DOUBLE CYCLING OF CRANE AT CONTAINER PORT

By

Abhinav LalR310210001

Page 2: Double Cycling of Crane at Container Port

Double CyclingWhy Double CyclingWorld Seaborne Trade By Types Of CargoWorld FleetDouble Cycling ProcessCase Of MICTFinancial Benefits Of Double CyclingImpact On Storage Space & EquipmentOperational Changes To Support Double CyclingEconomic Evaluation Of Double Cycling

Page 3: Double Cycling of Crane at Container Port

Double Cycling

Double cycling is an operating technique that can be used to improve the utilization of quay cranes by converting empty crane moves into productive ones. Instead of using the current method, single cycling, where all relevant containers are unloaded before any are loaded, with double cycling, containers are loaded and unloaded simultaneously.

Page 4: Double Cycling of Crane at Container Port

DOUBLE CYCLING PROCESS

Vessel

Crane

Page 5: Double Cycling of Crane at Container Port

WHY DOUBLE CYCLING

Page 6: Double Cycling of Crane at Container Port

World Seaborne Trade By Type of Cargo

1995 2000 2005 20100

500

1000

1500

2000

2500

3000

ContainerBulkCrude Oil

Source:RMT2011,UNCTAD

Page 7: Double Cycling of Crane at Container Port

World Fleet(DWT IN Mn)

1995 2000 2005 20100

50

100

150

200

250

300

350

400

450

500

ContainerOil TankerDry Bulk

Source:UNCTAD2011

Page 8: Double Cycling of Crane at Container Port

Case OF AMICT

Single CyclingDouble cycling(Proposed)

Crane productivity : 30 moves per hour

Cost Per Moves:$100

Vessel turnaround time : 12 hours (1000lifts per call)

Berth productivity : 60 moves per hour

Crane Productivity:60 Moves per hour

Cost Per Move:$150

Vessel turnaround time:07

hours(1000lifts per call)

• Berth Productivity:100 moves per hour

(Source : Adani Mundra International Container Terminal)

Page 9: Double Cycling of Crane at Container Port

Financial Benefit Of Double Cycling

During the trial at the Port Of Rottardam , the adjusted average time for a single cycle was 1 minute and 45 seconds, and for a double cycle, 2 minutes and 50 seconds. Intercontinental freight rates are estimated at $.045 per TEU-km (Notteboom 2004). At this rate, each hour of idle vessel time costs the ship operator $10,000. The 40 second benefit of each double cycle is worth approximately $100. During typical operations, double cycling could provide approximately $350 per hour, saving about $15,000 on a large container vessel. With three cranes per vessel, this is comparable to the total crane operator’s wages for loading and unloading the vessel

Page 10: Double Cycling of Crane at Container Port

IMPACT ON STORAGE SPACE AND STORAGE EQUIPMENTImpact on Storage Spaces

Impact on Storage Equipment

Page 11: Double Cycling of Crane at Container Port

OPERATIONAL CHANGES TO SUPPORT DOUBLE CYCLINGLoading Plans

Load Sequencing

Yard Storage Locations

Stevedores

Container Handling Equipment

Page 12: Double Cycling of Crane at Container Port

Economic Evaluation Of Double CyclingVessel Productivity

Crane Productivity

Berth Utilization

Landside Vehicles & Drivers

Chassis

Page 13: Double Cycling of Crane at Container Port

Special Thanks To

Capt.Yogendra Bhattacharya Capt.Sarabjit Bhutalia Nakul Malhotra Prakash Chandra