries of the project, work to be performed and
agreed-on between, stakeholders, project manager, and project team.
6. System improvement objectives – identify, analyze, and recommend a candidate solution
for in-house software
7. Business requirements statement – defines and prioritizes business and users’ requirements.
8. System proposal – analyzes candidate solutions for software
9. Application architecture – defines the system’s design process.
10. Database structure – designs and constructs database schema and database program
Monica Macedon 20 4/12/2023
11.Operational System – prepares conversion plan .
Assumptions:
Operational feasibility – the system will require training for users.
Technical feasibility – the system will be able to handle projected growth of the business in
the future.
Economic feasibility – stream-lining the current business processes will improve efficiency
and reduce costs.
Constraints:
Budget Constraints
The system cannot cost more than $160,000.
The system must be able to attain a 50% improvement level.
Technology Constraints
The system must provide employee self-services
The system must coordinate HR/Payroll implementation with insurance carriers’ system.
The system must automatically update changes and calculate deductions based on
insurance carriers criteria.
The system must enable HR/Payroll administrators to track past, current, and pending
employee benefit file.
Monica Macedon 21 4/12/2023
Appendix D HRMS Work Breakdown StructureTBD Below is a generic WBS in Excel Spreadsheet form. The original WBS will be created in Microsoft Project 2003 and be implemented in the Final Draft.
Monica Macedon 22 4/12/2023
Appendix E Stakeholder Communication Analysis
Monica Macedon 23 4/12/2023
StakeholdersAccountability
Document Name/Delivery
DocumentFormat
Objectives Frequency Permission
Access
Sponsor System Improvement Report
(Repository)DatabaseDirectory
To review expectations for the new system.
Bi-Monthly read, write, make changes
PM, HRM, BM, IT, DBA, QM, SA, ADV
Sponsor Team Progress Report
E-mail To express support and appreciation of the project team’s accomplishments.
Bi-Monthly PM, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Project Status Report
(Repository)DatabaseDirectory
To review successes, constraints and progresses.
Bi-weekly read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Project Charter (Repository)DatabaseDirectory
To review work being performed during the final project development.
As needed read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Project Schedule (Repository)DatabaseDirectory
To review outlined activities and tasks for the planned project.
Monthly read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
System ProposalReport
Hard copy Evaluate recommended system solution and feasibility assessment.
As needed SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Risk Management Plan
(Repository)DatabaseDirectory
To evaluate and control what might go wrong in the final project before it becomes a threat.
As needed read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Change Control Log
(Repository)DatabaseDirectory
To review and managed appropriate changes throughout the final project.
As needed read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Implementation Plan
(Repository)DatabaseDirectory
To review and ensure that the installed system software meets user requirements and expectation.
As needed read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Conversion Plan (Repository)DatabaseDirectory
To review the strategy and smooth transition of converting from the old system to the new system.
As needed read, write, make changes
SP, HRM, BM, IT, DBA, QM, SA, ADV
Project Manager
Team Meeting E-mail To provide the opportunity to develop ideas and collaborate on the final project.
Bi-weekly SP, HRM, BM, IT, DBA, QM, SA, ADV
HR Manager Staff Acquisition Plan
(Repository)DatabaseDirectory
View the needs of each team members’ tasks and work hours.
As needed SP, PM, BM, IT, DBA, QM, SA, ADV
Monica Macedon 24 4/12/2023
HR Manager Team DevelopmentPlan
(Repository)DatabaseDirectory
To review team members’ productivity and create an environment for growth and prosperity.
As needed read, write, make changes
SP, PM, BM, IT, DBA, QM, SA, ADV
Business Manager
CommunicationPlan
Email Provide appropriate and consistent levels of information to all stakeholders
Weekly read, write, make changes
SP, PM, HRM, IT, DBA, QM, SA, ADV
IT Design Statement (Repository)DatabaseDirectory
Serves as a blueprint for the detailed design system.
As needed read, write, make changes
SP, PM, HRM, CFO, DBA, QM, SA, ADV
IT Process/Logical Models
(Repository)DatabaseDirectory
To review system models and business processing requirements.
As needed read, write, make changes
SP, PM, HRM, CFO, DBA, QM, SA, ADV
Database Administrator
Database prototype (Repository)DatabaseDirectory
To review design specifications and requirements.
As needed read, write, make changes
SP, PM, HRM, CFO, IT, QM, SA, ADV
Database Administrator
Application Architecture
(Repository)DatabaseDirectory
To review internal and external design of each system components.
As needed read, write, make changes
SP, PM, HRM, CFO, DBA, QM, SA, ADV
Quality Manager
Quality Plan ISO Manual To evaluate and monitor the deliverables and overall project performance.
Periodically read, write, make changes
SP, PM, HRM, CFO, IT, DBA, SA, ADV
Quality Manager
Audit Test Plan (Repository)DatabaseDirectory
To certify that the system is free of errors and is ready to be placed into operation.
Periodically read, write, make changes
SP, PM, HRM, CFO, IT, DBA, SA, ADV
Systems Analyst
RequirementsStatement
(Repository)DatabaseDirectory
To review specified system requirements.
As needed read, write, make changes
SP, PM, HRM, CFO, IT, DBA, QM, ADV
Systems Analyst
Use Cases (Repository)DatabaseDirectory
To review system functions and graphical requirements of the business.
As needed read, write, make changes
SP, PM, HRM, CFO, IT, DBA, QM, ADV
Quality Manager
Test Plan (Repository)DatabaseDirectory
To review appropriate system testing and verify all requirements
Periodically Read, write, make changes
SP, PM, HRM, CFO, IT, DBA, QM, SA
Advisor Training Plan Manual To provide group training and properly guide
As needed SP, PM, HRM, CFO, IT, DBA, QM, SA
Key Access Role: SP – Sponsor PM – Project Manager HRM – HR Manager SA – Systems Analyst QM – Quality Manager CFO – Chief Financial Officer IT- Information Tech DBA – Database Administrator
Monica Macedon 25 4/12/2023
Appendix F Status Report
Project Name: Project Management HRMS projectTeam Member Name: Monica Macedon, [email protected]: November 1, 2005Work completed this week:Work to complete next week:What’s going well and why:What’s not going well and why:Suggestions/Issues:Project changes
Appendix F Control Change Plan
Process Topic Item Manage
Cost Control Project Cost Management
Cost estimating, cost budgeting
Measure, monitor, and control overall cost performance. Documentation of any constraints.
Quality Control Quality Management Plan
Quality assurance, Quality checklistsQuality Metrics
Determine correctness of deliverables. Recommended corrective actions. Documentation of lesson learned.
Risk Monitoring and Control
Project Risk Management
Risk IdentificationQualitative Risk AnalysisRisk response planning
Documentation reviews. List of identified risks and root causes. Update risk register.
Schedule Control Project Time Management
Schedule development. Activity definition and activity sequencing.
Identifying and documenting logical relationships among schedule activities. Periodic Progress reporting.
Table 1. Control Change Plan
Monica Macedon 26 4/12/2023
Appendix G HMRS Cost Estimates
HRMS Project Estimated Cost for a Proposed System Solution and supporting detailsEstimated Costs for Proposed Systems Solution
DEVELOPMENT COSTS:
Personnel:
1 Project Manager(418 hours/ea $65.00/hr) $ 27,170.00
1 Sponsor(198 hours/ea $50.00/hr) $ 9,900.00
1 Quality Manager(110 hours/ea $50.00/hr) $ 5,500.00
1 Business Manager (98 hours/ea $50.00/hr) $ 4,900.00 1 HR Manager (84 hours/ea $50.00/hr) $ 4,200.00
1 IT Tech(252 hours/ea $40.00/hr) $ 10,080.00
1 Systems Analyst(322 hours/ea $50.00/hr) $ 16,100.00
1 DB Administrator(218 hours/ea $40.00/hr) $ 8,720.00
1 Payroll Advisor (156 hours/ea $30.00/hr) $ 4,680.00
Total $ 91,250.00
Expenses:6 Group training for system users ($995.00/student) $ 5,970.00
Total $ 5,970.00
New software & hardware:1 MS SQL Server DBMS $ 3,000.00 1 HRMS software application $ 4,000.00 1 Intranet/Intranet Client/Server $ 19,000.00 1 DBMS server software $ 4,500.00 7 DBMS client software ($800.00 per client) $ 5,600.00
Total $ 36,100.00
Total Development Costs: $ 133,320.00
Projected Annual Operating Costs
Personnel:
Monica Macedon 27 4/12/2023
2 Programmer/Analyst(125 hours/ea $35.00/hr) $ 8,750.00
1 Database administrator (30 hours/ea $20.00/hr) $ 600.00 Total $ 9,350.00
Expenses:
1Program/System Maintenance Fee $ 995.00
1Maintenance Agreement for Server DBMS server $ 385.00
1 Software license payments $ 525.00 $ 1,905.00
Total Projected Annual Costs: $ 11,255.00
Monica Macedon 28 4/12/2023
Appendix H Risk Management Plan
Knowledge Area/Category
Risk Identification Severity Probability Mitigation Strategies
Project Initiation Schedule Commitment - needto identify adequate resources to allocate to the scheduled tasks at the scheduled time.
High Medium Produce a more detailed plan to identify stakeholders at the start and establish the procedures that will be used by the project stakeholders.
Project Planning Scope
Business Strategic Objectives – cannot start project planning until a business plan is develop.
High Medium Conduct an analysis study and develop a plan to address risk to stakeholders and the project team.
Project Cost Management
Budge and Costs – cost overrun of project funding likely to occur.
High Low Monitor project approved expenditures and report status of budget on a monthly basis.Actual or potential problems need to be communicated to Executive Steering Committee for immediate resolution.
Project Risk Management
Project Management Ability and Expertise – cannot implement risk plan without appropriate management and technical risk assessment.
High Medium Adequate risk assessment practice. Develop a procedure document on Risk Identification, Qualitative Risk Analysis, Risk Response Planning, and Security Planning.
Project Scope Management
Change Organizational Structure and Focus – misalignment of work, policies, and procedures will affect the business strategy and goal.
High Medium Establish a preliminary or baseline scope during the initial project plan. Educate stakeholders about effects of changes. Adopt a formal change management plan.Develop a contingency plan.
Project Quality Management
Product Performance Requirements – failure or non-conformance is likely to result in design problems/functions.
High Medium Develop explicit rules that must address the business requirements. Prioritize requirements
Cost Estimation Economic Conditions – new software technology.
Moderate Low Develop an economic analysis and forecasting plan.
Process Management Development Process/Tools – poor quality software will exceed schedule and budget.
High Low Integrate agile methodologies and tools that will support in-house software solution.
Project Management Technical Approach – functionality of the system must be optimized to fit the business
High Low Follow a system philosophy to understand how the final project relates to the business.Continuously reevaluate feasibility and risks through out the final project.
Project CommunicationManagement
Stakeholders Needs – misinformation, stress tension, and lack of accountability can create low performance level and time wasted.
High Medium Create a communication plan Establish a community portal (Intranet) to open lines of communication. Interpersonal, effective communication, and
Monica Macedon 29 4/12/2023
listening skills. Table 2. Risk Management Plan MatrixAppendix I Business Requirement Use Case
{Employee Self Services System}
Author (s): Monica Macedon_ Date: October 28, 2004 Version:1.0__________
USE CASE NAME: Select Benefits USE CASE TYPEUSE CASE ID: BEP BUC00-1.0 Business Requirements:
PRIORITY: HighSOURCE: Requirement – BPE-R1.00PRIMARY BUSINESS ACTOR:
Employee
OTHER PARTICIPATING ACTORS:
Human Resources Payroll Department Insurance Carriers
OTHER INTERESTED STAKEHOLDERS:
Business/Financial Management – Interested in enrollment activity in order to manage the company’s financial resources.
Insurance Carriers – Interested in enrollment activity in order to collect premiums.
Board of Directors – Interested in benefits activity in order to evaluate company performance and employee satisfaction
DESCRIPTION: This use case describes the event of the employee making online benefits enrollment selections and receiving confirmation directly from Eastern Carolina Vocational Center’s web-based, self-service site. The employee’s enrollment data is a validated accordingly to the business rules and imported to HR database. On completion, the employee will be sent a confirmation statement.
PRE-CONDITION: The employee submitting the benefits selection is subject to final employer authorization.
TRIGGER: This use case is initiated when benefits selection is submitted.TYPICAL COURSE Actor Action System ResponseOF EVENTS: Step 1: The employee
provides his or her network credentials (username and password).
Step 2: The system responds by validating all required information that has been provided by the user against the employee record in HR database.
. Step 3: Once authorized, the system asks the user to view, browse, and make selections. Step 4: If employee views current status, the system displays benefits package. Step 5: If the employee browses for choices, the system presents available benefits plans according to the user’s preferences.Step 6: If employee decides to make a selection that is finalized, the system presents a summary of the employee’s choices and costs.Step 7: Once the employee saves the choices, the system generates a confirmation
Monica Macedon 30 4/12/2023
statement and sends it to the employee by email.
ALTERNATE COURSES:
Alt-Step 2: If an employee does not enroll within the allotted time, the default level of coverage will be applied. Notifications to the employee will be generated.Alt-Sep 3: If changes are required due to major life events (birth, injury, etc.), the employee can review their benefits selection and make changes as required, throughout the year.
Alt-Step4: If missing or incorrect information, or requirements of rules that are overlooked, the system will automatically inform the employee to edit the information correctly.
Alt-Step 5: If the member requests additional assistance, the system answers simple employee questions regarding their benefits and helps the employee research physicians, access and completes forms, and contact agents and insurers.
CONCLUSION: This use case concludes when the employee receives a confirmation statement.
POST-CONDITION: The benefits selection has been transmitted to the HR database.BUSINESS RULES Confidentiality of employee benefits information, authentication,
authorization, access and data integrity are secured.IMPLEMENTATION CONTRAINTS AND SPECIFICATIONS
Web-based interface to be provided for Eastern Carolina Vocational Center’s users, and web screen to be provided for employees.
ASSUMPTIONS: The system should send e-mail reminders to those who haven't enrolled.
OPEN ISSUES: None
Figure 1 “Select Benefits” Use Case
Systems Analysis Use Case
{Employee Self Services System}
Author (s): Monica Macedon_ Date: October 28, 2004 Version: 1.0__________
USE CASE NAME: Maintain Benefits USE CASE TYPEUSE CASE ID: BPE BUC00 -1.0 Systems Analysis: PRIORITY: HighSOURCE: Requirement – BPE-R1.00PRIMARY BUSINESS ACTOR:
Human Resources
OTHER PARTICIPATING ACTORS:
Employees Payroll Department Insurance Carriers
OTHER INTERESTED STAKEHOLDERS:
Business/Financial Management – Interested in enrollment activity in order to manage the company’s financial resources.
Board of Directors – Interested in benefits activity in order to evaluate company performance and employee satisfaction
Insurance Carriers – Interested in enrollment activity in order to collect premiums.
Monica Macedon 31 4/12/2023
DESCRIPTION: This use case describes the event of Human Resources processing a benefits package for the employee. The employee’s benefits information is extracted from HR database and views the validated employee’s benefits statement. Once the benefits package is approved, a report is created and transmitted to the Payroll database.
PRE-CONDITION: The HR associate must be provided with a complete list of required administrative tasks.
TRIGGER: This use case is initiated when the benefits package is processed.TYPICAL COURSE Actor Action System ResponseOF EVENTS: Step 1: HR associate extracts
employee demographic data from the Benefits Enrollment database.
Step 2: The system responds by returning the electronic data into HRIS.
Step 3: The HR associate imports the data into a spreadsheet report.
Step 3: The system displays the employee’s benefits and costs summary.
Step 4: The HR associate views the benefits package. If no changes are made, the associate approves and saves the data.
Step 5: The system retrieves and process the data, then uploads the information into the Payroll database.
ALTERNATE COURSES: Alt-Step 6: If the benefits package requires changes, the HR associate can place the benefits package on hold (the associate contacts the employee, either by a valid e-mail or in person). The system place the information in pending status. Once the employee is contacted and changes are made, the system reprocesses the package (go to step 5). Alt-Sep 3: If the HR associate needs assistance, the system’s authoring tools provide guidance through a series of questions to gather and manage data and policy changes.
CONCLUSION: This use case concludes when HR completes and/or updates the benefits package.
POST-CONDITION: The benefits package has been uploaded to the Payroll database.BUSINESS RULES Data is defined by the business’ benefits offering of eligibility and premiums.
Event code-driven that corresponds to data requirements are generated when a given event code is used.
IMPLEMENTATION CONTRAINTS AND SPECIFICATIONS
Provide the logic, calculations and data to define a business’ benefits offerings in order to verify eligibility and premiums.
Provide employees self-service access to their benefits. Provide data connectivity and synchronization to insurance providers, HR,
information systems, and payroll. Transmits data to HRIS and payroll system (for payroll deduction and data
synchronization), then to benefit providers via an EDI interface.ASSUMPTIONS: HR must be trained to update application, for example, change benefits level
(separate use case). Employees have online, year-around access to their own benefits, HR and
managers will become less involved in administering the employment lifecycle.
OPEN ISSUES: Need to determine how insurance carriers are communicated. The new application and process must be integrated with HR and payroll databases (Change Management Process). Integrates with this vendor’s systems for COBRA administration, HIPAA compliance, and retiree premium billing.
Figure 2 “Maintain Benefits” Use Case
Monica Macedon 32 4/12/2023
Appendix J Benefits Use Case
Figure 3. Benefits Use Case Diagram
Monica Macedon 33 4/12/2023
Appendix J Activity Diagram
Monica Macedon 34 4/12/2023
Figure 4. Activity DiagramAppendix K Organizational Structure Web Site
Monica Macedon 35 4/12/2023
Figure 5. Information ArchitectureAppendix L Network Architecture
ECVCHomepage
Personal DataManagement
Life/Health/Accidental Death Plan
Long TermDisability Plan
Medical/Dental/ Vision Plan
EnrollmentProcess
InformationCenter
CompanyInformation
SupportDesk Form
Gate Keeper
EnrollmentMenu
PrivacyStatement
Successful Login
InvalidLogin
Sign Out
Terms Of Use
OpenEnrollment
Short TermDisability Plan
Login Area 1
Thank You Confirmation
Update Personal Data Management Form
Update Enrollment Process Form
Eastern Carolina Vocational Center,
Inc.Secure Access
Monica Macedon 36 4/12/2023
Benefits InformationandService Response
Automatically Upload Files
Read requestedBenefits Selection
and eligibility
MailFiles
Communication Employee Data Exchange ECVC Data Exchange Carrier Data Exchange
Windows/Access2000
SQL/Serverexecuted here
Database
Retrieve Benefits Information Request
Request to create, read, update, or delete records Import Files
UpdatedBenefits
User
Web Browser
Web ServerHTML/JAVAWeb scripts
executed here
Client PCEnrollment
Internet Explorer and Netscape
HTML: Page Content andXML: Data Content
Benefits Information and Service Requests
Authentication
Employee Protected Login Area
Web Server
Simple Mail Transfer Protocol (SMTP)
File Transfer Protocol (FTP)Utility enables file transfer to and from the server
Enroll Access
Application logic executed here
Application Server
ESS Database stored here
WebPages
Figure 6. Network Computing System: Intranet/InternetLinking an internal database to the Web.
Monica Macedon 37 4/12/2023
Appendix M Test Plan
Purpose
This test plan is designed to describe the HRMS Project’s scope, approach, resources, and
schedule of all activities. The plan identifies the items to be tested, the features to be
tested, the types of testing to be performed, the personnel responsible for testing, the
resources and schedule required to complete the testing, security, and the risks associated
with the plan. This document will be used to test and validate functional and technical
requirements, which supports the following objectives:
Analyze users, needs, and tasks/determine test user groups:
Find problems with the information structure in order to improve it
Ensure integrity and availability of the database environment
Incorporate software engineering/AQ Assurance practices/standards
Determine usability/accessibility task goals
Measure qualitative and quantitative data
Schedule key dates for testing
Develop test cases/create scenarios
Prepare test documents/test environment software
Scope Definition
This document provides instruction and strategy for incorporating software testing
practices and procedures into the project. The scope of the project team’s work is
presented in a Work Breakdown Structure. Requirements specification (Business Use
Case), Design Specifications (Business Activity Diagram and Application Architecture
Structure) will be use to create test cases.
Monica Macedon 38 4/12/2023
Test Goals
Test all modifications, interfaces and data delivery developed for the
implementation
Test design specification and requirement specification
Validate all set up, Web pages (HTML), and security login
Determine errors, report errors for resolution prior to implementation
Features (availability, response time)
Validate Quality Conformance Report
Features Not To Be Tested
Entity Relationship Diagram/Data Integrity Rules – they will be addressed by the
existing Business Case and Activity processes.
Assumptions
The tools, resources, technical support, and infrastructure essential for testing will be
available through a successful implementation. Necessary project team members
(includes key departments) will assist in or resolve any problems discovered during
testing.
Risks
Shortage of testing personnel due to illness or understaffed. The contingency plan
is to train other team members to use testing tools and testing methodologies.
Not enough time to adequately test all processes before the implementation date.
The contingency plan is to prioritize testing efforts, testing critical and major
processes early in the schedule as soon as possible.
Monica Macedon 39 4/12/2023
Software Test Strategy
This approach describes in details the major testing tasks and identifies the types of
testing to be performed along with the methods, criteria, procedures, and software
environment requirements to be used in performing test activities.
Testing Roles and Responsibilities
This table presents the recommended resources for the HRMS Project, their main
responsibilities, and their knowledge or skill set.
Role/Worker Specific ResponsibilitiesTest Project Manager – Monica Provides technical direction, acquire
appropriate resources, and provide management reporting
Test Manager – Beth Provides management oversight and monitor testing process.
Test Designer(s) – Crystal, Monica Generates and document test case for functional and performance testingTest Web interfaces, input/output control modules
Test Designer - Crystal Evaluates effectiveness of test effortsProject Manager - MonicaTester - John Documents test results and problemsData Logger - Tina Observes and logs data metricsTest System Administrator - Charles Set-up and maintain software environmentTest Moderator- Monica Performs usability/accessibility testDatabase Administrator - Ellen Ensure test data (database) are managed and
maintainedSecurity Testing - Monica Test logon security and apply security rolesQA Management - Doug Quality assurance testing validating
individual components of softwareTechnical/Security Setup - Charles Provides technical support for testing toolsAcceptance testing - All workers Ensure user requirements and objectives are
met. Table 1. Roles and Responsibilities
Software Test Environment
Environmental requirements are described below to specify both the necessary
and desired properties for the test environment:
Monica Macedon 40 4/12/2023
Software items – Windows XP, Microsoft Navision Server, HTML, ASP
JavaScript, ASP VBScript & CGI Script, ESS Database, Open Database
Connection with Microsoft Access 2000
Interface item - Macromedia Dreamweaver MX 2004
Hardware items – Intel Pentium III Processor with 1GB of RAM and redundant
disk storage
Network - Three-tiered client/server
Communications – Web (Intranet/Internet), Employee Data Exchange, Business
Data Exchange, Carrier Data Exchange
Equipment items – one computer workstation with the full software, softer
lighting, and three seats: one for the participant, one for the test monitor, and one
for the observer (data logger)
Assistive Technology – if needed, can provide screen readers,
voice input, alternative keyboard or pointing device
Test lab set-up – located in business testing room
Other materials – test scripts and final testing report
Tools – Web guideline checklist, HTML authoring tool, SQL
Scripting tool, Web Design HTML Validator, W3C Validation
tool, data collection instruments
Staffing and training needs – training on the software, training for
any test tools to be used, provide onsite usability expert for users
with accessibility issues or problems.
Monica Macedon 41 4/12/2023
Schedule
The schedule is based on realistic and validated estimates, which ties all test dates
directly to their related development activity dates. This will help in identifying and
tracking potential slippage in the schedule caused by the test process. See Appendix A of
the developed timeline for the Execute Test development.
Testing Types
Each type of test provides a description and technique of the test and why it is being
implemented and executed.
Function Testing
The target of this test focuses on the requirements that are traced directly to the Business
use case and business rules. See Table 2, below for this testing.
Test Objective: Ensure proper test functionality of site navigation, data entry, form processing, and retrieval
Technique: Execute an input form using valid and invalid data to verify the following:
The expected results occurred when valid data is used (input form processed successfully) The appropriate error or warning messages are displayed when invalid data is used.Navigation provides a logical architecture to the information in the site. Consistent primary navigation (links to home page and other key content areas) on all pages.
Completion Criteria: All planned test executed and each business rules applied properlyAll identified defects been addressed (description of one target page inaccurate) Applied appropriate link description
Table 2. Function Testing
Data and Database Integrity Testing The target of this test focuses on the subsystem of the HRMS Project. See Table 3 on the
next page for this testing.
Monica Macedon 42 4/12/2023
Test Objective: Ensure database access methods and processes function properly and without data corruption.
Technique: Invoke SQL scripting for proper loading of all tables in the database through DSN connection to the database to check the following: Database has been populated as intended, including events of updating. Data validated properly. Correct data was retrieved for the correct reason
Completion Criteria: All database access methods and processes function as designed and without any data corruption. No defects addressed
Table 3. Data/Database Integrity Testing
User Interface Testing
The target of this test verifies a user’s interaction with the system. See Table 4, below for
this testing.
Test Objective: Verify the following:User Interface provides the user with the appropriate access methods (tab keys, mouse movements) and navigation Window objects and characteristics, such as menus, size, position, and focus conform to standards
Technique: Create or modify each window to verify proper navigation and object for each application window
Completion Criteria: Each window successfully verified to remain consistent within acceptable standards.
Table 4. User Interface Testing
Web Page Testing
The target of this test verifies each Web page document for HTML conformance. See
Table 5 below, for this testing.
Test Objective: Verify the following:test internal controls such as authorization to login, functional testing of command action buttons validate each Web page for syntax errors and undefined document type definitions
Technique: Tools used to test for valid HTML:
HTML authoring tool in Macromedia Dreamweaver MXWeb Design HTML Validator
Completion Criteria: Each Web page has been validated for HTML conformance.Table 5. Web Page Testing
Monica Macedon 43 4/12/2023
4.1 Security and Access Control TestingThis testing focuses on two key areas – Application-Level security and System-
Level Security. See Table 6 below, for this testing.
Test Objective: Application-level Security: Verify that a user can access onlythose functions or data for which their user type is providedpermissions.System-level Security: Verify that only those users with accessto the system and applications are permitted to access them.
Technique: Application-Level - Identify and list each user type and the functions or data each type has permissions for.System Access Level – see consideration below
Completion Criteria: Transaction permission for each data typed is verified correctly as available or denied access rights.
Consideration: Access to the system must be reviewed with the appropriate network or systems administrator. This testing may not be required as it may be a function of network or systems administration.
Table 6. Security and Access Control Testing
Usability/Accessibility Testing
Now that all functional testing has been completed, this testing focuses on the system
performance to measure the success rate for participants using the site to perform specific
tasks. See below for the Usability/Accessibility Testing Plan
Introduction
This document describes the usability/accessibility testing plan for
http://www.lc.capellauniversity.edu/~143714/SecureAccess.html. The purpose of a
usability evaluation is to predict the expected performance of the actual user using the
current product and materials, as well as detect any serious problems prior to the release
of the product. This plan includes the following sections:
User Testing Preparation Worksheet Task lists Testing scripts Design of the usability evaluation
Monica Macedon 44 4/12/2023
User Testing Preparation Worksheet
User Testing Project __ HRMS Project_________ ____________________________________ Scheduled Dates and Times _____________________________________________________Location: On-site testingTesters _____________________________________________________________________Observers ___________________________________________________________________Required demographic _________________________________________________________Number of test users 4__________________________________________________________Computer configuration(s): Hardware ___________________________________________________________________OS and version ______________________________________________________________Browser and version __________________________________________________________Other software ______________________________________________________________Other equipment: Stopwatch
Task listTo clarify the goals of this test, the testing script provides the exact wording for each of these:
Task 1. Speed, Design Structure Task 2. Main navigational elements (links, navbars) Task 3. Is site useful for disabled users?
Task 1 Description
TaskStarting StateSuccessful Completion CriteriaBenchmarkScript
Task 2 Description
TaskStarting StateSuccessful Completion CriteriaBenchmarkScript
Task 3 Description
TaskStarting StateSuccessful Completion CriteriaBenchmarkScript
Usability/Accessibility Evaluation Form
Monica Macedon 45 4/12/2023
Tester’s name_________________________
Task tested_____________________
User’s name__________________________
Design of the Usability/Accessibility Form
This evaluation is to ensure that the web site is on track to satisfy the goals of the design and the user.
Observe the user:
1. User preference setting.2. Does the user get frustrated/confused
while completing the task or a specific step?
3. Did the user complete the task successfully?
Accessibility of web site.Interview the user and analyze the data based on your observations and interview:
1. What is the biggest problem with the site?
2. Navigating the web.
3. Did the visual design and style help the user, or did they create problems? What problems? How can they be solved?
4. Download time and system performance time.
5. Error tolerant.
Make recommendations based on your analysis:
1.2.3.4.5.
Form 1. Usability/Accessibility Evaluation Form
Monica Macedon 46 4/12/2023
Web Usability and Accessibility Guide
1. Technical Features:Description Compliance
Yes No Partial1.1 Appropriate DOCTYPE tag at the top of each page, e.g. <!
DOCTYPE HTML PUBLIC “-//W3C//DTD HTML 4.0 Transitional//EN”>Appropriate use of KEYWORDS and DESCRIPTION meta tags.Compatibility with current Netscape and Microsoft IE browsers
1.2 Compatibility with current Netscape and Microsoft IE browsers
1.3 Appropriate html TITLE (in head section) for each page1.4 Appropriate use of KEYWORDS and DESCRIPTION meta tags1.5 Compatibility with current Netscape and Microsoft IE browsers
Results
1.6 Site Speed (seconds) 1st 2nd average
Home page download time with 56 kbps modem (two attempts)
1.7 Broken Links Total Broken % links links broken
1.8 Broken links on site
2. Essential Information:Description Compliance
Yes No Partial2.1 Clear identification of business on home page
2.2 Privacy and Terms Of Use easily available from all relevant pages
2.3 Feedback facility and/or email link to an appropriate person2.4 Human Resource contact information available from home
page2.5 Date of Last Update of information on pages
Usability Scoring Information
The N/A – the item described in the statement is not available at all;
1. Strongly Disagree – the statement DOES NOT apply to almost the entire site and/or
any pages of the site;
2. Disagree - The statement DOES NOT apply to most of the site and/or any pages of the
site (about 70%);
3. Neither Agree Nor Disagree – with the statement;
Monica Macedon 47 4/12/2023
4. Agree – The statement DOES apply to most of the site and/or any pages of the site
(about more than 70%);
5. Strongly Agree – The statement DOES apply to almost the entire site and/or any
pages of the site.
3. NavigationDescription N/A Strongly Disagree/
Strongly Agree1 2 3 4 5
3.1 The navigation features of the site are clear and easy to use.
3.2 The link labels and link names were clear and directed me to the correct information.
3.3 There is clear and consistent primary navigation (finding links to the home page and other key content are) on all pages.
3.4 The text used for links is descriptive, appropriate and useful.
4. Content:Description N/A Strongly Disagree/
Strongly Agree1 2 3 4 5
4.1 All information is accurate and requirements met.
4.2 The content is suitable and relevant to the purpose of the site.
4.3 The headings and subheadings are meaningful to the users of the site.
4.4 Key content is presented in languages appropriate to the users of the site.
5. Page layout and presentation:Description N/A Strongly Disagree/
Strongly Agree1 2 3 4 5
5.1 The site clearly identified the services and information available.
5.2 No errors in spelling, punctuation or grammar.
5.3 All images have an ALT tag describing the image and where it links.
5.4 Forms on the site contain sufficient information about their purpose and the form fields are easy to identify and fill in.
5.5 The page layout is uncluttered, clear and easy to follow.
5.6 Each page has appropriate heading or identifier that is consistent with the link label.
5.7 All content in tables are contained within the display screen area with a setting of 800x600 pixels.
6. Accessibility:
Monica Macedon 48 4/12/2023
Description N/A Strongly Disagree/Strongly Agree1 2 3 4 5
6.1 Alternative text provided for all image type buttons in forms.
6.2 No errors in spelling, punctuation or grammar.
6.3 All images have an ALT tag describing the image and where it links.
6.4 Forms on the site contain sufficient information about their purpose and the form fields are easy to identify and fill in.
6.5 The page layout is uncluttered, clear and easy to follow.
6.6 Each page has appropriate heading or identifier that is consistent with the link label.
6.7 Use of high contrast and highly legible fonts
Test Results TBD
Monica Macedon 49 4/12/2023
SYSTEM IMPLEMENTATION
Integration Plan
The purpose of the implementation is:
To define the organization of the code, in terms of implementation subsystems organized
in layers
To implement classes and objects in terms of components (source files, binaries, and
executables).
To test and develop components as units
To integrate the results produced by individual implementers (or teams), into an
executable system.
Workflow will be managed through the document approval and information copy process.
Integrated imaging must support the storage and retrieval of both systems generated and
manually prepared documents. Appropriate business and technical resources will be available
during the project’s duration.
Conversion Plan
Conversions to a new system will require mapping old data elements to new elements in the
new data structure (SQL Server). Extraction of the flat files in its raw form will enable the web
based technology to access the data via an import program. Then business rules must be applied
to determine which system has the best data quality. Always extract the data from the legacy
system in its raw legacy stored form to a delimited flat file format. This serves two purposes.
First, a delimited flat file enables every technology to access the data via an import. Steps of the
conversion plan include:
Plan or revision of an existing one
Yes
Monica Macedon 50 4/12/2023
Document data flow and actions
Develop functional and technical models
Assess IT and user issues for flexibility
Identify relationships between the data
For each repository document, the actions performed on and controlled by data
Develop a logical data architecture
Schema and Meta Data sources
Develop a physical data architecture
Identify non-relational and relational
constraints
Develop, extract, transform and load processes
for each database
Develop cleaning process
Determine data loading process - ODBC/JDBC
Determine the appropriate tools to execute
conversion
Develop audit trail and track business metrics
Monica Macedon 51 4/12/2023
CONCLUSION
TBDQuality Conformance ReportUser AcceptanceRelease of software
Monica Macedon 52 4/12/2023
References
Skilled Team Members:
Monica Macedon – Project Manager (managing project)
Daneel LeRoux – President (sponsor)
Charles Buck – business analyst/IT expert (mentor)
Beth Davis – Chief Financial Officer
John Salisbury – Human Resource
Crystal Talmadge – Systems Analyst
Ellen Jackson – Database Administrator
Doug Bonds – Quality Manager
Tina Wainwright – Payroll Supervisor
Configuration Management: Best Practices White Paper (2005). Figure 1. High-level
process flow for Configuration Management Plan.
http://www.cisco.com/warp/public/126/configmgmt.html
Do It Yourself Assessment 2001. Retrieved on 11-01-2005, from Web site:
http://www.dartmouth.edu/~webteach/articles/assessment.html
Gomik, Davor (2001). IBM Rational Unified Process: Best Practices for Software
Development Teams.
http://www-306.ibm.com/software/rational/offerings/lifecycle.html
Monica Macedon 53 4/12/2023
Green, Garo & Lynda Weinman (2004). Macromedia Dreamweaver MX 2004. Hands-on
training. Published by Peachpit Press. Indianapolis, IN>
Martin, Paula K. (2001). The new role of the Project Manager. Retrieved on 10/08/05,
from Web site: www.gantthead.com/article.cfm?ID=15744&authenticated=1
Mochal, Tom (2003). Project mangers must manage their work plans to be successful.
Retrieved on 10/08/05, from Web site: http://techrepublic.com.com/5100-6315-
5034543.html
Noyes, Brian (2002). Define a flexible process with Rational Unified Process.
Retrieved from Web site:
http://www.fawcette.com/resources/managingdev/methodologies/rup/
Project Management Body of Knowledge (2004). 3rd Edition. Published by Project
Management Institute, Inc. Newtown Square, Pennsylvania.
Project Management Framework (2004). Retrieved on 10/12/05, from Web site:
www.dis.wa.gov/pmframework/planning/communications.htm
Raynor, Darrel (1998). Communicating Risk to Management. Retrieved on 10/12/05,
from Web site: www.projectmanager.com/dataanalysis/RaynorColumns.htm
Monica Macedon 54 4/12/2023
Schwalbe, Kathy (2004). Information Technology Project Management. 3rd Edition.
Published by Course Technology. Boston, Massachusetts.
Sharma, Sunil (2002). Determining ROI of IT Projects: But how do you quantify all
benefits? Retrieved on 10/13/05, from Web site:
www.gantthead.com/article.cfm?ID=145956&authenticated=1
Software Test Plan (STP) Template (n.d.). Retrieved on November 10, 2005, from
Web site:
http://www.industrex.com/dynamic/reference/software_test_plan_template.doc.
Test Plan Recruitment (2005). Retrieved on October 19, 2005, from Web site:
http://stars.sas.cornell.edu/testing/recruittestplan.pdf